You are on page 1of 118

Organization

Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

END USER MANUAL


SAP, PRODUCTION PLANNING (PP) MODULE

PROJECT

VISION
SUJAN BARRE THOMAS ANTIVIBRATION SYSTEMS PVT. LTD.,
Thane

Prepared By,
HARRIS PANCHAL
SAP Consultant, PP
Mahindra IT Consulting Pvt. Ltd., Mumbai

Page 1 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

DOCUMENT CONTROL

Sr. No.

Revision

Date of
Creation

Date of
Modification

Remarks

1.0

07-February-09

07-February-09

---

Security Classification: COMPANY CONFIDENTIAL

Page 2 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

Contents
1. CHECK SCHEDULING AGREEMENT MD04....................................................................................4
2. CHECK STOCK OF MATERIAL - MMBE.............................................................................................6
3. EXPLODED BOM VIEW CS11 ..........................................................................................................9
4. RESERVATION CREATION ...............................................................................................................11
4.1a BY MANUAL CREATION THROUGH MB21...................................................................11
4.1b RESERVATION DISPLAY PRINT FOR INTIMATION MB25 .......................................14
4.1c STOCK TRANSFER POSTING MB26 ............................................................................18
4.2 BY MANUAL CREATION THROUGH MB1B ....................................................................19
5. CHECK BILL OF MATERIAL CS03 ................................................................................................21
5.1 CHECKING STANDARD BOM.............................................................................................21
5.2 ADDING AN ALTERNATIVE BOM .......................................................................................23
6. CHECK ROUTING CA03 .................................................................................................................25
6.1 CHECKING STANDARD ROUTING ....................................................................................25
6.2 ADDING AN ALTERNATIVE ROUTING ..............................................................................28
7. PRODUCTION ORDER CREATION MANUAL CO01..................................................................30
8. SHOP FLOOR PRINTING PRODUCTION ORDER CO04 ...........................................................35
9. PRODUCTION ORDER CONFIRMATION CO11n ..........................................................................39
10. QUALITY INSPECTION QA32.......................................................................................................43
11. PRODUCTION ORDER SETTLEMENT KO88 ..............................................................................51
12. PRODUCTION ORDER TECO (Technically Complete) CO02 ................................................53
13. CHECK PRODUCTION ORDER REPORTS ....................................................................................55
13.1 PRODUCTION ORDER INFORMATION SYSTEM - COOIS ............................................56
13.2 CAPACITY PLANNING - STANDARD OVERVIEW CM01 ............................................61
13.3 CAPACITY PLANNING - CAPACITY EVALUATION CM50 ..........................................63
13.4 ORDER PROGRESS REPORT CO46 ............................................................................66
13.5 DISPLAYING PRODUCTION ORDER CONFIRMATION CO14 ....................................68
13.6 CHECK PRODUCTION ORDER DELIVERY MB51........................................................69
13.7 CHECK RAW MATERIAL ISSUE MB51 .........................................................................71
13.8 CHECK RAW MATERIAL RECEIPT MB51.....................................................................73
13.9 MATERIAL USAGE ANALYSIS - MCRE............................................................................75
13.10 ANALYZE PRODUCTION ORDER KKBC_ORD ..........................................................77
13.11 CHECKING FAILED GOODS MOVEMENT - COGI ........................................................79
14. PRODUCTION ORDER THROUGH DEMAND MANAGEMENT ..................................................80
14.1 CREATE PLANNED INDEPENDENT REQUIREMENT MD61.......................................80
14.2 MRP AT PLANT LEVEL MD01.....................................................................................83
14.3 MRP AT MATERIAL LEVEL MD02 ..............................................................................85
14.4 PRODUCTION ORDER CONFN. WITH REWORK CO11n............................................93
14.5 PRODUCTION ORDER CREATION REWORK CO07 ................................................97
14.6 REWORK PRODUCTION ORDER CONFIRMATION CO11n ......................................101
14.7 GOODS RECEIPT OF REWORK ORDER MB31 .........................................................104
15. MRP FOR PLANNED ORDER + PURCHASE REQUISITION....................................................107
16. CO-PRODUCT SCENARIO ............................................................................................................114

Page 3 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

1. CHECK SCHEDULING AGREEMENT MD04


Sales & Distribution (SD) Module would be inputting Scheduling Agreement in the SD Module which
would be visible in the Stock Requirement List (Dynamic Listing).

SAP ECC menu

Logistics Production MRP Planning Evaluations


Stock/Requirements List

Transaction code

MD04

Here enter the Material and the Plant whos Requirements are to be checked.

Page 4 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

Here you can see the Scheduling Agreement inputted by SD.

Page 5 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

2. CHECK STOCK OF MATERIAL - MMBE


The Stock of the Raw Material is checked against the Selection criteria.

SAP ECC menu

Logistics Material Management Inventory


Management Environment Stock Stock Overview

Transaction code

MMBE

Double click on the Transaction code and give the selection condition as per your requirement.

Page 6 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

Click on Execute

The System will Show you the Stock as of that particular Item. The system will show you the Actual
stock lying at different areas such as Unrestricted, Quality Inspection, Reserved and Blocked Stock etc.

