1. AERATION BASIN SIZING CALULATIONS
Summer:
[(220 ppm)(2.0 MGD)(8.34)/(20 #80D/day/ 10008?
183. 48*1000 ft?
= 183,480 ft*
Surface area =12, 510 ft? @ 14’ - 8’ SWD
heck winter operation:
(220ppm)(0.5 MGD)(8.34), =5#BOD/day/ 1000ft.*
(183.48* 1000ft.*)
This loading rate is too low. A loading this low would result in high $F
setting. Consider designing winter loading at 30 #day/ 1000 ft.?. Part
the aeration of the aeration chamber for winter service only.Winter:
Va ={(220 ppm)(0.5 MGD)(8.34)/ (30 #BOD/ day/ 1000ft*)
30,58*L000ft? =30, 580 ft?
Surface area required =2085 ft?
‘The aeration basin will therefore be divided into two compartments. The larc
will be 152,900 ft? for summer use only. The smaller cormpartment will be 30
summer and winter use. Mixed Liquor transfer will be accomplished through
Pipes, multi-purpose launders or airlift punrps.
4, CLARIFIER SZING CALCULATIONS
Design based on solids loading rate. Assume 100%RAS flow @ 2.0 MGD influent flow
ppm Therefore, total average daily flow (ADF) to darifier equals 4.0 MGD.
‘Solids loading (SL) =(4000 ppm)(4.0 MGD)(8.34) = 133,440 #MILSS/ day
At peak flow, assume 150%RAS based on ADF.
Peak flow =4 +(2)(1.5) =7.0MGD
(QL) at peak flow =(4000 ppm)(7 MGD)(8.34) =233,520 #MILSS/ day
FromTable 1, select a dlarifier loading rate of 50 # day/ft?
‘The darifier surface area is equal to:
SA. =(233,520 #MLSS/day)(50 # day/ft?) =4670 ft?
Based on the use of two treatment units, two (2) 55’ @ darifiers will be required.
Check hydraulic loading rates at peak flow:
00207 O00
‘4750 TF
=842 pd/ft?
OK based on Table 1 Value
Overflow Rate (OR) =XT and poor sludge
ition a section of
DESIGN EXAMPLE
Wastewater comes froma seasonal resort facili
Ww
‘Average daily flow, MGD 0.
Influent BOD;, ppm 2
Tnfluent NHs, ppm a
Influent Total Suspended Solids, ppm 2
Nitrification? Ni
Peaking factor Ni
Other assumptions:
1. Selected activated sludge process is cor
during summer months.
No primary darification
Influent TSS includes 50%NVSS_
Digester only, no sludge holding tanks
Volatile sludge yield =0.45 4VSS/ #80D
Digester sludge concentration =2%(20
Digester detention time =14 days
‘Stee! tank construction
WP MNAYRWN
Local regulatory agency requires 2 treat
2. SLUDGE LOADING/ DIGESTER SIZING CALCULATION
NVSS (#/day) =(200 ppm)(8.34)
(2.0MGD\(0.5)
MLVSS (# day)={220 ppm)(8.34)
(2.0 MGD)(0.45 #Ksss/ Hod)
=1651 #MLCSS/ day
Total Solids Loading to Digester =
1668 #/day +1651 4 day =3319 #/ day
Vo =[(3319 # day)(14days)Y/ [(20,000)(8.34)]yer compartment
580 ft? for
additional transfer
and MLSS of 4000
=278MG
=37, 237 f°
‘Surface Area =2539 ft? @ 14’ - 8” SWD_
5, CALGULATE OVERALL PLANT SZNG
Total area per plant required
Zone Total Trial Area (ft. 2)
[Aeration® ————~——C~S CH
Digester 1270
‘Chlorine Contact Zar
[Carifier(SS) ——C«CC BS
[Total ———..C‘*d*«a AN.
*Total Winter/Summer
Overall plant diameter, ft. =
vi(4)(10,11. DY pi
A113. 5ft.
Round of to 115-ft. diameter
Compartment size can be calculated. For example, the angular sf
chamber will be:
(6255 ft“2)/7736 ft“2) x 360° =290° (rounded of f)
‘Summer/ winter use =50°
Summer use only =240
Similarly,
Digester =60°
Chlorine Contract =10°
Final design loadings can then be recalculated, based on the final
requirements can be calculated by using the second entitled "Aer7. CALQULATE ACTUAL OXYGEN REQUIREMENTS,
For deterrrining actual oxygen requirements (AOR),
requirements for the biological loading. Typical corr
are 1.8 Ibs. O,/Ib. BOD and 4.6 Ibs. O,/lbs, NH. Nitri
may cause its occurrence. Therefore, additional oxy
calculation of AORis as follows:
AOR (Ibs. /day) =(1.8) (Ibs. BOD/ day) +(4.6) (Ilbs.N
Ups. BOD/ D =(BOD Conc.) (Ave. Daily Flow, MGD)
Ups. NH / D =(NH; Conc.) (Ave. Daily Flow, MGD) (€
Lbs. / BOD/ D (winter) =(220) (0.5) (8.34) =917
Lbs. / BOD/ D (summer) =(220) (2.0) (8.34) =3,669
Ups. / NH / day (winter) =(30) (0.5) (8.34) =125
Ups. / NH /day (summer) =(30) (20) (8.34) =500
AOR (winter) =(1.8) (917) +(4.6) (125) =2,226 Ibs. /
AOR (summer) =(1.8) (3669) +(4.6) (500) =8,904 Ik
To calaulate the corresponding Standard Oxygen Re
“Aeration Design Section”. Selection of the type of :ty. Flow characteristics are as follows:
inter ‘Summer
5 2.0
20 220
d 30
0 200
2 Yes
one.
aventional nitrification loaded at 20#BOD/day/ 1000 ft?
sment units
3. Chlorine Contact Basi
Use 15 rrinutes of deter
MGD (2780 gom)
Vec ={(2780 gomn\(15 ri
=5575 fC
So =423 ft? @ 13’ - 2'
(SAcc =Surface area of cTial Area (ft. 72) ‘Annulis Trial Area (ft. 2)
6255
1270
2i1
2 7, 736K. 2
example, the angular space occupied by the aeration
ded off)
ated, based on the final volume calculations. Air
ne second entitled "Aeration Design” and "Airlifts".
6. CALQULATE CLARIFIE
The equation for Torat
Running Torque (T) =V
Where:
W =sludge load on rak
R =radius of darifier (fF
For secondary “Activat
W =6 lbs. /ft.
For a 55 ft. diameter d
R=27.5 ft?an estimate must be made to deterrrine the oxygen
‘bined aeration and digestion oxygen requirements
fication may not be required, however conditions
gen may be required to satisfy this demand. The
Hs/ day)
(8.34 lbs. / gal)
3.34 Ibs. / gal)
day
s/ day
‘quirements (SOR) and air requirements refer to the
air diffusion system is also discussed in this section>n Sizing Calculations
ation time at a peak flow of 4.0
nutes)/7.48
”"SWD
‘hlorine contact basin)ER RAKE DRIVE TOQUE & SIZING
Je calculation is:
vRe
eam lbs. /ft. of arm)
t)
ed Sudge”’
arifier: