Professional Documents
Culture Documents
Net Ana-KR PDF
Net Ana-KR PDF
CPM
AON system
(Activity on Node
system )
Problem 1.
Construct an arrow diagram for the following project.
Activities
Relationship
A
B
C
Precedes B,C
Precedes D,E
Precedes D
D
E
F
Precedes F
Precedes G
Precedes G
E
B
G
A
F
C
D
Problem 2.
Construct an arrow diagram for the following project.
Job
Immediate
predecessor
Duration
14 Days
3 Days
7 Days
4 Days
B,D
10 Days
E
10
14
4
C
7
Key
Job
Duration
Problem 3.
Construct an arrow diagram for the following project.
Job
Immediate predecessor
A,B
C,E
C
B
F
A
E
D
Problem 4.
Construct an arrow diagram for the following project.
Activity
Predecessor
A,B
B,C
A
B
C
Problem 5.
Construct an arrow diagram for the following project.
Activity
A
Predecessor
-
B
C
D
E
A,B
B,C
A,B,C
A
B
F
C
Problem 6.
Draw the PERT network for the following project
Event A is followed by events B & C
Event D is preceded by events B & C
Event H is the successor to event E
Event E is the successor to event B
Event F is the successor to event D & G
Event C is the predecessor to event G
Event J is preceded by events F,G, & H
E
B
H
A
D
F
C
G
10
CRITICAL PATH
Meaning: The longest path in a project network which determine the duration of the
project is known as critical path.
8
5
5
3
1
6
3
4
11
8
5
5
3
1
6
3
4
12
Float (Slack)
Float (Slack ) refers to the amount of time by which a particular event or an
activity can be delayed without affecting the time schedule of the network.
Float (Slack)
Float (Slack) is defined as the difference between latest allowable and the earliest
expected time.
Event Float/Slack = LS ES
Where LS = Latest start time
ES = Early start time.
Earliest start : Denoted as ES
Earliest start time is the earliest possible time by which the activity can be started.
Early finish time : Denoted as EF
Early finish time is the earliest possible time by which the activity can be completed.
Latest start time : Denoted as LS
Latest start time is the latest possible time by which the activity can be started
Late finish time : Denoted as LS
Late finish time is the latest possible time by which the activity can be completed
Total float (TF) / Total slack (TS)
Total float of the job is the differences between its Late start and Early start or Late
finish and Early finish
i.e.
TF( CA) = LS (CA) - ES (CA)
Or
TF( CA) = LF (CA) - EF (CA)
CA = Current activity
Free float (FF)
Free float is the amount of time a job can be delayed without affecting the Early start
time of any other job.
FF(CA) = ES(SA) EF (CA)
CA = Current Activity
SA = Succeeding Activity
Independent Float (IF)
Independent Float is the amount of time that can be delayed without affecting either
predecessor or successor activities.
IF = ES(SA) LF(PA) - Duration of CA
ES = Early Start
LF = Late Finish
SA = Succeeding Activity
PA = Preceding Activity
CA = Current Activity
13
Example 1
Construct the Network for the following
Project and determine the following
i) Critical Path
ii) ES,EF,LS,LF
iii) TF,FF
Activity