Page 7 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

If the stock is not available at IS01 (Issuing In-Between Storage Location), then, In-House Stock
transfer of components has to be done, i.e. ST01 to IS01. Production Order will be consuming the
Stock from ST01 (General Storage Location) to IS01 (In-between / WIP Storage Location).
Also if the production department has determined the total quantity required for a particular material,
say ROH, then they can check the same by exploding the total BOM Quantity.

Page 8 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

3. EXPLODED BOM VIEW CS11


To check the Total Raw Material requirement by means of Exploding the Total BOM of a particular
Material.

SAP ECC menu

Logistics Production Master Data Bills of Material


Reporting BOM Explosion Material BOM

Transaction code

CS11

Enter Material / Plant / Required Qty. / BOM Application and click on Execute

Page 9 of 118

icon.

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

After the execution, it will show the Total Requirement for that Finish Product in terms of Raw Material
requirement.

Page 10 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

4. RESERVATION CREATION
4.1a BY MANUAL CREATION THROUGH MB21
Now known the total quantity the Reservation needs to be created for the total requirement which was
being put at the time of exploding the BOM.

SAP ECC menu

Logistics Material Management Inventory


Management Reservation Create

Transaction code

MB21

Enter Movement No.: 311 for Plant 1000.

Page 11 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

Enter Material, its Quantity, Unit oF Measure, the Receving Storage Location (IS01) and Storage
Location (ST01)

And Click on SAVE. Reservation is created and it will be shown with a Green Tick and a Reservation
No. being created.

Page 12 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

Note the Reservation No. shown in the System Status bar.

Page 13 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

4.1b RESERVATION DISPLAY PRINT FOR INTIMATION MB25


SAP ECC menu

Logistics Material Management Inventory


Management Reservation Reservation List

Transaction code

MB25

Enter Material & Plant 1000.

Page 14 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

Click on Execute

Reservation List Display will be seen.


Select the Reservation Line and Click on Change Layout From Drop Down menu

Page 15 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

Select Choose to select the saved Layout.

Page 16 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

Now you can see the details as per the selected Layout.

Select this line and Click on Print Option. Once the Spool is created, go to Spool Management to select
the print to be printed as a Hard Copy which then can be given to the Stores for issuing the material
from ST01 to IS01.

Page 17 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

4.1c STOCK TRANSFER POSTING MB26


SAP ECC menu

Logistics Material Management Inventory


Management Reservation Picking

Transaction code

MB26

You can enter here the Material / Reservation No. / Order No. / Plant as per your filtering requirement.
After entering you can simply select the One Reservation which you want to post, multiple selection is
also possible. If only 1 is to be posted then you need to delete the other postings and then Post the one
which was kept.
Goods movement would take place, which would mention it by Displaying a Green Tick mark in the
status bar.
Now the required material is available at IS01.

Page 18 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

4.2 BY MANUAL CREATION THROUGH MB1B


SAP ECC menu

Logistics Logistics Execution Internal Whse


Processes Posting Change Inventory
Management Enter Posting Change

Transaction code

MB1B

Here with this TCode you can directly post the required stock within plant.

Page 19 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

Enter the following details on the main Screen viz.


1. Movement Type: 311
2. Plant: 1000
3. Storage Location (Where the goods exists, Transfer from location): ST01
On the next screen Enter the following:
1. Rcvg SLoc (Where the material is needed to consume): IS01
2. Enter the Material details and Storage Location

And SAVE to post the material to the required Storage location.

Page 20 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

5. CHECK BILL OF MATERIAL CS03


5.1 CHECKING STANDARD BOM
SAP ECC menu

Logistics Production Master Data Bills OF Material


Material BOM Display

Transaction code

CS03

Now enter the Material number of which you BOM you want to see and execute.

Page 21 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

System will show you the Bill Of Material with details like material included in bill of material, description
of the component, quantity required with unit of measure.

Page 22 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

5.2 ADDING AN ALTERNATIVE BOM


SAP ECC menu

Logistics Production Master Data Bills OF Material


Material BOM Create

Transaction code

CS01

At times there are chances that an Alternative Material is available to produce a particular component.
In that case an Alternative BOM for the same FERT would be required.
To do so, CS01 can be used to create an Alternate over an Existing BOM.

It would highlight that an Alternative 2 added to BOM and a New Page for entering the BOM
components would come where you can enter the new / alternate components.

Page 23 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

Other relevant details such as Storage Location and SAVE the BOM.
Once you have created it and when you open the BOM in change mode it would show you 2
alternatives and you can select which one you want to view / modify.

Page 24 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

6. CHECK ROUTING CA03


6.1 CHECKING STANDARD ROUTING
SAP ECC menu

Logistics Production Master Data Routings


Standard Routings Display

Transaction code

CA03

Enter the Material Number & Plant to display the Routing.

Page 25 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

System will display the routing of the material with details such as work center used operation
performed, Base quantity and the Activities. If the Group No. is already visible in the field, remove the
same and give Enter.

A Production Resource Tool (PRT) i.e. in case of SBT it is a Mould can be checked. In the above view
th

9 Column shows the TICK MARK which is grayed for PRT being applied to that operation. Select this
operation and click on

above.

