Professional Documents
Culture Documents
Calculating Critical Path & Float For A Network Diagram: Task Name, Duration (D)
Calculating Critical Path & Float For A Network Diagram: Task Name, Duration (D)
Late Start
(LS)
Early Start
(ES)
Task Name,
Duration (D)
Late Finish
(LF)
Early Finish
(EF)
Find out the length of all the paths in the network diagram
The longest path is the critical path
Float = EF - LF
= ES - LS
Task 2
4 days
4 days
Task 1
Task 5
3 days
Task 3
7 days
Task 4
9
Task 5,
4 days
14
18
4
Task 3,
3 days
4
Task 4,
7 days
7
14
14
Task 2,
5 days
14
18
Task 5,
4 days
14
18
Task 1,
4 days
0
4
Task 3,
3 days
4
14
Task 4,
7 days
7
14
For all tasks on Critical Path (Task1, Task 3, Task 4, Task 5), EF = LF & ES = LS
Thus, float (slack) for tasks on Critical Path = LF EF = 0
Float for Task 2 = LF EF = 14 9 = 5 days