Institute For Sustainable Infrastructure (ISI): Case Studies Page 1 of I
cenvision™ case studies
bitps/ www sustainableinfrastructue.ongleasestudies/index cfm soareoi-MWRA Section $2 Phase 2 Water Ms
Boston, Massachusetts
‘Project Backuround: This project involved the
design and construction of more than two
niles of water transmission msin in Brookline
and Boston, Massachusetts. The existing see!
Pipeline was constructed in 1927-1928 and
serves asa major water transmission main for
the Massachusetts Water Resource Authority
(MWRA) Southern High Service Area.
Approximately 800 feet ofthe originl
pipeline was replaced in 1997 due to
‘excessive leaks and eorsion, leaving the
termining 11,500 fet in place. The
reenaining original pipe was rehabilitated
uring his projec uilizing innovative
trenchless technologies. Some key challenges
inthis project involved ensuring tha thee
were no averse impacts to the heathy mature
shade tres and significant wetland system byapat a Wa Ma TTT
located along the pipeline path. The multiple
rehabilitation methods used on the project, combined with work unde Route 9, work through resident
properties in Brookline, work through Hellen College, work under wetlands, and having fo maintain
water supply to customers at all imes made his complex project.
Project Stage and Budget This was a $10 million dollar project andi s 100% complet and operable as
of August 2007
“Triple Boom Lines
‘+ Economic - By performing extensive enginering investigation ofthe pipeline over its two (2)
nile length, inluding both internal and external inspections e multiple locations and peeforming
laboratory testing ofthe pipe material, sccurate assessments of the condition ofthe pipeline were
‘made for rehabilitation purposes. Because the condition ofthe pipe varied over the length ofthe
ligument, the evaluation determined which segments had corrosion issues (requiring
replacement or strtual rehabilitation) and which segments could be rehabilitated by simple
leaning. and cement-mortar lining techniques. AS a result of the extensive field work and
engineering analyses, it was determined thatthe life span of certain segments of the pipeline
could be extended for at least anther SO years by cleaning and lining, rater than structural
fehabilittion or replacement, In other areas where the pipe required replacement due to corosion
issues trenchless technologies, such as siplining and constructing ¢reinforeed cement-mortar
ining, were used in order o eliminate having to trench across a major state highway and through
sensitive environmental areas. Without performing. the extensive field investigtions and
engineering analyses to determine the condition of the existing pipe and lis potential for‘habitation, the design approach would have been o replace the pipe along the entire alignment
‘wing opencut trench excavation, which would have potentially doubled the cost of the projet
and would have generated significantly more waste material, environmental impact and
isturbance to the surounding area. Furthermore, performing extensive fed investigations and
engineering analyses as part of the design process allowed for accurate constuction documents,
‘which resuted in minimal change orders during construction.
‘+ Bavironmental ~ By using trenchless technologies to rehabilitate the pipe instead of
performing conventional open-cut trench excavation, the projet was able o aoid disturbing a
large wetland resource area, root systems of numerous mature shade tees, residetial propetos,
traffic, School zones, and a major intersection along Sate Route 9 in Brookline tt caries trafic
fiom the west of Boston into and ou ofthe city. One of the main project goals was to minimize
Aisturbance tothe environment and surrounding area during contruction and the project met this
oa in exemplary fashion.
