Professional Documents
Culture Documents
Two Way Slab Design With Column Capital PDF
Two Way Slab Design With Column Capital PDF
Capitals
Wayne Hoklas
Brendan Nee
Justin Zimmerman
Dec 16, 2003
Table of Contents
Introduction
Design Summary
Calculations
Slab Thickness
Loads
Direct Design Method
Mo
Plan View of Panels
Lateral Distribution of Moments
Plan View of Moment Regions
Flexural Design
One Way Shear
Corner Panels
E-W Edge Panels
N-S Edge Panels
Interior Panels
Punching Shear
Corner Columns
E-W Edge Columns
N-S Edge Columns
Interior Columns
Unbalanced Moment Transfer
Corner Columns
E-W Edge Columns
N-S Edge Columns
Interior Columns
Negative Moment Reinforcement Checks
Equivalent Frame Calculations
Exterior Frame
Interior Frame
EFM Analysis
Node Diagram with Coordinates
Exterior Frame
Output
Loaded Structure
Moment Diagrams
Shear Diagrams
Member 10
Member 21
Member 32
Interior Frame
Output
Loaded Structure
Moment Diagrams
Shear Diagrams
-2-
Page
4
6
11
11
12
15
15
19
20
26
27
42
42
43
44
45
46
46
47
48
49
50
50
53
56
59
62
63
63
66
69
69
70
70
79
79
79
80
81
82
83
83
91
91
91
92
93
94
95
96
97
97
98
99
100
100
101
102
-3-
Introduction
The goal of this project was to design an intermediate floor of a six story concrete building in one
direction using the Direct Design Method (DDM) outlined in ACI-318-02. In addition, the Equivalent Frame
Method (EFM) for obtaining bending moments in the slab, also outlined in ACI-318-02, was performed. The
bending moments obtained from the EFM were then compared to those found using the equations of the DDM.
The following information was given to our design team:
c/c story height = 12 ft
min. c/c column spacing = 22 ft
cladding weight = 250 plf
partition weight = 20 psf
electrical/mechanical system weight = 6 psf
service live load = 80 psf
fc = 5 ksi
fy = 60 ksi
preliminary dimensions:
columns 18x18 in
In addition to this information, our design team was instructed to follow a flat slab design that had no beams
between columns and included column capitals.
Our preliminary estimates of the shear capacity of the slab showed that column capitals were probably not
needed. However, since their use was required, we arbitrarily chose to use 9 column capitals. Upon making this
decision, the minimum slab thickness allowed by ACI-318-02 was used and the general procedures of the DDM
were followed for the North-South direction of the floor. Following this, checks for one and two way shear were
made, as well as a check for unbalanced moment transfer. For the EFM analysis, two equivalent frames were
analyzed. One frame consisted of a column line on an exterior edge of the building, and the other frame consisted
of an interior column line.
Five computer programs were used to assist in our design. Mathcad was used to assist performing the general
calculations. Excel was used for designing the flexural reinforcement and performing cost and quantity
-4-
-5-
Design Summary
Initial Design Work
The first step in the design process was to take the given information and determine the geometry of the
floor system. In order to make calculations simpler, all center to center column spaces in the same direction were
made equal for all panels. This was accomplished by subtracting two one half column widths from the out to out
dimensions in the North-South and East-West directions. The remaining dimension was then divided into thirds
in the North-South direction and into four panels in the East-West direction to obtain center to center column
spacing. Next, some preliminary estimates of the required column capital size were made to ensure adequate
capacity for punching shear, because this often controls the acceptable slab thickness and the need for drop
panels and column capitals. It was determined that column capitals would likely not be needed. Because of this,
relatively small, nine inch column capitals were chosen.
