International Journal of Software Engineering & Applications (IJSEA), Vol.3, No.

1, January 2012

PEOPLE FACTORS IN AGILE SOFTWARE


DEVELOPMENT AND PROJECT MANAGEMENT

Vikash Lalsing1, Somveer Kishnah2 and Sameerchand Pudaruth3


1
TNT Express ICS Mauritius, Ebene Cybercity, Rose Hill
vikash.lalsing@gmail.com
2
Department of Computer Science Engineering, University of Mauritius, Reduit, Moka
s.kishnah@uom.ac.mu, s.pudaruth@uom.ac.mu

ABSTRACT
With the increasing popularity of Agile Methods, many software organisations are moving away from
traditional methods to adopt Agile development methodologies. Instead of being predictive, Agile is
rather adaptive and people-focussed. It advocates a small and collaborative team that work closely
together. But team size is a factor that is in turn constrained by people factors. When implementing
Agile, these key factors are often overlooked. This study aims at identifying the underlying people
factors to consider when adopting Agile for a team to be effective. The method used is the study of
three different sized Agile teams developing products based on the same technologies and using Scrum.
Both objective and subjective measures were used and the results are supported by a survey. The
results clearly show that for agile methodologies to work well, it is crucial to select the right people for
the right team.

KEYWORDS
Agile Methodology, Scrum, Agile Teams, Software Development, Project Management

1. INTRODUCTION
Agile project management is a conceptual framework in software engineering where software is
built within a relatively short period of time and has several iterations which yield stable release
of software (Hariyadi, 2011). According to the Agile Manifesto (2011), Agile is based on a set
of principles that focus on customer value, iterative and incremental delivery, intense
collaboration, small integrated teams, self-organization and small and continuous
improvements. It is often stated that Agile Management works best with small teams.
According to Bustamante and Sawhney (2011), the ideal Agile project team is small, co-
located, communicate face to face on a daily basis and has an ideal team size not exceeding nine
people. Along with this, Agile methods such as Scrum recommend an optimal team size of
seven plus or minus two. However some industry specialists claim that Agile is a one size fits
all methodology and that it can be scaled up to a 150 person team. In general Agile
Management is faced with one key challenge:

What is the optimal team size to which Agile should be applied for the team to be effective?

DOI : 10.5121/ijsea.2012.3109 117


International Journal of Software Engineering & Applications (IJSEA), Vol.3, No.1, January 2012

Since Agile is very people focussed, there is a further need to understand how team size
affects individual behaviour and productivity within an Agile team. This gives rise to another
challenge:

What people factors should be considered when managing an Agile team to make it
effective?

This paper analyses an Agile project management methodology, pilot it in practice with real life
projects and aims at identifying the people factors to be considered for an Agile team to be
effective. This study takes into consideration to some extent a few psychological factors that can
affect team collaboration such as working memory, optimal experience and recommended team
size based on social behaviours. To achieve this, three sample Agile teams of different size will
be used and managed with the same Agile principles. The results will help determine which
team, given that they all have all the necessary skills sets and similar team member profiles, will
work best and produce the most optimal results. Agile recommends that, instead of having only
developers, Agile teams should have all the required skills sets.

Although some Agile methodologies such as Scrum do have a recommended team size, it is a
widely believed that Agile is a concept of one size fits all and is therefore scalable. But the
question then arises, how big is too much for an Agile team before it starts to lose its
efficiency? In a research performed by Ancona and Caldwells (1992), the results indicated
that team size may have a direct impact on group performance and communication. Agile
Management is very people focus whereas Software Project Management is a rather technical
discipline. Project Managers moving from traditional to Agile Methods often spend more time
managing projects rather than managing the people working on the projects. This implies that
people factors are often not considered when managing Agile teams and they may not be
performing at their optimal level.

In spite of the growing popularity of Agile Management (Agile Manifesto, 2011) the rate at
which software projects are failing is still alarming. According to the Standish 2009 Chaos
Report (Standish, 2009), the average success rate is of all IT projects is 32%, 44% were
challenged and the failure rate is 24%. The project success rate has decreased from previous
years with only 32% being successful, whereby these were delivered on time, to budget and
with all required functionalities. 44% of the projects were challenged which means that either
they were delivered late, over budget, and/or with less functionalities that were initially
intended. The remaining 24% of IT projects failed and had to be cancelled prior to completion
and were never used.

Furthermore, according to Scott W. Ambler (2010a), the success rates for Agile projects are
60% are successful, 28% are challenged, and 12% are failures. The success rate for Agile
projects is 83% for small teams (less than eleven people), 70% for medium-sized teams
(between eleven and twenty-five people), and 55% for large teams (more than twenty-five
people). Based from these figures it is clear that Agile team size has a direct incidence on the
success rate of the project.

The motivation for this paper is to provide an overview of the people factors that are often
ignored when using agile for setting-up of software development teams. Further to this finding,
an insight is provided into the size of an optimal collocated agile team. In section 2, related agile
management ideas are discussed. The research method is discussed in section 3. Results and

118
International Journal of Software Engineering & Applications (IJSEA), Vol.3, No.1, January 2012

discussion from the study are included in sections 4. Section 5 presents a conclusion and an
outline for future work.