‘+ Social - A significant portion of the pipeline is located in cross-country eassments that ran
‘through private properties in auent residential neighborhoods of Boston and Brookline, ss well,
18 through a college carpus. The MWRA and the design team held a number of public
inforatonaeightnroed meetings in order exp he need othe pj the aemates
that were evaluated, and how the prefered
erative was the most cost-effective,
‘vironmentally sensitive and east
Ssruptive option. The public meetings
allowed abutters to be involved in the
process, provide input, and have
foreknowledge of what would. happen
uring construetion. J. D'Amico, Ine. was
‘warded the contraction contract and they
also became involved in the meeting
process once they received thee Notice to
Proceed. The neighborhood mostngs paid
Iuge dividends during construction as
‘here were vitally no complaints ftom
residents (or subsequent delays),
‘Sustensbilty: The project came in under budget, met alts goals and reste in minimal disturbance to
(eo complains ffom) abutters because it was designed with the “tiple bottom line in mind. The
Aecisionto incorporate sustainability int the project was established by the MWRA and was stated in the
orginal Request for Proposals (REP) for design services. The MWRA established Hieycle cot,
‘environmental and neighborhood goals forthe project and also provided a detailed scope of work that
allowed for extensive engineering investigations and analyses to be performed, which aimetely saved
‘money, extended the useful life ofthe existing pipeline, minimized disroption and avoided environmental
iompoct
MWRA allowed the design team o thoroughly explore trenchless technology options to extend the life of
the exiting pipeline, thereby reducing costs, environmental impacts, neighborhood disruption and‘unnecessary waste of resources. The project will conserve water by repirng leskng pipes. The project
also avoided impacting wetland and healthy mature shade tres
‘More time and money was spent during the preliminary design
hase for fled investigations and engineving analyses that were
required to determine if (and how) the exsing pipe could be
fehabilitated as opposed to simply replacing it through open-eut
trench excavation. Also, designing trenchless pipe rehabilitation
methods was more complicated than designing anew pipe in an
opencut trench. However, the upfront investment in ational
engineering saved milions of dolls in constuction costs
compared to pipe replacement in an open-ut trench and allowed
‘the MWRA to meet its goals forthe projec, including minimizing
the amount of disturbance to sbutes andthe environment,
Based on MWRA’s (andthe design tea’ experience with
major infrastructure improvements in the Boston are and
MALY nowledge of ict environmental regulations in Mssechusts,
the projet was able to take advantage of several proven
‘eenchless technology techniques fo meet MWRA's goals. The design team also developed some new
innovative approaches to prevent corrosion of the tel pipeline inthe futur and ensure the pipeline lasts
{or at least another 50 years. The project was awarded the 2009 Gold Engineering Excelence Award
from the American Council of Engineering Companies of Massachusets (ACECIMA) fr the innovative
ee oftheve trenches echnolgies,
Envision™: The rating system was completed by Peter A. Richardson, P.E, LEED AP, the Vice
President of Green Intemational AMiates, Inc, Green served a the Prime Consultant on an experienced
engineering design team for this project, which also included Weston & Sampson Engineers, GEL
Consultants and CorrTech, Ine. The entire process of completing Envision™, including time to review
and understand the rating tool, took approximately 16-20 hours. Richardson agrees that the
esigning/planning stage isthe optimal time to complete Envision™ but if lilized Inter in the process he
secs it as tool to se how sustainable a recenly designed and constructed project was and where
sustaimble engineering opportunites were mised.
Atthough the design ofthe MWRA projet precede te 1S itv by couple of ears, he gts of
the MIRA projet aligned well with cna abjoctves ofthe rating system tht we pited. However,
cersn pars of th rating system werent applicable to a water main rehabilitation projet specify.
Though this projet was acady complete when plot esting Envision”, a pat deal fhe poet met
the tiple toto line witout ving been designed specifically with hese tree objcs in mind. This
process proves tat a well-enginered project inherently considers economic, environmental and sci
Inpcts. The rating tem aio elfimed the inporanceof performing bth cost-benefit ad tie cle
cost analyses fox projets o prove if project is sustainable and pilot esters elves should be a
euied prt ofthe submission.‘Utimately, using Envision™ on foture projects will depend on whether the project owner ses value in
using the tol. I is believed thatthe tool wil lly have value ifthe financial industry adops tas a way
to determine if project is good, sustsinabe investment and to deve which projets receive the best
Joan rates and bond ratings.
“Links:
todo newa.ore/PDE/AprConfbasess10:330.pdf