Page 26 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

CONTROL KEY:
You maintain the control key for operations in Customizing for Shop Floor Control. This is customizing
operation.
For SBT Scenario we are using 3 Control Keys viz.
1. PP01 - Routing/Ref. op. set - internal proc.
2. PP03 - Routing - in-house prod. auto. goods rct
3. PP07 - For Rework
PP01
Is used for all Operations other than the Last Operation as it has a Auto GR Tick which will allow the
components to be Goods received after the Final confirmation.
PP03
Is used for the Last operation or where Goods Receipt is to take place.
NOTE: Auto Goods Receipt can take place in 1 Operation only in the whole Routing sequence.
PP07
This is specifically used for to be used in Rework Order operations. Manual GR is mandatory for
Rework Orders.

Page 27 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

6.2 ADDING AN ALTERNATIVE ROUTING


To add an alternative routing you have through TCode CA01 itself.

SAP ECC menu

Logistics Production Master Data Routings


Standard Routings Create

Transaction code

CA01

Here it would show that Sequence No. 1 with Group Counter 1 is the only one existing. Hence to create
an Alternate Routing for the same FERT, i.e. if 1 Single Product is having more than 1 way of
manufacturing the product.
Click on NEW

Page 28 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

Here you can see the Counter as 2.


Enter the Usage as 1 and Status 4 and click on Operations.
Now you can enter the new sequence of operation that you want and give Enter.

Enter the Setup Time, Machine Time and Labour Time and SAVE.

Page 29 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

7. PRODUCTION ORDER CREATION MANUAL CO01


SAP ECC menu

Logistics Production Shop Floor Control Order


Create With Material

Transaction code

CO01

Enter the following:


1. Material Number:

XXXXXXXX

2. Production Plant:

1000

3. Order Type

ZS01

Page 30 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

Enter the following:


1. Quantity of Production
2. Basic Dates (As per the Scheduling Type)

Page 31 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

As we have an Alternative Routing for the FERT, you need to select the Icon Production Version
in the top frame.
It would then prompt you for the Routing which needs to be selected for the FERT as per the machine
availability.

Select the required sequence and then you can continue as per the regular Production Order
execution.
PRE-REQUISITE FOR PRODUCTION VERSION:
Production version needs to be maintained in Work Scheduling View or MRP4 View of the
Material Master for the FERTs who have more than 1 combination of BOM and/or Routings.
Now, Click on the following:
1. Material Availability Check

It would show that the Material is available or not, if not it would mention that the material is shortage
and material need to be made available at the required storage location.

Page 32 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

Click on the following:


1. Capacity Check

It would show whether the Capacity is Available or not.

Page 33 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

Click on the Calculator on the Top Frame, to calculate the costs. Thereafter the system should
message as shown below.

Click on the Green Flag to RELEASE the Order.

System would show that the Order has been released.


Now you can SAVE the production order and note the Production Order No.

Page 34 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

8. SHOP FLOOR PRINTING PRODUCTION ORDER CO04


SAP ECC menu

Logistics Production Shop Floor Control Control


Print

Transaction code

CO04N

Enter the Production Order No. & Plant and give Execute.

Page 35 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

Select the Order description line and Press F8 (Execute).

Page 36 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

Select OWN SPOOL REQUESTS from the Pull Down Menu and select the latest Spool and select the
printer to Print the Shop Floor Paper.

Page 37 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

The Production Order print can now be taken by the Production Supervisor and can move the same
along with the Material being provided from IS01.
Once the Production Order is printed the same cannot be printed as a New Print, it has to be printer as
a RE-PRINT and the Heading would show DUPLICATE for the Shop Floor personnels to understand
that it is a Duplicate Print of the prodcution Order.

Page 38 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

9. PRODUCTION ORDER CONFIRMATION CO11n


SAP ECC menu

Logistics Production Shop Floor Control


Confirmation Enter For Operation

Transaction code

CO11N

Page 39 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

As we would be Confirming the Order Operation Wise we can go for Time-Ticket Confirmation.

Enter the Order No. and the Operation which you want to confirm and Click on ACTUAL. DATA
to get the Existing Data which has come along with the Production Order. Here you
can now enter the ACTUAL Data which you have got through Production to be seen as the Variance
during the Production Order reporting.

Page 40 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

Also select on Confirmation Type, for the Qty is to be processed and the reservations to be cleared,
select Final Confirmation and Clear Open Reservations.

Page 41 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

Also you can click on Goods Movement

to enter the Actual material usage for

the Qty entered on the main confirmation screen.

Here you can see 2 Goods Movement i.e. Goods Issue and Goods Receipt to be happening in a Single
Confirmation command.
Thereafter click on SAVE.
Check for any System Messages which appear in the Status Bar.

Now the material has been posted to QA for Quality Inspection. The same can be checked in the Stock
Overview List of the FERT material.

Material qty. can be seen in Quality Inspection Stage.

Page 42 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

10. QUALITY INSPECTION QA32


SAP ECC menu

Logistics Quality Management Quality Inspection


Worklist Inspection Change Data

Transaction code

QA32

Page 43 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

First check the Stock Overview MD04 for the FERT material.

