Professional Documents
Culture Documents
Power System Protection-Requirement & Solutions
Power System Protection-Requirement & Solutions
ABB Group
June 13, 2013 | Slide 1 E-mail: jianping.wang@se.abb.com
Contents
VT CT
IR
IS
IT
Protection System Structure
Protection System
CT Circuit Breaker
Circuit
Protection Breaker
VT Trip
Equipment Mecha-
Coil
nism
TE
DC-System
Benefits of Clearing of Power System Faults
1- phase faults
Transient faults
80- 85%of all faults in transmission lines
Mainly caused by lightning strokes ( 0,2 - 3/ 100 km/year )
Additional faults by birds, trees, galloping lines etc.
Disappears if the line is disconnected and reclosed
Persistent faults
Broken conductor or insulator
Fallen tree
Has to be localised and repaired before the line can be
reenergized
Main Requirement on Power System Protection
1 u
Induction
Limits stress and Limits the risk to injure Limits the consequences
damages on lines, people and reduces the risk for the power system
busbars and equipment for long term damage
Personal Safety
Angle
t
5
t
4
t
3
t
2
t1
Time
Fault time t < t < t < t < t 4 5
1 2 3
Relay protection: Speed
2-phase faults
Speed
Stability
G G Less damage
Less stress 3-phase faults
Less ionization
0 60 100 200 ms
Fault disconnection time
Relay Protection: Sensitivity
28700
R f = 1.4 * L
I
Wrong settings
Unwanted trip
(at system fault) Faulty device
Non redundant protection system
+ -
Tripping unit
CABLE
CB Trip coil CABLE
CT CABLE
CABLE
VT
CABLE
Protective device
Redundant protection system
Trip coil 1
CABLE
CABLE
CABLE
CABLE
Battery 1
+ - CABLE
Tripping u. 1
CABLE CABLE
Battery 2
CABLE
+ - Main 1 Main 2
CABLE
Non-redundant and redundant protection
schemes
I
Redundant protection scheme with
1 out of 2 operating condition
II
Redundant protection
I II scheme with 2 out of 2
operating condition
Reliability of non-redundant and redundant
functions
R R
Probability of failure to operate
R
(dependability)
R R
IMPACT OF
SELF-SUPERVISION
Probability of unwanted operation (security)
Failure Rate of Protection Relays
BATHTUB CURVE
100
80
Failure rate
60
40
20
0
0 20 40 60 80 100
T ime
Part Two: Power System Protection
Applications
Inputs of A Protection Relay
RMS-measurement: <2%
Mean value measurement: < 20 %
100 %
Line Protection: General Practice
Transmission
Distance protection
Differential protection
Phase comparison protection
Transient measuring based protection
Distribution
- Over current protection: Directional/Non-Directional
- Differential protection
Transmission Line protection: Distance protection
K
Transmission Line protection: Distance protection
Algorithm I
G
XS U XL RL
X . di
u = i .R +
o. dt
Transmission Line Protection: Distance protection
time delayed
time delayed zone 3 zone 3
zone 2 zone 2
zone 1 zone 1
Related Issues:
Maximum reach Switch on to faults
around 80-90 %
Power Swing Block
Weak-end infeed logic
Current reversal logic
Line protection transmission: Distance protection
time delayed
A A- zone 2
A- zone 1
Z< B
G
B- zone 1 Z< Z< Z<
time delayed
B- zone 2
x
ph - ph ph - E The measurement is based on the
complete loop equations
Independent setting for each zone
of:
Reach in reactive direction
Reach in resistive direction for:
R phase to phase faults
phase to earth faults
Ground return compensation
Directionality
K
Transmission Line Protection:
Current differential protection
diff
diff
Current differential protection
L1
L2
L3
Under-reach Unblocking
Permissive
Unblocking
