You are on page 1of 182

Biro Konsultan

CV. CENDANA CONSULTANT


Muliambut Mulia
Kabupaten Puncak Jaya

PEKERJAAN : PEMBANGUNAN DAN PENGADAAN PLTMH ILU


LOKASI : DISTRIK ILU KABUPATEN PUNCAK JAYA

URAIAN PEKERJAAN JUMLAH HARGA

I PEKERJAAN PENDAHULUAN Rp 87,160,219.50


II PEKERJAAN BANGUNAN INTAKE Rp 1,362,041,058.38
III PEKERJAAN SALURAN PEMBUANG / PEMBILAS Rp 85,638,406.61
IV PEKERJAAN SALURAN PEMBAWA Rp 305,491,906.74
V PEKERJAAN BAK PENENANG DAN PENGENDAP (HEAD TANK) Rp 1,817,179,862.51
VI PEKERJAAN BETON PENYANGGA DAN BLOCK ANGKER Rp 1,436,331,900.17
VII PEKERJAAN PIPA PENSTOK Rp 3,101,740,950.69
VIII PEKERJAAN RUMAH TURBIN (POWER HOUSE) Rp 1,032,993,237.44
IX PEKERJAAN MEKANIKAL ELEKTRIKAL Rp 2,129,807,142.86
X PEKERJAAN AKHIR Rp 5,000,000.00

A. Biaya Real Cost : Rp 11,363,384,684.90


B. PPN 10 % : Rp 1,136,338,468.49
C. Total Cost : A+ B Rp 12,499,723,153.39
D Dibulatkan : Rp 12,499,723,000.00
Terbilang : Dua belas miliar empat ratus sembilan puluh sembilan juta tujuh ratus dua puluh tiga ribu rupiah,-

Mulia, Pebruari 2015


Konsultan Perencana
CV. CENDANA CONSULTANT

NATALIA ALLOBUA, S.Sos


Direktris

REKAP ILU THP I - 182


REKAP ILU THP I - 182
Biro Konsultan
CV. CENDANA CONSULTANT
Muliambut Mulia
Kabupaten Puncak Jaya

OWNER'S ESTIMATE (OE)


PEKERJAAN : PEMBANGUNAN DAN PENGADAAN PLTMH ILU
LOKASI : DISTRIK ILU KABUPATEN PUNCAK JAYA

:
Uraian Pekerjaan Analisa Volume Sat. Harga Satuan (Rp) Jumlah Harga (Rp)

