ID Task Name Duration Start Finish

19 Mar '17 26 Mar '17 02 Apr '17 09 Apr '17 16 Apr '17 23 Apr '17
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W
1 Trial Embankment (Core Material) 16 days? Mon 27/03/17 Tue 11/04/17

2 Administration Document 16 days Mon 27/03/17 Tue 11/04/17


3 Method Statement 14 days Mon 27/03/17 Sun 09/04/17
4 Request of Work 2 days Mon 10/04/17 Tue 11/04/17
5 Preparation of Yard 8 days Sat 08/04/17 Sat 15/04/17
6 Survey area 2 days Sat 08/04/17 Sun 09/04/17
7 Take sample subgrade 1 day Mon 10/04/17 Mon 10/04/17
8 Laboratory test (proctor) 3 days Tue 11/04/17 Thu 13/04/17
9 Grading & compaction 2 days Fri 14/04/17 Sat 15/04/17
10 Field density test 2 days Fri 14/04/17 Sat 15/04/17
11 Stockpile 20 days Mon 27/03/17 Sat 15/04/17
12 Excavation (Borrow Area 12 days Mon 27/03/17 Fri 07/04/17
No.4)
13 Take core material sample 2 days Fri 07/04/17 Sat 08/04/17
14 Laboratory test 7 days Sun 09/04/17 Sat 15/04/17
15 Execution of Trial Embankment 3 days Sun 16/04/17 Tue 18/04/17

16 Mob. of equipment 2 days Sun 16/04/17 Mon 17/04/17


17 Spreading & compaction 1 day Tue 18/04/17 Tue 18/04/17
18 In-situ test 1 day Tue 18/04/17 Tue 18/04/17
19 Report of Trial Embankment 6 days Wed 19/04/17 Mon 24/04/17
20 Make a report 4 days Wed 19/04/17 Sat 22/04/17
21 Submit official 2 days Sun 23/04/17 Mon 24/04/17