2. LITERATURE REVIEW
This chapter analyses existing research and studies performed on Agile development teams.

2.1. Agile and People Management

People and team management are based on various models such as The five dysfunctions
(Lencioni, 2001) and Tuckmans model (Tuckman, 1965). All of these models require that team
members have a lot of interaction. The more persons there is on a team, the more interaction is
required and the more difficult it is to manage such teams. In an Agile team, the project
manager must define the relationships between the roles to enable the effective coordination and
control of the project. The following rules should be applied when defining organisational
structures:

Ensure that each member of the team reports to one and only one person (the unity of
command principle)

Ensure that each person has no more than seven people reporting directly to him or her (the
rule of seven principle) (Fayol, 1917).

However, individuals with different personalities are often expected to work together as a
cohesive team. Team efficiency is often dependent on the interaction between team members
and the coordination of the team leader. According to studies, team efficiency is at its peak
when team size is of 3 to 7 and it starts to decrease when team size goes beyond 9 members
(Abilla, 2006). Agile teams also work best in a common workspace or war room, which
enable team members to work in a shared environment. This approach facilitates
communication and collaboration and has proved to an effective mean of increasing team
productivity.

In a software project the objective is to deliver a project on time, to budget and within the
agreed quality level. Therefore software project managers have the responsibility for the success
of projects. Managers should be skilled leaders and good at organising problem-solving sessions
that enable maximizing collaboration across departments (Johnson, 2008).

AGILE like many methods ... look great on paper but fail to work in reality because they forget
the human factor. Any paradigm, which has human interaction at its heart, will fail if human
psychology is not understood and taken into account. The key aspects of human nature which IT
development/project management methods have to take into account are no different to those at
the heart of most modern economic theories, (Brady, 2006):

People will always put their own interests ahead of the interests of the group

People are self-interested

Commercial production decisions are based on rational expectations

119
International Journal of Software Engineering & Applications (IJSEA), Vol.3, No.1, January 2012

Karl Poppers First law of collective action. You can never get more than 5 people to
agree on anything.

Cognitive studies tend to explain the state of mind of team members working in a collaborative
environment. This is addressed by the Theory of Flow (Cskszentmihlyi, 1990). Flow (Optimal
Experience), is the rational state in which a person in an activity is totally absorbed, totally
focus, have full engrossment, and eventually acquires success in the process. The state of flow
is attained when a person has both higher than above challenge and skills in a specific activity.
Not only Flow is important to individuals but it can also contribute to team efficiency and
organizational goals. Flow generally leads to higher productivity, innovation, and employee
development (Csikszentmihalyi, 1990). While it is not readily feasible to identify the state of
mind of employees within an Agile team, a psychological evaluation may be required in order
to determine how to achieve the optimal experience for individuals in an Agile team.

Alan Baddeley represented the model of working memory and clearly demonstrated how the
short-term memory works (Baddeley and Sala, 1996). He stipulates that the mind processes
different types of information in different ways. The human mind is limited in its capacity to
retain short term information and this can have an impact on an individuals performance in an
Agile team whereby work progressed is continuously changing and in short periods of time.

One of the root causes of failure in projects is communication either a lack thereof, or
miscommunication. Large teams are inherently vehicles for bad communication. This is based
on the number of communication channels which grow geometrically, not linearly (Abilla,
2006). A three member team has three communication channels and a five member team has
ten, twice the number of persons. However a six member team has as much as fifteen
communication channels. This can be represented as below:

Figure 1. Overview of communication channel complexity (N x (N - 1) / 2)

Therefore the more persons there is on a team the more difficult it is to communicate and share
information among team members. Thus team size affects both efficiency and productivity of
teams directly. For Agile to work best each team member should have visibility of what the
team is doing. Given that the human mind has such limitations as discussed above then Agile
may probably work best with a small team size consisting of highly motivated individuals.
Staffs have a sense of belonging towards the company or the team if there is group project and
social events and well-being. Recognition and appreciation of work, promotion and job
designation is the achievement of esteem needs. Knowing that people achieve best when they
reach the esteem and self actualization level, Agile Management may need to focus a lot on
ensuring that team members reach that level of satisfaction within the team.

In a research performed by Elizabeth Whitworth (Whitworth, 2006), she tackled the


psychological aspect of Agile development team members to determine their state when
working in an Agile team. The outcomes of this study showed that Agile practices bring a
certain level of motivation to individuals that make them tend to collaborate more compared
120
International Journal of Software Engineering & Applications (IJSEA), Vol.3, No.1, January 2012

to traditional methods. This creates cohesion between Agile team members and has a positive
impact on both personal and team productivity. The author does not go into detail to
understand the motivation and cohesion of Agile team members based on the team size in
which they have worked. This can be a key differentiator to determine the level of satisfaction
and motivation one has when working in different team sizes.

In a study performed by Sudhakar et al. in 2011, it was found that there are several soft factors
that can affect the performance of team members in a software development team. It is stated
that there are four categories of factors that affect the performance of a development team:
technical, non-technical, organizational and environmental.

The authors proposed the following soft factors that can affect software team performance:

Team climate: shared perceptions and objectives to achieve organisational goals.

Team diversity: The variation of team member skills, levels of experience,


qualifications, gender and race for instance.

Team innovation: new approaches to problem solving and value added skills.

Team member competencies and characteristics: Technical and personal competencies


of people on team that impact familiarity and collaboration.

