MADE IN DAGENHAM REHEARSAL ACT 2 SCHEDULE

Week

Session 1: 7.00-7.45pm

Session 2: 7.45-9.00pm

12th July

Act 2 Sc 1/10

This Is America

19th July

Act 2 Sc 4/Sc 5/Sc 5a

This Is America

26th July

Act 2 Principle Singing

Cortina

2nd August

Act 2 Sc 6/Sc 9

Cortina

9th August

Act 2 Sc 2

Storm Clouds/ Sc 3

16th August

Act 2 Sc 7/ Sc 8

Viva Eastbourne

23rd August

Act 2 Sc 12

Viva Eastbourne

30th August

Act 2 Sc 13

Stand Up

4th September (SUNDAY) 1-5

Stand Up

Act 2 Run

6th September

Prop Making

Act 2 Recap

Setting

7th September (WEDNESDAY)


11th September (SUNDAY) 3-6.30

Full Show Run

Full Show Run

13th September

Costumes

Hair/Make Up

18th September (SUNDAY) 3-6.30

Dress Show Run

Dress Show Run

20th September

Notes

Full Show Run

21st September (WEDNESDAY)


25th September (SHOW WEEK)

Act 2 Scene Recap


Band Call

Blocking/Staging

26th September (SHOW WEEK)

Tech

27th September (SHOW WEEK)

Dress Run

28th September (SHOW WEEK)

Show 1

29th September (SHOW WEEK)

Show 2

30th September (SHOW WEEK)

Show 3

1st October (SHOW WEEK)

Show 4

Show 5

ACT 2 SCHEDULE
Session 3: 9.00-10.00pm
This Is America

Back Room
Nearly Had It All

This Is America
Cortina

The letter/Act 2 Sc 6

Storm Clouds
Storm Clouds/ Sc 3
Viva Eastbourne
Viva Eastbourne
Stand Up
Act 2 Run
Act 2 Recap

Setting
Full Show Run
Recap
Dress Show Run
Full Show Run
Act 2 Scene Recap
Tech
Dress Run

Ideal World