Duration
1-2
14
1-4
2-3
2-4
3-5
4-5
5-6
10
3
F
B
5
10
G 0
14
D
2
14
Determination of TF and FF
A(
0,
14
)(0
(0
)
,1
4)
(0
)
D(14,21)(0)
2
7(14,21)(0)
F(25,35)(0)
5
E(21
,25)(
0)
4(21
,25)
(0)
14
C(14
,17)
(8)
3(2
2,25
)(8)
0(22,22)
G(14,14)
1)
(1
)
9)
3
0,
)(1
2
B(
,2
19
3(
10(25,35)(0)
Job (ES,EF)(FF)
Duration (LS,LF)(TS)
Activity Duration
ES
EF
LS
LF
TF
FF
1-2
14
14
14
1-4
19
22
19
11
2-3
14
21
14
21
2-4
14
14
22
22
3-5
21
25
21
25
4-5
14
17
22
25
5-6
10
25
35
25
35
15
Example 2
Construct the Network for the following
Project and determine the following
i) Critical Path
ii) ES,EF,LS,LF
iii) TF,FF
Activity
Duration
1-2
2-3
2-4
3-5
3-6
4-6
4-7
5-8
6-8
7-8
16
(0, 2)(0)
1
(2,
2(0, 2)(0)
5(2
,
7)(
0)
7)(
0)
(9
,1
3)
(0
4(1
)
6,
20
)(7
)
)
5)(0
(2,
(3)
, 8)
3(5
5
(9,1
7)(0
0)
(
)
)
8
(12
,9
3)
,20
(
(5
)
)
2
(
3
)
,1
4(8
3
(5,
)
6)(
20)(0
1(1
7)
(13,
2,
(0)
13
, 20)
)(7
)
7(13
6
0)
) ( 0)
3
(
,1
(7 , 13)
7 (7, 9)(0)
(
6
4
7
2(14,16)(7)
(ES,EF)(FF)
Key
Duration (LS,LF)(TS)
Activity
Duration
ES
EF
LS
LF
TF
FF
1-2
2-3
2-4
3-5
3-6
4
1
5
5
9
6
8
12
12
13
3
7
0
7
4-6
13
13
4-7
5-8
2
8
7
9
9
17
14
12
16
20
7
3
0
0
6-8
13
20
13
20
7-8
13
16
20
17
18
Example 1
Construct the Network for the following project and
calculate the probability of completing the project in 25 days
Activity
to
tm
tp
1-2
10
1-3
12
2-3
2-4
3-4
3-5
4-6
10
14
5-6
4-
8-
12
2-4-6
2-
10
6-
-0
6-
10
-0
1-
3-6-9
3
4-
5
3-
19
6
1
4-
8-
12
2-4-6
4
6
2-
-10
-0
6-
410
10
-0
0
1-
3-6-9
3
-5
3
5
6
6
1
4-
8-
12
2-4-6
4
6
2-
-10
-0
6-
410
10
-0
0
1-
3-6-9
3
-5
3
5
6
Key
to - tm - tp
te
20
Activity
to
tm
tp
Critical
activities
2 = ((t p t o) / 6)2
1-2
10
1-2
1.78
1-3
12
2-3
2-3
2-4
3-4
3-4
3-5
4-6
10
14
4-6
5-6
0.44
1.78
2 = 4.00
21
Example 2.
The following table lists the jobs of a network along with their
time estimates.
Activity
to
tm
tp
1-4
27
1-3
15
1-2
12
30
4-5
07
3-5
27
3-6
08
5-6
12
30
2-6
19
28
4-1
9-
30
26 -1
3 - 6 - 15
-9
2-5-8
3-
-2
7
4
28
9-
27
6-
12
0
-3
22
4-1
928
18
30
21
6
14
3 - 6 - 15
2-5-8
3-
-9
11 - 27
9-
11
27
1-4-7
2-1
30
14
4-1
928
18
30
21
6
14
3 - 6 - 15
2-5-8
3-
-9
11 - 27
11
4
9-
27
1-4-7
4
Key
2-1
30
14
to - tm - tp
te
23
As there are two Critical Paths, the path which gives more variance(2) is taken as
Critical Path
Path A
Activity
2 = ((t p t o) / 6)2
1-2
((30 6)/6)2
16
2-6
((28 4)/6)2
16
2 = 32.00
Path B
Activity
2 = ((t p t o) / 6)2
1-3
((15 3)/6)2
3-5
((27 3)/6)2
16
5-6
((30 6)/6)2
16
2= 36.00
= 2 = 36
=6
24
CPM Model
In 1958 Du Pont Company used a technique called Critical Path Method (CPM) to
schedule and control a very large project like overhauling of a chemical plant, there by
reducing the shutdown period from 130hrs to 90 hrs saving the company 1 million dollar.
Both of these techniques are referred to as project scheduling techniques.
Direct cost
Crash
Normal
Indirect cost
Job duration
Shorter the duration higher will be the Direct expenses
Crash
Normal
Job duration
25
Cost
Total cost
Dire
ct c
ost
ost
ct c
e
r
i
Ind
Crash
Optimum
Normal
Job duration
Example 1.