Team leader behaviour: Less micro-management approach and more people


management and a facilitator role.

Top management support: Commitment from management to the project

From this study, two key factors were found to be the most influential on software team
performance, namely: trust and effective communication. The study is generalised and fails to
identify the relationship between the project management methodologies used with these soft
factors. It may be that different people factors influence the success of an Agile team.

Shane Hastie (2004) discusses how Agile differs from traditional methods by putting much
more emphasis on team work, cooperation and self organisation. One of the key to the success
of Agile is trust, which needs to be present both between the leader and the team and among the
team members themselves.

The paper does give a good insight on the factors that may influence the productivity of Agile
teams. However the factors were not investigated with relation to team size and did not make
adequate consideration on how this could influence people factors in an Agile team. As seen
from previous studies, team size can be a key factor to the success of a software project. It can
also influence individuals behaviour and possibly give rise to other soft factors that may need
consideration.

In a paper by Turner and Boehm in 2003, they tend to examine the people factors that influence
both Agile and Plan Based methods. It has been proven that people factors are the most critical
success factors for development teams. There is enough evidence from previous research in
psychology of software teams that suggest that people factors have a direct influence on the cost

121
International Journal of Software Engineering & Applications (IJSEA), Vol.3, No.1, January 2012

and quality of software. In a software project, the key areas which are impacted by people
factors are:

Staffing: The right persons should be selected to work for the development of a software
project. In broad terms, it means that the customer should be represented by skilled staffs
who are collaborative, representative, authorized, committed, and knowledgeable (CRACK)
(Turner and Boehm, 2003). The characteristics of developers within an Agile team should
include amicability, talent, skill, and communication.

Culture: Agile requires a true cultural change from plan based approach, not only a simple
change in the processes used.

Values: One of the most neglected challenges in software development is the consolidation
and value of requirements from all stakeholders involved.

Communication: Agile requires more frequent and intense communication, the more
persons on a team the more challenging and problematic it becomes to communicate
effectively.

Managing Expectations: Software development teams often fail to manage expectations and
this can cause issues between the teams and the customer.

Whilst the paper covers the major areas impacted by people factors in a development team and
even mention communication complexity and impact of team size, the authors do not explore
the ideal team size that can affect the effectiveness of an Agile team. There is also limited
reference to the actual people factors that should be considered within Agile but more on the
areas impacted.

In a study published in 2011 (Conboy et al., 2011) it was found that the increasing use of Agile
approaches and growing pressure to adopt Agile Management, contribute to the need for human
resource departments and project managers to address people challenges. There is a need to
identify the problems that the Agile transition may cause. A list of the most important people
challenges in Agile was proposed as follows: developer fear caused by transparency of skill
deficiencies, the need for developers to be a master of all trades, increased reliance on social
skills, a lack of business knowledge among developers, the need to understand and learn values
and principles of Agile, not just the practices, lack of developer motivation to use Agile
methods and the need for Agile compliant performance evaluation.

There is one questionable issue though; the need for an agile developer to be multi skilled is
relative. Although Agile recommends that the team should have all the skill sets required to
execute the project, it does not necessary mean that each single team member should have this
flexibility. This is subject to interpretation and instead, an Agile team can consist of different
roles that provide the skill completeness that Agile advocates.

122
International Journal of Software Engineering & Applications (IJSEA), Vol.3, No.1, January 2012

3. PROPOSED METHODOLOGY
The following chapter focuses on the methodology used to identify the people factors that can
affect an Agile teams performance.

3.1 Company background

This study has been made with the development teams of an organisation that specialises in
transportation and freight services. The organisation is a major player in Europe and is fully
operational across the Middle East, Asia, South America and Australia. The IT department of
the organisation exist for well over 30 years and has reached a sound level of maturity in the
software industry. It has been using several development methodologies including a fully
customised Rational Unified Process and recently moved to Agile Methodology using Scrum.
The software development teams are based in Mauritius with the head office located in the
United Kingdom.

3.2 Study of Agile Teams


This study has been performed using three different sized projects using Agile Methodology
over a period of six months. Not all the projects have taken the full six months for completion;
as some have been completed within a shorter timeframe. Completion is considered as the phase
at which the project is successfully deployed into production and signed off by the customer.
Based on the subject matter of this study and to increase the rate of accuracy, no other
parameters apart from the project size and team size were drastically different. All three agile
teams had the same roles, skill sets and using the same Agile processes i.e.: Scrum. For
confidentiality purposes, the projects used will be referred to as A, B and C within this study.

3.2.1 Project size

The projects were initially estimated as follows:

Table 1. Overview of Project Size.

Project Initial Estimate MD


Project A 1800 (8.2 man yrs)

Project B 800 (3.6 man yrs)


Project C 120 (0.5 man yrs)

3.2.2 Architecture and Level of complexity

Table 2 below outlines the technologies used and the level of complexity for each project which
has been evaluated as per the organisation standards.

123
International Journal of Software Engineering & Applications (IJSEA), Vol.3, No.1, January 2012

Table 2. Overview of technologies and complexity.

Project Language/Technology Complexity


A Java Services, WebSphere Portal, Oracle, Spring MVC, Free-Marker High
B Java Services, WebSphere Portal, Oracle Database, Spring MVC High
C Java Services, WebSphere Portal, Oracle Database, Spring MVC, Free- High
Marker

All three projects used for this study have the same architecture, similar complexity but
different scale. The applications have been developed using WebSphere Portal technology for
the User Interface and Java back-end services which in turn talk to Domain objects and Oracle
database.

