Microsoft Project - NewestTimelineLNG
Microsoft Project - NewestTimelineLNG
Start Finish
Complete Jan 29, '17 Feb 12, '17 Feb 26, '17 Mar 12, '17 Mar 26, '17 Apr 9, '17 Apr 23, '17 May 7, '17 May 21, '17 Jun 4, '17 Jun 18, '17
S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F
0 22% Entire Timeline-LNG 89d Fri 2/10/17 Thu 6/15/17
1 16% PCTFE Seated 76d Fri 2/10/17 Fri 5/26/17
2 100% Standard Port 15d Fri 2/10/17 Fri 3/3/17
3 100% 150#/300# Class 15d Fri 2/10/17 Fri 3/3/17
4 100% 2-inch (PS15020) 0d Fri 2/10/17 Fri 2/10/17 2/10
Task Summary External Milestone Inactive Summary Manual Summary Rollup Finish-only
Project: Entire Timeline-LNG
Split Project Summary Inactive Task Manual Task Manual Summary Deadline
Date: Fri 3/17/17
Milestone External Tasks Inactive Milestone Duration-only Start-only Progress
Page 1
ID % Predecessors Task Name Duration
Start Finish
Complete Jan 29, '17 Feb 12, '17 Feb 26, '17 Mar 12, '17 Mar 26, '17 Apr 9, '17 Apr 23, '17 May 7, '17 May 21, '17 Jun 4, '17 Jun 18, '17
S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F
87 0% 81 * 0d Thu 6/15/17 Thu 6/15/17 6/15
Task Summary External Milestone Inactive Summary Manual Summary Rollup Finish-only
Project: Entire Timeline-LNG
Split Project Summary Inactive Task Manual Task Manual Summary Deadline
Date: Fri 3/17/17
Milestone External Tasks Inactive Milestone Duration-only Start-only Progress
Page 2