Activities Required Duration/day(s)


Select Leader - 1
Choose Project Select Leader 1
Project Charter Select Leader, Choose 4
Project
Business Case Project Charter, Choose 6
Project
Kickoff Meeting Choose Project 1
SPMP Business Case 10
Verify & Validate Proj. SPMP 7
Req.
Procure Softwares Verify & Validate Proj. 4
Req.
Design Project Procure Softwares 10
Develop Project Design Project 20
Update SPMP Develop Project 4