3.2.3 Team Profile and Structure

Each team is lead by a Project Leader and the whole project is owned by a Project Manager.
The table below gives an overview of the various roles that were allocated within each team:

Table 3. Overview of Project Teams.

Project Business Analyst Test Analyst Technical Total


Analyst Programmer Architect
A 2 12 6 2 22
B 1 7 3 1 12
C 1 2 1 1 5

3.2.4 Method of Measurement

A project outcome can be measured using both objective and subjective measures (Kemerer,
1989; Bahli and Buyukkurt, 2005; Ong et al., 2005). A teams performance can be measured
by evaluating whether the output produced is on schedule and on budget (Boehm, 1981). This
includes measuring the quality of software produced and compliance to schedules and budget
(Huckman et al., 2009). Quality of software can be measured using number of defects found
in testing (Boehm, 1981). For the purpose of this study, the objective measures used are
metrics based whereas the subjective measures are based on a team survey and management
observations. The following metrics were measured for each team.

Budget

The budget for each project is allocated by the Project Board. This committee approves the
budget based on the business value of the project and the estimates as provided by the
respective Project Manager. Actual budget spend is calculated based on two measures: amount
of work time logged in JIRA against each tasks and the amount of time logged in Clarity, the
organisation time sheet system.

124
International Journal of Software Engineering & Applications (IJSEA), Vol.3, No.1, January 2012

On Time Delivery

Project planning is performed on JIRA and it provides a road map with different releases and
their planned release dates. The actual release dates are updated whenever the release goes out
to the consumer. At the end of the project, any release deadlines that are not achieved can
easily be tracked on JIRA.

Defects

Defects are categorised as non fulfilment of requirements as per defined documentation or


undesired functionality due to coding error. Defects can have four types of severity:

Critical: Resulting in a total loss of the functionality of the system or a partial loss in a key
area of the system that makes the software unusable or unstable.

Major: Resulting in a core requirement not being fulfilled and impact a main functional
flow or process. Often causes data discrepancy and failure of several alternative flows.

Blocker: A coding error or a pending change based on requirements that impacts the
alternate flows of a requirement and prevents the usage of a particular functionality which is
regarded as low impact.

Minor: A negligible defect that can pertain to graphical user interface, basic validation with
non-breaking effect.

Rework Level

Rework is calculated as the actual man-days spent on a project to fix defects that have been
raised by system or integration testing. This figure is then divided by the budget actual to
determine the percentage of rework:

Time spent fixing defect


Rework Level = X 100
Time spent on the development

JIRA is used as the tool to track defects and time spent fixing a defect. This provides the data
to calculate rework level.

Defect Rate

Defect rate is based on the number of defects detected on a software over the total amount of
actual time spent on the development of the software. For instance:
Number of days spent on a project : 100 man-days
Total number of defects found on the project : 150
Defect rate of the team : 1.5
So for every day of work produced, approximately 1.5 defects are introduced.

125
International Journal of Software Engineering & Applications (IJSEA), Vol.3, No.1, January 2012

Release and Change Management

In a team where the number of issues fixed or functionalities being developed on a daily basis
are high, nightly builds help in identifying any potential issues with the code as early as
possible so that a stable release is made available to the test team as the end of each sprint.
This has been the case mostly for Project B whereby a high number of defects were raised by
test team and needed to be fixed as soon as possible. Table 4 provides an overview of the
release frequency for each project as well that the frequency for testing cycles and the types of
testing that were done.

Table 4. Release Frequency.

Project Sprint Length Release Frequency/Test Cycles


A 1 Week At the end of each Sprint System Testing

Every month Integration Testing


B 2 Weeks Every Day Automation testing

At the end of each Sprint System and Integration Testing


C 2 Weeks At the end of each Sprint System Testing

At project completion Integration Testing

Changes in each project are managed through the organisation change process which consists of
the following stages:

Initiation Changes are documented and raised by the Business Analysts and created on
JIRA

Analysis and estimation This stage involves the approval from Technical Architect for the
change to be performed from an architecture perspective. Changes are then reviewed by the
development team with the risks and impact assessed and estimates are produced.

Approval Business Analyst and Project Manager approve both budget and planning on the
change

Implementation and delivery Changes are planned in the appropriate Sprints and delivered
as per agreed timelines and budget spends. Whenever changes are approved and
implemented, the estimated costs are added to the overall estimate of the project.

Questionnaire Design

For the purpose of this study, a questionnaire has been designed to receive feedback in three
key areas, namely Management, People and Product. A copy is attached in Appendix A.
126
International Journal of Software Engineering & Applications (IJSEA), Vol.3, No.1, January 2012

Section A Agile Management. This section consists of five questions and aims at
understanding how the team members felt about the way their respective projects were
run from an Agile Management perspective.

Section B Team Work. This section of the questionnaire will help understand the
mindset of the team members and motivation. It will also help in identifying some key
people factors that have been mentioned in the previous research.

Section C Product. The questions in this section are aimed to understand the level of
challenge that the individual has to face in the project and overall perception of the end
product to gauge the satisfaction level.

Each team members will be required to fill in the questionnaire at the end of the project and
the data will be collected on a per project basis.

