Capital Cost Estimate of A Typical Condensate Refinery
Capital Cost Estimate of A Typical Condensate Refinery
The cost estimates are of an accuracy of +/- 20% and reflect 2006 prices for
project completion in Iran in south of Iran.
The cost estimate also includes the forward escalation for the project
execution period as detailed in the Project Schedule which is issued as a
separate document.
The cost estimate for the first charge of catalysts and chemicals as well as
spare parts for the first two years of operation of the refinery is included in the
OPEX.
1. PROCESS UNITS:
1
E. Kerosene Treater Unit (KTU) 1.7
2. UTILITIES:
D. MP Steam 12
E. LP Steam 8.5
2
3. FLARES & TANKAGE:
A. Flares 3.7
B. Tankage 114.7
A. SBM 32
B. On Shore Pipelines 12
C. Pumping 1.5
3
TOTAL CAPEX 657.8
Personnel 3.2
Maintenance 1.5
Insurance 2.1
Shipping costs 15