Uraian Pekerjaan Analisa Volume Sat. Harga Satuan (Rp) Jumlah Harga (Rp)
I PEKERJAAN PENDAHULUAN
1 Pembuatan Gudang semen dan peralatan A.2 9.00 m2 3,244,688.83 29,202,199.50
2 Pembuatan bedeng buruh A.4 18.00 m2 3,219,890.00 57,958,020.00
Total 87,160,219.50
87,160,219.50
II PEKERJAAN INTAKE
A PEKERJAAN PERSIAPAN
1 Pengukuran dan pasang bowplank (profil melintang) A.1 16.00 M' 147,617.33 2,361,877.28
2 Pengerukan dasar sungai (excavator) sewa 1.00 hari 11,843,099.03 11,843,099.03
11,8 Sub Total 14,204,976.310
B PEKERJAAN TANAH
1 Galian Tanah Kolam Bak Intake (dengan excavator) Analisa EI - 135.41 M3 95,070.66 12,873,518.21
2 Urugan kembali B.2 16.90 M3 24,568.50 415,207.65
Sub Total 13,288,725.860
C PEKERJAAN PASANGAN BATU/BETON
1 Pek. Pondasi pas. Batu Kali camp. 1 Pc : 4 Ps C.1 22.55 M3 12,702,010.10 286,430,327.76
2 Pek. Dinding tembok pas. Batu kali camp. 1 Pc : 4 Ps C.1 23.96 M3 12,702,010.10 304,340,162.00
3 Siar mata sapi dinding tembok saluran adukan 1 Pc : 2 Ps D.3 17.22 M2 420,943.75 7,248,651.37
4 Plester dinding dalam bak camp. 1 Pc : 2 Ps D.1 46.10 M2 645,446.01 29,755,061.06
5 Pas. Batu kosong bawah lantai C.2 9.00 M3 3,749,773.50 33,747,961.50
6 Cor lantai bak intake beton 1 Pc : 2 Ps : 3 Kr E.2 6.75 M3 21,628,034.47 145,989,232.67
7 Pas. Bronjong bentuk I type D (keranjang uk. 2 x 1 x 0,5) N.1 14.00 M3 4,271,025.00 59,794,350.00
59,7 Sub Total 867,305,746.36
D PEKERJAAN BETON BERTULANG
1 Pekerjaan Sloof (60/15) beton 1 Pc : 2 Ps : 3 Kr
Pembesian Sloof E.3 266.80 Kg 80,373.62 21,443,681.82
Pas. bekesting Sloof E.5 36.20 M2 413,513.57 14,969,191.23
14,9 Pengecoran beton Sloof 1 Pc : 2 Ps : 3 Kr E.2 3.62 M3 21,628,034.47 78,293,484.78
Jumlah 1 114,706,357.83
2 Pekerjaan Kolom K1 (60/60) beton 1 Pc : 2 Ps : 3 Kr
Pembesian kolom K1 E.3 141.16 Kg 80,373.62 11,345,540.20
Pas. bekesting Kolom K1 E.6 10.57 M2 955,264.36 10,097,144.29
Pengecoran beton Kolom K1 1 Pc : 2 Ps : 3 Kr E.2 3.17 M3 21,628,034.47 68,560,869.27
Jumlah 2 90,003,553.76
3 Pekerjaan Ringbalk (60/15) beton 1 Pc : 2 Ps : 3 Kr
Pembesian Ringbalk R1 E.3 309.99 Kg 80,373.62 24,915,018.46
Pas. bekesting Ringbalk R1 E.7 5.28 M2 955,264.36 5,043,795.82
Pengecoran beton Ringbalk R1 1 Pc : 2 Ps : 3 Kr E.2 3.17 M3 21,628,034.47 68,560,869.27
Jumlah 3 98,519,683.55
Sub Total 303,229,595.140
E PEKERJAAN ACCESORIS
1 Pasang besi profil C 50.38 (10 bh x 50 cm) O.1 27.85 kg 2,871,024.75 79,958,039.29
2 Pas. Penyaring Teralis besi beton 12 mm P.1 2.00 Unit 11,951,407.14 23,902,814.28
3 Pas. Sponning Pintu Penguras P1 besi profil P.4 2.00 Unit 1,873,065.48 3,746,130.96
4 Pas. Sponning Pintu Pengontrol P2 besi profil P.5 2.00 Unit 1,491,779.21 2,983,558.42
5 Pas. Pintu Penguras P1 P.6 2.00 Unit 13,355,367.94 26,710,735.88
EE ILU THP I - 3
Uraian Pekerjaan Analisa Volume Sat. Harga Satuan (Rp) Jumlah Harga (Rp)
EE ILU THP I - 4
Uraian Pekerjaan Analisa Volume Sat. Harga Satuan (Rp) Jumlah Harga (Rp)
EE ILU THP I - 5
Uraian Pekerjaan Analisa Volume Sat. Harga Satuan (Rp) Jumlah Harga (Rp)
Jumlah 3 87,109,066.54
4 Pekerjaan Plat (tebal 12 cm) Beton Bertulang 1 Pc : 2 Ps : 3 Kr
Pembesian plat beton E.4 111.82 Kg 80,373.62 8,987,378.19
Pasang bekesting E.8 5.10 M2 1,448,064.36 7,385,128.24
Pengecoran plat beton E.2 0.79 M3 21,628,034.47 17,086,147.23
Jumlah 4 33,458,653.66
Sub Total 302,624,060.790
EE ILU THP I - 6
Uraian Pekerjaan Analisa Volume Sat. Harga Satuan (Rp) Jumlah Harga (Rp)
E PEKERJAAN ACCESORIS
1 Pas. Trashrack besi beton 12 mm P.2 1.00 Unit 14,459,030.76 14,459,030.76
2 Pengadaan Pipa GIP dia 8" Harga Bahan dan upah 1.00 btg 15,525,300.00 15,525,300.00
3 Pengadaan Flange + Plat penutup pipa penguras dia 8" Harga Bahan dan upah 1.00 set 6,462,550.00 6,462,550.00
4 Pengecatan trashrack dengan meni besi K.4 43.99 M2 47,550.25 2,091,735.50
5 Pengecatan trashrack dengan cat besi K.5 43.99 M2 51,730.25 2,275,613.70
Sub Total 40,814,229.960
Total 1,817,179,862.510
EE ILU THP I - 7
Uraian Pekerjaan Analisa Volume Sat. Harga Satuan (Rp) Jumlah Harga (Rp)
2 Pas. Pondasi dan dinding batu kali camp. 1 Pc : 4 Ps C.1 12.22 M 12,702,010.10 155,218,563.42
3 Pas. Pondasi rabat batu kali camp. 1 Pc : 4 Ps C.1 1.39 M 12,702,010.10 17,655,794.04
4 Pas. Dinding batu batako camp. 1 Pc : 4 Ps F.1 54.67 M 1,808,030.90 98,845,049.30
5 Pek. Siar mata sapi dinding batu kali camp. 1 Pc : 2 Ps D.3 17.53 M 420,943.75 7,379,143.94
6 Plesteran dinding batako camp. 1 Pc : 4 Ps D.2 112.07 M 443,765.60 49,732,810.79
7 Pas. Pipa PVC 2" bawah lantai untuk kabel M.3 8.00 M' 356,324.33 2,850,594.64
8 Cor lantai rumah beton tumbuk 1 Pc : 3 Ps : 5 Kr tebal 10 cm E.1 4.17 M 15,292,396.09 63,769,291.70
9 Plesteran Lantai Rumah camp. 1 Pc : 2 Ps tebal 15 mm D.1 41.67 M 645,446.01 26,895,735.24
10 Acian Lantai Rumah D.4 41.67 M 206,704.14 8,613,361.51
11 Pek. Dinding blok beton pas. Bt. Kali camp. 1 Pc : 4 Ps C.1 5.97 M 12,702,010.10 75,831,000.30
12 Pek. Dinding Saluran pembuang pas. batu kali camp. 1 Pc : 4 Ps C.1 5.95 M 12,702,010.10 75,576,960.10
13 Plesteran dinding saluran pembuang camp. 1 Pc : 2 Ps D.1 25.74 M 645,446.01 16,613,780.30
14 Pas. Batu kosong bawah lantai saluran pembuang C.2 2.27 M 3,749,773.50 8,511,985.85
15 Cor lantai saluran beton 1 Pc : 3 Ps : 3 Kr E.2 1.70 M 21,628,034.47 36,767,658.60
Sub Total 659,148,330.530
EE ILU THP I - 8
Uraian Pekerjaan Analisa Volume Sat. Harga Satuan (Rp) Jumlah Harga (Rp)
EE ILU THP I - 9
Uraian Pekerjaan Analisa Volume Sat. Harga Satuan (Rp) Jumlah Harga (Rp)
2 Pek. Pengecatan Daun Pintu Panil (cat minyak) K.1 11.84 M 100,380.26 1,188,502.28
3 Pek. Pengecatan Daun Jendela panil kaca (cat minyak) K.1 1.29 M 100,380.26 129,490.54
4 Pek. Pengecatan teralis jendela (cat besi) K.5 2.94 M 51,730.25 152,086.94
5 Pek. Pengecatan Plafond (cat tembok) K.3 65.55 M 45,536.31 2,984,905.12
6 Pek. Pengecatan Dinding Tembok (cat minyak) K.1 129.60 M 100,380.26 13,009,281.70
7 Pek. Pengecatan balok pengikat kolom (cat minyak) K.1 3.60 M 100,380.26 361,368.94
8 Pek. Pengecatan listplank (cat minyak) K.1 6.56 M 100,380.26 658,494.51
9 Pek. Pengecatan Dinding Kap (cat minyak) K.1 12.70 M 100,380.26 1,274,829.30
10 Pek. Pengecatan tiang teras (cat minyak) K.1 1.80 M 100,380.26 180,684.47
11 Pek. Pengecatan atap (cat atap) K.2 69.42 M 53,562.14 3,718,283.76
Sub Total 24,420,817.540
EE ILU THP I - 10
Uraian Pekerjaan Analisa Volume Sat. Harga Satuan (Rp) Jumlah Harga (Rp)
X PEKERJAAN AKHIR
1 Dokumentasi/Pelaporan Ditafsir 1.00 Ls 2,500,000.00 2,500,000.00
2 Pembongkaran dan pembersihan gudang dan bedeng buruh Ditafsir 1.00 Ls 2,500,000.00 2,500,000.00
Sub Total 5,000,000.000
Total 5,000,000.000
EE ILU THP I - 11
ANALISA BIAYA KONSTRUKSI (ABK)
BANGUNAN GEDUNG DAN PERUMAHAN
DISTRIK NIOGA
EE Analisa Harga - 12
Menggali 1 m3 Tanah biasa
6.1.2 Tenaga :
Pekerja 0.7500 OH x Rp 100,000.00 = Rp 75,000.00
Mandor 0.0250 OH x Rp 165,000.00 = Rp 4,125.00
A. JUMLAH UPAH = Rp 79,125.00
B. Overhead + Profit (10%) = Rp 7,912.50
B.1 C. Total = Rp 87,037.50
B.2 SNI 2835 - 2008 (6.9)
1 M Urugan Kembali
6.9.2 Tenaga :
Pekerja 0.1920 OH x Rp 100,000.00 = Rp 19,200.00
Mandor 0.0190 OH x Rp 165,000.00 = Rp 3,135.00
A. JUMLAH UPAH = Rp 22,335.00
B. Overhead + Profit (10%) = Rp 2,233.50
B.2 C. Total = Rp 24,568.50
EE Analisa Harga - 13
B.3 SNI 2835 - 2008 (6.10)
Memadatkan 1 m3 tanah (per 20 cm)
Tenaga :
6.10.2 Pekerja 0.5000 OH x Rp 100,000.00 = Rp 50,000.00
Mandor 0.0500 OH x Rp 165,000.00 = Rp 8,250.00
A. JUMLAH UPAH = Rp 58,250.00
B. Overhead + Profit (10%) = Rp 5,825.00
B.3 C. Total = Rp 64,075.00
B.4 SNI 2835 - 2008 (6.11)
Mengurug 1 m3 pasir urug
6.11.1 Bahan :
Pasir Urug 1.2000 M x Rp 2,000,000.00 = Rp 2,400,000.00
A. JUMLAH HARGA BAHAN = Rp 2,400,000.00
6.11.2 Tenaga :
Pekerja 0.3000 OH x Rp 100,000.00 = Rp 30,000.00
Mandor 0.0100 OH x Rp 165,000.00 = Rp 1,650.00
B. JUMLAH UPAH = Rp 31,650.00
C. JUMLAH BAHAN DAN UPAH = Rp 2,431,650.00
D. Overhead + Profit (10%) = Rp 243,165.00
B.4 E. Total = Rp 2,674,815.00
B.5 SNI 2835 - 2008 (6.15)
Mengurug 1 m3 Batu Kali
6.15.1 Bahan :
Batu kali 1.2000 M x Rp 2,000,000.00 = Rp 2,400,000.00
A. JUMLAH HARGA BAHAN = Rp 2,400,000.00
6.15..2 Tenaga :
Pekerja 0.3000 OH x Rp 100,000.00 = Rp 30,000.00
Mandor 0.0100 OH x Rp 165,000.00 = Rp 1,650.00
B. JUMLAH UPAH = Rp 31,650.00
C. JUMLAH BAHAN DAN UPAH = Rp 2,431,650.00
D. Overhead + Profit (10%) = Rp 243,165.00
B.5 E. Total = Rp 2,674,815.00
C. PEKERJAAN PONDASI SNI 2836 - 2008
C.1 SNI 2836 - 2008 (6.2)
Memasang 1 M pondasi batu kali, campuran 1 Pc :4 Ps
6.2.1 Bahan :
Batu kali 1.2000 M x Rp 2,000,000.00 = Rp 2,400,000.00
Semen PC 163.0000 Kg x Rp 48,028.57 = Rp 7,828,656.91
Pasir Pasang 0.5200 M x Rp 2,000,000.00 = Rp 1,040,000.00
A. JUMLAH HARGA BAHAN = Rp 11,268,656.91
6.2.2 Tenaga :
Pekerja 1.5000 OH x Rp 100,000.00 = Rp 150,000.00
Tukang batu 0.7500 OH x Rp 140,000.00 = Rp 105,000.00
Kepala Tukang 0.0750 OH x Rp 150,000.00 = Rp 11,250.00
Mandor 0.0750 OH x Rp 165,000.00 = Rp 12,375.00
B. JUMLAH UPAH = Rp 278,625.00
C. JUMLAH BAHAN DAN UPAH = Rp 11,547,281.91
D. Overhead + Profit (10%) = Rp 1,154,728.19
C.1 E. Total = Rp 12,702,010.10
C.2 SNI 2836 - 2008 (6.9)
Memasang 1 M Batu Kosong (Aanstamping)
6.9.1 Bahan :
Batu kali 1.2000 M x Rp 2,000,000.00 = Rp 2,400,000.00
Pasir Pasang 0.4320 M x Rp 2,000,000.00 = Rp 864,000.00
A. JUMLAH HARGA BAHAN = Rp 3,264,000.00
6.9.2 Tenaga :
Pekerja 0.7800 OH x Rp 100,000.00 = Rp 78,000.00
Tukang batu 0.3900 OH x Rp 140,000.00 = Rp 54,600.00
Kepala Tukang 0.0390 OH x Rp 150,000.00 = Rp 5,850.00
Mandor 0.0390 OH x Rp 165,000.00 = Rp 6,435.00
B. JUMLAH UPAH = Rp 144,885.00
C. JUMLAH BAHAN DAN UPAH = Rp 3,408,885.00
D. Overhead + Profit (10%) = Rp 340,888.50
C.2 E. Total = Rp 3,749,773.50
D. PEKERJAAN PLESTERAN SNI 2837 - 2008
D.1 SNI 2837-2008 (6.2)
Membuat 1 m2 plesteran 1 Pc:2 Ps tebal 15 mm
6.2.1 Bahan :
Semen Pc 10.2240 Kg x Rp 48,028.57 = Rp 491,044.10
Pasir Pasang 0.0200 M x Rp 2,000,000.00 = Rp 40,000.00
EE Analisa Harga - 14
A. JUMLAH HARGA BAHAN = Rp 531,044.10
6.2.2 Tenaga :
Pekerja 0.3000 OH x Rp 100,000.00 = Rp 30,000.00
Tukang batu 0.1500 OH x Rp 140,000.00 = Rp 21,000.00
Kepala Tukang 0.0150 OH x Rp 150,000.00 = Rp 2,250.00
Mandor 0.0150 OH x Rp 165,000.00 = Rp 2,475.00
B. JUMLAH UPAH = Rp 55,725.00
C. JUMLAH BAHAN DAN UPAH = Rp 586,769.10
D. Overhead + Profit (10%) = Rp 58,676.91
D.1 E. Total = Rp 645,446.01
EE Analisa Harga - 15
D.2 SNI 2837-2008 (6.4)
Membuat 1 m2 plesteran 1 Pc:4 Ps tebal 15 mm
6.4.1 Bahan :
Semen PC 6.2400 Kg x Rp 48,028.57 = Rp 299,698.28
Pasir Pasang 0.0240 M x Rp 2,000,000.00 = Rp 48,000.00
A. JUMLAH HARGA BAHAN = Rp 347,698.28
6.4.2 Tenaga :
Pekerja 0.3000 OH x Rp 100,000.00 = Rp 30,000.00
Tukang batu 0.1500 OH x Rp 140,000.00 = Rp 21,000.00
Kepala Tukang 0.0150 OH x Rp 150,000.00 = Rp 2,250.00
Mandor 0.0150 OH x Rp 165,000.00 = Rp 2,475.00
B. JUMLAH UPAH = Rp 55,725.00
C. JUMLAH BAHAN DAN UPAH = Rp 403,423.28
D. Overhead + Profit (10%) = Rp 40,342.33
