You are on page 1of 1

Individual Progress

Progress Summary by Project Area-Piping Fabrication


Project Quantity Progress Weighting Overall
Man hour Weighting
Area (Dia-inch) by Area (Overall) Progress
A 1000 6000 0.43 100% 0.086957 8.7%
B 1500 8000 0.57 100% 0.115942 11.6%
Total 2500 14000 1.00
Data from detail
Progress Summary by Project Area-Piping Erection tracking sheet
Project Quantity Progress
Man hour Weighting
Area (Dia-inch) by Area
A 300 4000 0.40 100% 0.057977 5.8%
B 450 6000 0.60 100% 0.086955 8.7%
Total 750 10000 1.00

Progress Summary by Project Area-Steel Fabrication


Project Quantity Progress
Man hour Weighting
Area (Tonage) by Area
A 100 4800 0.61 100% 0.069565 6.9%
B 70 3100 0.39 100% 0.044928 4.5%
Total 170 7900 1.00

Progress Summary by Project Area-Steel Erection


Project Quantity Progress
Man hour Weighting
Area (Tonage) by Area
A 100 4800 0.61 100% 0.069565 6.9%
B 70 3100 0.39 100% 0.044928 4.5%
Total 170 7900 1.00
Progress Summary by Project Area-Tie-in Installation
Project Progress
Qty (Pcs) Man hour Weighting
Area by Area
A 10 1500 0.45 100% 0.021739 2.2%
B 5 1800 0.55 100% 0.026087 2.6%
Total 15 3300 1.00
Progress Summary by Project Area-Piping Hydro Testing
Project Quantity Progress
Man hour Weighting
Area (Meter) by Area
A 5000 2800 0.44 92% 0.04058 3.7%
B 7000 3500 0.56 52% 0.050725 2.6%
Total 12000 6300 1.00
Progress Summary by Project Area-Equipment Erection
Project Quantity Progress
Man hour Weighting
Area (Tonage) by Area
A 159 1600 0.44 80% 0.023188 1.8%
B 168 2000 0.56 89% 0.02898 2.6%
Total 327 3600 1.00
Progress Summary by Project Area-Painting
Project Quantity Progress
Man hour Weighting
Area (Tonage) by Area
A 300 2000 0.36 36% 0.02898 1.1%
B 450 3500 0.64 57% 0.050731 2.9%
Total 750 5500 1.00
Progress Summary by Project Area-Insulation
Project Quantity Progress
Man hour Weighting
Area (Tonage) by Area
A 2000 4500 0.43 100% 0.065217 6.5%
B 3000 6000 0.57 87% 0.086957 7.6%
Total 5000 10500 1.00
Progress Summary by Project Area-all disciplines
Overall
Project
Man hour Weighting(Overall) Progress
Area
by Area
A 32000 0.464 43.7%
B 37000 0.536 47.6%
Total 69000 1.000 91.3%

Developed by Toolbox4Planning
Learn more at http://www.toolboxforplanning.com

You might also like