Flooring for Amethyst House

No. JOB DESCRIPTION D1 D2 D4 D5 D6 D7 D8 D9 D10 D11 D12 D13 D14 D15 D16 D17 D18 D19 20
Flooring
1 Installation of perimeter forms TARGET
ACTUAL
2 Concrete pouring on wall footing TARGET
ACTUAL
3 Installation of plumbing TARGET
ACTUAL
4 Installation of rebars TARGET
ACTUAL
5 Concrete pouring on slab TARGET
ACTUAL

Water Treatment Facilities


No. JOB DESCRIPTION D1 D2 D3 D4 D5 D6 D7 D8 D9 D10 D11 D12 D13 D14 D15 D16 D17 D18 D19 D20 D21 D22 D24 D25 D26 D27

1 Excavation TARGET
ACTUAL
2 Installation of form on perimeter TARGET
ACTUAL
3 Installation of rebars on footing TARGET
ACTUAL
4 Concrete pouring on footing TARGET
ACTUAL
5 Installation of rebars on slab TARGET
ACTUAL
6 Concrete pouring on slab TARGET
ACTUAL
7 Installation of rebars on wall TARGET
ACTUAL
8 Installation of forms on wall TARGET
ACTUAL
9 Concrete Pouring on walls TARGET
ACTUAL
10 Detaching of forms on wall TARGET
ACTUAL
11 Fabrication of pvp pipe TARGET
ACTUAL
12 Backfill of Gravel and Sand TARGET
ACTUAL
13 Installation of ladders TARGET
ACTUAL
14 Installation of scaffolding and form on cover TARGET
ACTUAL
15 Installation of rebars on cover TARGET
ACTUAL
16 Concrete Pouring on Cover TARGET
ACTUAL
17 Removing of form after 28 days TARGET
ACTUAL
18 Installation of manhole TARGET
ACTUAL
18
D28 D29 D30 D31 D32 D33 D34