You can check the QM Lot being created.


The inspection of the components would be done in the QA Department and thereafter you can type in
the TCode QA32 for viewing the Inspection Lot which has been created in the QA.
In the Inspection Lot Enter Plant & Material whos Inspection Lot is to be checked.

Page 44 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

Select the Inspection Lot which is to be confirmed after Inspection and click on Usage Decision Box at
the top

Page 45 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

Select the Usage Code 04 GOODS RECEIPT FROM PRODUCTION ACCEPT and Give ENTER
and select on INSPECTION LOT STOCK

Here you can enter the Quantity which is OK, To Be Scrapped or to be moved to Block Storage.
For E.g.:
Total Qty.:

5 Nos.

Unrestricted Use:

3 Nos.

To Block Storage (Rework):

1 Nos.

To New Material (Scrap):

1 Nos.

Page 46 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

As the Scrap would be posted against a Pre-Defined Scrap material, say TEST-SCRAP, the Material
has to be selected against To New Material.

Page 47 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

Page 48 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

After the Usage Decision is Saved, selected Inspection Lot appears with a TICK mark on its left side
and a Lot No. is created which can be seen at the System Status bar.

Click on REFRESH button to see the QM Lot being cleared (not appearing anymore in the list).

Page 49 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

You can also check the Stock Overview for this FERT component whose inspection has been done.
The same can be done through Transaction Code MMBE.

Also you can see that the Qty has been reduced from Quality Inspection Stock and Qty. 3 nos. has
been moved to Un-Restricted Use and 1 Nos. in Blocked Storage.

Page 50 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

11. PRODUCTION ORDER SETTLEMENT KO88


SAP ECC menu

Logistics Production->Shop Floor Control->Period End


Closing ->Settlement-> Individual Processing

Transaction code

KO88

Page 51 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

On the: Initial Screen, make the following entries:


Field name

User action and values

Comment

Order

1000128

Example

Settlement period

10

Example

Fiscal year

2008

Example

Processing type

Automatic

Example

Deselect Test run & Select Check trans. Data. Click on Execute Button

Variance amount has been settled to the Price Difference account

Page 52 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

12. PRODUCTION ORDER TECO (Technically Complete) CO02


The production Order remains Open and Changeable until it is explicitly completed. In this context,
distinction is made between logistical and the accounting based completion.
TECO After the completion of the production order the order is no longer logistically relevant; that is, it
is marked as being no longer MRP relevant, and all the reservations for the components and capacity
requirements that may still exist are deleted. The production order is assigned the status TCMP, which
stands for Technically Completed (TECO). It is also now no longer possible to post any sots to the
production order. Moreover, it is no longer possible to trigger any confirmation for the production order.

SAP ECC menu

Logistics Production Shop Floor Control Order


Change

Transaction code

CO02

Page 53 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

After opening the order in Change Mode, from the pull down menu select, Functions->Restrict
Processing -> Technically Complete.
You can see now that the Order Status has now changed to TECO.

Page 54 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

13. CHECK PRODUCTION ORDER REPORTS


SAP ECC menu

Information systems General Report Selection


Production Planning Production Control

All the necessary reports for PRODUCTION PLANNING Module can be get from the above menu.

Page 55 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

13.1 PRODUCTION ORDER INFORMATION SYSTEM - COOIS


The order information system is a tool for shop floor control and process industries with reporting
functions for production orders, planned orders and process orders. Evaluations take place - as with the
IOC logical database, via the original order tables.

SAP ECC menu

Information systems General Report Selection


Production Planning Production Control Order
Information System

Transaction code

COOIS

On the Production Order Information System screen, make the necessary entries to run the report as
desired.

Page 56 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

You can view all the orders in the system, including the orders with deletion flags or deletion indicators.
Archived orders are not taken into account.
The order information system has the following display options:

In an individual object list, a list is generated for the selected object (for instance, order header,
operation, and component). You can define the structure and appearance of the individual
object list with a layout

On the object overview the individual orders are displayed with their subordinate objects in a
hierarchical structure. With an overall profile, you can define which fields are displayed and
which objects (order headers, items, sequences, and so on) are read or displayed. In addition,
you can define which fields are displayed for the individual objects

Page 57 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

Reports regarding SCRAP / REJECTION can also be seen through this report where in you need to
select CONFIRMATION as the header of the report.

Page 58 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

HEADER - ORDER WISE

HEADER - ITEMWISE

HEADER - DOCUMENTED GOODS MOVEMENT

HEADER - OPERATION WISE

Page 59 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

HEADER - COMPONENT WISE

HEADER - CONFIRMATION WISE

HEADER - AUTOMATIC GOODS MOVEMENT WISE

Page 60 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

13.2 CAPACITY PLANNING - STANDARD OVERVIEW CM01


You can use capacity evaluations to analyze capacity loads in your company. You can adjust the
analyses for each user according to the planning level, planning horizon and the area of responsibility.
Available capacities and capacity requirements can be selected according to various criteria and
cumulated using any period split you choose.
You can use work center hierarchies to cumulate the available capacities of production work centers
and their capacity requirements to superior planning work centers.