D.2 E. Total = Rp 443,765.60
D.3 SNI 2837-2008 (6.26)
MEMASANG 1 M2 FINISHING SIAR PASANGAN BATU KALI ADUKAN 1 PC : 2 PP
6.26.1 Bahan :
Semen PC 6.3400 Kg x Rp 48,028.57 = Rp 304,501.13
Pasir Pasang 0.0120 M x Rp 2,000,000.00 = Rp 24,000.00
A. JUMLAH HARGA BAHAN = Rp 328,501.13
6.26.2 Tenaga :
Pekerja 0.3000 OH x Rp 100,000.00 = Rp 30,000.00
Tukang batu 0.1400 OH x Rp 140,000.00 = Rp 19,600.00
Kepala Tukang 0.0140 OH x Rp 150,000.00 = Rp 2,100.00
Mandor 0.0150 OH x Rp 165,000.00 = Rp 2,475.00
B. JUMLAH UPAH = Rp 54,175.00
C. JUMLAH BAHAN DAN UPAH = Rp 382,676.13
D. Overhead + Profit (10%) = Rp 38,267.61
D.3 E. Total = Rp 420,943.75
D.4 SNI 2837-2008 (6.27)
MEMASANG 1 M2 ACIAN
6.27.1 Bahan :
Semen PC 3.2500 Kg x Rp 48,028.57 = Rp 156,092.85
A. JUMLAH HARGA BAHAN = Rp 156,092.85
6.27.2 Tenaga :
Pekerja 0.1500 OH x Rp 100,000.00 = Rp 15,000.00
Tukang batu 0.1000 OH x Rp 140,000.00 = Rp 14,000.00
Kepala Tukang 0.0100 OH x Rp 150,000.00 = Rp 1,500.00
Mandor 0.0080 OH x Rp 165,000.00 = Rp 1,320.00
B. JUMLAH UPAH = Rp 31,820.00
C. JUMLAH BAHAN DAN UPAH = Rp 187,912.85
D. Overhead + Profit (10%) = Rp 18,791.29
D.4 E. Total = Rp 206,704.14
E. PEKERJAAN BETON SNI 7394 - 2008
E.1 SNI 2002 . 6.1
Membuat 1 m3 beton tumbuk 1 Pc : 3 Ps : 5 Kr
6.1.1 Bahan :
Semen PC 218.0000 Kg x Rp 48,028.57 = Rp 10,470,228.26
Pasir Cor 0.5200 M x Rp 2,000,000.00 = Rp 1,040,000.00
Kerikil pecah 0.8700 M x Rp 2,500,000.00 = Rp 2,175,000.00
A. JUMLAH HARGA BAHAN = Rp 13,685,228.26
6.1.2 Tenaga :
Pekerja 1.6500 OH x Rp 100,000.00 = Rp 165,000.00
Tukang batu 0.2500 OH x Rp 140,000.00 = Rp 35,000.00
Kepala Tukang 0.0250 OH x Rp 150,000.00 = Rp 3,750.00
Mandor 0.0800 OH x Rp 165,000.00 = Rp 13,200.00
B. JUMLAH UPAH = Rp 216,950.00
C. JUMLAH BAHAN DAN UPAH = Rp 13,902,178.26
D. Overhead + Profit (10%) = Rp 1,390,217.83
E.1 E. Total = Rp 15,292,396.09
E.2 SNI 2002. 6.13
1 M3 Membuat beton bertulang, 1 Pc : 2 Ps : 3 Kr
6.13.1 Bahan
Semen PC 336.0000 Kg x Rp 48,028.57 = Rp 16,137,599.52
Pasir Cor 0.5400 M3 x Rp 2,000,000.00 = Rp 1,080,000.00
Kerikil pecah 0.8100 M3 x Rp 2,500,000.00 = Rp 2,025,000.00
A. JUMLAH HARGA BAHAN = Rp 19,242,599.52
6.13.2 Tenaga
EE Analisa Harga - 16
Pekerja 2.0000 Oh x Rp 100,000.00 = Rp 200,000.00
Tukang Batu 0.3500 Oh x Rp 140,000.00 = Rp 49,000.00
Kepala Tukang 0.0350 Oh x Rp 150,000.00 = Rp 5,250.00
Mandor 1.0000 Oh x Rp 165,000.00 = Rp 165,000.00
B. JUMLAH UPAH = Rp 419,250.00
C. JUMLAH BAHAN DAN UPAH = Rp 19,661,849.52
D. Overhead + Profit (10%) = Rp 1,966,184.95
E. Total = Rp 21,628,034.47
EE Analisa Harga - 17
E.3 PEMBESIAN 1 KG DENGAN BESI POLOS
6.17.1 Bahan :
Besi beton polos 1.0500 Kg x Rp 66,728.57 = Rp 70,065.00
Kawat ikat 0.0150 Kg x Rp 76,728.57 = Rp 1,150.93
A. JUMLAH HARGA BAHAN = Rp 71,215.93
6.17.2 Tenaga :
Pekerja 0.0070 OH x Rp 100,000.00 = Rp 700.00
Tukang besi 0.0070 OH x Rp 140,000.00 = Rp 980.00
Kepala Tukang 0.0007 OH x Rp 150,000.00 = Rp 105.00
Mandor 0.0004 OH x Rp 165,000.00 = Rp 66.00
B. JUMLAH UPAH = Rp 1,851.00
C. JUMLAH BAHAN DAN UPAH = Rp 73,066.93
D. Overhead + Profit (10%) = Rp 7,306.69
### E. Total = Rp 80,373.62
E.4 SNI 7394-2008 (6.20)
MEMASANG 1 M2 BEKESTING UNTUK PONDASI
6.20.1 Bahan :
Kayu papan 0.0400 M3 x Rp 5,600,000.00 = Rp 224,000.00
Paku campur 0.3000 Kg x Rp 73,628.57 = Rp 22,088.57
Minyak bekesting 0.1000 Ltr x Rp 52,428.57 = Rp 5,242.86
A. JUMLAH HARGA BAHAN = Rp 251,331.43
6.20.2 Tenaga :
Pekerja 0.5200 OH x Rp 100,000.00 = Rp 52,000.00
Tukang kayu 0.2600 OH x Rp 140,000.00 = Rp 36,400.00
Kepala Tukang 0.0260 OH x Rp 150,000.00 = Rp 3,900.00
Mandor 0.0260 OH x Rp 165,000.00 = Rp 4,290.00
B. JUMLAH UPAH = Rp 96,590.00
C. JUMLAH BAHAN DAN UPAH = Rp 347,921.43
D. Overhead + Profit (10%) = Rp 34,792.14
E.4 E. Total = Rp 382,713.57
E.5 SNI 7394-2008 (6.21)
MEMASANG 1 M2 BEKESTING UNTUK SLOOF
6.21.1 Bahan :
Kayu papan 0.0450 M3 x Rp 5,600,000.00 = Rp 252,000.00
Paku campur 0.3000 Kg x Rp 73,628.57 = Rp 22,088.57
Minyak Bekesting 0.1000 Ltr x Rp 52,428.57 = Rp 5,242.86
A. JUMLAH HARGA BAHAN = Rp 279,331.43
6.21.2 Tenaga :
Pekerja 0.5200 OH x Rp 100,000.00 = Rp 52,000.00
Tukang kayu 0.2600 OH x Rp 140,000.00 = Rp 36,400.00
Kepala Tukang 0.0260 OH x Rp 150,000.00 = Rp 3,900.00
Mandor 0.0260 OH x Rp 165,000.00 = Rp 4,290.00
B. JUMLAH UPAH = Rp 96,590.00
C. JUMLAH BAHAN DAN UPAH = Rp 375,921.43
D. Overhead + Profit (10%) = Rp 37,592.14
E.5 E. Total = Rp 413,513.57
E.6 SNI 7394-2008 (6.22)
MEMASANG 1 M2 BEKESTING UNTUK KOLOM
6.22.1 Bahan :
Kayu papan 0.0400 M3 x Rp 5,600,000.00 = Rp 224,000.00
Paku campur 0.4000 Kg x Rp 73,628.57 = Rp 29,451.43
Minyak Bekesting 0.2000 ltr x Rp 52,428.57 = Rp 10,485.71
Kayu balok 0.0150 M3 x Rp 5,600,000.00 = Rp 84,000.00
Tripleks 6 mm 0.3500 lbr x Rp 496,828.57 = Rp 173,890.00
Balok 5/10 panjang 3 m 2.0000 btg x Rp 112,000.00 = Rp 224,000.00
A. JUMLAH HARGA BAHAN = Rp 745,827.14
6.22.2 Tenaga :
Pekerja 0.6600 OH x Rp 100,000.00 = Rp 66,000.00
Tukang besi 0.3300 OH x Rp 140,000.00 = Rp 46,200.00
Kepala Tukang 0.0330 OH x Rp 150,000.00 = Rp 4,950.00
Mandor 0.0330 OH x Rp 165,000.00 = Rp 5,445.00
B. JUMLAH UPAH = Rp 122,595.00
C. JUMLAH BAHAN DAN UPAH = Rp 868,422.14
D. Overhead + Profit (10%) = Rp 86,842.21
E.6 E. Total = Rp 955,264.36
E.7 SNI 7394-2008 (6.23)
MEMASANG 1 M2 BEKESTING UNTUK BALOK
6.23.1 Bahan :
Kayu papan 0.0400 M3 x Rp 5,600,000.00 = Rp 224,000.00
Paku campur 0.4000 Kg x Rp 73,628.57 = Rp 29,451.43
EE Analisa Harga - 18
Minyak Bekesting 0.2000 ltr x Rp 52,428.57 = Rp 10,485.71
Kayu balok 0.0150 M3 x Rp 5,600,000.00 = Rp 84,000.00
Tripleks 6 mm 0.3500 lbr x Rp 496,828.57 = Rp 173,890.00
Balok 5/10 panjang 3 m 2.0000 btg x Rp 112,000.00 = Rp 224,000.00
A. JUMLAH HARGA BAHAN = Rp 745,827.14
6.23.2 Tenaga :
Pekerja 0.6600 OH x Rp 100,000.00 = Rp 66,000.00
Tukang besi 0.3300 OH x Rp 140,000.00 = Rp 46,200.00
Kepala Tukang 0.0330 OH x Rp 150,000.00 = Rp 4,950.00
Mandor 0.0330 OH x Rp 165,000.00 = Rp 5,445.00
B. JUMLAH UPAH = Rp 122,595.00
C. JUMLAH BAHAN DAN UPAH = Rp 868,422.14
D. Overhead + Profit (10%) = Rp 86,842.21
E.7 E. Total = Rp 955,264.36
EE Analisa Harga - 19
E.8 SNI 7394-2008 (6.24)
MEMASANG 1 M2 BEKESTING UNTUK LANTAI
6.24.1 Bahan :
Kayu papan 0.0400 M3 x Rp 5,600,000.00 = Rp 224,000.00
Paku campur 0.4000 Kg x Rp 73,628.57 = Rp 29,451.43
Minyak Bekesting 0.2000 ltr x Rp 52,428.57 = Rp 10,485.71
Kayu balok 0.0150 M3 x Rp 5,600,000.00 = Rp 84,000.00
Tripleks 6 mm 0.3500 lbr x Rp 496,828.57 = Rp 173,890.00
Balok 5/10 panjang 3 m 6.0000 btg x Rp 112,000.00 = Rp 672,000.00
A. JUMLAH HARGA BAHAN = Rp 1,193,827.14
6.24.2 Tenaga :
Pekerja 0.6600 OH x Rp 100,000.00 = Rp 66,000.00
Tukang besi 0.3300 OH x Rp 140,000.00 = Rp 46,200.00
Kepala Tukang 0.0330 OH x Rp 150,000.00 = Rp 4,950.00
Mandor 0.0330 OH x Rp 165,000.00 = Rp 5,445.00
B. JUMLAH UPAH = Rp 122,595.00
C. JUMLAH BAHAN DAN UPAH = Rp 1,316,422.14
D. Overhead + Profit (10%) = Rp 131,642.21
E.8 E. Total = Rp 1,448,064.36
E.9 SNI 7394-2008 (6.25)
MEMASANG 1 M2 BEKESTING UNTUK DINDING
6.25.1 Bahan :
Kayu papan 0.0300 M3 x Rp 5,600,000.00 = Rp 168,000.00
Paku campur 0.4000 Kg x Rp 73,628.57 = Rp 29,451.43
Minyak Bekesting 0.2000 ltr x Rp 52,428.57 = Rp 10,485.71
Kayu balok 0.0200 M3 x Rp 5,600,000.00 = Rp 112,000.00
Tripleks 6 mm 0.3500 lbr x Rp 496,828.57 = Rp 173,890.00
Balok 5/10 panjang 3 m 3.0000 btg x Rp 112,000.00 = Rp 336,000.00
Formtie/penjaga Jarak Bekisting/Spacer 4.0000 BH x Rp 16,949.29 = Rp 67,797.16
A. JUMLAH HARGA BAHAN = Rp 897,624.30
6.25.2 Tenaga :
Pekerja 0.6600 OH x Rp 100,000.00 = Rp 66,000.00
Tukang besi 0.3300 OH x Rp 140,000.00 = Rp 46,200.00
Kepala Tukang 0.0330 OH x Rp 150,000.00 = Rp 4,950.00
Mandor 0.0330 OH x Rp 165,000.00 = Rp 5,445.00
B. JUMLAH UPAH = Rp 122,595.00
C. JUMLAH BAHAN DAN UPAH = Rp 1,020,219.30
D. Overhead + Profit (10%) = Rp 102,021.93
E.9 E. Total = Rp 1,122,241.23
E.10 Permen PU No. 11/PRT/M/2013 (B.35)
MEMBONGKAR BEKESTING 1 M2 SECARA BIASA DAN MEMBERESKAN PUING-PUING
Tenaga :
Pekerja 0.0400 OH x Rp 100,000.00 = Rp 4,000.00
Mandor 0.0040 OH x Rp 165,000.00 = Rp 660.00
A. JUMLAH UPAH = Rp 4,660.00
B. Overhead + Profit (10%) = Rp 466.00
E.10 C. Total = Rp 5,126.00
F. PEKERJAAN DINDING SNI 6897 - 2008
F.1 SNI 6897 - 2008 (6.9)
MEMASANG 1 M2 DINDING BATAKO (9 X 14 X 29) CM , CAMPURAN SPESI 1 PC : 4 PP
6.9.1 Bahan :
Batu batako 22.0000 Bh x Rp 50,798.56 = Rp 1,117,568.32
Semen PC 7.9150 Kg x Rp 48,028.57 = Rp 380,146.13
Pasir Pasang 0.0250 M3 x Rp 2,000,000.00 = Rp 50,000.00
A. JUMLAH HARGA BAHAN = Rp 1,547,714.45
6.9.2 Tenaga :
Pekerja 0.6000 OH x Rp 100,000.00 = Rp 60,000.00
Tukang Batu 0.2000 OH x Rp 140,000.00 = Rp 28,000.00
Kepala Tukang 0.0200 OH x Rp 150,000.00 = Rp 3,000.00
Mandor 0.0300 OH x Rp 165,000.00 = Rp 4,950.00
B. JUMLAH UPAH = Rp 95,950.00
C. JUMLAH BAHAN DAN UPAH = Rp 1,643,664.45
D. Overhead + Profit (10%) = Rp 164,366.45
F.1 E. Total = Rp 1,808,030.90
EE Analisa Harga - 20
Harga 1 m3 beton tumbuk 1:3:5 (non overhead + profit) An E.1 13,902,178.26
Harga 1 bh batako Rp=An E.1/J 50,798.56
EE Analisa Harga - 21
G. PEKERJAAN KAYU SNI 3434 - 2008
G.1 SNI 3434 - 2008 (6.2)
MEMBUAT DAN MEMASANG 1 M3 KOSEN PINTU DAN KOSEN JENDELA KAYU KELAS II DAN III
6.2.1 Bahan :
Kayu Balok 1.2000 M3 x Rp 5,600,000.00 = Rp 6,720,000.00
Paku campur 1.2500 Kg x Rp 73,628.57 = Rp 92,035.71
Lem kayu 1.0000 Kg x Rp 92,828.57 = Rp 92,828.57
A. JUMLAH HARGA BAHAN = Rp 6,904,864.28
6.2.2 Tenaga :
Pekerja 6.0000 OH x Rp 100,000.00 = Rp 600,000.00
Tukang Kayu 18.0000 OH x Rp 140,000.00 = Rp 2,520,000.00
Kepala Tukang 1.8000 OH x Rp 150,000.00 = Rp 270,000.00
Mandor 0.3000 OH x Rp 165,000.00 = Rp 49,500.00
B. JUMLAH UPAH = Rp 3,439,500.00
C. JUMLAH BAHAN DAN UPAH = Rp 10,344,364.28
D. Overhead + Profit (10%) = Rp 1,034,436.43
G.1 E. Total = Rp 11,378,800.71
G.2 SNI 3434 - 2008 (6.2b)
MEMBUAT DAN MEMASANG 1 M3 GELAGAR, KOLOM, DAN RINGBALK KAYU 10/10
6.2b.1 Bahan :
Kayu Balok 1.2000 M3 x Rp 5,600,000.00 = Rp 6,720,000.00
Paku campur 1.2500 Kg x Rp 73,628.57 = Rp 92,035.71
Lem kayu 1.0000 Kg x Rp 92,828.57 = Rp 92,828.57
A. JUMLAH HARGA BAHAN = Rp 6,904,864.28
6.2b.2 Tenaga :
Pekerja 4.0000 OH x Rp 100,000.00 = Rp 400,000.00
Tukang Kayu 12.0000 OH x Rp 140,000.00 = Rp 1,680,000.00
Kepala Tukang 1.2000 OH x Rp 150,000.00 = Rp 180,000.00
Mandor 0.2000 OH x Rp 165,000.00 = Rp 33,000.00
B. JUMLAH UPAH = Rp 2,293,000.00
C. JUMLAH BAHAN DAN UPAH = Rp 9,197,864.28
D. Overhead + Profit (10%) = Rp 919,786.43
G.2 E. Total = Rp 10,117,650.71
G.3 SNI 3434 - 2008 (6.5)
MEMBUAT DAN MEMASANG 1 M2 DAUN PINTU PANEEL KELAS I ATAU II
6.5.1 Bahan :
Kayu Papan 0.0400 M3 x Rp 5,600,000.00 = Rp 224,000.00
Lem kayu 0.5000 Kg x Rp 92,828.57 = Rp 46,414.29
A. JUMLAH HARGA BAHAN = Rp 270,414.29
6.5.2 Tenaga :
Pekerja 1.0000 OH x Rp 100,000.00 = Rp 100,000.00
Tukang Kayu 3.0000 OH x Rp 140,000.00 = Rp 420,000.00
Kepala Tukang 0.3000 OH x Rp 150,000.00 = Rp 45,000.00
Mandor 0.0500 OH x Rp 165,000.00 = Rp 8,250.00
B. JUMLAH UPAH = Rp 573,250.00
