Results Analysis (RA) Conversion Steps: Raj Thyagarajan & Karen Szu - Lockheed Martin
Results Analysis (RA) Conversion Steps: Raj Thyagarajan & Karen Szu - Lockheed Martin
[ Introduction - Company
Missiles and Fire Control (MFC) is
a Business Unit of Lockheed Martin
MFC develops, manufactures, and supports
advanced combat, missile, rocket and space
systems for military customers that include the
U.S. Army, Navy, Air Force, Marine Corps,
NASA, and dozens of foreign nations.
The Lockheed Martin Missiles and Fire Control
(MFC) company is one of six companies that
comprise the Lockheed Martin Electronic
Systems business area.
http://www.lockheedmartin.com/us/mfc.html
Real Experience. Real Advantage.
Project Systems RA
Only one contract type is demonstrated (FIXED or POT)
More focus on the conversion steps
Less focus on the RA configuration
Profit Ctr A
Sales
$100
Sales
$100
Cost
$20
Cost
$20
Profit Ctr A
Sales
$100
Sales
$100
Cost
$20
Cost
$20
Undelivered
Cost (4xxxxx)
$70
Profit Ctr A
Sales
$100
Sales
$100
Cost
$20
Cost
$20
ME cost to WIP
-$20
ME cost to WIP
-$20
COGS after RA
$90
COGS after RA
$90
Profit Ctr A
Sales
$100
Sales
$100
Cost
$20
Cost
$20
ME cost to WIP
(499998)
-$20
ME cost to WIP
(499998)
-$20
Custom Code 1
New RA
(499011)
$90
New RA Key
Custom Code
(499011)
-$90
COGS (499211)
$90
COGS (499211)
$90
Custom Code 2
Custom Code 2
OKG3
OKG4
OKG8
OKG2 details
[ Implementation Steps
Open CO periods for Automat. WIP/results analysis as far
back as needed (Auto RA) OKP1(include manual as needed)
Reverse RA for all periods/years SAPKKA13 (program)
Ensure FI period is current OB52
Post RA reversals to FI via project settlement CJ88/CJ8G
Validate RA accounts as needed
Close CO periods to make current
Change RA keys for all conversion projects
Change plan data if applicable CJR2
Make any one- time manual entries if applicable (FB50-499998)
Run catch up RA KKA2/KKAJ and save
Analyze RA and settle to FI CJ88/CJ8G
[ Implementation Steps-OKP1
10
[ Implementation Steps-SAPKKA13
11
[ Implementation Steps-SAPKKA13
12
[ Implementation Steps
Open CO periods as far for Automat. WIP/results analysis
back as needed (Auto RA) OKP1
Reverse RA for all periods/years SAPKKA13 (program)
Ensure FI period is current OB52
Post RA reversals to FI via project settlement CJ88/CJ8G
Validate RA accounts as needed
Close CO periods to make current
Change RA keys for all conversion projects
Change plan data if applicable CJR2
Make any one- time manual entries if applicable (FB50-499998)
Run catch up RA KKA2/KKAJ and save
Analyze RA and settle to FI CJ88/CJ8G
13
[ Implementation Steps-CJ02
14
[ Implementation Steps
Open CO periods for Automat. WIP/results analysis as far
back as needed (Auto RA) OKP1
Reverse RA for all periods/years SAPKKA13
Ensure FI period is current OB52
Post RA reversals to FI via project settlement CJ88/CJ8G
Validate RA accounts as needed
Close CO periods to make current
Change RA keys for all conversion projects
Change plan data if applicable CJR2
Make any one- time manual entries if applicable (FB50-499998)
Run catch up RA KKA2/KKAJ and save
Analyze RA and settle to FI CJ88/CJ8G
15
[ Implementation Steps-CJR2
16
[ Implementation Steps
Open CO periods for Automat. WIP/results analysis as far
back as needed (Auto RA) OKP1
Reverse RA for all periods/years SAPKKA13 (program)
Ensure FI period is current OB52
Post RA reversals to FI via project settlement CJ88/CJ8G
Validate RA accounts as needed
Close CO periods to make current
Change RA keys for all conversion projects
Change plan data if applicable
Make any one- time manual entries if applicable (FB50-499998)
Run catch up RA KKA2/KKAJ and save
Analyze RA and settle to FI CJ88/CJ8G
17
[ Implementation Steps-FB50
18
[ Implementation Steps-KKA2
19
[ Implementation Steps-CJ88/CJ8G
20
21
[ Learning Points
Full reversal of old RA process or partial (depends on process)
Open CO periods as far back as needed (Auto and manual RA)
RA is an FI only posting
Beware if the FI only account used has been inadvertently
converted to a cost element
Results analysis stored in CO table (COEPB)
Results analysis is a two step process (RA and settle)
Moving regular costs to WIP and then posting COGS via RA
may improve performance in addition to convenience of
analysis (RA has to read only one cost element as opposed to
many)
22
[ Best Practices
Understand the RA processes previously used and ascertain if
any manual entries occurred (may or may not have to
reversed)
Reverse using SAP functionality and use test run to confirm the
requirements
Configure the new RA keys and test them well in advance
Exercise the methodical steps in a test instance before
production
23
[ Key Learnings
Understand the old RA process and postings
Test the new RA process well in advance
Test the mass conversion in a test instance
Get concurrence from Accounting
Pick the right month to implement the conversion
Use the first half of the month to convert to give enough time
before month end close
SAPKKA13/CJ88 two step RA reversal process
Carefully pick the right month and ensure sufficient time for
validation
Methodology can be used on all contract types
24