SAP ECC menu

Logistics Production Capacity Planning Evaluation


Work Center View Load

Transaction code

CM01

On the Capacity Planning: Selection screen, make the necessary entries to run the report as desired.

Page 61 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

In the capacity evaluation you can display the planned capacity requirements and the remaining
capacity requirements

Page 62 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

13.3 CAPACITY PLANNING - CAPACITY EVALUATION CM50


To Check all the Capacity Available for more than 1 Work Center.

SAP ECC menu

Logistics Production Shop Floor Control Information


System Capacity Evaluation Extended Evaluation
Work Center View

Transaction code

CM50

Page 63 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

On the Capacity Evaluation : Selection screen, make the necessary entries to run the report as desired.
Here you can get a complete capacity evaluation for more than 1 Work Center, i.e. a Range of Work
Centers can be inputted here.

Page 64 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

Likewise, all the selected range of work centers can be seen here.

Page 65 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

13.4 ORDER PROGRESS REPORT CO46


When you work with the order progress report, you can

Choose the individual objects in the report in a flexible manner

Adapt the contents and the presentation of the report (for example, include hierarchy levels
later)

Execute functions (for example, convert planned orders)


Go to object maintenance (for instance, Change production order)

SAP ECC menu

Logistics Production MRP Evaluations Order


Progress

Transaction code

CO46

A progress report can be displayed for more than one sales order or a WBS element. The requirement
elements and procurement elements are displayed.
If you want to display all objects for a sales order, enter the sales order with item number. By entering a
material or production order, you can further limit the number of objects displayed.
If you want to display objects from the Project System, you have to choose a network or a material. The
selected object (network or material) must be assigned to a WBS element. Depending on what you
have entered, a structure is displayed, from which you can select a network or material.

Page 66 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

Page 67 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

13.5 DISPLAYING PRODUCTION ORDER CONFIRMATION CO14


You use this to display the confirmations of production orders.

SAP ECC menu

Logistics Production Shop Floor Control


Confirmation Display

Transaction code

CO14

On the Display Production Order Confirmation: Initial screen, make the necessary entries to run the
report as desired.

If several confirmations exist, the system branches to an operation overview containing the
confirmations. Choose one or more confirmations. If you choose more than one confirmation then you
can switch between confirmations in the detail display. You can print the operation overview and define
a user-specific layout for it (column selection and sorting).
If only one confirmation exists, the system branches directly to the detail screen for the confirmation.

Page 68 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

13.6 CHECK PRODUCTION ORDER DELIVERY MB51


SAP ECC menu

Logistics Material Management Inventory


Management Environment List Displays Material
Documents

Transaction code

MB51

Page 69 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

After selecting MB51 Enter filtering criterias such as Material, Plant, Movement Type, etc.
Click on Execute.

st

2 highlighted in the Boxes displays the GR done 1 by Original Production Order and later through
Rework Production Order.

Page 70 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

13.7 CHECK RAW MATERIAL ISSUE MB51


SAP ECC menu

Logistics Material Management Inventory


Management Environment List Displays Material
Documents

Transaction code

MB51

Enter and Input the Filtering criterias. Here we input 261 and 262 Goods Movement for Issuing of Raw
material.

Page 71 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

Page 72 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

13.8 CHECK RAW MATERIAL RECEIPT MB51


SAP ECC menu

Logistics Material Management Inventory


Management Environment List Displays Material
Documents

Transaction code

MB51

Enter and Input the Filtering criterias. Here we input 101 and 102 Goods Movement for Issuing of Raw
material.

Page 73 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

This report would display the Total Receipt of Raw Material in the plant i.e. the Qty. which is being
procurred externally.
Note: Attached herewith is an Non-SBT example (as no live data is available at present in the System).

Page 74 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

13.9 MATERIAL USAGE ANALYSIS - MCRE


SAP ECC menu

Information Systems Logistics Production


Material Material Consumption

Transaction code

MCRE

Page 75 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

Enter the Plant and Production Order whose Material Consumption Analysis is to be done and click on
Execute.

Click on Sujan Barre Thomas and click on Switch Drill Down and select the Level at which you want to
analyze. Say you want to analyze at the Order Level, so select Order.

Here you can see the Total Requirement Qty (Planned Qty.) vs Withdrawal Qty. (Actual Consumption).

Page 76 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

13.10 ANALYZE PRODUCTION ORDER KKBC_ORD


Transaction code

KKBC_ORD

This will report based on Production as well as Accounting for a particular order.
Enter the Order No. which is to be analyzed.

You can also select

Layouts to select which type of Report you would like to see for that particular

order.

Page 77 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

Say you select the first layout, Target/Actual Comparison, now click on Execute.
Select on

to select the required fields.

Page 78 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

13.11 CHECKING FAILED GOODS MOVEMENT - COGI


SAP ECC menu

Logistics Production-Process Process Order


Environment Material Movement Failed Goods
Movement

Transaction code

COGI

You can check Errors in Goods Movement through COGI Transaction code.

Page 79 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

14. PRODUCTION ORDER THROUGH DEMAND MANAGEMENT


14.1 CREATE PLANNED INDEPENDENT REQUIREMENT MD61
As part of material requirements planning using the net change method, the planned independent
requirements are exploded across the entire BOM structure. As a result, the system also determines
dependent requirements for purchased parts and raw materials.