I PEKERJAAN PENDAHULUAN
1 Pembuatan Gudang semen dan peralatan A.2 9.00 m2 3,244,688.83 29,202,199.50
2 Pembuatan bedeng buruh A.4 18.00 m2 3,219,890.00 57,958,020.00
Total 87,160,219.50
87,160,219.50
II PEKERJAAN INTAKE
A PEKERJAAN PERSIAPAN
1 Pengukuran dan pasang bowplank (profil melintang) A.1 16.00 M' 147,617.33 2,361,877.28
2 Pengerukan dasar sungai (excavator) sewa 1.00 hari 11,843,099.03 11,843,099.03
11,8 Sub Total 14,204,976.310
B PEKERJAAN TANAH
1 Galian Tanah Kolam Bak Intake (dengan excavator) Analisa EI - 135.41 M3 95,070.66 12,873,518.21
2 Urugan kembali B.2 16.90 M3 24,568.50 415,207.65
Sub Total 13,288,725.860
C PEKERJAAN PASANGAN BATU/BETON
1 Pek. Pondasi pas. Batu Kali camp. 1 Pc : 4 Ps C.1 22.55 M3 12,702,010.10 286,430,327.76
2 Pek. Dinding tembok pas. Batu kali camp. 1 Pc : 4 Ps C.1 23.96 M3 12,702,010.10 304,340,162.00
3 Siar mata sapi dinding tembok saluran adukan 1 Pc : 2 Ps D.3 17.22 M2 420,943.75 7,248,651.37
4 Plester dinding dalam bak camp. 1 Pc : 2 Ps D.1 46.10 M2 645,446.01 29,755,061.06
5 Pas. Batu kosong bawah lantai C.2 9.00 M3 3,749,773.50 33,747,961.50
6 Cor lantai bak intake beton 1 Pc : 2 Ps : 3 Kr E.2 6.75 M3 21,628,034.47 145,989,232.67
7 Pas. Bronjong bentuk I type D (keranjang uk. 2 x 1 x 0,5) N.1 14.00 M3 4,271,025.00 59,794,350.00
59,7 Sub Total 867,305,746.36
D PEKERJAAN BETON BERTULANG
1 Pekerjaan Sloof (60/15) beton 1 Pc : 2 Ps : 3 Kr
Pembesian Sloof E.3 266.80 Kg 80,373.62 21,443,681.82
Pas. bekesting Sloof E.5 36.20 M2 413,513.57 14,969,191.23
14,9 Pengecoran beton Sloof 1 Pc : 2 Ps : 3 Kr E.2 3.62 M3 21,628,034.47 78,293,484.78
Jumlah 1 114,706,357.83
2 Pekerjaan Kolom K1 (60/60) beton 1 Pc : 2 Ps : 3 Kr
Pembesian kolom K1 E.3 141.16 Kg 80,373.62 11,345,540.20
Pas. bekesting Kolom K1 E.6 10.57 M2 955,264.36 10,097,144.29
Pengecoran beton Kolom K1 1 Pc : 2 Ps : 3 Kr E.2 3.17 M3 21,628,034.47 68,560,869.27
Jumlah 2 90,003,553.76
3 Pekerjaan Ringbalk (60/15) beton 1 Pc : 2 Ps : 3 Kr
Pembesian Ringbalk R1 E.3 309.99 Kg 80,373.62 24,915,018.46
Pas. bekesting Ringbalk R1 E.7 5.28 M2 955,264.36 5,043,795.82
Pengecoran beton Ringbalk R1 1 Pc : 2 Ps : 3 Kr E.2 3.17 M3 21,628,034.47 68,560,869.27
Jumlah 3 98,519,683.55
Sub Total 303,229,595.140
E PEKERJAAN ACCESORIS
1 Pasang besi profil C 50.38 (10 bh x 50 cm) O.1 27.85 kg 2,871,024.75 79,958,039.29
2 Pas. Penyaring Teralis besi beton 12 mm P.1 2.00 Unit 11,951,407.14 23,902,814.28
3 Pas. Sponning Pintu Penguras P1 besi profil P.4 2.00 Unit 1,873,065.48 3,746,130.96
4 Pas. Sponning Pintu Pengontrol P2 besi profil P.5 2.00 Unit 1,491,779.21 2,983,558.42
5 Pas. Pintu Penguras P1 P.6 2.00 Unit 13,355,367.94 26,710,735.88

EE ILU THP I - 3
Uraian Pekerjaan Analisa Volume Sat. Harga Satuan (Rp) Jumlah Harga (Rp)

6 Pas. Pintu Pengontrol P2 P.6 2.00 Unit 13,355,367.94 26,710,735.88


Sub Total 164,012,014.710
Total 1,362,041,058.38

III PEKERJAAN SALURAN PEMBUANG / PEMBILAS


A PEKERJAAN PERSIAPAN
1 Pengukuran dan pasang bowplank (profil melintang) A.1 4.00 M' 147,617.33 590,469.32
Sub Total 590,469.320
B PEKERJAAN TANAH
1 Galian Tanah untuk saluran pembuang (dengan excavator) Analisa EI - 7.35 M3 95,070.66 698,769.36
2 Urugan Kembali A.2 1.84 M3 24,568.50 45,206.04
Sub Total 743,975.400

EE ILU THP I - 4
Uraian Pekerjaan Analisa Volume Sat. Harga Satuan (Rp) Jumlah Harga (Rp)

C PEKERJAAN PASANGAN BATU/BETON


1 Pas. Batu kali saluran camp. 1 Pc : 4 Ps C.1 4.59 M3 12,702,010.10 58,302,226.36
2 Plesteran dinding saluran tebal 15 mm camp. 1 Pc : 4 Ps D.2 8.19 M2 443,765.60 3,634,440.26
3 Pas. Batu kosong bawah lantai C.2 1.12 M3 3,749,773.50 4,199,746.32
4 Cor lantai saluran 1 Pc : 2 Ps : 3 Kr E.2 0.84 M3 21,628,034.47 18,167,548.95
Sub Total 84,303,961.890
Total 85,638,406.610

