You are on page 1of 2

VALVES TO BE OPENNED OR CLOSE DURING CHANGE BUNKER

M/E = IS IN D.O
BLR= IN F.O.
2. OPEN VALVE
NOTE: IF OPEN IN D.O.
IF CLOSE IN F.O

3. CLOSE F.O LOW SUCTION V/V


4. OPEN F.O HIGH SUCTION V/V

NOTE: IF THE BOILER IS IN F.O. BUNKER CONSUMPTION AND


BOTH F.O. SUCTION V/V IS CLOSE THERE WILL BE NO F.O. TO BE
SUCTIONED
BY THE AUX.BLR F.O. BURNING PUMP
THEREFORE RESULTING FO THE BOILER TO TRIP.
SO THE F.O HIGH SUCTION V/V MUST BE OPENED.

1. OPEN D.O

NOTE: IF OPEN IN D.O.


IF CLOSED IN F.O
After f.o ChangE Bunker to D.o
1. Open the f.o heater for f.o to raise the temp. of D.o temp. up to 80 degreesbefore change bunker from f.o to D.o
2. Close the v/v

3. close d.o v/v