4. RESULTS AND DISCUSSION


It should be noted that the results that came out of this research should not be considered as
wide practice or as a standard across the software industry. However they do provide an insight
of what is the best option for an Agile team size and the factors that need to be considered.

4.1 Budget

The budget spent for each projects were collated following their completion from tools such as
JIRA and Clarity. The results are as follows:

Table 5. Budget.

Project Initial estimate (MD) Budget spend (MD) % Deviation

Project A 1800 (8.2 man yrs) 3200 (14.1 man yrs) 66

Project B 800 (3.6 man yrs) 950 (4.3 man yrs) 18

Project C 120 (0.5 man yrs) 130 (0.6 man yrs) 8

As seen in the table above, the over spend has been largest in Project A with a deviation of
over 65%. This has been mainly attributed to the following factors:

Team Communication and Collaboration: There was little interaction between the two
Agile sub-teams at the start of the project partly due to lack of familiarity between the
team members. This has caused several dependant functionalities not properly developed.
There was lack of clear communication of requirements and queries raised by the
Mauritius team were not being answered in a timely manner by the UK team. This did not
allow good relationship to be developed between both agile sub teams early in the project
life cycle. The issue was partially resolved by having each member of the Mauritius team
travelling to the UK office to work alongside the on-shore Agile team for a given amount
of time that ranged from four to six weeks. The collaboration and communication
gradually increased but much time was spent fixing issues that were already raised during
127
International Journal of Software Engineering & Applications (IJSEA), Vol.3, No.1, January 2012

the early stage of the project. This had a significant impact on the project budget as not
only time was required to fix unexpected issues but also to ensure proper integration after
these fixes were made.

Trust: It was observed that there were trust issues amongst team members. In some
situations, individuals would not allocate tasks to others on the basis that they did not
think the other person could complete the work in an effective manner and on time and
hence took up these tasks themselves. This has caused delays on certain areas.

Team Interaction: Each sub team had to hold its own daily meeting and pass any
information relevant to the other team through the project leaders. However the
coordination between the two teams was not always easy. It was not very practical to hold
the daily Scrum meetings. More than often about an hour was spent in the daily updates.
Some members who had already provided their updates for the day were keen to leave the
meeting to be able to continue working on their assigned tasks. They did not think that
they the information being discussed was relevant to them and felt that they were being
unproductive.

Code Integration: There have been a large number of code integration issues between the
two Agile sub teams that caused a lot of rework to make the integration of components
work as expected. Each team were performing their own daily Scrums and aiming at
completing tasks assigned to their respective team. However there was little visibility on
what the other teams was doing, mainly because there was not enough time for team
members to dig into the tasks assigned to the other team. There were simply too many
tasks for a team to look into the other teams work basket. A lot of functionalities were not
in synched, for instance components did not match the expected behaviour due to
developers making changes in their component without proper evaluation of impact on its
dependencies or did not remember communicating the changes to everyone or even did
not communicate information to people who they do not get along that well.

Last minute defects: Integration issues were often uncovered at the last minute when
performing a release as both sub Agile teams would start integrating their work as least
one day before a planned release date. This was performed on a weekly basis and a
release made to system testing team. However since the issues were uncovered late, this
caused a lot of rework and quite a number of releases got delayed.

Defect Rate: The fact that a lot of functionalities were being delivered on a weekly basis
meant that continuous testing had to be performed. This in turn gave rise to a significant
amount of defects to be raised and require fixing. The impact was that rework level
increased and impacted on the budget.

Requirements Clarification: The velocity at which the teams were working was quite
high. However Business Analysts were unable to provide clarifications on time for
queries that were raised to them. There were too many queries raised and many people
raising them. The turnaround time eventually impacted the time to fix issues and delay
releases. Even though clarifications were obtained, they were not systematically passed on
to the other members of the team mainly because developers would often forget to include
everyone in their communication or they would think that the information would not be
relevant to fellow colleagues.

128
International Journal of Software Engineering & Applications (IJSEA), Vol.3, No.1, January 2012

Management views on Project A are that is was difficult to manage the team using Agile
approach and there were many instances where team members focussed mainly on their own
deliverable rather than team output and forgot to pass information to everyone.

Project B was 18% over budget and this was mainly attributed to:

Communication and Collaboration: Communication was not effective in the team as a few
team members would not share information obtained fro the Business Analysts either
because they tend to forget to pass the information to all team members or they thought
that the information would not be relevant to the other areas being developed. Based on
this, quite a number of requirements were not properly implemented and required some
re-work.

Requirements: Some of the development team members were not familiar enough with
the business processes that were being implemented and therefore more time was spent in
requirements clarifications with the business analyst. There were also little or no
documentation for some areas of the project and the knowledge resided with some key
team members only.

Quality of information shared: There was often inaccurate information being provided
when clarifications were requested. This caused a large number of defects to be raised by
testers as they would test according to documentation available whereas developers would
perform development based on knowledge and information gathered from the Business
Analyst.

Conflicting views: Daily Scrum meetings would sometime overrun because it was
difficult to get agreements on some issues and this meant that separate meetings had to be
held to ensure that a consensus is reached so that development could run smoothly.

Management views are that the project was delivered late and over budget but it matched all
requirements requested by the business.