After defining the columns and capitals, the minimum allowable slab thickness was determined using the
clear span distance. From Table 9.5 (C) in ACI-318-02, the controlling minimum thickness was for exterior
panels without drop panels and without edge beams. This thickness was rounded up to 8.5 inches and used for
the rest of the design. Once all dimensions of the floor system were known, the widths of column and middle
strips and the factored dead and live loads were calculated. To handle the effects of the cladding load on the
exterior equivalent frame, all area loads were multiplied by the width of the frame to create line loads. The line
load of the cladding was then added to the dead weight line load and the resulting dead and live line loads were
subsequently factored. The effects from cladding located on East-West building edges were neglected in the
DDM calculations since they will not create significant bending moments in the North-South direction. The effect
of this cladding must be taken into account when the building is designed in the East-West direction.
-6-
-7-
Shear Checks
The next step was to check the slab system to see if it possessed adequate shear capacity. First, the oneway, or beam shear, method of failure was checked. After some consideration, it was decided to assume that the
cladding weight was distributed over the entire panel. While this is probably not an ideal assumption, it should be
satisfactory because the one-way shear capacity was three to four times greater than the applied shear loading.
ACI-318-02 provided no guidance on this issue, thus it is up to the designers discretion.
Two-way, or punching shear, was the next check performed. Four separate regions were identified: corner
panel columns, E-W edge panel columns, N-S edge panel columns, and interior panel columns. The edge columns
have the same shear capacity but not the same loading. All regions were found to have excess shear capacity.
-9-
Unit Cost
$100/yd3
$1200/ton
$200/hr
$9/ft2
Amount
161.774 yd3
11.378 tons
140 hours
6612 ft2
Total Cost
$ 16,177.40
$ 13,653.60
$ 28,000.00
$ 59,535.00
44,420.17
$ 266,521.00
It can be seen that the formwork and design add significant costs to the floor system. However, the
formwork is reusable for each of the six floors and the design need only be performed once, so long as the
column size does not vary. This allows these costs to be divided among all six floors. The material cost applies to
each floor. Thus, the material cost of steel and concrete makes up only 68% of the total flooring cost. This cost
estimate does not consider columns, cladding, roof material, foundations, or partitions.
Finally, drawings and diagrams to make our design clear and understandable were constructed using
Autocad, and our results were reviewed for errors. These drawings can be seen throughout the calculations
section of this report.
- 10 -
h s_min :=
ln
30
h s_min = 8.4668in
From table 9.5 (C) for interior panels with no drop panels and without edge beams
h s_min :=
ln
33
h s_min = 7.6971in
s_min
up to 8.5 inches
h s := 8.5 in
- 11 -
- 12 -
- 13 -
- 14 -
- 15 -
- 16 -
Mo
Mexterior
Exterior