Overreach
weak infeed
transient blocking
Blocking Overreach
Auto-reclosing (AR)
The distribution of transient and permanent faults
on the one utility 130 kV system during 1987-1996
80
Auto-reclosing will in this
70
aspect increases the 60
availability 50 Series1
40
It will also have a positive 30
stability 10
0
Transient Permanent
faults faults
Transformer Protection
ABB Group
June 13, 2013 | Slide 42
Main Functions in Transformer Protection
ABB Group
June 13, 2013 | Slide 43
Differential Protection-Main Protection for Transformers
IFAULT IN IFAULT IN
3I0 IN 3I0 IN
G G G G
Typical Configuration of a Power Plant
Substation
Busbar in Substation
HV - Breaker
Power plant
Generator Breaker
Excitation Transformer
Excitation System
Turbine valve
Turbine - Generator G Field Circuit Breaker
Earthing System
Fault Classification on Generators
Internal External
Stator Rotor Stator Rotor Turbine
Short circuit Short circuit frequency
87 Differential
32 Reverse power 59 Over-voltage
51V Voltage/over-current
Rotor Stator
Single Line Diagram for a Unit Protection Scheme
51T 51NT
3
Step-up 1
(1)
24V/f 3
Transformer
59N
87GT (1)
87UAT 1
3 60
3
51N
3 32 59 81 24V/f
Auxiliary
1 Service
87G G 64R
Transformer
3 46 49S 51V 40 78 27/50 21
Generator with 1
64S
grounding system
Example of Damage Due to Failure of Trip by Protection
Busbar Protection-Requirement
Security
G G
G G
Stability for external
faults
G
Dependability
Correct operation for
internal faults
LOAD
G
Main Issues in Busbar Protection
Double busbar
Single busbar T1 Q0
Q1 Q2 Q1 Q2 Q1 Q2 Q1 Q2 Q1 Q2 Q1 Q2 Q1 Q2
T1
Q0 Q0 Q0 Q0 Q0 Q0 Q0 Q0
Q0 Q0 Q0 Q0 Q0 Q0 Q0 T1 T1 T1 T1 T1 T1 T1
T1 T1 T1 T1 T1 T1 T1
Q1 Q2 Q3 Q1 Q2 Q3 Q1 Q2 Q3 Q1 Q2 Q3 Q1 Q2 Q3 Q1 Q2 Q3
Q01 Q01 Q01 Q01 Q01
T01 T01 T01 T01 T01
Q0 Q0 Q0 Q0 Q0
.. . .. .
Reserve 1 Reserve 2
Four Zone Double Bus with two bus-coupler CBs and two
bus-section CBs and up to 20/21 feeder bays on each station side
Main 1 Main 2
.. . .. .
Reserve 1 Reserve 2
Four Zone Double Bus with two BC-CBs one BS-CB and one sectionalizing
disconnector with up to 18-20 feeder bays in the whole station
4
x 10 Prov nr 72 Stable for
3 external
2 fault!!!
1
0
Primary Current [A]
-1
-2
-3
-4
-5
Itot
-6 IX
Trip
PERFORMANCES
ARE IN GENERAL
IMPROVED
Electromechanical Relays 1903
Static Relays 1960
INX2 BBP 1966
Micro Processor Relays & INX5 BBP 1981
Numerical Generator Protection 1987
Numerical Protection &Control Devices 1991
Numerical HV Automation System 1991
Numerical Busbar & Breaker Failure Protection 1994
From 1903
to 2013
Analogue A/D Main GPS Binary Binary Binary Binary Binary mA Power
Input Conversion Processing Synch I/O I/O I/O I/O I/O Input Supply
Module Module Module Module Module Module Module Module Module Module Module
TRM AD1 NUM GSM BIM BIM BIM BOM BOM MIM PSM
3
PCU
3
Logics CAN
3 1Mbit/s
6I
A/D
6U
3
OEM
~
~ ~
~
LDCM
Comm-
uni-
cation
I/O I/O I/O I/O I/O mA
Modern Protection Products (IEDs)
RE_ 670
RE_ 630+RE_650
RE_ 615
Modern Protection Relays
known as Intelligent Electronic
RE_ 60_
Devices (IEDS)
Distribution Transmission
ModernTransmission Protection and Control Portfolios
parallel, parallel,
hardwired hardwired Process Bus
cabling cabling
Function Integration-Less Panels in Substation
Control Room
Line
12 12 6 6 3
Transformer
68 Cubicles, >180 Devices
Busbar
Feeders
Controllers
39 39 39 32 7
SAS690
Station Station
computer gateway
GOOSE
Network Engineering/
Control HSI
Monitoring
Center
Router switch