The budget deviation for budget for Project C was around 8% and the main causes were:

Underestimated areas of work: Due to the fact that requirements were not properly
analysed at the start of the project, some areas of development were not properly
estimated and the impact on sub components not identified. During development the
impact became obvious and impacted to initial budget.

The allowable deviation from budget for all projects based on the organisation standards is
10%. Therefore only Project C was within the standards whereas Project A was well outside.

4.2. On Time Delivery

The rate at which releases were performed on time was measured as follows:

129
International Journal of Software Engineering & Applications (IJSEA), Vol.3, No.1, January 2012

Table 6. On Time Delivery.

Project Releases performed Releases on time % on Time

Project A 40 12 30

Project B 25 15 60

Project C 10 9 90

From Table 6, it can be seen that Project A had the largest number of releases and due to the
fact that most of them were performed late and testing and deployment were in turn delayed.
The project itself was not implemented on time and way off its target delivery date. The main
reasons for late deliveries were the large number of defects that were raised due mainly to
integration and coding issues.

Project B also faced some similar issues as Project A. Releases were not on time due to
integration problems and also lack of coordination with external teams such infrastructure
meant that environments were often not working as expected. Deployment and configuration
were not performed in an effective manner as the team were focussing mainly on completion
of pure development tasks as a priority and often meant that setting up of environments were
requested late. The organisations standards allow for a minimum of 90% on time delivery for
all projects. Based on the information collected, only Project C satisfied this criterion.

4.3 Rework

The rework level for each project has been calculated as below:

Table 7. Rework Level.

Project Actual Spend MD Rework MD Rework Level - %

A 3200 (14.1 man yrs) 800 25

B 950 (4.3 man yrs) 150 16

C 130 (0.6 man yrs) 20 15

The amount of time spent fixing defects against the total time spent on development the actual
software was highest for Project A. Out of 3200 man days, about 800 were spent on pure
defect fixing which accounts to about a quarter of the total budget spent. The rework level on
project B and C were relatively low but still outside of the required range as per organisation
standards which is 10%.

130
International Journal of Software Engineering & Applications (IJSEA), Vol.3, No.1, January 2012

4.4 Defect Rate

The defect rates recorded have been as follows:

Table 8. Defect Rate.

Project Actual Spend Defects Raised Defect Index

A 3200 (14.1 man yrs) 1633 1.9

B 950 (4.3 man yrs) 305 3.0

C 130 (0.6 man yrs) 40 3.0

Project A has that highest defect index, for every 1.9 man days of work produced a new defect
was being introduced. In Project C, the index was higher and for every three days of worked
produced a new defect was obtained.

Based on the figures for both rework level and defect count, in general a defect on all three
projects would cost about 0.5 man day to be fixed i.e.:

Project A: 1633 defects requiring 800 man days rework

Project B: 300 defects for 150 man days rework

Project C: 40 defects for 20 man days rework

This clearly indicates that the level of complexity for all three projects is comparable and
therefore confirms that the projects used were ideal candidates for this study.

4.5 People Aspect

During this study, soft factors of the Agile teams were not measured with any tools or
methods except the employee survey and subjective measures such as observations.

As part of the subjective measures, some observations were made on how the individuals
behaved during the life of the projects. For all three projects used it this study, particular
attention were made to make use of people management best practices. A few issues were
encountered in some areas due to inherent complexity in managing particular teams. Such
issues could not be quantified on a scale but from an objective view only as described below:

Accountability: members of all three teams were given clear tasks ownership and this was
easily monitored via JIRA. For each task on the project, a corresponding JIRA ticket was
created and assigned to a member of the team. In this way there was clear visibility of who
owns what and who does what. However for Project A there were about 20% of the tasks
that changed ownership as developers were not sure which sub teams had the responsibility
131
International Journal of Software Engineering & Applications (IJSEA), Vol.3, No.1, January 2012

to produce the work. This meant that management had to intervene to allocate such tasks to
the appropriate teams or individuals. There was a clear lack of visibility and communication
that was demonstrated by the fact that some team members did not have a clear knowledge
of who does what or who owns what.

Empowerment: all persons involved on the teams were provided adequate technical training
where required and the authority to create dependant JIRA tasks where necessary. These
tasks were then either assigned to other team members or to external teams to progress.
Initiators of such tasks were required to monitor the progress until completion.

Developer Skills and Fear: On project A three of the developers who were not good
communicators did not raise concerns regarding technical areas where they not really good
at. This was attributed to the fact that they did not want to show in the daily Scrum meetings
that they were technically behind the other team members. This led to more time being
spent on tasks assigned to them. The same issue was encountered on Project B whereby one
developer did not raise his concerns. But on Project C there were no such issues and when
developers needed coaching, this was raised promptly without any fear in daily Scrum
meetings. Based on this reaction, it would seem that individuals fear to raise their skill
deficiencies in a large group while this creates no concerns when in a much smaller group.

Leadership: The teams were provided coaching when required and blockers or impediments
that were raised promptly during the daily Scrums had to be progressed either by the Project
Leader or Project Manager. This ensured that management acted as a facilitator to the teams
while they focus on the delivery of the product.

Performance management: JIRA provides the facility to view a projects progress and status
via a dashboard. This was monitored on a day to day basis to ensure that the individual and
hence the team is performing as expected and any discrepancies were readily visible and
corrective actions could be taken. For instance if a team member were to stay too long on a
JIRA ticket this will be seen on the dashboard as below and enable prompt action to be
taken during the daily Scrum meetings.