Frame
Interior
Frame
End span
Minterior
interior span
M+
M-
M+
2478
644
1734
1288
1610
867
4262.4
1108
2984
2217
2771
1492
- 17 -
l2 := 22.125ft
CSwidth_int = 11.063ft
CSwidth_ext = 11.813ft
Middle strip width for interior equivalent frames and exterior equivalent frames
MSwidth := l2 CSwidth_int
MSwidth = 11.063ft
- 18 -
- 19 -
- 20 -
- 21 -
- 22 -
- 23 -
- 24 -
1
554
1,330
1,019
0
887
373
0
515
434
644
773
1,301
2
1,039
448
1,039
346
298
346
403
347
403
1,208
520
1,208
3
1,019
1,330
554
373
887
0
434
515
0
1,301
773
644
4
554
1,330
1,119
0
887
373
0
887
373
554
1,330
1,119
5
1,039
448
1,039
346
298
346
346
298
346
1,039
448
1,039
- 25 -
6
1,119
1,330
554
373
887
0
373
887
0
1,119
1,330
554
7
554
1,330
1,119
0
887
373
0
887
373
554
1,330
1,119
8
1,039
448
1,039
346
298
346
346
298
346
1,039
448
1,039
9
1,119
1,330
554
373
887
0
373
887
0
1,119
1,330
554
10
554
1,330
1,019
0
887
373
0
515
434
644
773
1,301
11
1,039
448
1,039
346
298
346
403
347
403
1,208
520
1,208
12
1,019
1,330
554
373
887
0
434
515
0
1,301
773
644
- 26 -
- 28 -
- 29 -
- 30 -
- 31 -
- 32 -
- 33 -
- 34 -
- 35 -
- 36 -
- 37 -
- 38 -
- 39 -
- 40 -
- 41 -
- 43 -
- 44 -
- 45 -
- 46 -
- 47 -
- 48 -
- 49 -
- 50 -
- 51 -
- 52 -
- 53 -
- 54 -
- 55 -
- 56 -
- 57 -
- 58 -
- 59 -
- 60 -
- 61 -
- 62 -
- 63 -
- 64 -
- 65 -
- 66 -
- 67 -
- 68 -
- 69 -
- 70 -
- 71 -
- 72 -
- 73 -
- 74 -
- 75 -
- 76 -
- 77 -
- 78 -
- 79 -
- 81 -
- 82 -
- 84 -
- 85 -
- 86 -
- 87 -
- 88 -
- 89 -
- 90 -
- 91 -
- 93 -
- 94 -
- 95 -
DDM moments
(k*ft) for exterior
frame
DDM moments
(k*ft) for interior
frame
M1
53.7
113.6
92.3
231.9
M2
107.3
109.1
184.8
190
M3
144.5
81.7
248.7
88.2
M4
134.2
111.6
230.9
173.8
M5
72.3
94.9
124.3
172.6
M6
134.2
111.6
230.9
173.8
M7
144.5
81.7
248.7
88.2
M8
107.3
109.1
184.8
190
M9
53.7
113.6
92.3
231.9
- 97 -
- 98 -
- 99 -
Rebar Quantities
ln
(ft)
20.5
Distance
between
column faces
in L1 Direction
(ft)
21.92
Steel
Density
(pcf)
490
100%
Bottom
Rebar
Length
ft.
50%
Bottom
Rebar
Length
ft.
50%
Bottom
Rebar
Length
ft.
22.92
22.92
5.01
22.92
17.925
22.92
17.925
22.92
17.925
4.51
22.92
22.92
5.01
4.51
Weight
lbs
6653.1
6915.8
9187.6
22756.4
- 100 -
Strip
Width
ft
6.3
6.3
6.3
6.3
11.1
11.1
11.1
11.1
11.1
11.1
11.1
11.1
11.1
11.1
11.1
Quantity
of
Rebar
Rebar
Length
ft
18.9
6.3
9.4
6.3
11.1
13.3
11.1
11.1
16.6
16.6
14.8
8.3
11.1
11.1
11.1
96.7
144.2
48.4
144.2
55.4
271.1
49.9
225.9
85.0
380.3
75.6
190.2
55.4
49.9
225.9
Concrete Quantities
Slab Thickness
in
Slab
Width
ft
Slab Depth
ft
8.5
74
90
Column
Quantity
Column
Area
in2
20
324
V=1/3(a2+a*b+b2)*h-182*h
Vol.
Capital
ft3
Vol. Capital
in3
3888
2.25
Capital
Dimensions
a
18
36
Quanitity
Volume
ft3
Slab
Volume
ft3
Slab Area
ft2
6660
Item
Corner Capitals
Edge Capitals
Interior Capitals
Slab
4335.0
Item Vol.
ft3
0.984375
1.546875
2.25
4335.0
4
10
6
1
Total
4367.9
Formwork
Area (ft2)
3.9
15.5
13.5
4335.0
6615
- 101 -
Edge
Capitals
ft3
Corner
Capitals
ft3
1.546875
0.984375
Total Costs
Item
Concrete
Steel
Design
Formwork
Unit Cost
$100/yd3
$1200/ton
$200/hr
$9/ft2
Amount
161.774 yd3
11.378 tons
140 hours
6612 ft2
Total Cost
$ 16,177.40
$ 13,653.60
$ 28,000.00
$ 59,535.00
$ 266,521.00
- 102 -
44,420.17