with its own staff and, if it subcontracts, 35% of the subcontracts must be awarded to SBEs.

Refer
to Section 2-218.46 of the District of Columbia Code for more details.

A.7 Selection Criteria

Proposals will be evaluated in accordance with Part C of this RFP. The following evaluation
criteria will be used for the proposals:

Proposal, Experience & References (20 points)


Key Personnel (25 points)
Program Management Plan (25 points)
Cost (20 points)
CBE Utilization Plan (10 points)

A.8 Procurement Schedule

The schedule for this procurement is as follows:

Issue RFP - November 30, 2015


Pre-proposal Conference - December 9th at 12:00 pm
Last Day for Questions/Clarifications - December 14, 2015
Proposals Due - December 30, 2015
Interviews - January 14, 15 & 18, 2016
Board Approval - TBD
Notice of Award - TBD

A.9 Project Schedule

The preliminary project schedule is as follows:

Issue RFP for Architect/Engineer - December 2, 2015


Engage Program Manager - TBD
Issue RFP for Construction Manager - TBD
NTP for Architect/Engineer - TBD
NTP for CM Preconstruction - TBD
Programming/Scope Reconciliation - mid-February 2016 to March 31, 2016
with Wizards/Mystics
Concept Design Complete - April 30, 2016
Demolition Completed by DC - July 1, 2016
Government (DGS)
Schematic Design Complete - July 30, 2016
Design Development Complete - October 15, 2016
Land Use/Entitlements - Fall 2016
(Exact Process TBD)