Effective Communication: The main role of the Project Leader was not only to ensure that
any blockers from external dependencies are progressed but as well to ensure that all
information received were cascaded in an effective manner to the team. Changes in
requirements were always cascaded and regular feedback on how the team is performing
was provided.

As recommended by Agile, the project teams worked in a shared workspace in an open office
structure that aimed at facilitating communication and collaboration. This was not easily
achievable with project A whereby the two sub Agile teams were located in different
geographical locations thus hindering communication to some extent.

The way the team members interact were somehow different across the three teams and there
were several observations made:

Interdependence: At least five team members from Project A, although their work had
some dependence on that of others, were seen to work in solo and would not provide
enough information to other team members on the impact of their work on other areas.
They were very focussed in the delivery of their own tasks on time and within the
132
International Journal of Software Engineering & Applications (IJSEA), Vol.3, No.1, January 2012

estimates even at the cost of not ensuring that integration is taken into consideration, at
least not until the last minute when it is actually required. This was also observed with a
least two members of team B. However for team C the team spirit was quite different and
members were communicating quite easily. On project B the same behaviour was
observed with only two team members who did not collaborate effectively and causing
their completed work to be incompatible with those of other team members. However no
such issues were raised from project team C.

Social Interaction: Although most of the teams had direct face to face communication on
a daily basis, some team members from Project A and B would make the use of chat tools
to communicate with each other during the day even if the other was in the same office
within a few metres. This meant that communication was kept to strict minimum between
these persons, only when obliged to do so via team meetings. For Project C the interaction
was much better and the team bonded more easily. Members would interact socially by
going out to lunch and communicate verbally quite often during the day and this improved
their familiarity. The general observation was that for teams A and B, most of the team
members did not allow much time to develop the social relationships between each other
but rather focussed on the deliverables and often seemed to work under stress. Agile has a
high reliance on social skills.

Perception of a group: While this was easily accepted in Project C and Project B, it was
much more difficult in Project A. The fact that there were two sub Agile teams, each
member acted as if they were part of their own sub team and could not easily fit
themselves in the overall Agile team. This meant that the teams worked independently
from each other and often led to communication gaps and integration issues. Most of the
team members who were based in the UK were emergent leaders and often took
ownership of tasks and at some point even formed mini-teams.

Commonality of purpose: This characteristic of an Agile team was seen in both Projects B
and C but as mentioned above there was not enough motivation for the group to work as
one team for project A. There was a lot of individuality in whereby some of the
developers were focussed on delivering their own work rather than seeing the overall
picture and where it fits in the whole project.

Motivation: The work on Project B was organised in such a way that specific areas of
development were assigned to a team member. One of the issues encountered however
was that some team members express themselves on the fact that they did not feel that the
work allocated to them were challenging enough.

4.6 Communication Channels

One of the key challenges that the Agile team members had to face was the communication
complexity. For Project C, it was not difficult for the team members to communicate
effectively. However for teams A and B this was much more difficult.

133
International Journal of Software Engineering & Applications (IJSEA), Vol.3, No.1, January 2012

Table 9. Communication Channels.

Project No of people on team No of communication channels

A 22 231

B 12 66

C 5 10

The above table clearly shows 231 communication channels for Project A which gives an
insight on how difficult and poor communication could have been among the team members.
Agile principles require than team members work in intense collaboration and have face-to-face
communication. This was achieved without any problem on Project C whereby the team was
small and showed intense collaboration. In project B, even if the team worked closely together
there were instances where team members will request to skip meetings so as to complete their
tasks. In project A however face to face communication was not always possible between the
two geographically dispersed teams even with the use of Video Conferencing systems. It was
difficult to coordinate the teams to work together and the distance did not allow direct
communication.

5. CONCLUSIONS
This study has been made exclusively based on the Agile Methodology and within an
organisation that is making use of Scrum. It did not take into consideration any projects using
other types of development methodologies. Therefore it is imperative that before any
organisation decides to adopt an Agile Method, it needs to assess whether the company
culture, operating structure, business processes and projects are suited for the use of an Agile
Project Management Methodology. This study was aimed at evaluating the people factors that
can affect the performance of an Agile team. The research was made with a small group of
similar projects that differed by size and team size only. This work will give valuable insight to
team leaders to select the appropriate number and type of people on each project. It will also be
highly beneficial to software organisation which will be in a better position to assess whether
agile could work for them. Future work will need to be performed to evaluate whether the same
result can be obtained with projects of varying organization, complexity and technology.

ACKNOWLEDGEMENTS
The authors would like to thank TNT Express ICS Mauritius for allowing them to run this study
with actual projects.