IV PEKERJAAN SALURAN PEMBAWA


A PEKERJAAN PERSIAPAN
1 Pengukuran dan pasang bowplank (profil melintang) A.1 4.00 M' 147,617.33 590,469.32
Sub Total 590,469.320
B PEKERJAAN TANAH
1 Galian Tanah untuk saluran pembawa (dengan excavator) Analisa EI - 18.34 M3 95,070.66 1,743,595.92
2 Urugan Kembali B.2 4.59 M3 24,568.50 112,769.42
Sub Total 1,856,365.340
C PEKERJAAN PASANGAN BATU/BETON
1 Pas. Batu kali saluran camp. 1 Pc : 4 Ps C.1 17.71 M3 12,702,010.10 224,952,598.87
2 Plesteran dinding saluran tebal 15 mm camp. 1 Pc : 2 Ps D.1 19.11 M2 645,446.01 12,334,473.25
3 Pas. Batu kosong bawah lantai C.2 3.29 M3 3,749,773.50 12,336,754.82
4 Cor lantai saluran 1 Pc : 2 Ps : 3 Kr E.2 2.47 M3 21,628,034.47 53,421,245.14
Sub Total 303,045,072.080
Total 305,491,906.740

V PEKERJAAN BAK PENENANG DAN PENGENDAP (HEAD TANK)


A PEKERJAAN PERSIAPAN
1 Pembersihan lokasi A.3 85.26 M2 20,075.00 1,711,594.50
2 Pengukuran dan Pemasangan Papan Bouwplank A.1 44.60 M' 147,617.33 6,583,732.92
Sub Total 8,295,327.420
B PEKERJAAN TANAH
1 Galian Tanah Kolam Bak Penenang (dengan excavator) Analisa EI - 186.01 M3 95,070.66 17,684,093.65
2 Urugan kembali B.2 46.50 M3 24,568.50 1,142,435.25
Sub Total 18,826,528.900
C PEKERJAAN PASANGAN BATU/BETON
1 Pek. Pondasi pas. Batu Kali camp. 1:4 C.1 30.31 M3 12,702,010.10 384,997,926.13
2 Pek. Dinding Bak Penenang Pas. Batu Kali Camp. 1:4 C.1 48.76 M3 12,702,010.10 619,350,012.48
3 Pas. Batu kosong bawah lantai bak C.2 3.51 M3 3,749,773.50 13,161,704.99
4 Cor lantai bak intake 1 Pc : 2 Ps : 3 Kr E.2 6.64 M3 21,628,034.47 143,610,148.88
5 Plester dinding bagian dalam bak penenang camp. 1 Pc : 2 Ps D.1 73.22 M2 645,446.01 47,259,556.85
6 Pas. Batu kali dinding saluran pelimpah camp. 1 Pc : 4 Ps C.1 15.29 M3 12,702,010.10 194,213,734.43
7 Plester dinding saluran pelimpah camp. 1 Pc : 4 Ps D.2 17.53 M2 443,765.60 7,779,210.97
8 Pas. Batu kosong bawah lantai saluran pelimpah C.2 1.88 M3 3,749,773.50 7,049,574.18
9 Cor lantai saluran pelimpah 1 Pc : 2 Ps : 3 Kr E.2 1.35 M 21,628,034.47 29,197,846.53
Sub Total 1,446,619,715.440
D PEKERJAAN BETON BERTULANG
1 Pekerjaan Sloof (40/20) Beton Bertulang 1 Pc : 2 Ps : 3 Kr
Pembesian Sloof E.3 240.16 Kg 80,373.62 19,302,528.58
Pasang bekesting E.5 7.25 M2 413,513.57 2,997,973.38
Pengecoran sloof E.2 2.90 M3 21,628,034.47 62,721,299.96
Jumlah 1 85,021,801.92
2 Pekerjaan Kolom (40/40) Beton Bertulang 1 Pc : 2 Ps : 3 Kr
Pembesian kolom E.3 175.74 Kg 80,373.62 14,124,859.98
Pasang bekesting E.6 15.70 M2 955,264.36 14,997,650.45
Pengecoran kolom E.2 3.14 M3 21,628,034.47 67,912,028.24
Jumlah 2 97,034,538.67
3 Pekerjaan Ringbalk (40/20) Beton Bertulang 1 Pc : 2 Ps : 3 Kr
Pembesian Ringbalk E.3 235.19 Kg 80,373.62 18,903,071.69
Pasang bekesting E.7 7.10 M2 955,264.36 6,782,376.96
Pengecoran ringbalk E.2 2.84 M3 21,628,034.47 61,423,617.89