Find the lowest cost and optimum cost schedule for the following project, given the over
head expenses as Rs.45/-day.
Activity
Normal duration
Crash
duration
Cost of crashing
per day
1-2
Rs.40
2-3
Rs.40
2-4
Rs.10
3-4
Rs.20
26
7-3
10
3 -1
4-
20
40
-2
40
3
Normal duration Crash duration
Key
Cost of crashing per day in Rs.
7-3
10
3 -1
4-
20
40
-2
40
3
Normal duration Crash duration
Key
Cost of crashing per day in Rs.
27
Step 1.
3 -1
1
4-2
5-2
2
40
3
7-3
12 days
20
40
10
Activity
crashed
Days
saved
Project
duration
Cost of crashing
Total
cost of
crashin
g
Over
Head cost
Total
cost
None
3-4
12
-Nil-
-Nil-
45 x 12
540
10
20 x 2 =40
40
45 x 10
490
3-4 &2-4
1-2
20x1+10x1 =30
70
45 x 9
475
40 x 2 =80
150
45 x 7
2-3&2-4
465
40x2+10x2 =100
250
45 x 5
475
Step 2.
3 -1
1
4-2
3-2
2
40
20
40
7-3
10 days
10
Activity
crashed
Days
saved
Project
duration
Cost of crashing
Total
cost of
crashin
g
Over
Head cost
Total
cost
None
12
-Nil-
-Nil-
45 x 12
540
3-4
10
20 x 2 =40
40
45 x 10
3-4 &2-4
20x1+10x1 =30
70
45 x 9
475
490
1-2
40 x 2 =80
150
45 x 7
465
2-3&2-4
40x2+10x2 =100
250
45 x 5
475
28
Step 3.
3 -1
1
4-2
2-2
2
40
20
40
6-3
9 days
10
Activity
crashed
Days
saved
Project
duration
Cost of crashing
Total
cost of
crashin
g
Over
Head cost
Total
cost
None
3-4
12
-Nil-
-Nil-
45 x 12
540
10
20 x 2 =40
40
45 x 10
490
3-4 &2-4
1-2
20x1+10x1 =30
70
45 x 9
475
40 x 2 =80
150
45 x 7
2-3&2-4
460
40x2+10x2 =100
250
45 x 5
475
Step 3.
3 -1
1
4-2
2-2
2
40
20
40
6-3
9 days
10
Activity
crashed
Days
saved
Project
duration
Cost of crashing
Total
cost of
crashin
g
Over
Head cost
Total
cost
None
12
-Nil-
-Nil-
45 x 12
540
3-4
10
20 x 2 =40
40
45 x 10
490
3-4 &2-4
20x1+10x1 =30
70
45 x 9
475
1-2
40 x 2 =80
150
45 x 7
460
2-3&2-4
40x2+10x2 =100
250
45 x 5
475
29
Step 4.
1 -1
1
4-2
2-2
2
40
20
40
6-3
7 days
10
Activity
crashed
Days
saved
Project
duration
Cost of crashing
Total
cost of
crashin
g
Over
Head cost
Total
cost
None
12
-Nil-
-Nil-
45 x 12
540
3-4
10
20 x 2 =40
40
45 x 10
490
3-4 &2-4
20x1+10x1 =30
70
45 x 9
475
1-2
40 x 2 =80
150
45 x 7
460
2-3&2-4
40x2+10x2 =100
250
45 x 5
475
Step 5.
3 -1
1
2-2
2-2
2
40
20
40
4-3
5 days
10
Activity
crashed
Days
saved
Project
duration
Cost of crashing
Total
cost of
crashin
g
Over
Head cost
Total
cost
None
3-4
12
-Nil-
-Nil-
45 x 12
540
10
20 x 2 =40
40
45 x 10
490
3-4 &2-4
1-2
20x1+10x1 =30
70
45 x 9
475
40 x 2 =80
150
45 x 7
2-3&2-4
460
40x2+10x2 =100
250
45 x 5
475
30