Procedure for the Application of the Building Permit/

Certificate of Occupancy and Ancillary Permits

Step 0: Pre-Processing Requirements


Get checklist of Requirements from OBO. Comply with all the listed pre-
requisite documents, such as but not limited to the following. Zoning
Locational Clearance, Fire Clearance, etc.
If Building Permit Application
1. Get endorsement from OBO to BFP.
2. Get endorsement from OBO to DPWH (If along National Road).
If Certificate of Occupancy get Order of Payment for BFP assessment

Step 1: Get a priority number at the receiving counter and wait for your