REFERENCES
1.Abilla, P., 2006. Team Dynamics: Size Matters Redux. [Online]. Available:
http://www.shmula.com/team-dynamics-size-matters-redux/182/. [Accessed: 27th April 2011]
2.Agile Manifesto (2011). The Agile Manifesto. [Online]. Available : www.Agilemanifesto.org.
[Accessed: 10th August 2011)
3.Ambler, S.W., 2010a. 2010 IT Project Success Survey. [Online]. Available:
http://www.ambysoft.com/surveys/success2010.html. [Accessed: 1st April 2011]

134
International Journal of Software Engineering & Applications (IJSEA), Vol.3, No.1, January 2012

4.Ancona, D.G., Caldwell, D.F., 1992. Work-groups; Organizational-climate; Organizational-


effectiveness. Administrative Science Quarterly. 37(??)p. 634-65.
5.Baddeley A, Della Sala, S., 1996. Working memory and executive control. Philos. Trans. R. Soc. Lond.,
B, Biol. Sci. 351 (1346): 1397403.
6.Boehm, B., 1981, Software Engineering Economics, Englewood Cliffs, N.J., USA, Prentice-Hall.
7.Bahli, B. and Buyukkurt, M.D., 2005. Group performance in information systems project groups: an
empirical study, Journal of Information Technology Education, Vol. 4.
8.Bustamante, A., Sawhney, R., 2011. Agile XXL: Scaling Agile for Project Teams, Seapine Software,
Inc.
9.Brady, K., 2006. AGILE/SCRUM Fails to get to grips with Human Psychology. [Online]. Available:
http://www.claretyconsulting.com/it/comments/Agile-Scrum-fails-to-get-to-grips-with-human-
psychology/2006-08-17/. [Accessed : 3rd August 2011]
10.Conboy, K. Coyle, S. Lero, X.W. Pikkarainen, M., 2011. People over Process: Key Challenges in
Agile Development July/August 2011 (vol. 28 no. 4) pp. 48-57
11.Cskszentmihlyi, M., 1990. Flow: The Psychology of Optimal Experience. New York: Harper and
Row, ISBN 0-06-092043-2.
12.Fayol, H., 1917. (French), Administration industrielle et gnrale; prvoyance, organisation,
commandement, coordination, contrle. Paris, H. Dunod et E. Pinat.
13.Hastie, S., 2004. The Agile Mindset: what does it take to make this stuff work? Software Education
Associates Ltd, Agile Development Conference Wellington & Sydney, September 2004
14.Huckman, R.S., Staats, B.R. and Upton, D.M., 2009. Team familiarity, role experience, and
performance: evidence from Indian Software Services, Management Science, Vol. 55 No. 1, pp. 85-
100.
15.Johnson, R., 2008. Six Principles of Effective Management. [Online]. Available:
http://ezinearticles.com/?Six-Principles-of-Effective-Team-Management&id=1803062. [Accessed:
28th March 2011]
16.Kemerer, C., 1989. An agenda for research in the managerial evaluation of computer-aided software
engineering (CASE) tool impacts, Proceedings of the 22nd Annual Hawaii International Conference on
System Sciences, Hawaii, pp. 219-28.
17.Lencioni, P., 2002. The Five Dysfunctions of a Team. Jossey-Bass
18.Ong, A., Tan, G.W. and Kankanhalli, A., 2005. Team expertise and performance in information
systems development projects, Proceedings of the 9th Asia Pacific Conference on Information Systems,
Bangkok, Thailand, July 7-10.
19.Standish Group., 2009. Chaos Report 2009. [Online]. Available from:
http://www1.standishgroup.com/newsroom/chaos_2009.php. [Accessed 20th May 2011].
20.Sudhakar, G.P. Farooq, A. Patnaik, S., 2011. Soft factors affecting the performance of software
development teams. Team Performance Management Vol. 17 No. 3/4, 2011 pp. 187-205
21.Tuckman, B., 1965. Developmental sequence in small groups. Psychological Bulletin 63 (6): 38499
22.Whitworth, E., 2006. Agile Experience: Communication and Collaboration in Agile Software
Development Teams. M.A Carleton University, Canada.

135
International Journal of Software Engineering & Applications (IJSEA), Vol.3, No.1, January 2012

APPENDIX A
Team Feedback Questionnaire

SECTION A - Agile Management


Please rate (tick) the following based on 1 2 3 4 5
how you perceived it within the team (1
- Lowest, 5 - Highest)

How clear were the objectives of the


1 project communicated to you?

How well was the product backlog


2 elaborated to you?

To what extent were the sprints well


3 organised?

According to you how effective were the


4 Scrum meetings?

How suitable was the team size for the


5 project?

Further comments:

SECTION B - Team work


Please rate (tick) the following based on 1 2 3 4 5
how you perceived it within the team (1
- Lowest, 5 - Highest)

What was the level of trust between you


6 and the team members in terms of:
a. Credibility
b. Reliability
c. Familiarity

How did you perceive the wellness of the


7 team in terms of:
a. Cohesion
b. Motivation
c. Collaboration
d. Communication

To what extent was your level of


8 contribution within the team?

9 How well did you integrate the team?

136
International Journal of Software Engineering & Applications (IJSEA), Vol.3, No.1, January 2012

What was your level of participation


10 during the Scrum meetings?

Further comments:

SECTION C - Product
Please rate (tick) the following based on 1 2 3 4 5
how you perceived it within the team (1
- Lowest, 5 - Highest)

What was the level of challenge of the


11 project?

What was the level of difficulty of tasks


12 assigned to you as per your expertise?

13 What was quality level of the project?

What was the complexity level of the


14 project?

How do you feel was the size of the


15 project?

According to you how satisfied was the


16 customer with the end product?

Further comments:

Respondent Profile

Name (optional): 21-25 26-30 31-35 36+


Age:

Role on Agile Team: Gender:

137