Connection of Chilled Water from Qatar Cool still pending.
Requirements to get the CHW connection.
1) Chilled water flushing and chemical treatment is completed by contractor. (Reports to be submitted) 2) Air Balancing is ongoing contractor will provide the report by end of 14-11-2016. 3) Chilled water balancing is ongoing contractor will provide the report before 21-11-2016.
After completing all the above three steps contract will proceed for Qatar Cool connection for CHW.