65 WHCP Schedule Level-1
65 WHCP Schedule Level-1
01
ID
WBS
Task Name
Duration
65 WHCP& SSV
1.1
Project Preliminaries
106 days
1.2
Engineering - Submissions
122 days
1.3
Engineering-Approvals
122 days
1.4
Procurement
312 days
10
1.4.1
Material Submission
15 days
16
1.4.2
Material Approval
29 days
22
1.4.3
Material Order
15 days
28
1.4.4
Material Delivery
277 days
34
1.5
Mousafah Works
90 days
37
1.6
Mobilization to Site
12 days
38
1.7
Site works
39
1.7.1
113 1.7.2
199 days
195 days
107 days
184 1.8
As Built documentation
90 days
185 1.9
Demobilization
0 days
Year 1
Year 2
M-1 M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 M20
550 days
Task
Milestone
Summary
Page 1