PROYECTO: MODULO BASICO DE JUSTICIA

PROPIETARIO:
ADJUDICACION DIRECTA N 0XX-2000-GCR/PJ
CONTRATISTA: ASOCIADOS
SUPERVISOR: ING
VALORIZA
FORMULA : 01 ESTRUCTURAS
PRESUPUESTO BASE : S/ 686,034.31 AL 30/04/2000
PRESUPUESTO CONTRATADO: S/ 617,431.00 INC. IGV

ITEM DESCRIPCION UND

1.00.00 OBRAS PROVISIONALES


1.01.01 OFICINA Y ALMACEN DE MATERIALES GLB
1.02.00 CARTEL DE OBRA S/ESPECIFICACIONES PZA
2.00.00 TRABAJOS PRELIMINARES
2.01.01 TRANSPORTE DE EQUIPO Y MATERIALES GLB
3.00.00 MOVIMIENTO DE TIERRAS
3.01.00 LIMPIEZA Y NIVELACION
3.01.01 TRAZO, NIVELES Y REPLANTEO PRELIMINAR M2
3.02.00 EXCAVACION DE ZANJAS
3.02.01 EXCAVACION ZANJAS PARA CIMIENTOS CORRIDOS H=35. M3
3.02.02 EXCAVACION PARA ZAPATAS H= 1.60 MT M3
3.02.03 EXCAVACION PARA VIGAS DE CIMENTACION H= 1.20 MT M3
3.03.00 RELLENOS CON MATERIAL PROPIO Y PRESTAMO
3.03.01 RELLENO Y COMPACTACION C/MATERIAL PROPIO M3
3.04.00 AFIRMADO INCLUYE LAS VEREDAS
3.04.01 AFIRMADO E= 0.10 PARA AMBIENTES INTERIORES M2
3.04.02 AFIRMADO E= 0.15 PARA AMBIENTES INTERIORES M2
3.05.00 ELIMINACION DE MATERIAL EXCEDENTE
3.05.01 ELIMINACION DE MATERIAL EXCEDENTE M3
4.00.00 OBRAS DE CONCRETO SIMPLE
4.01.00 CIMIENTOS CORRIDOS
4.01.01 CONCRETO CIMIENTOS C:H 1:8 +30% P.G M3
4.02.02 SOLADO PARA ZAPATA
4.02.01 CONCRETO C:H 1:10 E= 2" SOLADO M2
4.03.00 FALSA ZAPATA
4.03.01 CONCRETO FALSA ZAPATA C:H 1:10 M3
4.04.00 FALSO PISO
4.04.01 FALSO PISO E= 4" F'C= 140 KG/CM2 M2
4.05.00 SOBRECIMIENTO
4.05.01 CONCRETO SOBRECIMIENTO 1:6(C:H)+ 25% P.M M3
4.05.02 ENCOFRADO Y DESENCOFRADO SOBRECIMIENTO M2
5.00.00 OBRAS DE CONCRETO ARMADO
5.01.00 SOBRECIMIENTO ARMADO
5.01.01 CONCRETO F'C= 175 KG/CM2 SOBRECIMIENTO ARMADO M3
5.01.02 ENCOFRADO Y DESENCOFRADO SOBRECIMIENTO ARMADO M2
5.01.03 ACERO DE REFUERZO FY= 4200 KG/CM2 SOBRECIMIENTO ARMAADO KG
5.02.00 ZAPATAS
5.02.01 CONCRETO F'C= 210 KG/CM2 ZAPATA M3
5.02.02 ACERO DE REFUERZO FY= 4200 KG/CM2 ZAPATA KG
5.03.00 VIGAS DE CIMENTACION
5.03.01 CONCRETO F'C= 210 KG/CM2 VIGAS DE CIMENTACION M3
5.03.02 ENCOFRADO Y DESENCOFRADO DE VIGA CIMENTACION. M2
5.03.03 ACERO DE REFUERZO FY= 4200 KG/CM2 VIGAS DE CIMENTACION KG
5.04.00 COLUMNAS
5.04.01 CONCRETO F'C=210 KG/CM2 COLUMNAS M3
5.04.02 ENCOFRADO Y DESENCOFRADO COLUMNAS NORMAL M2
5.04.03 ACERO DE REFUERZO FY= 4200 KG/CM2 COLUMNAS KG
5.05.00 COLUMNAS DE AMARRE
5.05.01 CONCRETO F'C=175 KG/CM2 COLUMNAS DE AMARRE M3
5.05.02 ENCOFRADO Y DESENCOFRADO COLUMNAS AMARRE M2
5.05.03 ACERO DE REFUERZO FY= 4200 KG/CM2 COLUMNAS DE AMARRE KG
5.06.00 VIGAS
5.06.01 CONCRETO F'C= 210 KG/CM2 VIGAS M3
5.06.02 ENCOFRADO Y DESENCOFRADO VIGAS M2
5.06.03 ACERO DE REFUERZO F'Y= 4200 KG/CM2 VIGAS KG
5.07.00 DINTELES
5.07.01 CONCRETO F'C= 175 KG/CM2 DINTELES M3
5.07.02 ENCOFRADO Y DESENCOFRADO DINTELES M2
5.07.03 ACERO DE REFUERZO FY= 4200 KG/CM2 DINTELES KG
5.08.00 LOSA ALIGERADA E= 0.20 M
5.08.01 CONCRETO FC= 210 KG/CM2 LOSA ALIGERADA M3
5.08.02 ENCOFRADO Y DESENCOFRADO NORMAL LOSA ALIGEARADA M2
5.08.03 ACERO DE REFUERZO FY=4200 KG/CM2 LOSA ALIGERADA KG
5.08.04 LADRILLO HUECO DE ARCILLA .15X30X30 M UND
5.09.00 CISTERNA
5.09.01 CONCRETO F'C= 210 KG/CM2 EN CISTERNA M3
5.09.02 ENCOFRADO Y DESENCOFRADO CISTERNA M2
5.09.03 ACERO DE REFUERZO F'Y= 4200 KG/CM2 CISTERNA KG
5.10.00 RAMPAS Y GRADAS
5.10.01 CONCRETO F'C = 140KG/CM2 ESCALERAS Y RAMPAS M3
5.10.02 ENCOFRADO Y DESENCOFRADO RAMPAS M2
5.11.00 JUNTAS
5.11.01 JUNTAS DE DILATACION CERCO PERIMETRICO COLUMNAS INTERIORES ML
5.11.02 JUNTAS DE DILAT EN EDIFICIO M2
TOTAL COSTO DIRECTO
GASTOS GENERALES 15%
UTILIDAD 10%
SUB TOTAL
% DE AVANSE
FACTOR DE RELACION: 0.90000
VALORIZACION MENSUAL N 01 DEL 03/11/2000 AL 30/11/2000