C. JUMLAH BAHAN DAN UPAH = Rp 843,664.29
D. Overhead + Profit (10%) = Rp 84,366.43
G.3 E. Total = Rp 928,030.71
G.4 SNI 3434 - 2008 (6.6)
MEMBUAT DAN MEMASANG 1 M2 PINTU DAN JENDELA KACA
6.6.1 Bahan :
Kayu Papan 0.0240 M3 x Rp 5,600,000.00 = Rp 134,400.00
Kaca bening 5 mm 0.7100 M2 x Rp 819,141.43 = Rp 581,590.42
Lem kayu 0.3000 Kg x Rp 92,828.57 = Rp 27,848.57
A. JUMLAH HARGA BAHAN = Rp 743,838.99
6.6.2 Tenaga :
Pekerja 0.8000 OH x Rp 100,000.00 = Rp 80,000.00
Tukang Kayu 2.4000 OH x Rp 140,000.00 = Rp 336,000.00
Kepala Tukang 0.2400 OH x Rp 150,000.00 = Rp 36,000.00
Mandor 0.0400 OH x Rp 165,000.00 = Rp 6,600.00
B. JUMLAH UPAH = Rp 458,600.00
C. JUMLAH BAHAN DAN UPAH = Rp 1,202,438.99
D. Overhead + Profit (10%) = Rp 120,243.90
G.4 E. Total = Rp 1,322,682.88
G.5 SNI 3434 - 2008 (6.13)
MEMASANG 1 M3 KONSTRUKSI KUDA-KUDA KONVENSIONAL
6.13.1 Bahan :
Kayu balok 1.1000 M3 x Rp 5,600,000.00 = Rp 6,160,000.00
Besi strip 15.0000 Kg x Rp = Rp -
Paku campur 5.6000 Kg x Rp 73,628.57 = Rp 412,319.99
EE Analisa Harga - 22
A. JUMLAH HARGA BAHAN = Rp 6,572,319.99
6.13.2 Tenaga :
Pekerja 4.0000 OH x Rp 100,000.00 = Rp 400,000.00
Tukang Kayu 12.0000 OH x Rp 140,000.00 = Rp 1,680,000.00
Kepala Tukang 1.2000 OH x Rp 150,000.00 = Rp 180,000.00
Mandor 0.2000 OH x Rp 165,000.00 = Rp 33,000.00
B. JUMLAH UPAH = Rp 2,293,000.00
C. JUMLAH BAHAN DAN UPAH = Rp 8,865,319.99
D. Overhead + Profit (10%) = Rp 886,532.00
G.5 E. Total = Rp 9,751,851.99
EE Analisa Harga - 23
G.6 SNI 3434 - 2008 (6.15)
MEMASANG 1 M3 KONSTRUKSI GORDING
6.15.1 Bahan :
Kayu balok 1.1000 M3 x Rp 5,600,000.00 = Rp 6,160,000.00
Besi strip tebal 5 mm *) 15.0000 Kg x Rp - = Rp -
Paku campur 3.0000 Kg x Rp 73,628.57 = Rp 220,885.71
A. JUMLAH HARGA BAHAN = Rp 6,380,885.71
6.15.2 Tenaga :
Pekerja 2.4000 OH x Rp 100,000.00 = Rp 240,000.00
Tukang Kayu 7.2000 OH x Rp 140,000.00 = Rp 1,008,000.00
Kepala Tukang 0.7200 OH x Rp 150,000.00 = Rp 108,000.00
Mandor 0.1200 OH x Rp 165,000.00 = Rp 19,800.00
B. JUMLAH UPAH = Rp 1,375,800.00
C. JUMLAH BAHAN DAN UPAH = Rp 7,756,685.71
D. Overhead + Profit (10%) = Rp 775,668.57
G.6 E. Total = Rp 8,532,354.28
G.7 SNI 3434 - 2008 (6.19)
MEMASANG 1 M2 RANGKA LANGIT-LANGIT (60 X 120 CM)
6.19.1 Bahan :
Kayu balok 0.0120 M3 x Rp 5,600,000.00 = Rp 67,200.00
Paku campur 0.1000 Kg x Rp 73,628.57 = Rp 7,362.86
A. JUMLAH HARGA BAHAN = Rp 74,562.86
6.19.2 Tenaga :
Pekerja 0.1500 OH x Rp 100,000.00 = Rp 15,000.00
Tukang Kayu 0.2500 OH x Rp 140,000.00 = Rp 35,000.00
Kepala Tukang 0.0250 OH x Rp 150,000.00 = Rp 3,750.00
Mandor 0.0750 OH x Rp 165,000.00 = Rp 12,375.00
B. JUMLAH UPAH = Rp 66,125.00
C. JUMLAH BAHAN DAN UPAH = Rp 140,687.86
D. Overhead + Profit (10%) = Rp 14,068.79
G.7 E. Total = Rp 154,756.64
G.8 SNI 3434 - 2008 (6.22)
MEMASANG 1 M' LISTPLANK UKURAN (2,5 x 30) CM KAYU KELAS I ATAU II
6.22.1 Bahan :
Kayu Papan 0.0135 M3 x Rp 5,600,000.00 = Rp 75,600.00
Paku campur 0.1000 Kg x Rp 73,628.57 = Rp 7,362.86
A. JUMLAH HARGA BAHAN = Rp 82,962.86
6.22.2 Tenaga :
Pekerja 0.1000 OH x Rp 100,000.00 = Rp 10,000.00
Tukang Kayu 0.2000 OH x Rp 140,000.00 = Rp 28,000.00
Kepala Tukang 0.0200 OH x Rp 150,000.00 = Rp 3,000.00
Mandor 0.0050 OH x Rp 165,000.00 = Rp 825.00
B. JUMLAH UPAH = Rp 41,825.00
C. JUMLAH BAHAN DAN UPAH = Rp 124,787.86
D. Overhead + Profit (10%) = Rp 12,478.79
G.8 E. Total = Rp 137,266.64
G.9 SNI 3434 - 2008 (6.26)
MEMASANG 1 M2 DINDING LAMRIZEERING DARI PAPAN
6.26.1 Bahan :
Kayu Papan 0.0070 M3 x Rp 5,600,000.00 = Rp 39,200.00
Paku campur 0.1000 Kg x Rp 73,628.57 = Rp 7,362.86
A. JUMLAH HARGA BAHAN = Rp 46,562.86
6.26.2 Tenaga :
Pekerja 0.6000 OH x Rp 100,000.00 = Rp 60,000.00
Tukang Kayu 1.8000 OH x Rp 140,000.00 = Rp 252,000.00
Kepala Tukang 0.1800 OH x Rp 150,000.00 = Rp 27,000.00
Mandor 0.0300 OH x Rp 165,000.00 = Rp 4,950.00
B. JUMLAH UPAH = Rp 343,950.00
C. JUMLAH BAHAN DAN UPAH = Rp 390,512.86
D. Overhead + Profit (10%) = Rp 39,051.29
G.9 E. Total = Rp 429,564.14
H. PEKERJAAN PENUTUP ATAP SNI 2002
H.1 SNI 2002 (6.38)
MEMASANG 1 M2 ATAP SENG GELOMBANG
6.38.1 Bahan :
Seng Gelombang BJLS 20 0.7000 Lbr x Rp 205,385.71 = Rp 143,770.00
Paku seng 0.0200 Kg x Rp 79,128.57 = Rp 1,582.57
A. JUMLAH HARGA BAHAN = Rp 145,352.57
6.38.2 Tenaga :
Pekerja 0.1200 OH x Rp 100,000.00 = Rp 12,000.00
EE Analisa Harga - 24
Tukang Kayu 0.0600 OH x Rp 140,000.00 = Rp 8,400.00
Kepala Tukang 0.0060 OH x Rp 150,000.00 = Rp 900.00
Mandor 0.0060 OH x Rp 165,000.00 = Rp 990.00
B. JUMLAH UPAH = Rp 22,290.00
C. JUMLAH BAHAN DAN UPAH = Rp 167,642.57
D. Overhead + Profit (10%) = Rp 16,764.26
H.1 E. Total = Rp 184,406.83
EE Analisa Harga - 25
H.2 SNI 2002 (6.39)
MEMASANG 1 M NOK ATAP SENG
6.39.1 Bahan :
Seng Plat BJLS 20 0.3000 Lbr x Rp 211,985.71 = Rp 63,595.71
Paku seng 0.0400 Kg x Rp 79,128.57 = Rp 3,165.14
A. JUMLAH HARGA BAHAN = Rp 66,760.86
6.39.2 Tenaga :
Pekerja 0.1500 OH x Rp 100,000.00 = Rp 15,000.00
Tukang Kayu 0.0700 OH x Rp 140,000.00 = Rp 9,800.00
Kepala Tukang 0.0080 OH x Rp 150,000.00 = Rp 1,200.00
Mandor 0.0060 OH x Rp 165,000.00 = Rp 990.00
B. JUMLAH UPAH = Rp 26,990.00
C. JUMLAH BAHAN DAN UPAH = Rp 93,750.86
D. Overhead + Profit (10%) = Rp 9,375.09
H.2 E. Total = Rp 103,125.94
I. PEKERJAAN LANGIT-LANGIT SNI 2839 - 2008
I.1 SNI 2839 - 2008 (6.5)
MEMASANG 1 M2 LANGIT-LANGIT TRIPLEKS UKURAN (120 X 240) CM, TEBAL 3 MM
6.5.1 Bahan :
Tripleks 3 mm 0.3750 Lbr x Rp 317,942.86 = Rp 119,228.57
Paku tripleks 0.0300 Kg x Rp 76,228.57 = Rp 2,286.86
A. JUMLAH HARGA BAHAN = Rp 121,515.43
6.5.2 Tenaga :
Pekerja 0.1000 OH x Rp 100,000.00 = Rp 10,000.00
Tukang Kayu 0.1000 OH x Rp 140,000.00 = Rp 14,000.00
Kepala Tukang 0.0100 OH x Rp 150,000.00 = Rp 1,500.00
Mandor 0.0050 OH x Rp 165,000.00 = Rp 825.00
B. JUMLAH UPAH = Rp 26,325.00
C. JUMLAH BAHAN DAN UPAH = Rp 147,840.43
D. Overhead + Profit (10%) = Rp 14,784.04
I.1 E. Total = Rp 162,624.47
I.2 SNI 2839 - 2008 (6.10)
MEMASANG 1 M' LIST LANGIT-LANGIT KAYU PROFIL
6.10.1 Bahan :
List Kayu Profil 1/3 cm pjg 4m 1.0500 m x Rp 19,250.00 = Rp 20,212.50
Paku tripleks 0.0100 Kg x Rp 76,228.57 = Rp 762.29
A. JUMLAH HARGA BAHAN = Rp 20,974.79
6.10.2 Tenaga :
Pekerja 0.0500 OH x Rp 100,000.00 = Rp 5,000.00
Tukang kayu 0.0500 OH x Rp 140,000.00 = Rp 7,000.00
Kepala Tukang 0.0050 OH x Rp 150,000.00 = Rp 750.00
Mandor 0.0030 OH x Rp 165,000.00 = Rp 495.00
B. JUMLAH UPAH = Rp 13,245.00
C. JUMLAH BAHAN DAN UPAH = Rp 34,219.79
D. Overhead + Profit (10%) = Rp 3,421.98
I.2 E. Total = Rp 37,641.76
J. PEKERJAAN KUNCI, ALAT GANTUNGAN DAN KACA SNI 03-3437- 2002
J.1 SNI-03-3437-2002 (6.1)
PASANG 1 BUAH KUNCI TANAM ANTIK
6.1.1 Bahan :
Kunci tanam 2 slaag (besar) 1.0000 Bh x Rp 317,119.64 = Rp 317,119.64
A. JUMLAH HARGA BAHAN = Rp 317,119.64
6.1.2 Tenaga :
Pekerja 0.0600 OH x Rp 100,000.00 = Rp 6,000.00
Tukang kayu 0.6000 OH x Rp 140,000.00 = Rp 84,000.00
Kepala tukang 0.0600 OH x Rp 150,000.00 = Rp 9,000.00
Mandor 0.0030 OH x Rp 165,000.00 = Rp 495.00
B. JUMLAH UPAH = Rp 99,495.00
C. JUMLAH BAHAN DAN UPAH = Rp 416,614.64
D. Overhead + Profit (10%) = Rp 41,661.46
J.1 E. Total = Rp 458,276.10
J.2 SNI-03-3437-2002 (6.2)
PASANG 1 BUAH KUNCI TANAM BIASA
6.2.1 Bahan :
Kunci tanam 2 slaag (kecil) 1.0000 Bh x Rp 251,866.07 = Rp 251,866.07
A. JUMLAH HARGA BAHAN = Rp 251,866.07
6.2.2 Tenaga :
Pekerja 0.0100 OH x Rp 100,000.00 = Rp 1,000.00
Tukang kayu 0.5000 OH x Rp 140,000.00 = Rp 70,000.00
Kepala tukang 0.0100 OH x Rp 150,000.00 = Rp 1,500.00
EE Analisa Harga - 26
Mandor 0.0050 OH x Rp 165,000.00 = Rp 825.00
B. JUMLAH UPAH = Rp 73,325.00
C. JUMLAH BAHAN DAN UPAH = Rp 325,191.07
D. Overhead + Profit (10%) = Rp 32,519.11
J.2 E. Total = Rp 357,710.18
EE Analisa Harga - 27
J.3 SNI-03-3437-2002 (6.5)
PASANG 1 BUAH ENGSEL PINTU
6.5.1 Bahan :
Engsel Pintu 1.0000 Bh x Rp 53,397.14 = Rp 53,397.14
A. JUMLAH HARGA BAHAN = Rp 53,397.14
6.5.2 Tenaga :
Pekerja 0.0150 OH x Rp 100,000.00 = Rp 1,500.00
Tukang kayu 0.1500 OH x Rp 140,000.00 = Rp 21,000.00
Kepala tukang 0.0150 OH x Rp 150,000.00 = Rp 2,250.00
Mandor 0.00075 OH x Rp 165,000.00 = Rp 123.75
B. JUMLAH UPAH = Rp 24,873.75
C. JUMLAH BAHAN DAN UPAH = Rp 78,270.89
D. Overhead + Profit (10%) = Rp 7,827.09
J.3 E. Total = Rp 86,097.98
J.4 SNI-03-3437-2002 (6.6)
PASANG 1 BUAH ENGSEL JENDELA
6.6.1 Bahan :
Engsel jendela 1.0000 Bh x Rp 43,447.86 = Rp 43,447.86
A. JUMLAH HARGA BAHAN = Rp 43,447.86
6.6.2 Tenaga :
Pekerja 0.0100 OH x Rp 100,000.00 = Rp 1,000.00
Tukang kayu 0.1000 OH x Rp 140,000.00 = Rp 14,000.00
Kepala tukang 0.0100 OH x Rp 150,000.00 = Rp 1,500.00
Mandor 0.0005 OH x Rp 165,000.00 = Rp 82.50
B. JUMLAH UPAH = Rp 16,582.50
C. JUMLAH BAHAN DAN UPAH = Rp 60,030.36
D. Overhead + Profit (10%) = Rp 6,003.04
J.4 E. Total = Rp 66,033.40
J.5 SNI-03-3437-2002 (6.9)
PASANG 1 BUAH KAIT ANGIN
6.9.1 Bahan :
Hak/kait angin 1.0000 Bh x Rp 62,997.14 = Rp 62,997.14
A. JUMLAH HARGA BAHAN = Rp 62,997.14
6.9.2 Tenaga :
Pekerja 0.0150 OH x Rp 100,000.00 = Rp 1,500.00
Tukang kayu 0.1500 OH x Rp 140,000.00 = Rp 21,000.00
Kepala tukang 0.0150 OH x Rp 150,000.00 = Rp 2,250.00
Mandor 0.00075 OH x Rp 165,000.00 = Rp 123.75
B. JUMLAH UPAH = Rp 24,873.75
C. JUMLAH BAHAN DAN UPAH = Rp 87,870.89
D. Overhead + Profit (10%) = Rp 8,787.09
J.5 E. Total = Rp 96,657.98
J.6 SNI-03-3437-2002 (6.9)
PASANG 1 BUAH HANDLE JENDELA
6.9.1 Bahan :
Handle jendela 1.0000 Bh x Rp 27,832.86 = Rp 27,832.86
A. JUMLAH HARGA BAHAN = Rp 27,832.86
6.9.2 Tenaga :
Pekerja 0.0150 OH x Rp 100,000.00 = Rp 1,500.00
Tukang kayu 0.1500 OH x Rp 140,000.00 = Rp 21,000.00
Kepala tukang 0.0150 OH x Rp 150,000.00 = Rp 2,250.00
Mandor 0.00075 OH x Rp 165,000.00 = Rp 123.75
B. JUMLAH UPAH = Rp 24,873.75
C. JUMLAH BAHAN DAN UPAH = Rp 52,706.61
D. Overhead + Profit (10%) = Rp 5,270.66
J.6 E. Total = Rp 57,977.27
J.7 SNI-03-3437-2002 (11)
PASANG 1 GRENDEL PINTU
6.11.1 Bahan :
Grendel pintu 1.0000 Bh x Rp 50,047.86 = Rp 50,047.86
A. JUMLAH HARGA BAHAN = Rp 50,047.86
6.11.2 Tenaga :
Pekerja 0.0200 OH x Rp 100,000.00 = Rp 2,000.00
Tukang kayu 0.2000 OH x Rp 140,000.00 = Rp 28,000.00
Kepala tukang 0.0200 OH x Rp 150,000.00 = Rp 3,000.00
Mandor 0.00100 OH x Rp 165,000.00 = Rp 165.00
B. JUMLAH UPAH = Rp 33,165.00
C. JUMLAH BAHAN DAN UPAH = Rp 83,212.86
D. Overhead + Profit (10%) = Rp 8,321.29
J.7 E. Total = Rp 91,534.15
EE Analisa Harga - 28
J.8 SNI-03-3437-2002 (11)
PASANG 1 GRENDEL JENDELA
6.11.1 Bahan :
Grendel Jendela 1.0000 Bh x Rp 46,173.21 = Rp 46,173.21
A. JUMLAH HARGA BAHAN = Rp 46,173.21
6.11.2 Tenaga :
Pekerja 0.0200 OH x Rp 100,000.00 = Rp 2,000.00
Tukang kayu 0.2000 OH x Rp 140,000.00 = Rp 28,000.00
Kepala tukang 0.0200 OH x Rp 150,000.00 = Rp 3,000.00
Mandor 0.00100 OH x Rp 165,000.00 = Rp 165.00
B. JUMLAH UPAH = Rp 33,165.00
C. JUMLAH BAHAN DAN UPAH = Rp 79,338.21
D. Overhead + Profit (10%) = Rp 7,933.82
J.8 E. Total = Rp 87,272.03
EE Analisa Harga - 29
K. PEKERJAAN PENGECATAN DAN FINISHING DINDING SNI 03-2842-2002
K.1 SNI 2842-2002 (6.8)
1 M2 PENGECATAN BIDANG KAYU BARU ( 1 lapis dempul, 1 lapis cat dasar, 2 lapis cat penutup)
6.8.1 Bahan :
Meni kayu 0.2000 Kg x Rp 81,328.57 = Rp 16,265.71
Dempul Kayu 0.1500 Kg x Rp 74,828.57 = Rp 11,224.29
Cat kayu 0.4300 Kg x Rp 126,028.57 = Rp 54,192.29
A. JUMLAH HARGA BAHAN = Rp 81,682.28
6.8.2 Tenaga :
Pekerja 0.0700 OH x Rp 100,000.00 = Rp 7,000.00
Tukang cat 0.0090 OH x Rp 140,000.00 = Rp 1,260.00
Kepala Tukang 0.0060 OH x Rp 150,000.00 = Rp 900.00
Mandor 0.0025 OH x Rp 165,000.00 = Rp 412.50
B. JUMLAH UPAH = Rp 9,572.50
C. JUMLAH BAHAN DAN UPAH = Rp 91,254.78
D. Overhead + Profit (10%) = Rp 9,125.48
K.1 E. Total = Rp 100,380.26
K.2 SNI 2842-2002 (6.13)
1 M2 PENGECATAN ATAP
6.13.1 Bahan :
Cat Atap 0.1000 Kg x Rp 140,428.57 = Rp 14,042.86
A. JUMLAH HARGA BAHAN = Rp 14,042.86
6.13.2 Tenaga :
Pekerja 0.0200 OH x Rp 100,000.00 = Rp 2,000.00
Tukang cat 0.2000 OH x Rp 140,000.00 = Rp 28,000.00
Kepala Tukang 0.0200 OH x Rp 150,000.00 = Rp 3,000.00
Mandor 0.0100 OH x Rp 165,000.00 = Rp 1,650.00
B. JUMLAH UPAH = Rp 34,650.00
C. JUMLAH BAHAN DAN UPAH = Rp 48,692.86
D. Overhead + Profit (10%) = Rp 4,869.29
K.2 E. Total = Rp 53,562.14
K.3 SNI 2842-2002 (6.14)
1 M2 PENGECATAN BIDANG TEMBOK BARU ( 1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup)
6.14.1 Bahan :
Plamur tembok 0.1000 Kg x Rp 66,728.57 = Rp 6,672.86
Cat tembok 0.3600 Kg x Rp 62,628.57 = Rp 22,546.29
A. JUMLAH HARGA BAHAN = Rp 29,219.14
6.14.2 Tenaga :
Pekerja 0.0200 OH x Rp 100,000.00 = Rp 2,000.00
Tukang cat 0.0630 OH x Rp 140,000.00 = Rp 8,820.00
Kepala Tukang 0.0063 OH x Rp 150,000.00 = Rp 945.00
Mandor 0.0025 OH x Rp 165,000.00 = Rp 412.50
B. JUMLAH UPAH = Rp 12,177.50
C. JUMLAH BAHAN DAN UPAH = Rp 41,396.64
D. Overhead + Profit (10%) = Rp 4,139.66
K.3 E. Total = Rp 45,536.31
K.4 SNI 2842-2002 (6.20.a)
1 M2 PENGECATAN PERMUKAAN BESI DENGAN MENI BESI
6.20a.1 Bahan :
Meni besi 0.1000 Kg x Rp 81,328.57 = Rp 8,132.86
Kuas biasa 0.0100 Bh x Rp 44,464.29 = Rp 444.64
A. JUMLAH HARGA BAHAN = Rp 8,577.50
6.20a.2 Tenaga :
Pekerja 0.0200 OH x Rp 100,000.00 = Rp 2,000.00
Tukang cat 0.2000 OH x Rp 140,000.00 = Rp 28,000.00
Kepala Tukang 0.0200 OH x Rp 150,000.00 = Rp 3,000.00
Mandor 0.0100 OH x Rp 165,000.00 = Rp 1,650.00
B. JUMLAH UPAH = Rp 34,650.00
C. JUMLAH BAHAN DAN UPAH = Rp 43,227.50
D. Overhead + Profit (10%) = Rp 4,322.75
K.4 E. Total = Rp 47,550.25
K.5 SNI 2842-2002 (6.20.b)
1 M2 PENGECATAN PERMUKAAN BESI DENGAN CAT BESI
6.20b.1 Bahan :
Cat besi 0.1000 Kg x Rp 119,328.57 = Rp 11,932.86
Kuas biasa 0.0100 Bh x Rp 44,464.29 = Rp 444.64
A. JUMLAH HARGA BAHAN = Rp 12,377.50
6.20b.2 Tenaga :
Pekerja 0.0200 OH x Rp 100,000.00 = Rp 2,000.00
Tukang cat 0.2000 OH x Rp 140,000.00 = Rp 28,000.00
EE Analisa Harga - 30
Kepala Tukang 0.0200 OH x Rp 150,000.00 = Rp 3,000.00
Mandor 0.0100 OH x Rp 165,000.00 = Rp 1,650.00
B. JUMLAH UPAH = Rp 34,650.00
C. JUMLAH BAHAN DAN UPAH = Rp 47,027.50
D. Overhead + Profit (10%) = Rp 4,702.75
K.5 E. Total = Rp 51,730.25
EE Analisa Harga - 31
L. ELECTRIKAL
L.1 1 TITIK PEKERJAAN INSTALASI LAMPU DAN KOTAK KONTAK
Bahan :
Kabel NYM 2 x 2,5 mm 11.0000 M' x Rp 29,258.72 = Rp 321,845.92
Perlengkapan 20% harga material 1.0000 x Rp 64,369.18 = Rp 64,369.18
A. JUMLAH HARGA BAHAN = Rp 386,215.10
Tenaga :
Pekerja 0.2000 OH x Rp 100,000.00 = Rp 20,000.00
Tukang Listrik 0.6000 OH x Rp 140,000.00 = Rp 84,000.00
B. JUMLAH UPAH = Rp 104,000.00
C. JUMLAH BAHAN DAN UPAH = Rp 490,215.10
D. Overhead + Profit (10%) = Rp 49,021.51
L.1 E. Total = Rp 539,236.61
L.2 PASANG 1 BUAH STOP KONTAK
Bahan :
Stop kontak 1.0000 Bh x Rp 55,423.93 = Rp 55,423.93
Perlengkapan 1% harga material 1.0000 x Rp 554.24 = Rp 554.24
A. JUMLAH HARGA BAHAN = Rp 55,978.17
Tenaga :
Tukang Listrik 0.1200 OH x Rp 140,000.00 = Rp 16,800.00
B. JUMLAH UPAH = Rp 16,800.00
C. JUMLAH BAHAN DAN UPAH = Rp 72,778.17
D. Overhead + Profit (10%) = Rp 7,277.82
L.2 E. Total = Rp 80,055.99
L.3 1 BUAH PEKERJAAN LAMPU SL 18 + FITTING
Bahan :
Lampu philips 18 W 1.0000 Bh x Rp 123,697.14 = Rp 123,697.14
Fitting duduk 1.0000 Bh x Rp 58,898.57 = Rp 58,898.57
Perlengkapan 1% harga material 1.0000 x Rp 1,825.96 = Rp 1,825.96
A. JUMLAH HARGA BAHAN = Rp 184,421.67
Tenaga :
Tukang Listrik 0.1200 OH x Rp 140,000.00 = Rp 16,800.00
B. JUMLAH UPAH = Rp 16,800.00
C. JUMLAH BAHAN DAN UPAH = Rp 201,221.67
D. Overhead + Profit (10%) = Rp 20,122.17
L.3 E. Total = Rp 221,343.84
L.4 PASANG 1 BH MCB BOX
Bahan :
MCB 6 A 1.0000 Set x Rp 93,298.57 = Rp 93,298.57
Perlengkapan 1% harga material 1.0000 x Rp 932.99 = Rp 932.99
A. JUMLAH HARGA BAHAN = Rp 94,231.56
Tenaga :
Tukang Listrik 0.1200 OH x Rp 140,000.00 = Rp 16,800.00
B. JUMLAH UPAH = Rp 16,800.00
C. JUMLAH BAHAN DAN UPAH = Rp 111,031.56
D. Overhead + Profit (10%) = Rp 11,103.16
L.4 E. Total = Rp 122,134.72
L.5 PASANG 1 BUAH SAKLAR GANDA
Bahan :
Saklar ganda 1.0000 Set x Rp 55,423.93 = Rp 55,423.93
Perlengkapan 1% harga material 1.0000 x Rp 554.24 = Rp 554.24
A. JUMLAH HARGA BAHAN = Rp 55,978.17
Tenaga :
Tukang Listrik 0.1200 OH x Rp 140,000.00 = Rp 16,800.00
B. JUMLAH UPAH = Rp 16,800.00
C. JUMLAH BAHAN DAN UPAH = Rp 72,778.17
D. Overhead + Profit (10%) = Rp 7,277.82
L.5 E. Total = Rp 80,055.99
L.6 PASANG 1 BUAH SAKLAR TUNGGAL
Bahan :
Saklar tunggal 1.0000 Set x Rp 50,423.93 = Rp 50,423.93
Perlengkapan 1% harga material 1.0000 x Rp 504.24 = Rp 504.24
A. JUMLAH HARGA BAHAN = Rp 50,928.17
Tenaga :
Tukang Listrik 0.1200 OH x Rp 140,000.00 = Rp 16,800.00
B. JUMLAH UPAH = Rp 16,800.00
C. JUMLAH BAHAN DAN UPAH = Rp 67,728.17
D. Overhead + Profit (10%) = Rp 6,772.82
EE Analisa Harga - 32
L.6 E. Total = Rp 74,500.99
EE Analisa Harga - 33
M. PEKERJAAN PIPA DAN SANITER RSNI T-15-2002
M.1 SNI 2002 (6.21)
PEMASANGAN 1 M' PIPA GIP 1,5"
6.21.1 Bahan :
Pipa GIP 1,5" 1.2000 m x Rp 187,750.64 = Rp 225,300.77
Perlengkapan 35% dari harga material 1.0000 x Rp 78,855.27 = Rp 78,855.27
A. JUMLAH HARGA BAHAN = Rp 304,156.04
6.21.2 Tenaga :
Pekerja 0.1080 OH x Rp 100,000.00 = Rp 10,800.00
Tukang las 0.1800 OH x Rp 140,000.00 = Rp 25,200.00
Kepala Tukang 0.0180 OH x Rp 150,000.00 = Rp 2,700.00
Mandor 0.0050 OH x Rp 165,000.00 = Rp 825.00
B. JUMLAH UPAH = Rp 39,525.00
C. JUMLAH BAHAN DAN UPAH = Rp 343,681.04
M.2 SNI 2002 ( 6.28)
MEMASANG 1 M' PIPA PVC 1,5" TIPE AW
6.28.1 Bahan
Pipa PVC 1" 1.0000 Set x Rp 94,428.57 = Rp 94,428.57
Perlengkapan 35% = Rp 33,050.00
A. JUMLAH HARGA BAHAN = Rp 127,478.57
6.28.2 Tenaga
Pekerja 0.0360 OH x Rp 100,000.00 = Rp 3,600.00
Tukang pipa 0.0600 OH x Rp 140,000.00 = Rp 8,400.00
Kepala Tukang 0.0060 OH x Rp 150,000.00 = Rp 900.00
Mandor 0.0018 OH x Rp 165,000.00 = Rp 297.00
B. JUMLAH UPAH = Rp 13,197.00
C. JUMLAH BAHAN DAN UPAH = Rp 140,675.57
D. Overhead + Profit (10%) = Rp 14,067.56
M.2 E. Total = Rp 154,743.13
M.3 SNI 2002 ( 6.29)
MEMASANG 1 M' PIPA PVC 2" TIPE AW
6.29.1 Bahan
Pipa PVC 2" 1.0000 Set x Rp 225,285.71 = Rp 225,285.71
Perlengkapan 35% = Rp 78,850.00
A. JUMLAH HARGA BAHAN = Rp 304,135.71
6.29.2 Tenaga
Pekerja 0.0540 OH x Rp 100,000.00 = Rp 5,400.00
Tukang pipa 0.0900 OH x Rp 140,000.00 = Rp 12,600.00
Kepala Tukang 0.0090 OH x Rp 150,000.00 = Rp 1,350.00
Mandor 0.0027 OH x Rp 165,000.00 = Rp 445.50
B. JUMLAH UPAH = Rp 19,795.50
C. JUMLAH BAHAN DAN UPAH = Rp 323,931.21
D. Overhead + Profit (10%) = Rp 32,393.12
M.3 E. Total = Rp 356,324.33
N. PASANGAN BROJONG SNI 03 - 0009 -1999
N.1 PASANGAN 1 M3 BRONJONG PABRIKASI BENTUK I Type D (L = 2, B = 1, T = 0,5) Kawat sisi 3,4 mm kawat pengikat 2 mm
Bahan :
Batu kali 1.4 m3 x Rp 2,000,000.00 = Rp 2,800,000.00
Kawat bronjong 3 mm 1 kotak x Rp 1,024,500.00 = Rp 1,024,500.00
A. JUMLAH HARGA BAHAN = Rp 3,824,500.00
Tenaga :
Pekerja 0.5 OH x Rp 100,000.00 = Rp 50,000.00
Mandor 0.05 OH x Rp 165,000.00 = Rp 8,250.00
B. JUMLAH UPAH = Rp 58,250.00
C. JUMLAH BAHAN DAN UPAH = Rp 3,882,750.00
D. Overhead + Profit (10%) = Rp 388,275.00
N.1 E. Total = Rp 4,271,025.00
EE Analisa Harga - 34
O. PEKERJAAN BESI DAN ALUMINIUM SNI 7393 - 2008
O.1 SNI 7393 - 2008 (6.1)
MEMASANG 1 KG BESI PROFIL
6.1.1 Bahan :
Besi profil C. 50. 38 mm panjang 6 m (33,42 Kg) 1.1500 Kg x Rp 2,255,850.00 = Rp 2,594,227.50
A. JUMLAH HARGA BAHAN = Rp 2,594,227.50
6.1.2 Tenaga :
Pekerja 0.0600 OH x Rp 100,000.00 = Rp 6,000.00
Tukang besi 0.0600 OH x Rp 140,000.00 = Rp 8,400.00
Kepala Tukang 0.0060 OH x Rp 150,000.00 = Rp 900.00
Mandor 0.0030 OH x Rp 165,000.00 = Rp 495.00
B. JUMLAH UPAH = Rp 15,795.00
C. JUMLAH BAHAN DAN UPAH = Rp 2,610,022.50
D. Overhead + Profit (10%) = Rp 261,002.25
O.1 E. Total = Rp 2,871,024.75
O.2 SNI 7393 - 2008 (6.3)
MENGERJAKAN 100 KG PERAKITAN
6.3.1 Bahan :
Solar 1.0000 Ltr x Rp 55,128.57 = Rp 55,128.57
Minyak pelumas 0.1000 Ltr x Rp 77,428.57 = Rp 7,742.86
A. JUMLAH HARGA BAHAN = Rp 62,871.43
6.3.2 Tenaga :
Pekerja 0.1000 OH x Rp 100,000.00 = Rp 10,000.00
Tukang Las 0.1000 OH x Rp 140,000.00 = Rp 14,000.00
Kepala Tukang 0.0010 OH x Rp 150,000.00 = Rp 150.00
Mandor 0.0050 OH x Rp 165,000.00 = Rp 825.00
B. JUMLAH UPAH = Rp 24,975.00
6.4.3 Peralatan :
sewa genset 0.8000 Jam x Rp 115,000.00 = Rp 92,000.00
C. JUMLAH ALAT = Rp 92,000.00
D. JUMLAH BAHAN, UPAH, DAN ALAT = Rp 179,846.43
E. Total harga untuk 1 kg = Rp 1,798.46
EE Analisa Harga - 35
6.18.1 Bahan :
Seng Plat BJLS 20 1.0500 M x Rp 211,985.71 = Rp 222,585.00
Paku Tripleks 0.0150 Kg x Rp 76,228.57 = Rp 1,143.43
Kayu papan 0.0096 M3 x Rp 5,600,000.00 = Rp 53,760.00
A. JUMLAH HARGA BAHAN = Rp 277,488.42
6.18.2 Tenaga :
Pekerja 0.1500 OH x Rp 100,000.00 = Rp 15,000.00
Tukang Kayu 0.3000 OH x Rp 140,000.00 = Rp 42,000.00
Kepala Tukang 0.0300 OH x Rp 150,000.00 = Rp 4,500.00
Mandor 0.0080 OH x Rp 165,000.00 = Rp 1,320.00
B. JUMLAH UPAH = Rp 62,820.00
C. JUMLAH BAHAN DAN UPAH = Rp 340,308.42
D. Overhead + Profit (10%) = Rp 34,030.84
O.5 E. Total = Rp 374,339.27
EE Analisa Harga - 36
P. ANALISA GABUNGAN
P.1 PASANG 1 BUAH SARINGAN TERALIS BESI BETON
Bahan :
Besi Profil L 50.50.5 mm 33.18 Kg x Rp 58,711.28 = Rp 1,948,040.42
Besi beton dia 12 mm 58.57 Kg x Rp 66,728.57 = Rp 3,908,292.34
O.2 Pekerjaan perakitan 91.75 Kg x Rp 1,798.46 = Rp 165,009.10
O.4 Pengelasan teralis besi dan besi siku 660 cm x Rp 6,896.66 = Rp 4,551,793.72
A. JUMLAH HARGA BAHAN = Rp 10,573,135.58
Tenaga :
Pekerja 1.2000 OH x Rp 100,000.00 = Rp 120,000.00
Tukang Las 1.2000 OH x Rp 140,000.00 = Rp 168,000.00
Kepala Tukang 0.0120 OH x Rp 150,000.00 = Rp 1,800.00
Mandor 0.0120 OH x Rp 165,000.00 = Rp 1,980.00
B. JUMLAH UPAH = Rp 291,780.00
C. JUMLAH BAHAN DAN UPAH = Rp 10,864,915.58
D. Overhead + Profit (10%) = Rp 1,086,491.56
E. Total = Rp 11,951,407.14
P.2 PASANG 1 BUAH TRASHRACK BESI BETON
Bahan :
Besi siku 50.50.5 mm 42.83 Kg x Rp 58,711.28 = Rp 2,514,604.31
Besi beton dia. 12 mm 102.26 Kg x Rp 66,728.57 = Rp 6,823,663.57
O.2 Pekerjaan perakitan 145.09 Kg x Rp 1,798.46 = Rp 260,939.18
O.4 Pengelasan teralis besi dan besi siku 470 cm x Rp 6,896.66 = Rp 3,241,428.86
A. JUMLAH HARGA BAHAN = Rp 12,840,635.92
EE Analisa Harga - 37
O.4 Pengelasan angker besi 22.608 cm x Rp 6,896.66 = Rp 155,919.62
A. JUMLAH HARGA BAHAN = Rp 1,210,272.92
Tenaga :
Pekerja 0.6000 OH x Rp 100,000.00 = Rp 60,000.00
Tukang besi 0.6000 OH x Rp 140,000.00 = Rp 84,000.00
Kepala Tukang 0.0060 OH x Rp 150,000.00 = Rp 900.00
Mandor 0.0060 OH x Rp 165,000.00 = Rp 990.00
B. JUMLAH UPAH = Rp 145,890.00
C. JUMLAH BAHAN DAN UPAH = Rp 1,356,162.92
D. Overhead + Profit (10%) = Rp 135,616.29
E. Total = Rp 1,491,779.21
EE Analisa Harga - 38
P.6 PASANG 1 BUAH PINTU AIR P1 dan P2 (121/60)
Bahan :
Besi Profil C 80.45 mm panjang 5.32 m 45.91 Kg x Rp 67,500.00 = Rp 3,098,925.00
Stang pintu air drag + mur 1 set x Rp 5,538,457.14 = Rp 5,538,457.14
O.3 Pintu air plat baja (rangkap), rangka baja siku 0.726 m2 x Rp 3,835,648.88 = Rp 2,784,681.09
O.2 Pekerjaan perakitan 45.91 Kg x Rp 1,798.46 = Rp 82,567.49
O.4 Pengelasan stang pintu dan besi profil 50 cm x Rp 6,896.66 = Rp 344,832.86
A. JUMLAH HARGA BAHAN = Rp 11,849,463.58
Tenaga :
Pekerja 1.2000 OH x Rp 100,000.00 = Rp 120,000.00
Tukang besi 1.2000 OH x Rp 140,000.00 = Rp 168,000.00
Kepala Tukang 0.0120 OH x Rp 150,000.00 = Rp 1,800.00
Mandor 0.0120 OH x Rp 165,000.00 = Rp 1,980.00
B. JUMLAH UPAH = Rp 291,780.00
C. JUMLAH BAHAN DAN UPAH = Rp 12,141,243.58
D. Overhead + Profit (10%) = Rp 1,214,124.36
E. Total = Rp 13,355,367.94
P.7 PENYAMBUNGAN 1 TITIK PIPA PENSTOK DENGAN PENGELASAN (berat 1 btg pipa 93,47 kg)
Bahan :
O.4 Pengelasan pipa 244 cm x Rp 6,896.66 = Rp 1,682,784.35
A. JUMLAH HARGA BAHAN = Rp 1,682,784.35
Tenaga :
Pekerja 1.2000 OH x Rp 100,000.00 = Rp 120,000.00
Kepala Tukang 0.0120 OH x Rp 150,000.00 = Rp 1,800.00
Mandor 0.0120 OH x Rp 165,000.00 = Rp 1,980.00
B. JUMLAH UPAH = Rp 123,780.00
C. JUMLAH BAHAN DAN UPAH = Rp 1,806,564.35
D. Overhead + Profit (10%) = Rp 180,656.43
E. Total = Rp 1,987,220.78
P.8 MEMASANG 1 SET EKSPANTION JOINT
Bahan :
O.4 Pengelasan ekspantion joint 488 cm x Rp 6,896.66 = Rp 3,365,568.69
A. JUMLAH HARGA BAHAN = Rp 3,365,568.69
Tenaga :
Pekerja 1.2500 OH x Rp 100,000.00 = Rp 125,000.00
Mekanik 1.2500 OH x Rp 165,000.00 = Rp 206,250.00
Kepala Tukang 0.0125 OH x Rp 150,000.00 = Rp 1,875.00
Mandor 0.0125 OH x Rp 165,000.00 = Rp 2,062.50
B. JUMLAH UPAH = Rp 335,187.50
C. JUMLAH BAHAN DAN UPAH = Rp 3,700,756.19
D. Overhead + Profit (10%) = Rp 370,075.62
E. Total = Rp 4,070,831.81
P.9 MEMASANG 1 SET FLANGE JOINT
Bahan :
O.4 Pengelasan flange joint 488 cm x Rp 6,896.66 = Rp 3,365,568.69
A. JUMLAH HARGA BAHAN = Rp 3,365,568.69
Tenaga :
Pekerja 0.6250 OH x Rp 100,000.00 = Rp 62,500.00
Mekanik 0.6250 OH x Rp 165,000.00 = Rp 103,125.00
Kepala Tukang 0.0063 OH x Rp 150,000.00 = Rp 945.00
Mandor 0.0063 OH x Rp 165,000.00 = Rp 1,039.50
P.9 B. JUMLAH UPAH = Rp 167,609.50
C. JUMLAH BAHAN DAN UPAH = Rp 3,533,178.19
D. Overhead + Profit (10%) = Rp 353,317.82
E. Total = Rp 3,886,496.01
P.10 PEMASANGAN 1 BH AIR VALVE PIPA GIP 1,5"
Bahan :
M.1 Pemasangan Pipa GIP 1,5" 2.0000 m x Rp 343,681.04 = Rp 687,362.08
O.4 Pengelasan 59.82 cm x Rp 6,896.66 = Rp 240,576.73
A. JUMLAH HARGA BAHAN = Rp 927,938.81
D. Overhead + Profit (10%) = Rp 92,793.88
E. Total = Rp 1,020,732.69
P.11 SNI 7393 - 2008 (6.1)
MEMASANG 1 BH KLEM SADEL BESI STRIP 50.5 MM
Bahan :
Besi strip 50.5 mm panjang 6 m (11,78 kg) 4.2300 Kg x Rp 371,838.13 = Rp 1,572,875.31
baut mur 1/2" 4.0000 bh x Rp 9,506.53 = Rp 38,026.11
A. JUMLAH HARGA BAHAN = Rp 1,610,901.42
Tenaga :
Pekerja 0.2538 OH x Rp 100,000.00 = Rp 25,380.00
EE Analisa Harga - 39
Tukang besi 0.2538 OH x Rp 140,000.00 = Rp 35,532.00
Kepala Tukang 0.0254 OH x Rp 150,000.00 = Rp 3,810.00
Mandor 0.0127 OH x Rp 165,000.00 = Rp 2,095.50
B. JUMLAH UPAH = Rp 66,817.50
C. JUMLAH BAHAN DAN UPAH = Rp 1,677,718.92
D. Overhead + Profit (10%) = Rp 167,771.89
P.11 E. Total = Rp 1,845,490.81
EE Analisa Harga - 40
Biro Konsultan
CV. CENDANA CONSULTANT
Muliambut Mulia
Kabupaten Puncak Jaya
1 2 3 4 5 6
I MATERIAL NON LOKAL
1 Semen PC Kg 48,028.57
2 Tripleks 3 mm Lbr 317,942.86
3 Tripleks 6 mm Lbr 496,828.57
4 Seng Gelombang BJLS 20 Lbr 205,385.71
5 Seng Plat BJLS 20 Lbr 211,985.71
6 Besi beton polos Kg 66,728.57
7 Besi siku 50.50.5 mm panjang 6 m (22,62 kg) Btg 1,406,037.86 1 m = 3,77 kg
8 Besi Siku 30.30.3 mm panjang 6 m (8,16 kg) Btg 600,273.63 1 m = 1,36 kg
9 Besi strip 50.5 mm panjang 6 m (11,78 kg) Btg 691,618.93 1 m = 1,96 kg
10 Besi strip 20.2 mm panjang 6 m (1,86 kg) Btg 137,283.03 1 m = 0,31 kg
11 baut mur 1/2" Bh 17,682.14
12 Paku seng Kg 79,128.57
13 Paku campur Kg 73,628.57
14 Paku Tripleks Kg 76,228.57
15 Kawat ikat Kg 76,728.57
16 Kawat las dos 475,742.86 1 dos = 5 kg
16 Kaca bening 5 mm m2 819,141.43
17 Kaca riben 5 mm m2 833,941.43
18 Kunci Tanam 2 slaag (besar) bh 317,119.64
19 Kunci Tanam 2 slaag (kecil) bh 251,866.07
20 Engsel pintu bh 53,397.14
21 Engsel Jendela bh 43,447.86
22 Grendel Pintu bh 50,047.86
23 Grendel Jendela bh 46,173.21
24 Hak/Kait Angin bh 62,997.14
25 Handle jendela bh 27,832.86
26 Meni kayu kg 81,328.57
27 Meni besi Kg 81,328.57
28 Cat tembok Kg 62,628.57
29 Cat kayu Kg 126,028.57
30 Cat besi Kg 119,328.57
31 Cat Aluminium Kg 126,028.57
32 Cat Atap Kg 140,428.57
33 Dempul kayu Kg 74,828.57
34 Plamur tembok Kg 66,728.57
35 Formtie bh 16,949.29
36 Lem kayu Kg 92,828.57
37 Lem PVC Tube 13,932.86
38 Kuas biasa bh 44,464.29
39 Kuas roll bh 59,346.43
40 Kabel NYM 2 x 1,5 mm roll 1,243,792.86
41 Kabel NYM 2 x 2,5 mm roll 1,462,936.00
42 Kabel NYM 3 x 2,5 mm roll 1,594,299.43
43 Lampu philips 14W bh 108,697.14
44 Lampu philips 18 W bh 123,697.14
45 Stop kontak bh 55,423.93
46 Saklar tunggal bh 50,423.93
47 Saklar ganda bh 55,423.93
1 2 3 4 5 6
48 Fitting duduk bh 58,898.57
49 MCB 6 A bh 93,298.57
50 Pipa PVC 1" btg 94,428.57
51 Pipa PVC 2" btg 225,285.71
52 Pipa GIP 1,5" btg 1,126,503.86
53 Sekring Box bh 109,746.43
54 Kawat Bronjong 3 mm kotak 1,024,500.00
55 Solar Ltr 55,128.57
56 Minyak pelumas Ltr 77,428.57
57 Minyak Bekesting Ltr 52,428.57
58 Besi plat 2 mm Lbr 3,352,300.99 1 lbr = 46,74 kg
59 Besi plat 3 mm Lbr 5,028,401.50 1 lbr = 70,10 kg
60 Batu batako bh 50,798.56
61 Pengadaan Pipa GIP dia 8" btg 15,525,300.00
1 2 3 4 5 6
62 Pengadaan Flange + Plat penutup pipa penguras dia 8" set 6,462,550.00
63 Pengadaan Turbin Cross Flow T 15 kapasitas 200 KVA: Unit 2,129,807,142.86
64 Pengadaan Turbin Cross Flow T 15 kapasitas 175 KVA: Unit 1,919,142,857.14
65 Pengadaan Pipa besi dia 30", pjg=1,2 m, tebal = 4 mm Btg 9,132,857.14 1 btg = 93,47 kg
66 Expansion Joint 77,64 cm set 32,832,142.86 1 Set = 125 kg
67 Sambungan pipa (flange + baut + paking karet) dia 77,64 cm psg 10,418,871.43 1 Set = 57,5 kg
68 Besi profil C. 50. 38 mm panjang 6 m (33,42 Kg) Btg 2,255,850.00 1 m = 5,57 kg
69 Besi profil C 65.42 mm panjang 6 m (42,54 kg) Btg 2,870,000.00 1 m = 7,09 kg
70 Besi profil C 80.45 mm panjang 6 m (51,78 kg) Btg 3,495,150.00 1 m = 8,63 kg
71 Stang pintu air drag + mur set 5,538,457.14
72 Kabel Twisted 3x35 + 1x25 mm2 mtr 103,094.29
73 Kabel Twisted 2 x 10 mm2 mtr 42,430.00
74 Tiang listrik 9 meter 150 daN btg 15,729,000.00
75 Lampu Jalan LED 70 Watt unit 5,139,750.00
76 Pengadaan dan pemasangan trafo step up 80 kVA Unit 186,000,000.00
77 Stang lampu jalan + clem stang lampu bh 914,928.57
78 Sensor lampu 6 A bh 89,265.71
79 Strain Wedge Clamp (service Klem /wik besar) bh 115,564.29
80 Service klem / wik kecil bh 75,298.57
81 Kaitan Kabel Twiested bh 80,597.14
82 Suspension Clamp with Chain Link (Gantungan kabel) set 75,431.43
83 Stainless steel strip 20 x 0,7 mm2 (pita pengikat) roll 1,155,742.86
84 Stainless steel strip 20 x 0,7 mm2 (pita pengikat) bh 48,155.95
85 Stoping buckle Stainless steel (pengikat pita baja) bh 9,000.00
86 Tap Connector 35-070/35-70 mm2 bh 100,298.57
87 Tap Konektor Distribusi 1 Baut bh 45,165.71
88 Tension Bracket (Penarik) bh 75,564.29
89 Galvanis steel wire 1/4" mtr 29,922.07
90 Klem Sling 1/4" bh 16,961.04
91 Spancroef 1/4" bh 36,222.07
92 Limit 2 A bh 75,298.57
93 Limit 4 A bh 85,298.57
94 Limit 6 A bh 93,298.57
95 Limit 10 A bh 100,298.57
96 MCB Box bh 91,265.71
97 Kawat BC 50 mm2 mtr 140,000.00
98 Cable schoen 50 mm CU mtr 78,400.00
II MATERIAL LOKAL
1 Batu kali M3 2,000,000.00
2 Pasir pasang M3 2,000,000.00
3 Pasir Cor M3 2,000,000.00
4 Pasir Beton M3 2,000,000.00
5 Pasir Urug M3 2,000,000.00
6 Kerikil pecah M3 2,500,000.00
7 Timbunan biasa M3 550,000.00
8 Kayu balok M3 5,600,000.00
9 Kayu Papan btg 5,600,000.00
10 Kayu cina M3 8,350,000.00
11 Balok 5/10 panjang 3 m M3 112,000.00
12 Papan les 1/4 Btg 7,700.00
13 List Kayu Profil 1/3 cm pjg 4m m' 19,250.00
III UPAH TENAGA KERJA
1 Pekerja L01 OH 100,000.00
2 Tukang Batu L02 OH 140,000.00
3 Tukang Kayu L02 OH 140,000.00
4 Tukang Besi L02 OH 140,000.00
5 Tukang Cat L02 OH 140,000.00
6 Tukang Listrik L02 OH 140,000.00
7 Tukang Las L02 OH 140,000.00
1 2 3 4 5 6
8 Tukang pipa L02 OH 140,000.00
9 Kepala Tukang L03 OH 150,000.00
10 Mandor L04 OH 165,000.00
11 Juru ukur L05 OH 140,000.00
12 Pembantu Juru ukur L06 OH 140,000.00
13 Pembantu Mekanik L07b OH 140,000.00
14 Mekanik L07 OH 165,000.00
15 Operator L08 OH 165,000.00
16 Pembantu Operator L09 OH 115,000.00
IV PERALATAN/ANGKUTAN
1 Sewa Excavator Hari 11,843,099.03
2 Sewa Excavator jam 1,691,871.29
3 Sewa Genset jam 115,000.00
4 Biaya angkutan lokasi kg 500.00
PEKERJAAN INTAKE
PEKERJAAN PERSIAPAN
1 Pengukuran dan pasang bowplank (profil melintang) Panjang bowplank = P
Jumlah patok bowplank = J
Panjang seluruh bowplank = PxJ
B PEKERJAAN TANAH
1 Galian Tanah Kolam Bak Intake (dengan excavator) Luas galian tanah = L
dalam galian rata-rata = d
volume galian = Lxd
2 Pek. Dinding tembok pas. Batu kali camp. 1 Pc : 4 Ps Hitungan volume dengan 3D autocad
volume =
3 Siar mata sapi dinding tembok saluran adukan 1 Pc : 2 Ps asumsi Luas plester/2
7 Pas. Bronjong bentuk I type D (keranjang uk. 2 x 1 x 0,5) Volume Bronjong I 10x1
Volume Bronjong II 8x0,5
Volume total
Luas
3 x 3 = 9 m2
6 x 4 = 24 m2
1.6 m
10 titik
16 m
104.16 m2
1.3 m
135.408 m3
42.24 m2
0.4 m
16.896 m3
22.55 m3
25.87 m3
0 m2 0
= 8.1
0,9-0,75x1,12-0,65x1,12 = 2.932
0,5+9x0,9-0,5x4,2x2 = 8.7
= 8.1
= 6.12
= 3
= 6.12
= 3
= 46.07
= 45
= 0.2
= 9
= 45
= 0.15
= 6.75
= 10
= 4
= 14
Biro Konsultan
CV. CENDANA CONSULTANT
Muliambut Mulia
Kabupaten Puncak Jaya
REKAPITULASI
Terbilang : T
Konsultan Perencana
CV. CENDANA CONSULTANT
:
No. Uraian Pekerjaan Analisa Volume Sat. Harga Satuan (Rp) Jumlah Harga (Rp)
Jumlah Harga (Rp)
I PEKERJAAN PERSIAPAN
A. Material Distribusi Utama (MDU)
1 Pengadaan Tiang listrik 9 m 150 daN Harga bhn & Upah 75.00 btg 15,729,000.00 1,179,675,000.00
2 Pengadaan Kabel Twisted, 3x35+1x25 mm2 Harga bhn & Upah 3,300.00 m 103,094.29 340,211,157.00
3 Pengadaan Kabel Twisted, 2x10 mm2 Harga bhn & Upah 6,250.00 m 42,430.00 265,187,500.00
Sub Total 1,785,073,657.000
B Material Pelengkap
1 Strain Wedge Clamp (service Klem /wik besar) Harga bhn & Upah 76.00 bh 115,564.29 8,782,886.04
2 Suspension Clamp with Chain Link (Gantungan kabel ) Harga bhn & Upah 37.00 bh 75,431.43 2,790,962.91
3 Stainless steel strip 20 x 0,7 mm2 Harga bhn & Upah 150.00 bh 48,155.95 7,223,392.88
4 Stoping buckle Stainless steel Harga bhn & Upah 150.00 bh 9,000.00 1,350,000.00
Sub Total 20,147,241.830
Total 1,805,220,898.830
II PEKERJAAN PENGECATAN
1 Pengecatan Tiang dengan cat meni K.4 275.53 M3 47,550.25 13,101,520.38
2 Pengecatan Tiang dengan cat besi K.5 275.53 M2 51,730.25 14,253,235.78
Total 27,354,756.160
III PEMASANGAN TIANG (KONSTRUKSI UTAMA)
1 Galian Tanah Lubang Tiang Listrik B.1 33.00 M3 87,037.50 2,872,237.50
2 Galian Tanah Lubang angker treck schoor B.1 0.13 M3 87,037.50 11,314.88
3 Pemasangan Tiang R-11 (Jalur Akhir/Adjust Dead End Assembly) Q.1 2.00 bh 238,562.50 477,125.00
5 Pemasangan Tiang R-13 (Jalur Lurus/Suspention Assembly) Q.1 73.00 bh 238,562.50 17,415,062.50
6 Pemasangan Treck Schoor Q.3 2.00 bh 800,470.99 1,600,941.98
7 Timbunan batu kali B.5 24.00 M3 2,674,815.00 64,195,560.00
8 Urugan kembali B.2 8.25 M3 24,568.50 202,690.13
9 Pengecoran pondasi tiang listrik beton mutu K125 Q.2 75.00 Ttk 2,521,990.72 189,149,303.73
10 Pengecoran blok angker trek schoor beton mutu K125 E.2 0.16 M3 800,470.99 128,075.36
11 Pemasangan angker tiang besi dia 12 mm Q.4 75.00 Unit 195,265.90 14,644,942.56
12 Pemasangan Grounding Q.5 1.00 Unit 2,386,011.05 2,386,011.05
Total 293,083,264.690
IV PEKERJAAN PEMASANGAN JARINGAN TR dan SR
1 Pemasangan Kabel Twisted, 3x35+1x25 mm2 Q.6 3.00 Kms 11,407,000.00 34,221,000.00
2 Penyambungan SR Q.7 250.00 SR 2,332,744.57 583,186,143.38
3 Pemasangan Lampu Jalan LED 70 Watt Q.8 75.00 bh 12,226,784.27 917,008,820.25
Total 1,534,415,963.630
V PEKERJAAN AKHIR
1 Dokumentasi/Pelaporan - 1.00 Ls 2,500,000.00 2,500,000.00
Total 2,500,000.000
Konsultan Perencana
CV. CENDANA CONSULTANT
JAR NIOGA - 48
Biro Konsultan
CV. CENDANA CONSULTANT
Muliambut Mulia
Kabupaten Puncak Jaya
REKAPITULASI
Terbilang :
Konsultan Perencana
CV. CENDANA CONSULTANT
:
No. Uraian Pekerjaan Analisa Volume Sat. Harga Satuan (Rp) Jumlah Harga (Rp)
JARINGAN ILU - 50
No. Uraian Pekerjaan Analisa Volume Sat. Harga Satuan (Rp) Jumlah Harga (Rp)
JARINGAN ILU - 51
Q. ANALISA JARINGAN LISTRIK TEGANGAN RENDAH
Q.1 PASANG 1 BH TIANG LISTRIK
Tenaga :
Pekerja 0.3750 OH x Rp 100,000.00 = Rp 37,500.00
Tukang listrik 0.3750 OH x Rp 140,000.00 = Rp 52,500.00
Kepala Tukang 0.1250 OH x Rp 150,000.00 = Rp 18,750.00
Mandor 0.1250 OH x Rp 165,000.00 = Rp 20,625.00
Biaya angkutan ke titik lokasi 160.0000 Kg x Rp 500.00 = Rp 80,000.00
Pemasangan material pelengkap 1.0000 Ls x Rp 7,500.00 = Rp 7,500.00
B. JUMLAH UPAH = Rp 216,875.00
D. Overhead + Profit (10%) = Rp 21,687.50
E. Total = Rp 238,562.50
I. ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Jam kerja efektif per-hari Tk 7.00 jam
3 Faktor pengembangan bahan Fk 1.20 -
4 Berat volume bahan D 1.60 Ton/M3
1. BAHAN
Tidak ada bahan yang diperlukan
2. ALAT
2.a. EXCAVATOR (E10)
Kapasitas Bucket V 0.93 M3
Faktor Bucket Fb 1.00 - kondisi tanah berbatu
Faktor Efisiensi alat Fa 0.83 - kondisi kerja baik
Faktor Konversi
Waktu siklus = T1 + T2 Ts1 1.80 menit masuk dalam
- Menggali, memuat dan berputar T1 1.00 menit waktu siklus
- Lain lain T2 0.80 menit disesuaikan dgn
Kap. Prod. / jam = V x Fb x Fa x 60 Q1 21.44 M3 lapangan
Ts1 x Fk
3. TENAGA
Produksi menentukan : EXCAVATOR Q1 21.44 M3/Jam
Produksi Galian / hari = Tk x Q1 Qt 150.09 M3
Kebutuhan tenaga :
- Pekerja P 4.00 orang
- Mandor M 1.00 orang
Koefisien tenaga / M3 :
- Pekerja = Tk x P : Qt (L01) 0.1866 OJ
- Mandor = Tk x M : Qt (L03) 0.0466 OJ
A. TENAGA
B. BAHAN
0.32
C. PERALATAN
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
ANALISA HARGA SATUAN PEKERJAAN (AHSP)
BIDANG CIPTA KARYA SNI 2002 DAN SNI 2008
Tenaga :
Operator 1.0000 OJ 23,571.43 23,571.43
Mekanik 0.5000 OJ 23,571.43 11,785.71
B. JUMLAH UPAH 35,357.14
Peralatan :
Sewa excavator 0.0120 Jam 1,691,871.29 20,302.46
C. JUMLAH ALAT 20,302.46
D. JUMLAH BAHAN, UPAH, DAN ALAT 55,659.60
E. Overhead + Profit (10%) 5,565.96
F. Total 91,016.74
SNI 2835 - 2008 (6.1)
Menggali 1 m3 Tanah biasa sedalam 1 m
Tenaga :
Pekerja 0.7500 OH 100,000.00 75,000.00
Mandor 0.0250 OH 165,000.00 4,125.00
A. JUMLAH UPAH 79,125.00
B. Overhead + Profit (10%) 7,912.50
C. Total 87,037.50
SNI 2835 - 2008 (6.1)
Menggali 1 m3 Tanah biasa sedalam 2 m
Tenaga :
Pekerja 0.9000 OH 100,000.00 90,000.00
Mandor 0.0450 OH 165,000.00 7,425.00
A. JUMLAH UPAH 97,425.00
B. Overhead + Profit (10%) 9,742.50
C. Total 107,167.50
1 SNI 2835 - 2008 (6.8)
Menggali 1 m3 Tanah keras
Tenaga :
Pekerja 1.2500 OH 100,000.00 125,000.00
Mandor 0.1250 OH 165,000.00 20,625.00
A. JUMLAH UPAH 145,625.00
B. Overhead + Profit (10%) 14,562.50
C. Total 160,187.50
2 SNI 2835 - 2008 (6.9)
1 M Urugan Kembali
Tenaga :
Pekerja 0.1920 OH 100,000.00 19,200.00
Mandor 0.0190 OH 165,000.00 3,135.00
A. JUMLAH UPAH 22,335.00
B. Overhead + Profit (10%) 2,233.50
C. Total 24,568.50
3 SNI 2835 - 2008 (6.10)
Memadatkan 1 m3 tanah (per 20 cm)
Tenaga Kerja
Pekerja 0.5000 OH 100,000.00 50,000.00
Mandor 0.0500 OH 165,000.00 8,250.00
A. JUMLAH UPAH 58,250.00
B. Overhead + Profit (10%) 5,825.00
C. Total 64,075.00
4 SNI 2835 - 2008 (6.11)
Mengurug 1 m3 pasir urug
Bahan :
Pasir Urug 1.2000 M 2,000,000.00 2,400,000.00
A. JUMLAH HARGA BAHAN 2,400,000.00
Tenaga :
Pekerja 0.3000 OH 100,000.00 30,000.00
Mandor 0.0100 OH 165,000.00 1,650.00
B. JUMLAH UPAH 31,650.00
MEMBUAT 1 M3 BETON MUTU F'C = 14,5 MPa (K 175), SLUMP (12 2) CM, W/C = 0,66 (menggunakan molen)
Bahan :
Semen PC 326.0000 Kg 48,028.57 15,657,313.82
Pasir Cor 0.5430 m3 2,000,000.00 1,086,000.00
Kerikil pecah 0.7620 m3 2,500,000.00 1,905,000.00
Air kerja 215.0000 ltr - -
A. JUMLAH HARGA BAHAN 18,648,313.82
Tenaga :
Pekerja 1.3300 OH 100,000.00 133,000.00
Tukang batu 0.1890 OH 140,000.00 26,460.00
Kepala Tukang 0.0190 OH 150,000.00 2,850.00
Mandor 0.0660 OH 165,000.00 10,890.00
N. ANALISA TAMBAHAN
SLOOF 60/15 60 / 15
BESI POKOK : 10.00 mm
BEGEL : 6.00 mm
SELIMUT BETON : 0.04 m
TINGGI BETON : 15.00 cm
LEBAR BETON : 60.00 cm
PERHITUNGAN BEKISTING
LUAS BEKISTING/M3 = 1.667
KOLOM 20/20 20 / 20
BESI POKOK : 10.00 mm
BEGEL : 6.00 mm
SELIMUT BETON : 0.04 m
TINGGI BETON : 20.00 cm
LEBAR BETON : 20.00 cm
RINGBALOK 30/30 30 / 30
BESI POKOK : 12.00 mm
BEGEL : 8.00 mm
SELIMUT BETON : 0.04 m
TINGGI BETON : 30.00 cm
LEBAR BETON : 30.00 cm
PERHITUNGAN BEKISTING
LUAS BEKISTING/M3 = 1.232
PONDASI FOOTPLATE 60 / 20
BESI POKOK : 10.00 mm
BEGEL : 10.00 mm
SELIMUT BETON : 0.04 m
TINGGI BETON : 20.00 cm
LEBAR BETON : 60.00 cm
PERHITUNGAN BEKISTING
LUAS BEKISTING/M3 = 3.333
DINDING TEBAL 30 CM
BESI POKOK : 12.00 mm
BESI PEMBAGI : 10.00 mm
SELIMUT BETON : 0.04 m
TINGGI BETON : 0.30 m
LEBAR BETON : 1.57 m
PERHITUNGAN
TULANGAN POKOK 12 mm
JUMLAH BESI = 14.154
PANJANG BESI = 22.222
TOTAL BERAT BESI = 19.733
TULANGAN PEMBAGI 10 mm
JARAK ANTAR TULANGAN = 0.150
JUMLAH BESI = 10.467
PANJANG BESI = 22.222
TOTAL BERAT BESI = 13.711
BLOK ANGKER
BESI POKOK : 10.00 mm
PANJANG BESI / bh : 0.93 m
JUMLAH BESI : 12.00 bh
TULANGAN POKOK 10 mm
JUMLAH BESI = 12.000
PANJANG BESI TOTAL = 11.160
TOTAL BERAT BESI = 6.886
TULANGAN PEMBAGI 8 mm
JUMLAH BESI = 7.000
PANJANG BESI = 22.400
TOTAL BERAT BESI = 8.848
PERHITUNGAN BEKISTING
m LUAS BEKISTING/M3 =
KOLOM 30/30 30 / 30
BESI POKOK : 12 mm
BEGEL : 6 mm
SELIMUT BETON : 0.04 m
TINGGI BETON : 30 cm
LEBAR BETON : 30 cm
RINGBALOK 40/20 40 / 20
BESI POKOK : 12.00 mm
BEGEL : 6.00 mm
SELIMUT BETON : 0.04 m
TINGGI BETON : 20.00 cm
LEBAR BETON : 40.00 cm
PERHITUNGAN BEKISTING
m LUAS BEKISTING/M3 =
m
m'
m'
m'
m'
bh
m
kg
bh
m
kg
m
bh
m
kg
kg
m
bh
m
kg
kg
kg
m
m2
m
bh
m
kg
m
bh
m
kg
kg
bh
m
kg
bh
m
kg
m
SLOOF 20/25 20 / 25
BESI POKOK : 10.00 mm
BEGEL : 6.00 mm
SELIMUT BETON : 0.04 m
TINGGI BETON : 25.00 cm
LEBAR BETON : 20.00 cm
PERHITUNGAN BEKISTING
3.333 m LUAS BEKISTING/M3
KOLOM 40/40 40 / 40
BESI POKOK : 12 mm
BEGEL : 6 mm
SELIMUT BETON : 0.04 m
TINGGI BETON : 40 cm
LEBAR BETON : 40 cm
RINGBALOK 50/20 50 / 20
BESI POKOK : 12.00 mm
BEGEL : 8.00 mm
SELIMUT BETON : 0.04 m
TINGGI BETON : 20.00 cm
LEBAR BETON : 50.00 cm
1 m2 9.461
0.12
8.33333333 78.84167
SLOOF 40/20 40 / 20
BESI POKOK : 12.00 mm
BEGEL : 6.00 mm
SELIMUT BETON : 0.04 m
TINGGI BETON : 20.00 cm
LEBAR BETON : 40.00 cm
PERHITUNGAN BEKISTING
= 5.000 m LUAS BEKISTING/M3
KOLOM 45/50 45 / 50
BESI POKOK : 12 mm
BEGEL : 6 mm
SELIMUT BETON : 0.04 m
TINGGI BETON : 50 cm
LEBAR BETON : 45 cm
RINGBALOK 60/15 60 / 15
BESI POKOK : 10.00 mm
BEGEL : 6.00 mm
SELIMUT BETON : 0.04 m
TINGGI BETON : 15.00 cm
LEBAR BETON : 60.00 cm
= 0.980 m'
= 0.170 m'
= 74.529 bh
= 73.039 m
= 16.215 kg
### mm
= 6.000 bh
= 75.000 m
= 66.600 kg
= 82.815 kg
= 2.500 m
KOLOM 50/60 60 /
BESI POKOK : 12 mm
BEGEL : 6 mm
SELIMUT BETON : 0.04 m
TINGGI BETON : 60 cm
LEBAR BETON : 60 cm
RINGBALOK 80/12 80 /
BESI POKOK : 10.00 mm
BEGEL : 8.00 mm
SELIMUT BETON : 0.04 m
TINGGI BETON : 12.00 cm
LEBAR BETON : 80.00 cm
M2 2 lapis
### mm
= 0.170 m
= 6.882 bh
= 13.765 m
= 114.706 m 0.12
= 70.774 kg 8.33333333
1
10 mm
= 0.170 m
= 6.882 bh
= 13.765 m
= 114.706 m
= 70.774 kg
= 141.547 kg
= 12.413 m
60
BESI BEGEL 6 mm
0.60 X 0.60 = 0.360 m
= 2.778 m'
= 0.04 m'
= 2.180 m'
= 0.17 m'
= 17.340 bh
= 37.801 m
= 14.931 kg
12 mm
= 12.000 bh
= 33.333 m
= 29.600 kg
= 44.531 kg
= 0.0014 m
= 0.004
= 3.333 m
12
BESI BEGEL 8 mm
### X 0.12 = 0.096 m
= 10.417 m'
= 0.040 m'
= 1.620 m'
= 0.200 m'
= 53.083 bh
= 85.995 m
= 33.968 kg
10 mm
= 11.000 bh
= 114.583 m
= 70.698 kg
= 109.899 kg
= 5.417 m
ANALISA HARGA SATUAN PEKERJAAN (AHSP)
BIDANG SUMBER DAYA AIR RSNI 2008
T.02 1 m2 Tebas tebang memotong berupa memotong dan membersihkan lokasi dari tanaman/
tumbuhan diameter < 15cm
No Uraian Kode Satuan Koefisien Harga Satuan Jumlah
A Tenaga Kerja
Pekerja L.01 OH 0.0750 100,000 7,500.00
Mandor L.04 OH 0.0075 165,000 1,237.50
Jumlah Harga Tenaga 8,737.50
B Bahan
T.03 Cabut 1 tunggul pohon tanaman keras diameter >15 cm dan membuang sisa tunggul kayu
dan akar-akar nya
No Uraian Kode Satuan Koefisien Harga Satuan Jumlah
A Tenaga Kerja
Pekerja L.01 OH 0.2000 100,000 20,000.00
Mandor L.04 OH 0.0200 165,000 3,300.00
Jumlah Harga Tenaga 23,300.00
B Bahan
Jumlah Harga Bahan 0.00
C Peralatan
Chainsaw E.06 Sewa-hari 0.1000
c. Pekerjaan Tanah Secara Manual ( T.06 s/d T.11, galian tanah sudah termasuk pembuangan hasil
galian dengan jarak angkut L < 3m serta perataan dan perapihan )
T.06 1 M3 Galian Tanah Biasa sedalam < 1 m
No Uraian Kode Satuan Koefisien Harga Satuan Jumlah
A Tenaga Kerja
Pekerja L.01 OH 0.5630 100,000 56,300.00
Mandor L.04 OH 0.0563 165,000 9,289.50
Jumlah Harga Tenaga
B Bahan
Jumlah Harga Bahan
C Peralatan
T.07 Galian Tanah Berbatu sedalam > 3 m, tambahan koefisien untuk setiap penambahan
kedalaman 1 m
No Uraian Kode Satuan Koefisien Harga Satuan Jumlah
A Tenaga Kerja
Pekerja L.01 OH 0.1500 100,000 15,000.00
Mandor L.04 OH 0.0150 165,000 2,475.00
Jumlah Harga Tenaga
B Bahan
Jumlah Harga Bahan
C Peralatan
Jack hammer E.14 sewa-hari 0.1500
T.08 Galian Batu dengan kedalaman >3 m, tambahan koefisien setiap penambahan kedalaman 1 m