EE ILU THP I - 5
Uraian Pekerjaan Analisa Volume Sat. Harga Satuan (Rp) Jumlah Harga (Rp)

Jumlah 3 87,109,066.54
4 Pekerjaan Plat (tebal 12 cm) Beton Bertulang 1 Pc : 2 Ps : 3 Kr
Pembesian plat beton E.4 111.82 Kg 80,373.62 8,987,378.19
Pasang bekesting E.8 5.10 M2 1,448,064.36 7,385,128.24
Pengecoran plat beton E.2 0.79 M3 21,628,034.47 17,086,147.23
Jumlah 4 33,458,653.66
Sub Total 302,624,060.790

EE ILU THP I - 6
Uraian Pekerjaan Analisa Volume Sat. Harga Satuan (Rp) Jumlah Harga (Rp)

E PEKERJAAN ACCESORIS
1 Pas. Trashrack besi beton 12 mm P.2 1.00 Unit 14,459,030.76 14,459,030.76
2 Pengadaan Pipa GIP dia 8" Harga Bahan dan upah 1.00 btg 15,525,300.00 15,525,300.00
3 Pengadaan Flange + Plat penutup pipa penguras dia 8" Harga Bahan dan upah 1.00 set 6,462,550.00 6,462,550.00
4 Pengecatan trashrack dengan meni besi K.4 43.99 M2 47,550.25 2,091,735.50
5 Pengecatan trashrack dengan cat besi K.5 43.99 M2 51,730.25 2,275,613.70
Sub Total 40,814,229.960
Total 1,817,179,862.510

VI PEKERJAAN BETON PENYANGGA DAN BLOCK ANGKER


A PEKERJAAN PERSIAPAN
1 Pengukuran dan Pemasangan Papan Bouwplank (Profil melintang A.1 18.00 m' 147,617.33 2,657,111.94
Sub Total 2,657,111.940
B PEKERJAAN TANAH
1 Galian Tanah Pondasi B.1 68.70 M3 87,037.50 5,979,476.25
2 Urugan kembali galian tanah B.2 17.17 M3 24,568.50 421,841.15
Sub Total 6,401,317.400
C PEKERJAAN PASANGAN BATU/BETON
1 Pek. Beton penyangga pas. Bt. Kali camp. 1:4 C.1 104.40 M3 12,702,010.10 1,326,089,854.44
2 Pas. Pondasi block angker pas. Bt. Kali camp. 1:4 C.1 2.10 M3 12,702,010.10 26,674,221.21
3 Pasangan batu kali Block angker C.1 1.50 M3 12,702,010.10 19,053,015.15
4 Pasang pembesian block angker E.3 33.04 Kg 80,373.62 2,655,544.40
5 Pengecoran block angker E.2 2.10 M3 21,628,034.47 45,418,872.39
Sub Total 1,419,891,507.590
D PEKERJAAN ACSESORIS
1 Pas. Klem sadel P.11 4.00 bh 1,845,490.81 7,381,963.24
Sub Total 7,381,963.240
Total 1,436,331,900.170

VII PEKERJAAN PIPA PENSTOK


A PEKERJAAN PERSIAPAN
1 Pengadaan Pipa penstok 30", tebal 4 mm pjg = 1,22 m Harga Bahan dan upah 296.00 btg 9,132,857.14 2,703,325,713.44
2 Pengadaan Expantion joint Harga Bahan dan upah 2.00 set 32,832,142.86 65,664,285.72
3 Pengadaan sambungan flange joint Harga Bahan dan upah 4.00 set 10,418,871.43 41,675,485.72
Sub Total 2,810,665,484.880
B PEKERJAAN PIPA
1 Pemasangan pipa penstok 30" (Pengelasan) P.7 140.00 ttk 1,987,220.78 278,210,909.29
2 Pemasangan expantion joint (pengelasan + baut-mur) P.8 1.00 set 4,070,831.81 4,070,831.81
3 Pemasangan sambungan flange joint (pengelasan + baut-mur) P.9 2.00 set 3,886,496.01 7,772,992.02
4 Pemasangan air valve pipa GIP 1,5" P.10 1.00 bh 1,020,732.69 1,020,732.69
5 Pengecatan Pipa Pesat (cat besi) K.5 - M 51,730.25 -
Sub Total 291,075,465.810
Total 3,101,740,950.690

