Professional Documents
Culture Documents
U K Nitrogen Removal Plant Starts Up
U K Nitrogen Removal Plant Starts Up
nitrogen-removal plant
starts up
This plant is part of projects for processing and commercializing natural gas
from the Liverpool Bay development. It was designed, installed, and
commissioned by Costain Oil, Gas & Process Ltd., Manchester.
Four fields
The Liverpool Bay development (Fig. 1) consists of four offshore fields in the
Irish Sea off the North Wales coast. Although oil is exported directly from the
Douglas platform, natural gas is brought ashore at the Point of Ayr terminal
through a 20-in., 33-km subsea pipeline.
The Point of Ayr gas terminal has a design capacity of 300 MMscfd. The inlet
facilities remove methanol (used for hydrate inhibition), water, and
condensate. The dry gas is then sweetened with an amine-based solvent.
Hydrogen sulfide content is reduced to 3.3 ppm, mercaptans to 35 ppm.
The gas-treatment plant normally expects to process 70 MMscfd but has been
designed to treat up to 200 MMscfd to cater for additional gas if the power
station is operated at reduced capacity.
Process design
While the natural gas is of adequate quality for power generation, it requires
treatment for the NTS. The Wobbe Index is less than permitted because of
the high nitrogen content (up to 11%), and the level of sulfur compounds must
be substantially reduced (Table 1).
A cryogenic process reduces the nitrogen content to less than 5% (Fig. 3).
This process consists of a double distillation-column system with an upstream
preseparation column to give low overall power consumption, a simple
configuration of process compressors, and tolerance to carbon dioxide.
Such triple-column systems have been used previously in the U.S. and
Western Europe for natural gas of similar nitrogen content.1 2 A rigorous
evaluation of alternative process flowsheets concluded that this configuration
was optimum for this particular application.
The heart of the process, cryogenics, requires deep gas drying. This is
achieved by molecular-sieve adsorbers which are sized to remove not only
water but also the sulfur compounds. Mercury is removed from the natural gas
before the cryogenic section to protect the brazed aluminum heat exchangers.
The treated gas from the cryogenic section is compressed to NTS pressure
and exported from the plant.
18-month turnkey
Along with the process plant, the contract included all necessary
infrastructure: firewater systems, control building, power distribution, flare,
sulfur-compounds incinerator, distributed control system (DCS), and process-
safeguarding systems.
The critical path for the 18-month, fast-track schedule was specification and
procurement of the sales-gas compressors and the design and fabrication of
the cryogenic cold boxes.
The cold-box designs required careful study early in the basic engineering of
the project to ensure constructability was adequately addressed. The size and
configuration of the heat exchangers, columns, separators, and pipe work
required detailed evaluation to ensure the most cost-effective overall solution.
Transport and lifting limitations were considered in detail because of the
restrictions of the site layout and limited access constraints.
To afford maximum time for civil works and to minimize site-construction work,
it was agreed that the plant should consist of several preassembled modules:
12 modules whose total weight exceeded 1,000 metric tons. The largest
modules were the two cold boxes, key in ensuring satisfactory operation of
the cryogenic process.
These were also critical items to the schedule. With overall shipping
dimensions exceeding 49 m x 5.5 m x 4.5 m, transport and lifting logistics
required detailed planning.
These were all factors in ensuring effective "single pass" design and
construction in the least amount of time. Field and module rework was kept to
an absolute minimum and represented less than 2% of costs with no program
slippage.
The use of PDMS is especially valuable for cold-box design. It simplifies
hydraulic analysis, enables layout to be generated and quickly assessed, and
often results in reduced box size and cost (Fig. 5).
This step helped to target those plant areas with low availability so that
solutions could be found to meet overall plant availability criteria. Overall plant
availability is designed to exceed 98%.
Cold-box modules
The two cold boxes, shop-fabricated near the construction site, comprise
complete package units in which aluminum plate-fin heat exchangers,
distillation columns, separators, piping, and instrument-sensing elements are
housed. The housing is a carbon steel frame, clad with plate (Fig. 6 ).
The equipment inside the cold boxes is a combination of aluminum and
stainless steel. Exchangers are of aluminum alloys; vessels and distillation
columns are of stainless steel. Cold equipment such as plate-fin exchangers
are supported on stainless steel beams that are insulated from the carbon-
steel frame via heat-resistant supports.