INICIO PLAZO CONTRACTUAL : 03/11/2000 PLAZO DE EJECUCION: 135 DIA


FIN DEL PLAZO CONTRACTUAL 17/03/2001 FACTOR DE RELACION: 0.90000

PRESUPUESTADO ANTERIOR ACTUAL ACUMULADO ACTUAL


CANTIDAD P.UNIT PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD

1.00 2,117.58 2,117.58 0.00 0.00 1.00 2,117.58 1.00


1.00 1,055.46 1,055.46 0.00 0.00 1.00 1,055.46 1.00

1.00 2,530.61 2,530.61 0.00 0.00 0.50 1,265.31 0.50

717.10 0.75 537.83 0.00 0.00 359.00 269.25 359.00

138.94 18.42 2,559.27 0.00 0.00 138.94 2,559.27 138.94


214.55 12.69 2,722.64 0.00 0.00 214.55 2,722.64 214.55
64.89 16.12 1,046.03 0.00 0.00 64.89 1,046.03 64.89

208.97 9.81 2,050.00 0.00 0.00 0.00 0.00 0.00

236.97 6.20 1,469.21 0.00 0.00 0.00 0.00 0.00


325.89 8.32 2,711.40 0.00 0.00 0.00 0.00 0.00

272.25 15.05 4,097.36 0.00 0.00 0.00 0.00 0.00

230.57 140.06 32,293.63 0.00 0.00 185.00 25,911.10 185.00

205.32 11.33 2,326.28 0.00 0.00 205.32 2,326.28 205.32

45.77 153.61 7,030.73 0.00 0.00 45.77 7,030.73 45.77

236.97 23.96 5,677.80 0.00 0.00 0.00 0.00 0.00

26.06 177.11 4,615.49 0.00 0.00 16.00 2,833.76 16.00


343.30 14.49 4,974.42 0.00 0.00 206.00 2,984.94 206.00
1.79 187.09 334.89 0.00 0.00 0.00 0.00 0.00
23.90 14.81 353.96 0.00 0.00 0.00 0.00 0.00
185.31 1.85 342.82 0.00 0.00 0.00 0.00 0.00

46.18 208.99 9,651.16 0.00 0.00 19.00 3,970.81 19.00


998.12 1.85 1,846.52 0.00 0.00 400.00 740.00 400.00

35.00 208.91 7,311.85 0.00 0.00 10.50 2,193.56 10.50


233.35 19.88 4,639.00 0.00 0.00 70.00 1,391.60 70.00
4,346.69 1.85 8,041.38 0.00 0.00 1,304.00 2,412.40 1,304.00

19.14 255.94 4,898.69 0.00 0.00 0.00 0.00 0.00


222.26 25.72 5,716.53 0.00 0.00 0.00 0.00 0.00
2,442.52 1.85 4,518.66 0.00 0.00 367.00 678.95 367.00

16.82 187.09 3,146.85 0.00 0.00 0.00 0.00 0.00


229.36 25.72 5,899.14 0.00 0.00 0.00 0.00 0.00
1,381.37 1.85 2,555.53 0.00 0.00 1,105.00 2,044.25 1,105.00

21.64 213.53 4,620.79 0.00 0.00 0.00 0.00 0.00


281.99 25.15 7,092.05 0.00 0.00 0.00 0.00 0.00
2,280.94 1.85 4,219.74 0.00 0.00 0.00 0.00 0.00

2.21 187.09 413.47 0.00 0.00 0.00 0.00 0.00


44.17 24.41 1,078.19 0.00 0.00 0.00 0.00 0.00
254.61 1.85 471.03 0.00 0.00 0.00 0.00 0.00

1.62 216.08 350.05 0.00 0.00 0.00 0.00 0.00


16.19 21.80 352.94 0.00 0.00 0.00 0.00 0.00
98.50 1.85 182.23 0.00 0.00 0.00 0.00 0.00
136.00 1.94 263.84 0.00 0.00 0.00 0.00 0.00

6.92 220.71 1,527.31 0.00 0.00 0.00 0.00 0.00


48.48 20.54 995.78 0.00 0.00 0.00 0.00 0.00
995.50 1.85 1,841.68 0.00 0.00 0.00 0.00 0.00

1.04 183.00 190.32 0.00 0.00 0.00 0.00 0.00


1.43 20.21 28.90 0.00 0.00 0.00 0.00 0.00

34.70 1.65 57.26 0.00 0.00 0.00 0.00 0.00


24.61 8.48 208.69 0.00 0.00 0.00 0.00 0.00
162,966.99 65,553.92
24,445.05 9,833.09
16,296.70 6,555.39
203,708.74 81,942.40
100.00 40.23%

ACUMULADO = ANTERIOR + ACTUAL


SALDO = PRESUPUESTO - ACUMULADO
AZO DE EJECUCION: 135 DIAS CALENDARIO
CTOR DE RELACION: 0.90000

ACUMULADO ACTUAL SALDO POR EJECUTAR SALDO


PARCIAL CANTIDAD PARCIAL %

2,117.58 0.00 0.00


1,055.46 0.00 0.00

1,265.31 0.50 1,265.30


0.00 0.00
0.00 0.00
269.25 358.10 268.58

2,559.27 0.00 0.00


2,722.64 0.00 0.00
1,046.03 0.00 0.00

0.00 208.97 2,050.00

0.00 236.97 1,469.21


0.00 325.89 2,711.40

0.00 272.25 4,097.36

25,911.10 45.57 6,382.53

2,326.28 0.00 0.00

7,030.73 0.00 0.00

0.00 236.97 5,677.80

2,833.76 10.06 1,781.73


2,984.94 137.30 1,989.48
0.00 1.79 334.89
0.00 23.90 353.96
0.00 185.31 342.82

3,970.81 27.18 5,680.35


740.00 598.12 1,106.52

2,193.56 24.50 5,118.29


1,391.60 163.35 3,247.40
2,412.40 3,042.69 5,628.98

0.00 19.14 4,898.69


0.00 222.26 5,716.53
678.95 2,075.52 3,839.71

0.00 16.82 3,146.85


0.00 229.36 5,899.14
2,044.25 276.37 511.28

0.00 21.64 4,620.79


0.00 281.99 7,092.05
0.00 2,280.94 4,219.74

0.00 2.21 413.47


0.00 44.17 1,078.19
0.00 254.61 471.03

0.00 1.62 350.05


0.00 16.19 352.94
0.00 98.50 182.23
0.00 136.00 263.84

0.00 6.92 1,527.31


0.00 48.48 995.78
0.00 995.50 1,841.68

0.00 1.04 190.32


0.00 1.43 28.90

0.00 34.70 57.26


0.00 24.61 208.69
65,553.92 97,413.07
9,833.09 14,611.96
6,555.39 9,741.31
81,942.40 121,766.34
40.23% 59.77%