SAP ECC menu

Logistics Production Production Planning Demand


Management Planned Independent Requirement
Create

Transaction code

MD61

Page 80 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

On the Create Planned Independent Requirement: Initial Screen, enter the


following data:
Field name

Description

Comment

Planned Independent Requirements for


Material

Enter Material Code.

Finished Good MTS


(You have to select the
radio button)

Plant

Enter Plant Code.

Always Enter Production


Plant.

Select Verson
Number.

Always select Active


Version

From

From Date

To

To Date

Change system default


if necessary.

Selection parameters
Version
Planning horizon

Planning period

Select the appropriate


Planning Period

Page 81 of 118

The default planning


period is M (month).
You can change the
default value for this
field by changing the
user settings.

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

Check the Stock Requirement List for the same through MD04.

The Independent Requirement which is generated can be seen here in the RED box being highlighted.

Page 82 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

14.2 MRP AT PLANT LEVEL MD01


MD01 is used for running the MRP for specific plant or number of plants to maintain the scope of
planning. In the scope of planning you can maintain number of plants and can use the scope to run
MRP for maintained plants.
Usually this is followed when the First MRP is run at the time of first Run in Production Environment.
Thereafter MRP is run at Material Level i.e. MD02. So if you want to run MRP for all plant and material
in that case we use MD01

SAP ECC menu

Logistics Production MRP Planning Total


Planning Online

Transaction code

MD01

Page 83 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

Page 84 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

14.3 MRP AT MATERIAL LEVEL MD02


MD02 is used to run MRP for a particular Material. This run would be for just one material , single item ,
multi level ( will explode whole BOM for particular material )

SAP ECC menu

Logistics Production MRP Planning Total


Planning Single Item, Multi Level

Transaction code

MD02

Page 85 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

Enter the following details:


1. Enter Material Name
2. Enter Plant
3. Select Processing Key
Specifies the type of MRP run. The following types are possible:

net change planning: NETCH

net change planning in the planning horizon : NETPL

online regenerative planning : NEUPL

4. Create Planned Order / Purchase Requisitions (In case of BOP)


5. Delivery Schedules: Whether To Create or No
6. Create MRP List
7. Planning Mode & Scheduling
Above details are shown in the image above. ENTER to run the MRP.
An MRP List will be generated.

Page 86 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

Now the Planned Orders will be generated for this PIR.


Through MD04 you can select this Planned Order. Shown below.

Page 87 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

Select the Row of Planned Order, and Click on CONVERT TO PRODUCTION ORDER through this
Icon

Page 88 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

Clicking on this, will take you to the Production Order Screen.


Enter the following:
3. Quantity of Production
4. Basic Dates (As per the Scheduling Type)

Click on the following:


1. Material Availability Check

It would show that the Material is available or not, if not it would mention that the material is shortage
and material need to be made available at the required storage location.

Page 89 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

Click on the following:


2. Capacity Check

It would show whether the Capacity is Available or not.


Click on the Calculator on the Top Frame, to calculate the costs. Thereafter the system should
message as shown below.

Click on the Green Flag to RELEASE the Order.

Page 90 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

System would show that the Order has been released.


Now you can SAVE the production order and note the Production Order No.

Page 91 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

Refresh the Stock Requirement List (MD04) to see the Planned Order being now converted to status
Production Order (Shown in red box below).

Shop Floor Printing can be performed thereafter through Transaction Code: CO04N.

SAP ECC menu

Logistics Production Shop Floor Control Control


Print

Transaction code

CO04N

Page 92 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

14.4 PRODUCTION ORDER CONFN. WITH REWORK CO11n


SAP ECC menu

Logistics Production Shop Floor Control


Confirmation Enter For Operation

Transaction code

CO11N

Page 93 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

As we would be Confirming the Order Operation Wise we can go for Time-Ticket Confirmation.

Enter the Order No. and the Operation which you want to confirm and Click on ACTUAL. DATA
to get the Existing Data which has come along with the Production Order. Here you
can now enter the ACTUAL Data which you have got through Production to be seen as the Variance
during the Production Order reporting.
As we would be doing REWORK activity in this Production Order, we can first check the Stock for the
part across the plant through T Code MMBE.

Page 94 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

On confirmation screen let us consider 200 as Yield Qty. and 100 as Qty. which is to be REWORKED.

Save the Confirmation


Check for any System Messages which appear in the Status Bar.

Now the material Qty. 200 has been posted to QA for Quality Inspection. The same can be checked in
the Stock Overview List of the FERT material.

Page 95 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

You can go back to CO02 for Production Order No. 100123 to see the status of the Qty.

Here you can see that out of the Total Qty. Delvrd is 200 and 100 is reworked which can be seen
through Operation Overview at the extreme Right End.

Page 96 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

14.5 PRODUCTION ORDER CREATION REWORK CO07


SAP ECC menu

Logistics Production Shop Floor Control Order


Create Without Material

Transaction code

CO07

PRE-REQUISITIES:
For Rework Order Following Pre-Requisites have to be followed.
1. A separate Rework Order has to be Created without Reference to any Material.
2. Goods Receipt for a Rework Order has to be done manually.