VIII PEKERJAAN RUMAH TURBIN (POWER HOUSE)


A PEKERJAAN PERSIAPAN
1 Pembersihan Lokasi A.3 90.25 M 20,075.00 1,811,768.75
2 Pengukuran dan Pasang Bouwplank (Keliling) A.1 37.20 M' 147,617.33 5,491,364.68
Sub Total 7,303,133.430
B PEKERJAAN TANAH
1 Galian Tanah untuk Pondasi Rumah B.1 12.92 M 87,037.50 1,124,524.50
2 Galian tanah untuk saluran pembuangan B.1 10.32 M 87,037.50 898,227.00
3 Galian Tanah untuk Pondasi plat B.1 10.77 M 87,037.50 937,393.88
4 Urugan kembali galian tanah pondasi rumah B.2 8.50 M 24,568.50 208,832.25
5 Urugan pasir untuk peninggian lantai rumah B.4 3.49 M 2,674,815.00 9,335,104.35
6 Memadatkan urugan pasir B.3 3.49 M 64,075.00 223,621.75
Sub Total 12,727,703.730
C PEKERJAAN PASANGAN BATU/BETON
1 Pas. Batu kosong bawah pondasi C.2 3.97 M 3,749,773.50 14,886,600.80

EE ILU THP I - 7
Uraian Pekerjaan Analisa Volume Sat. Harga Satuan (Rp) Jumlah Harga (Rp)

2 Pas. Pondasi dan dinding batu kali camp. 1 Pc : 4 Ps C.1 12.22 M 12,702,010.10 155,218,563.42
3 Pas. Pondasi rabat batu kali camp. 1 Pc : 4 Ps C.1 1.39 M 12,702,010.10 17,655,794.04
4 Pas. Dinding batu batako camp. 1 Pc : 4 Ps F.1 54.67 M 1,808,030.90 98,845,049.30
5 Pek. Siar mata sapi dinding batu kali camp. 1 Pc : 2 Ps D.3 17.53 M 420,943.75 7,379,143.94
6 Plesteran dinding batako camp. 1 Pc : 4 Ps D.2 112.07 M 443,765.60 49,732,810.79
7 Pas. Pipa PVC 2" bawah lantai untuk kabel M.3 8.00 M' 356,324.33 2,850,594.64
8 Cor lantai rumah beton tumbuk 1 Pc : 3 Ps : 5 Kr tebal 10 cm E.1 4.17 M 15,292,396.09 63,769,291.70
9 Plesteran Lantai Rumah camp. 1 Pc : 2 Ps tebal 15 mm D.1 41.67 M 645,446.01 26,895,735.24
10 Acian Lantai Rumah D.4 41.67 M 206,704.14 8,613,361.51
11 Pek. Dinding blok beton pas. Bt. Kali camp. 1 Pc : 4 Ps C.1 5.97 M 12,702,010.10 75,831,000.30
12 Pek. Dinding Saluran pembuang pas. batu kali camp. 1 Pc : 4 Ps C.1 5.95 M 12,702,010.10 75,576,960.10
13 Plesteran dinding saluran pembuang camp. 1 Pc : 2 Ps D.1 25.74 M 645,446.01 16,613,780.30
14 Pas. Batu kosong bawah lantai saluran pembuang C.2 2.27 M 3,749,773.50 8,511,985.85
15 Cor lantai saluran beton 1 Pc : 3 Ps : 3 Kr E.2 1.70 M 21,628,034.47 36,767,658.60
Sub Total 659,148,330.530

EE ILU THP I - 8
Uraian Pekerjaan Analisa Volume Sat. Harga Satuan (Rp) Jumlah Harga (Rp)