No Uraian Kode Satuan Koefisien Harga Satuan Jumlah
A Tenaga Kerja
Pekerja L.01 OH 0.3750 100,000 37,500.00
Mandor L.04 OH 0.0375 165,000 6,187.50
Jumlah Harga Tenaga
B Bahan
Jumlah Harga Bahan
C Peralatan
Jack hammer *) E.14 sewa-hari 0.3300
T.09 Galian Tanah Cadas atau tanah keras > 3 m, tambahan koefisien setiap penambahan kedalaman 1 m
No Uraian Kode Satuan Koefisien Harga Satuan Jumlah
A Tenaga Kerja
Pekerja L.01 OH 0.1000 100,000 10,000.00
Mandor L.04 OH 0.0100 165,000 1,650.00
Jumlah Harga Tenaga
B Bahan
Jumlah Harga Bahan
C Peralatan
Jack hammer *) E.14 sewa-hari 0.1250
T.10 1 m3 Galian Lumpur sedalam > 3 m, tambahan koefisien untuk setiap penambahan kedalaman 1 m
No Uraian Kode Satuan Koefisien Harga Satuan Jumlah
A Tenaga Kerja
Pekerja L.01 OH 0.1000 100,000 10,000.00
Mandor L.04 OH 0.0100 165,000 1,650.00
Jumlah Harga Tenaga
B Bahan
Jumlah Harga Bahan
C Peralatan
T.11 1 m3 Galian Pasir untuk pondasi bangunan sedalam > 3 m, tambahan koefisien setiap penambahan kedalaman 1 m
No Uraian Kode Satuan Koefisien Harga Satuan Jumlah
A Tenaga Kerja
Pekerja L.01 OH 0.1000 100,000 10,000.00
Mandor L.04 OH 0.0100 165,000 1,650.00
Jumlah Harga Tenaga
B Bahan
Jumlah Harga Bahan
C Peralatan
Jumlah Harga Peralatan
D Jumlah harga tenaga, Bahan, dan Peralatan (A+B+C) 11,650.00
E Overhead + Profit (10%) 10% xD 1,165.00
0.3750
0.0380
Kode
Ganco/Balincong T.01
Cangkul T.02
Sekop T.03
Sabit T.04
Sapu lidi T.05
Ekrak/Pengki T.06
Kereta Dorong T.07
Cetok/Sendok Tembok T.08
Ember/Timba T.09
Garu T.10
Sikat ijuk T.11
Hammer/Martil T.12
Parang T.13
Palu T.14
Linggis T.15
Kereta Dorong Besar T.16
Alat Perata T.17
Tempat Penggorengan Aspal T.18
Kuas T.19
Ampelas T.20
Sikat Baja T.21
Gunting Potong Baja T.22
Kunci Pembengkok T.23
Helmet T.24
Rompi T.25
Sepatu T.26
Roskam T.27
DAFTAR PERHITUNGAN BIAYA PE
B IAYA PE M I LI KAN
OPERASI (OWNERSHIP COST)
UMUR PER HARGA CRF B IAYA
KODE JENIS PERALATAN TENAGA ALAT TAHUN SETEMPAT i = 20 % DEPRESIASI ASURANSI PEMILIKAN
ALAT ( HP ) ( TAHUN ) ( JAM ) /JAM
(A) (W) (B) (C) (D) (E) (F)
i(1+i) ^A (90 % x B) x C (3 % + (3% x 10 %))xB (D)+(E)
(1+i)^A-1 W W
( Rp.) ( Rp.) ( Rp.)
1 2 3 4 5 6 7 8 9 10
E 020 EXCAVATOR 90.00 8.00 1,500.00 1,113,465,075.00 0.260609 174,107.69 24,496.23 198,603.93
E 010 MOTOR GRADER 100.00 8.00 1,500.00 1,036,234,112.50 0.260609 162,031.42 22,797.15 184,828.57
Produktivitas Alat excavator
Waktu gali
Kondisi/kedalaman gali Ringan sedang agak sulit sulit
0-2m 6 9 15 26
2-4m 7 11 17 28
4 m lebih 8 13 19 30
TOTAL
A
PEKERJA VOLUME HARI KODE VOL UPAH (Rp / O/H)
.
(O/H)
Mandor 1.00 1.00 1.00 165,000.00
Pekerja 4.00 1.00 4.00 100,000.00
JUMLAH HA
OVERHEAD & PROFIT
HARGA SATUAN PEKERJAAN ( D + E )
Volume : 97.65 M3 Harga Sat 146,127.13
t berat (97,65 m3 / hari)
anpa angkutan)
SUB TOTAL
BIAYA (Rp)
(Rp)
165,000.00
400,000.00
PEKERJA 565,000.00
SUB TOTAL
BIAYA (Rp)
(Rp)
MATERIAL -
SUB TOTAL
BIAYA (Rp)
(Rp)
### 0.142857
-
PERALATAN ###
TOTAL (Rp) ###
1,861,214.85
###
per M3
1 Asphalt mixing plant E01 294 1 Asphalt mixing plant E01 2
2 Asphalt finisher E02 72.4 2 Asphalt finisher E02 72,4 1
3 Asphalt sprayer E03 4 3 Asphalt sprayer E03 4,0 85
4 Bulldozer 100-150 hp E04 155 4 Bulldozer 100-150 hp E04
5 Compressor 4000-6500 l\m E05 60 5 Compressor 4000-6500 l\m
6 Concrete mixer 0.3-0.6 m E06 20 6 Concrete mixer 0.3-0.6 m
7 Crane 10-15 ton E07 138 7 Crane 10-15 ton E07 138,0
8 Dump Truck 3.5 ton E08 100 8 Dump Truck 3.5 ton E08 10
9 Dump Truck 10 ton E09 190 9 Dump Truck 10 ton E09 19
10 Excavator 80-140 hp E10 133 10 Excavator 80-140 hp E10
11 Flat bed truck 3-4 m E11 190 11 Flat bed truck 3-4 m E11
12 Generator set E12 180 12 Generator set E12 180,0
13 Motor grader >100 hp E13 135 13 Motor grader >100 hp E1
14 Track Loader 75-100 hp E14 70 14 Track Loader 75-100 hp E
15 Wheel Loader 1.0-1.6 m E15 96 15 Wheel Loader 1.0-1.6 m
16 Three wheel roller 6-8 t E16 55 16 Three wheel roller 6-8 t E
17 Tandem roller 6-8 t. E17 82 17 Tandem roller 6-8 t. E17 8
18 Tire roller 8-10 t. E18 100.5 18 Tire roller 8-10 t. E18 100
19 Vibratory roller 5-8 t. E19 82 19 Vibratory roller 5-8 t. E19
20 Concrete vibrator E20 5.5 20 Concrete vibrator E20 5,5
21 Stone crusher E21 220 21 Stone crusher E21 220,0
22 Water pump 70-100 mm E22 6 22 Water pump 70-100 mm E
23 Water tanker 3000-4500 l. E23 100 23 Water tanker 3000-4500 l
24 Pedestrian roller E24 8.8 24 Pedestrian roller E24 8,8
25 Tamper E25 4.7 25 Tamper E25 4,7 121,00 T
26 Jack Hammer E26 0 1330 26 Jack Hammer E26 0,0 1.3
27 Fulvi mixer E27 27 Fulvi mixer E27 345,0 2.0
28 Concrete pump E28 28 Concrete pump E28 100,
29 Trailer 20 ton E29 29 Trailer 20 ton E29 175,0 2
30 Pile driver + hammer E30 30 Pile driver + hammer E30
31 Crane on track 35 ton E31 31 Crane on track 35 ton E3
32 Welding set E32 32 Welding set E32 40,0 250
33 Bore pile machine E33 33 Bore pile machine E33 15
34 Asphalt liquid mixer E34 34 Asphalt liquid mixer E34 5
35 Tronton E35 35 Tronton E35 150,0 15,0 T
36 Cold milling E36 36 Cold milling E36 248,0 1.
37 Rock drill breaker E37 37 Rock drill breaker E37 3,0
38 Cold recycler E38 38 Cold recycler E38 900,0 2
39 Hot recycler E39 39 Hot recycler E39 400,0 3,
40 Aggregat (chip) spreader E40 40 Aggregat (chip) spreader
41 Asphalt distributor E41 41 Asphalt distributor E41 11
42 Slip form paver E42 42 Slip form paver E42 105,0
43 Concrete pan mixer E43 43 Concrete pan mixer E43 1
44 Concrete breaker E44 44 Concrete breaker E44 29
45 Aspahlt tanker E45 45 Aspahlt tanker E45 190,0
46 Cement tanker E46 46 Cement tanker E46 190,0
47 Condrete mixer (350) E47 47 Condrete mixer (350) E47
48 Vibrating rammer E48 48 Vibrating rammer E48 4,2
49 Truk mixer (agitator) E49 49 Truk mixer (agitator) E49
50 Bore pile machine E50 50 Bore pile machine E50 12
51 Crane on track 75-100 ton E51 51 Crane on track 75-100 ton
52 Blending equipment E52 52 Blending equipment E52
53 Asphalt liquid mixer E34a 53 Asphalt liquid mixer E34a
54 Water jet E53 54 Water jet E53 - 600 Liter/
1 Asphalt mixing plant E01 294,0 60,0 T/Jam 4.818.593,08 1 Asphalt mixing plant E01 294,0 60,0 T/Jam 4.818.593,08
2 Asphalt finisher E02 72,4 10,0 Ton 820.779,19 2 Asphalt finisher E02 72,4 10,0 Ton 820.779,19
3 Asphalt sprayer E03 4,0 850,0 Liter 3 Asphalt sprayer E03 4,0 850,0 Liter
4 Bulldozer 100-150 hp E04 155,0 - - 402.799,43 4 Bulldozer 100-150 hp E04 155,0 - - 402.799,43
5 Compressor 4000-6500 l\m E05 60,0 5.000,0 CPM/(L/m) 106.890 5 Compressor 4000-6500 l\m E05 60,0 5.000,0 CPM/(L/m) 106.890
6 Concrete mixer 0.3-0.6 m E06 20,0 500,0 Liter 6 Concrete mixer 0.3-0.6 m E06 20,0 500,0 Liter
7 Crane 10-15 ton E07 138,0 15,0 Ton 7 Crane 10-15 ton E07 138,0 15,0 Ton
8 Dump Truck 3.5 ton E08 100,0 3,5 Ton 8 Dump Truck 3.5 ton E08 100,0 3,5 Ton
9 Dump Truck 10 ton E09 190,0 10,0 Ton 420.000.000 212.812,53 9 Dump Truck 10 ton E09 190,0 10,0 Ton 420.000.000 212.812,53
10 Excavator 80-140 hp E10 133,0 0,9 m 934.000.000 383.294,39 10 Excavator 80-140 hp E10 133,0 0,9 m 934.000.000 383.294,39
11 Flat bed truck 3-4 m E11 190,0 10,0 ton 11 Flat bed truck 3-4 m E11 190,0 10,0 ton
12 Generator set E12 180,0 135,0 KVA 277.104,99 12 Generator set E12 180,0 135,0 KVA 277.104,99
13 Motor grader >100 hp E13 135,0 10.800,0 - 327.468,61 13 Motor grader >100 hp E13 135,0 10.800,0 - 327.468,61
14 Track Loader 75-100 hp E14 70,0 0,8 m 14 Track Loader 75-100 hp E14 70,0 0,8 m
15 Wheel Loader 1.0-1.6 m E15 96,0 1,5 m 253.964,94 15 Wheel Loader 1.0-1.6 m E15 96,0 1,5 m 253.964,94
16 Three wheel roller 6-8 t E16 55,0 8,0 Ton 16 Three wheel roller 6-8 t E16 55,0 8,0 Ton
17 Tandem roller 6-8 t. E17 82,0 8,1 Ton 379.339,78 17 Tandem roller 6-8 t. E17 82,0 8,1 Ton 379.339,78
18 Tire roller 8-10 t. E18 100,5 9,0 Ton 335.448,22 18 Tire roller 8-10 t. E18 100,5 9,0 Ton 335.448,22
19 Vibratory roller 5-8 t. E19 82,0 7,1 Ton 316.831,09 19 Vibratory roller 5-8 t. E19 82,0 7,1 Ton 316.831,09
20 Concrete vibrator E20 5,5 25,0 - 18.353,23 20 Concrete vibrator E20 5,5 25,0 - 18.353,23
21 Stone crusher E21 220,0 50,0 T/Jam 21 Stone crusher E21 220,0 50,0 T/Jam
22 Water pump 70-100 mm E22 6,0 - - 22 Water pump 70-100 mm E22 6,0 - -
23 Water tanker 3000-4500 l. E23 100,0 4.000,0 Liter 155.193,02 23 Water tanker 3000-4500 l. E23 100,0 4.000,0 Liter 155.193,02
24 Pedestrian roller E24 8,8 835,00 Ton 24 Pedestrian roller E24 8,8 835,00 Ton
25 Tamper E25 4,7 121,00 Ton 25 Tamper E25 4,7 121,00 Ton
26 Jack Hammer E26 0,0 1.330,00 - 15.795,70 26 Jack Hammer E26 0,0 1.330,00 - 15.795,70
27 Fulvi mixer E27 345,0 2.005,00 - 27 Fulvi mixer E27 345,0 2.005,00 -
28 Concrete pump E28 100,0 8,00 m 155.156,84 28 Concrete pump E28 100,0 8,00 m 155.156,84
29 Trailer 20 ton E29 175,0 20,00 Ton 29 Trailer 20 ton E29 175,0 20,00 Ton
30 Pile driver + hammer E30 25,0 2,50 Ton 30 Pile driver + hammer E30 25,0 2,50 Ton
31 Crane on track 35 ton E31 125,0 35,0 Ton 31 Crane on track 35 ton E31 125,0 35,0 Ton
32 Welding set E32 40,0 250,0 Amp 32 Welding set E32 40,0 250,0 Amp
33 Bore pile machine E33 150,0 2.000,0 Meter 33 Bore pile machine E33 150,0 2.000,0 Meter
34 Asphalt liquid mixer E34 5,0 1.000,0 Liter 34 Asphalt liquid mixer E34 5,0 1.000,0 Liter
35 Tronton E35 150,0 15,0 Ton 35 Tronton E35 150,0 15,0 Ton
36 Cold milling E36 248,0 1.000,0 m 36 Cold milling E36 248,0 1.000,0 m
37 Rock drill breaker E37 3,0 - - 266.452,13 37 Rock drill breaker E37 3,0 - - 266.452,13
38 Cold recycler E38 900,0 2,2 M 38 Cold recycler E38 900,0 2,2 M
39 Hot recycler E39 400,0 3,0 M 39 Hot recycler E39 400,0 3,0 M
40 Aggregat (chip) spreader E40 115,0 3,5 M 40 Aggregat (chip) spreader E40 115,0 3,5 M
41 Asphalt distributor E41 115,0 4.000,0 Liter 41 Asphalt distributor E41 115,0 4.000,0 Liter
42 Slip form paver E42 105,0 2,5 M 426.628,68 42 Slip form paver E42 105,0 2,5 M 426.628,68
43 Concrete pan mixer E43 134,0 600,0 Liter 493.265,26 43 Concrete pan mixer E43 134,0 600,0 Liter 493.265,26
44 Concrete breaker E44 290,0 20,0 m/jam 44 Concrete breaker E44 290,0 20,0 m/jam
45 Aspahlt tanker E45 190,0 4.000,0 liter 45 Aspahlt tanker E45 190,0 4.000,0 liter
46 Cement tanker E46 190,0 4.000,0 liter 46 Cement tanker E46 190,0 4.000,0 liter
47 Condrete mixer (350) E47 20,0 350,0 liter 47 Condrete mixer (350) E47 20,0 350,0 liter
48 Vibrating rammer E48 4,2 80,0 KG 48 Vibrating rammer E48 4,2 80,0 KG
49 Truk mixer (agitator) E49 220,0 5,0 M 449.232,73 49 Truk mixer (agitator) E49 220,0 5,0 M 449.232,73
50 Bore pile machine E50 125,0 60,0 CM 50 Bore pile machine E50 125,0 60,0 CM
51 Crane on track 75-100 ton E51 200,0 75,0 Ton 51 Crane on track 75-100 ton E51 200,0 75,0 Ton
52 Blending equipment E52 50,0 30,0 Ton 52 Blending equipment E52 50,0 30,0 Ton
53 Asphalt liquid mixer E34a 40,0 20.000,0 Liter 53 Asphalt liquid mixer E34a 40,0 20.000,0 Liter
54 Water jet E53 - 600 Liter/Jam 18.534,21 54 Water jet E53 - 600 Liter/Jam 18.534,21
4.818.593,08 1 Asphalt mixing plant E01 294,0 60,0 T/Jam 4.818.593,08 1 Asphalt mixing plant E01 294,0 60,0 T/Jam 4.