All lines passing through the cladding are of stainless steel or similar material
and terminate with external flanges. Cold lines that penetrate the cladding
have specially designed and fabricated thermal shunts to protect carbon-steel
plate from brittle fracture.
Insulation of the cold equipment is achieved by filling the internal void of the
cold box with free flowing nonflammable expanded perlite after erection at
site. To ensure a safe atmosphere in the cold-box housing, the internal void is
continuously purged with dry nitrogen.
Gas drying
The molecular sieves are regenerated with hot waste nitrogen from the
cryogenic section of the plant to desorb water and sulfur compounds that are
then destroyed in a thermal oxidizer. The resulting sulfur dioxide is dispersed
to atmosphere through a 45-m stack.
The design of this system was fully evaluated against the Best-Available-
Technology-Not-Entailing-Excessive-Cost requirements of the U.K.
Environmental Agency.
If, for any reason, one of the molecular-sieve vessels is unavailable, the
control sequence enables plant operation to continue with two beds to ensure
high availability.
The dry sulfur-free feed gas from the molecular sieves containing 8-11%
nitrogen passes to the cryogenic nitrogen-removal system (Fig. 8) which
produces a natural-gas stream containing less than 1.5 mol % nitrogen and a
nitrogen-rich off-gas containing less than 1.5 mol % methane.
Costain Oil, Gas & Process6 also applied this concept for the British Gas
North Morecambe terminal farther north on the English coast.7 The
preseparation step upgrades the nitrogen level and reduces the feed rate to
the double-column system, which further improves the efficiency of the overall
cryogenic process.
The associated reduction in column size and exchanger size for the double-
column system reduced cold-box size and cost.
The Control of Industrial Major Accident Hazard regulations apply to the site,
and the plant has operated in accordance with the Integrated Pollution Control
requirements of the 1990 Environmental Protection Act.
This requirement dominated much of the thinking behind the process and
engineering design.
Helium removal
The refluxing heat exchanger has the equivalent of several equilibrium stages
and provides a 30% rich helium stream, which is passed into the reject-
nitrogen stream.
Capacity control
The turndown requirements for the unit were to be able to run at any capacity
between 30 MMscfd and 200 MMscfd and to be able to move between plant
capacities at a ramp rate of 2 MMscfd/min.
As the plant throughput increases, the suction pressure to the machine rises
and the control system would automatically start another compressor. As the
plant throughput decreases, the sales-gas flow would decrease and the
control system would automatically stop one of the compressors.
Molecular sieves. At minimum feed-gas nitrogen content-that is,
8%-all of the reject nitrogen produced by the cold box is required for
mol-sieve regeneration.
To ensure there was always sufficient reject nitrogen for regeneration, the
molecular sieves ran on a variable on stream time, depending on the feed gas
flow rate. The on stream time was considerably extended during turndown
conditions based on flow totalizers, which automatically ensured complete
regeneration. This approach also reduced overall regeneration-energy needs.
By application of "feed-forward control," the DCS then increases the feed flow
at the maximum ramp rate allowed and adjusts the set points of all cold-box
controllers to the values required for the new feed flow rate.
The main reason for this approach is the relatively rapid ramp rate and the
need to maintain process temperatures and liquid levels. Some controllers
use temperature set points cascaded onto flow controllers.
Construction strategy
Such preassembly dramatically reduced the time for mechanical and electrical
field construction compared to industry norms. Commencement of module
installation to mechanical completion required less than 10 weeks.
Because of the overall sizes of the heating medium heater, ground flare, and
thermal oxidizer, these items were site assembled. They were contracted as
turnkey packages from the proprietary equipment suppliers.
The control of site construction work was especially important because the
plant location, adjacent the River Dee, is a "site of special scientific interest";
strict environmental conditions controlled all stages of the project including
minimization of emissions and site and plant appearance.
In scope, construction work was managed under the U.K. National Agreement
for the Engineering Construction Industry, the site being nominated as part of
the overall power-plant construction project.
References
Mike Healy is process engineering manager at Costain Oil, Gas & Process
Ltd., Manchester, U.K. Previously, he worked for M.W. Kellogg Ltd., London.
Healy holds a BS in chemical engineering from Nottingham University and is a
fellow of the Institution of Chemical Engineers and a chartered engineer in the
U.K.