You are on page 1of 6

Calculating Critical Path & Float for a Network Diagram

Late Start
(LS)
Early Start
(ES)

Task Name,
Duration (D)

Late Finish
(LF)
Early Finish
(EF)

Find out the length of all the paths in the network diagram
The longest path is the critical path
Float = EF - LF
= ES - LS

Calculating Critical Path for a Network Diagram


Identify tasks, durations & dependencies.
5 days

Task 2

4 days
4 days

Task 1

Task 5

3 days
Task 3

7 days
Task 4

Step 1: Draw a Network Diagram


For forward pass, calculate the Early Start (ES) and Early Finish (EF).
Task 2,
5 days
4
Task 1,
4 days
0

9
Task 5,
4 days
14
18

4
Task 3,
3 days
4

Task 4,
7 days
7

14

Task 5 is dependent on Task 2 and Task 4 being complete.


So, ES for Task 5 is 14 days (dependent on Task 4, which is the longer task.

Step 2: Determine Critical Path


To determine critical path, calculate length (durations) of all the paths:

Length of all tasks:


Task1 Task2 Task5 = 4 + 5 + 4 = 13 days
Task1 Task3 Task4 Task5 = 4 + 3 + 7 + 4 = 18 days
The longest path is the critical path

Critical path = longest path = 18 days


Critical Path = Task1 Task3 Task4 Task5

Step 3: Calculate Float in all tasks Backward Pass


ES = Early Start
EF = Early Finish
LS = Late Start
LF = Late Finish
0

14

Task 2,
5 days

14
18
Task 5,
4 days
14
18

Task 1,
4 days
0

4
Task 3,
3 days
4

14

Task 4,
7 days
7

14

For all tasks on Critical Path (Task1, Task 3, Task 4, Task 5), EF = LF & ES = LS
Thus, float (slack) for tasks on Critical Path = LF EF = 0
Float for Task 2 = LF EF = 14 9 = 5 days

Step 4: Calculate Project Float


Customer requests an end date of 25 days.
Project Float is the total amount of time that the project can be delayed
without delaying the project completion date required by the customer.
25 days 18 days = 7 days.
Project float can be negative when the date imposed by the customer is before
the duration required in the project schedule.
For negative project float, the project must be crashed or fast-tracked.
Crashing is a technique used to decrease the duration of the project by
assigning additional resources to tasks and decreasing the duration required
for those tasks.

Fast Tracking is a technique used to shorten project time by scheduling some


activities concurrently that were originally scheduled sequentially.

You might also like