Page 97 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

Production Order Initial Screen will appear. Here enter Production Plant & Order Type for that Rework
Order.

GENERAL TAB
Thereafter on the Header Screen, Enter the following:
1. Material Description
2. Total Qty. to be reworked and Its Unit of Measurement
3. Basic Dates

Page 98 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

After giving ENTER it would give a Dialogue Box.

Here select on GENERATE OPERATION.


On the next Screen, i.e. Main Settlement Rule: Overview enter the following:
1. Category: ORD (i.e. to be settled against a Production Order)
2. Settlement Receiver: Production Order No. (In this case it is 1000123) & give ENTER.
Here it will now show the relevant details.

Go Back now.

Page 99 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

ASSIGNMENT TAB

Enter MRP Controller

Enter Profit Center

GOODS RECEIPT

Control Data: Stock Type ; X Quality Inspection

Thereafter Click on Operation Overview Icon


Select the following:

Work Center on which the rework is taking place

Control Key: PP07 (For Rework Production)

Can also enter the Operation Description and give ENTER.

Thereafter Click on Component Overview

to enter the components to be processed.

Enter the Component to be reworked.

Enter the Quantity (can be calculated through CS11 for total requirement as per the rework
quantity).

After entering the details and giving ENTER it would ask for the Operation Assignment, i.e. the
component is to be assigned to which Operation. Select the operation and give Enter. Also
check for the Storage Location i.e. from where the Material will be issued, which should be
IS01 in our case.

Go back now.

Like a Normal Production, Check for Material Availability, Capacity Availability, Pre-Cost it and then
Release the Rework (Production) Order and Save it and note the Rework Production Order No.

Page 100 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

14.6 REWORK PRODUCTION ORDER CONFIRMATION CO11n


SAP ECC menu

Logistics Production Shop Floor Control


Confirmation Enter For Operation

Transaction code

CO11N

Page 101 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

As we would be Confirming the Order Operation Wise we can go for Time-Ticket Confirmation.

Enter the Order No. and the Operation which you want to confirm and Click on ACTUAL. DATA
to get the Existing Data which has come along with the Production Order. Here you
need to enter the ACTUAL Data which you have got through Production as the same will not be copied.

Page 102 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

Check for any System Messages which appear in the Status Bar.

Now the material has been posted to QA for Quality Inspection. GR for the order needs to be done
manually.

Page 103 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

14.7 GOODS RECEIPT OF REWORK ORDER MB31


SAP ECC menu

Logistics Production Shop Floor Control Goods


Movement Goods Receipt

Transaction code

MB31

NOTE: Goods Receipt for a REWORK Order has to be done manually. Auto GR is not possible.
Now, here enter the following:

Movement Type: 101

Order No. would be the parent Production Order, 1000123

Plant : 100

Storage Location : FG01

Page 104 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

After entering select the item No.1

Click on

And SAVE. You can see the Document No.

Page 105 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

You can go back to the Order 1000123 and see that all the 300 Nos. have been delivered.

Components are now posted to QA, which can be checked through MMBE

Hereafter the QA Cycle can be followed Index Point No. 11 to clear the Production Order.

Page 106 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

15. MRP FOR PLANNED ORDER + PURCHASE REQUISITION


So far we have seen MRP being run to generate PLANNED ORDER further to generate Production
Order to be run in Production environment. Now here we would see the MRP to be run to generate
Planned order as well as Purchase Requisition by a Single MRP Run through MD02.
MD02 is used to run MRP for a particular Material. This run would be for just one material , single item ,
multi level ( will explode whole BOM for particular material ).

SAP ECC menu

Logistics Production MRP Planning Total


Planning Single Item, Multi Level

Transaction code

MD02

Page 107 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

Here we take another Material as an Example.


FERT Material: TEST-FG12
Requirement in MD61 : 35 Qty.

First we check the existing Stock for TEST-FG12 through MD04.

Page 108 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

Enter the following details:


1. Enter Material Name
2. Enter Plant
3. Select Processing Key
Specifies the type of MRP run. The following types are possible:

net change planning: NETCH

net change planning in the planning horizon : NETPL

online regenerative planning : NEUPL

4. Create Planned Order / Purchase Requisitions (In case of BOP)


5. Delivery Schedules: Whether To Create or No
6. Create MRP List
7. Planning Mode & Scheduling
Above details are shown in the image above. ENTER to run the MRP.
An MRP List will be now generated.

Page 109 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

Now we go back to MD04 to check the Stock.

We can see that NO STOCK is available to Manufacture the FERT, shown as 0 in Available Qty. in
BLUE colour.
Click on the Eye Glass to get the new Dialogue Box.

Now click on

to see the Order Report.

Page 110 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

Here you can see the Components which are contained in that FERT. And can Browse through, by
Double Clicking on the components to check the availability and the List below will show the latest
Stock position for that particular component.
Say we Click on IT-ROH03 (ROH material, whose Purchase Requisition is to be created).

