YAKIN WEST BRAVO PRE RIG ARRIVAL

NO DESCRIPTION 4-Jun 5-Jun 6-Jun 7-Jun 8-Jun 9-Jun


GENERAL
1 QSOP
2 MSW TRAINING ( DUE DATE 9-10 JUNE 2014 )
SITE VERIFIKASI SUPPORT CABLE TRAY / TUBING TRAY FOR LAYING
3
CABLE & TUBING
4 SITE ENGINEERING SURVEY FLOWLINE,VENTING & STRUCTURE
5 ENGINEERING DRAWING
6 CHEVRON AFC DRAWING
WORKSHOP
5 FABRICATION OF SPOOL
Flow Line 3" (16,17,18,19) from Wellhead to Test Header
Venting Line 2" (16,17,18,19) from Wellhead to Vent Header
6 FABRICATION OF SUPPORT CABLE TRAY
7 DELIVERY
FIELD
8 INSTALL SCAFFOLDING
PIPING WORK
9 Flow Line 3" (16,17,18,19) from Wellhead to Test Header
Hot Bolting & Demolish Spools
Install Spade Blind Flange/Blind Flange
10 Venting Line 2" (16,17,18,19) from Wellhead to Vent Header
Hot Bolting
Install Spade Blind Flange/Blind Flange
ELECTRICAL INSTRUMENT
11 INSTALL SUPPORT & CABLE TRAY
12 LAYING CABLE CONNECTING TUBING
13 CLEANING
Scrap pipe spool

NOTE
1.THE MTO MATERIAL ON SCHEDULE TOBE COMPLETED
10-Jun 11-Jun 12-Jun 13-Jun 14-Jun 15-Jun 16-Jun 17-Jun 18-Jun 19-Jun 20-Jun 21-Jun 22-Jun 23-Jun 24-Jun
25-Jun 26-Jun 27-Jun 28-Jun 29-Jun 30-Jun 1-Jul 2-Jul 3-Jul 4-Jul 5-Jul 6-Jul 7-Jul