2 Asphalt finisher E02 72,4 10,0 Ton 820.779,19 2 Asphalt finisher E02 72,4 10,0 Ton 820.779,1
3 Asphalt sprayer E03 4,0 850,0 Liter 3 Asphalt sprayer E03 4,0 850,0 Liter
4 Bulldozer 100-150 hp E04 155,0 - - 402.799,43 4 Bulldozer 100-150 hp E04 155,0 - - 402.799,4
0,0 CPM/(L/m) 106.890 5 Compressor 4000-6500 l\m E05 60,0 5.000,0 CPM/(L/m) 106.890 5 Compressor 4000-6500 l\m E05 60,0 5.000,0
6 Concrete mixer 0.3-0.6 m E06 20,0 500,0 Liter 6 Concrete mixer 0.3-0.6 m E06 20,0 500,0 Lit
7 Crane 10-15 ton E07 138,0 15,0 Ton 7 Crane 10-15 ton E07 138,0 15,0 Ton
8 Dump Truck 3.5 ton E08 100,0 3,5 Ton 8 Dump Truck 3.5 ton E08 100,0 3,5 Ton
0.000.000 212.812,53 9 Dump Truck 10 ton E09 190,0 10,0 Ton 420.000.000 212.812,53 9 Dump Truck 10 ton E09 190,0 10,0 Ton 420.0
34.000.000 383.294,39 10 Excavator 80-140 hp E10 133,0 0,9 m 934.000.000 383.294,39 10 Excavator 80-140 hp E10 133,0 0,9 m 934.
11 Flat bed truck 3-4 m E11 190,0 10,0 ton 11 Flat bed truck 3-4 m E11 190,0 10,0 ton
12 Generator set E12 180,0 135,0 KVA 277.104,99 12 Generator set E12 180,0 135,0 KVA 277.104
0 - 327.468,61 13 Motor grader >100 hp E13 135,0 10.800,0 - 327.468,61 13 Motor grader >100 hp E13 135,0 10.800,0 -
14 Track Loader 75-100 hp E14 70,0 0,8 m 14 Track Loader 75-100 hp E14 70,0 0,8 m
253.964,94 15 Wheel Loader 1.0-1.6 m E15 96,0 1,5 m 253.964,94 15 Wheel Loader 1.0-1.6 m E15 96,0 1,5 m 2
16 Three wheel roller 6-8 t E16 55,0 8,0 Ton 16 Three wheel roller 6-8 t E16 55,0 8,0 Ton
17 Tandem roller 6-8 t. E17 82,0 8,1 Ton 379.339,78 17 Tandem roller 6-8 t. E17 82,0 8,1 Ton 379.33
18 Tire roller 8-10 t. E18 100,5 9,0 Ton 335.448,22 18 Tire roller 8-10 t. E18 100,5 9,0 Ton 335.448
19 Vibratory roller 5-8 t. E19 82,0 7,1 Ton 316.831,09 19 Vibratory roller 5-8 t. E19 82,0 7,1 Ton 316.8
20 Concrete vibrator E20 5,5 25,0 - 18.353,23 20 Concrete vibrator E20 5,5 25,0 - 18.353,23
21 Stone crusher E21 220,0 50,0 T/Jam 21 Stone crusher E21 220,0 50,0 T/Jam
22 Water pump 70-100 mm E22 6,0 - - 22 Water pump 70-100 mm E22 6,0 - -
00,0 Liter 155.193,02 23 Water tanker 3000-4500 l. E23 100,0 4.000,0 Liter 155.193,02 23 Water tanker 3000-4500 l. E23 100,0 4.000,
24 Pedestrian roller E24 8,8 835,00 Ton 24 Pedestrian roller E24 8,8 835,00 Ton
25 Tamper E25 4,7 121,00 Ton 25 Tamper E25 4,7 121,00 Ton
26 Jack Hammer E26 0,0 1.330,00 - 15.795,70 26 Jack Hammer E26 0,0 1.330,00 - 15.795,70
27 Fulvi mixer E27 345,0 2.005,00 - 27 Fulvi mixer E27 345,0 2.005,00 -
28 Concrete pump E28 100,0 8,00 m 155.156,84 28 Concrete pump E28 100,0 8,00 m 155.156,
29 Trailer 20 ton E29 175,0 20,00 Ton 29 Trailer 20 ton E29 175,0 20,00 Ton
30 Pile driver + hammer E30 25,0 2,50 Ton 30 Pile driver + hammer E30 25,0 2,50 Ton
31 Crane on track 35 ton E31 125,0 35,0 Ton 31 Crane on track 35 ton E31 125,0 35,0 Ton
32 Welding set E32 40,0 250,0 Amp 32 Welding set E32 40,0 250,0 Amp
33 Bore pile machine E33 150,0 2.000,0 Meter 33 Bore pile machine E33 150,0 2.000,0 Meter
34 Asphalt liquid mixer E34 5,0 1.000,0 Liter 34 Asphalt liquid mixer E34 5,0 1.000,0 Liter
35 Tronton E35 150,0 15,0 Ton 35 Tronton E35 150,0 15,0 Ton
36 Cold milling E36 248,0 1.000,0 m 36 Cold milling E36 248,0 1.000,0 m
37 Rock drill breaker E37 3,0 - - 266.452,13 37 Rock drill breaker E37 3,0 - - 266.452,13
38 Cold recycler E38 900,0 2,2 M 38 Cold recycler E38 900,0 2,2 M
39 Hot recycler E39 400,0 3,0 M 39 Hot recycler E39 400,0 3,0 M
40 Aggregat (chip) spreader E40 115,0 3,5 M 40 Aggregat (chip) spreader E40 115,0 3,5 M
41 Asphalt distributor E41 115,0 4.000,0 Liter 41 Asphalt distributor E41 115,0 4.000,0 Liter
42 Slip form paver E42 105,0 2,5 M 426.628,68 42 Slip form paver E42 105,0 2,5 M 426.628,68
r 493.265,26 43 Concrete pan mixer E43 134,0 600,0 Liter 493.265,26 43 Concrete pan mixer E43 134,0 600,0 Liter 4
44 Concrete breaker E44 290,0 20,0 m/jam 44 Concrete breaker E44 290,0 20,0 m/jam
45 Aspahlt tanker E45 190,0 4.000,0 liter 45 Aspahlt tanker E45 190,0 4.000,0 liter
46 Cement tanker E46 190,0 4.000,0 liter 46 Cement tanker E46 190,0 4.000,0 liter
47 Condrete mixer (350) E47 20,0 350,0 liter 47 Condrete mixer (350) E47 20,0 350,0 liter
48 Vibrating rammer E48 4,2 80,0 KG 48 Vibrating rammer E48 4,2 80,0 KG
49 Truk mixer (agitator) E49 220,0 5,0 M 449.232,73 49 Truk mixer (agitator) E49 220,0 5,0 M 449.2
50 Bore pile machine E50 125,0 60,0 CM 50 Bore pile machine E50 125,0 60,0 CM
51 Crane on track 75-100 ton E51 200,0 75,0 Ton 51 Crane on track 75-100 ton E51 200,0 75,0 T
52 Blending equipment E52 50,0 30,0 Ton 52 Blending equipment E52 50,0 30,0 Ton
53 Asphalt liquid mixer E34a 40,0 20.000,0 Liter 53 Asphalt liquid mixer E34a 40,0 20.000,0 Lite
54 Water jet E53 - 600 Liter/Jam 18.534,21 54 Water jet E53 - 600 Liter/Jam 18.534,21
E01 294,0 60,0 T/Jam 4.818.593,08
72,4 10,0 Ton 820.779,19
4,0 850,0 Liter
p E04 155,0 - - 402.799,43
500 l\m E05 60,0 5.000,0 CPM/(L/m) 106.890,74
0.6 m E06 20,0 500,0 Liter
7 138,0 15,0 Ton
E08 100,0 3,5 Ton
E09 190,0 10,0 Ton 420.000.000 212.812,53
hp E10 133,0 0,9 m 934.000.000 383.294,39
m E11 190,0 10,0 ton
180,0 135,0 KVA 277.104,99
hp E13 135,0 10.800,0 - 327.468,61
00 hp E14 70,0 0,8 m
1.6 m E15 96,0 1,5 m 253.964,94
6-8 t E16 55,0 8,0 Ton
. E17 82,0 8,1 Ton 379.339,78
18 100,5 9,0 Ton 335.448,22
t. E19 82,0 7,1 Ton 316.831,09
E20 5,5 25,0 - 18.353,23
220,0 50,0 T/Jam
0 mm E22 6,0 - -
-4500 l. E23 100,0 4.000,0 Liter 155.193,02
24 8,8 835,00 Ton
48,0 1.000,0 m
E37 3,0 - - 266.452,13
900,0 2,2 M
1 2 3 4 5 6
1 2 3 4 5 6
45 Kabel NYM 2 x 2,5 mm M106 roll 1,462,936.00
46 Kabel NYM 3 x 2,5 mm M107 roll 1,594,299.43
47 Lampu philips 14W M112 bh 108,697.14
48 Lampu philips 18 W M113 bh 123,697.14
49 Stop kontak M121 bh 55,423.93
50 Saklar tunggal M122 bh 50,423.93
51 Saklar ganda M123 bh 55,423.93
52 Fitting duduk M124 bh 58,898.57
53 MCB 6 A M125 bh 93,298.57
54 Sekring Box M127 bh 109,746.43
55 Kloset Duduk KIA M128 set 3,881,957.14
56 Kloset Jongkok KIA M130 set 3,064,385.71
57 Washbak stainless steel M133 bh 895,978.57
58 Floor drain M137 bh 79,598.57
59 Kran air 1/2" M138 bh 47,223.93
60 Stop kran GIP dia 1/2" M139 bh 54,665.71
1 2 3 4 5 6
61 Stop kran GIP dia 3/4" M140 bh 78,998.57
62 Pipa PVC dia 1/2" M146 Btg 60,364.29
63 Pipa PVC dia 3/4" M147 Btg 77,346.43
64 Seal tape M159 bh 15,463.29
65 Air Valve GIP dia 1" M248 bh 293,085.71
66 Solar M289 Ltr 55,128.57
67 Minyak pelumas M290 Ltr 77,428.57
68 Besi plat 2 mm M292 Lbr 3,352,300.99 1 lbr = 45,22 kg
69 Besi plat 3 mm M293 Lbr 5,028,401.50 1 lbr = 67,82 kg
70 Batu batako bh 25,000.00
71 Pengadaan Turbin Cross Flow T 15 kapasitas 200 KVA: Unit 2,129,807,142.86
72 Pengadaan Pipa besi dia 30", pjg=1,2 m, tebal = 4 mm Btg 9,132,857.14 1 btg = 74,93 kg
73 Expansion Joint 77,64 cm set 32,832,142.86 1 Set = 125 kg
74 Sambungan pipa (flange + baut + paking karet) dia 77,64 cm psg 10,418,871.43 1 Set = 62,5 kg
75 Besi profil C. 50. 38 mm panjang 6 m (33,42 Kg) Btg 2,255,850.00 1 m = 5,57 kg
76 Besi profil C 65.42 mm panjang 6 m (42,54 kg) Btg 2,870,000.00 1 m = 7,09 kg
77 Besi profil C 80.50 mm panjang 6 m (51,78 kg) Btg 3,495,150.00 1 m = 8,63 kg
78 Stang pintu air drag + mur set 5,538,457.14
II MATERIAL LOKAL
1 Batu kali M3 2,000,000.00
2 Pasir pasang M3 2,000,000.00
3 Pasir Cor M3 2,000,000.00
4 Pasir Beton M3 2,000,000.00
5 Pasir Urug M3 2,000,000.00
6 Kerikil pecah M3 2,500,000.00
7 Timbunan biasa M3 550,000.00
8 Kayu balok M3 5,600,000.00
9 Kayu Papan btg 5,600,000.00
10 Kayu cina M3 8,350,000.00
11 Balok 5/10 panjang 3 m M3 112,000.00
12 Papan les 1/4 Btg 7,700.00
13 List Kayu Profil 1/3 cm pjg 4m m' 19,250.00
III UPAH TENAGA KERJA
1 Pekerja L01 OH 100,000.00
2 Tukang Batu L02 OH 140,000.00
3 Tukang Kayu L02 OH 140,000.00
4 Tukang Besi L02 OH 140,000.00
5 Tukang Cat L02 OH 140,000.00
6 Tukang Listrik L02 OH 140,000.00
7 Tukang Las L02 OH 140,000.00
8 Tukang pipa L02 OH 140,000.00
9 Kepala Tukang L03 OH 165,000.00
10 Mandor L04 OH 165,000.00
11 Juru ukur L05 OH 140,000.00
12 Pembantu Juru ukur L06 OH 140,000.00
13 Pembantu Mekanik L07b OH 140,000.00
14 Mekanik L07 OH 165,000.00
15 Operator L08 OH 165,000.00
16 Pembantu Operator L09 OH 115,000.00
IV PERALATAN
1 Sewa Excavator Hari 11,843,099.03
2 Sewa Excavator jam 1,691,871.29
3 Sewa Molen Hari 500,000.00
4 Sewa Theodolit jam
5 Sewa Mesin las listrik jam 75,000.00
6 Sewa Genset jam 40,000.00
7 Sewa Tackel jam 40,000.00
1 2 3 4 5 6
Mulia, 1 April 2014
Konsultan Perencana
CV. CENDANA CONSULTANT
Contoh
Kebutuhan Bahan setiap 1 m3 pas. Batu Batako (29x14x9)
1 m3 Batako dibutuhkan perekat 0.243425 m3
1 m3 Pas. Batu Kali dibutuhkan perekat 0.495 m3 224.01434
1:4 1:3 1:2 1:4 1:3 1:2
batu batako #DIV/0! #DIV/0! #DIV/0! batu batako 300.63 300.63 300.63
Semen (sak) 87.9425578 109.257181 144.209123 Semen (sak) 1.7589 2.19 2.88
Pasir (m3) 0.28141618 0.26221724 0.2307346 Pasir (m3) 0 0 0.0000
1:4 1:3 1:2 1:4 1:3 1:2
Batu Kali 1.20 1.20 1.20 1.20 1.20 1.20
Semen (kg) 178.82948 222.172352 293.246445 Semen (sak) 3.58 4.44 5.86
Pasir (m3) 0.57225434 0.53321364 0.46919431 Pasir (m3) 0 0 0.0000
100
0.0520 19.24
0.1995842 3.84
8.23E+010