Page 111 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

Here the one shown in RED Box, is the Planned Order which can be converted to Purchase
Requisition.
Click on Eye Glass.

Click on PUR. REQ. in the new dialogue Box. It will take you to Convert Planned order to Purchase
Requisition : Details Screen.
Here you can related information details such as, Storage Location (say ST01) and SAVE it. You will
get a Confirmation Message.

Page 112 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

REFRESH the list. Now you can see the List has been updated as shown in the RED BOXES below.

Further more, a PURCHASE ORDER can be created through PURCHASE REQUISITION. If release
Strategy has been set for Purchase Requisitions, the PR needs to be released before it is converted to
Purchase Order. This activity would be done by Purchase Dept. personnel.

Page 113 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

16. CO-PRODUCT SCENARIO


Products that are usually manufactured together can be produced using one production order.
The main product is the primary reason for the production process. It is displayed in the production
order header. The system also creates a separate order item for the main product.
A co-product is a product that is produced in conjunction with other products. The system creates a
separate order item in the production order for each co-product. As a result, it is possible to display
actual costs at co-product level.
Creating a production order to manufacture co-products has the following advantages:

Main product and co-product(s) are settled to different receivers

Goods movements can be posted simultaneously for all products manufactured in the order.

Pre-Requisities
The following prerequisites must be fulfilled if you want to create a production order with co-products or
by-products.
Prerequisite for the main product:
The indicator Co-product must be activated in the material master of the main product (MRP area)
Prerequisites for a co-product:

The indicator Co-product must be activated in the material master of the co-product (MRP area)

The co-product must be listed as an item in the bill of material of the main product with a
negative value.

On the Basic data tab page of the BOM item, the indicator Co-product must be activated in the
field group General data.

Example:
Say we have a Family Mould with 2 Family Components viz
1. TEST-COP01
2. TEST-COP02
Now say we want to take the Production of these 2 Family FERTs.

Page 114 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

Say we consider the Header / Main Product is TEST-COP01 we create a Production Order for this
Header Material.
BOM For TEST-COP01 would be as seen below.

Highlighted in Red is the Famiyl Component with ve (negative) Quantity.


When we check the Production Order it would show it as follows.

NOTE: GR for such an Order for a Co-Product scenario has to be done MANUALLY by MB31.
Also, whatever the Rejection / Scrap which is going to get posted will be of the Main Product whose
Production Order is being made.

Page 115 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

To Summarize:
1. A co-product is a product that is produced in conjunction with other products. The system
creates a separate order item in the production order for each co-product. As a result, it is
possible to display actual costs at co-product level.
2. The main product is the primary reason for the production process. It is displayed in the
production order header. The system also creates a separate order item for the main product.
3. The indicator Co-product must be activated in the material master of the main product (MRP 2)
as well as the Co-Product.
4. The co-product must be listed as an item in the bill of material of the main product with negative
Qty.
5. On the Basic data tab page of the BOM item, the indicator Co-product must be activated in the
field group General data.

6. Production Order would be of the Main Product, hence also the Confirmation and scrapping
would be of the Main Product Only.
7. Production Qty mentioned in the Production Order, say Qty. 10 means 10 Qty. of Co-Product 1,
and 10 Qty. of Co-Product 2.
8. Raw Material qty. to be issued would be the qty. required to product both the co-products.
9. In Production Order you need to maintain the settlement Rule in pull down menu i.e. Header ->
Settlement Rule
10. You cannot post Auto-GR for Co-Products. You have to follow Manual GR by MB31 101 Movt.
11. If you want to scrap co-product do the following steps.

Confirm all the qty as yield qty in . ( ok + scrap)

Do goods receipt for main product & co-product (total qty).

Physically you know the how much rejected qty. Move that qty from accepted str
location to rejection str location by using MB1B 311 mvt.

Now yield qty will reduce.

Check in MB51 with mvt type 311 with corresponding period, you came to know how
much quantities are rejected.

By 551 mvt materials scrap that rejected qty.

12. But if you want the Sell the scrap, then follow the following steps:
a. Confirm all the qty as yield qty ( ok + scrap)
b. Do goods receipt for main product & co-product (total qty).
c.

Scrap the Material to a Scrap material, say SCRAP-MATERIAL through QA32 (QM).

Page 116 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

Suppose you have a Co-Product scenario for LH & RH of a particular FERT.


In this case you want to run only a few nos. of Cavity of RH keeping the nos. of cavities of LH running
as it is. In that case follow the below mentioned procedure.
Most important of all you need to maintain the Base Qty. relation of the 2 co-products.
Say for 4 Components of LH you want only 2 Components of RH. Here you need to maintain in BOM of
LH the following:

Select the Co-product with negative value (i.e. RH) and double click on Item No. to enter detail
information

Page 117 of 118

Organization
Project

Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane


VISION

Document

END USER MANUAL

Module

Production Planning (PP)

Version
No.

After entering, on the Basic Data Screen, maintain the negative Qty. as 0.50

Now you can go ahead and create the production order.

Now you will get only 2 Components of RH for 4 components of LH. Shown is the Production
Order.

One important thing to remember here is that the Cost apportionment is to be maintained
accordingly in Settlement rule.

Page 118 of 118