D PEKERJAAN BETON BERTULANG


1 Pas. Pondasi plat tebal 30 cm beton 1 Pc : 3 Ps : 3 Kr
Pembesian pondasi plat E.3 43.41 Kg 80,373.62 3,489,018.84
Pas. Bekesting E.5 2.63 M 382,713.57 1,006,536.69
Pengecoran pondasi plat E.2 1.44 M 21,628,034.47 31,144,369.64
Jumlah 1 35,639,925.17
2 Pas. Sloof pondasi plat 30/30 beton 1 Pc : 3 Ps : 3 Kr
Pembesian sloof pondasi plat E.3 28.25 Kg 80,373.62 2,270,554.76
Pengecoran sloof pondasi plat E.2 0.27 M 21,628,034.47 5,839,569.31
Jumlah 2 8,110,124.07
3 Pas. Kolom pondasi plat 30/30 beton 1 Pc : 3 Ps : 3 Kr
Pembesian kolom pondasi plat E.3 38.80 Kg 80,373.62 3,118,496.46
Pengecoran kolom pondasi plat E.2 0.56 M 21,628,034.47 12,111,699.30
Jumlah 3 15,230,195.76
4 Pas. Dinding beton tebal 30 cm 1 Pc : 3 Ps : 3 Kr
Pembesian dinding E.3 71.91 Kg 80,373.62 5,779,667.01
Pas. Bekesting E.9 16.36 M 1,122,241.23 18,359,866.52
Pengecoran dinding E.2 2.15 M 21,628,034.47 46,500,274.11
Jumlah 4 70,639,807.64
5 Pas. Ringbalk 30/30 beton 1 Pc : 3 Ps : 3 Kr
Pembesian Ringbalk E.3 153.79 Kg 80,373.62 12,360,659.02
Pengecoran ringbalk E.2 1.47 M 21,628,034.47 31,793,210.67
Jumlah 5 44,153,869.69
6 Pek. Plat lantai beton bertulang 1 Pc : 3 Ps : 3 Kr
Pembesian plat lantai E.3 69.46 Kg 80,373.62 5,582,751.65
Pas. bekesting E.8 2.97 M 1,448,064.36 4,300,751.15
Pengecoran plat lantai E.2 1.60 M 21,628,034.47 34,604,855.15
Jumlah 6 44,488,357.95
Sub Total 218,262,280.280
E PEKERJAAN KAYU
1 Pek. Kusen Pintu dan jendela kayu 5/10 G.1 0.19 M 11,378,800.71 2,161,972.13
2 Pas. Kuda-kuda kayu 5/10 G.5 1.09 M 9,751,851.99 10,629,518.67
3 Pas. Balok gording kayu 5/10 G.6 1.06 M 8,532,354.28 9,044,295.54
4 Pas. Kolom kayu 10/10 G.2 0.39 M 10,117,650.71 3,945,883.78
5 Pas. Balok pengikat kolom kayu 5/10 G.2 0.12 M 10,117,650.71 1,214,118.09
6 Pek. Ringbalk kayu 10/10 G.2 0.38 M 10,117,650.71 3,844,707.27
7 Pek. Listplank papan 2/25 G.8 32.82 M' 137,266.64 4,505,091.12
8 Pek. Dinding Kap papan 2/10 G.9 12.70 M 429,564.14 5,455,464.58
Sub Total 40,801,051.180
F PEKERJAAN ATAP DAN PLAFON
1 Pas. Atap Seng BJLS 0.20 H.1 69.42 M 184,406.83 12,801,522.14
2 Pas. Nok atap H.2 12.60 M' 103,125.94 1,299,386.84
3 Pas. Talang Jurai atap O.5 7.80 M' 374,339.27 2,919,846.31
4 Pas. rangka plafond G.7 65.55 M 154,756.64 10,144,297.75
5 Pas. Plafond Tripleks 3 mm I.1 65.55 M 162,624.47 10,660,034.01
Sub Total 37,825,087.050
G PEKERJAAN PINTU, JENDELA DAN ALAT GANTUNG
1 Pas. Pintu Panil Papan 3,5 cm G.3 5.38 M 928,030.71 4,992,805.22
2 Pas. Jendela paneel kaca G.4 1.88 M 1,322,682.88 2,486,643.81
3 Pas. Teralis jendela besi beton dia 12 mm P.3 7.00 set 1,581,378.01 11,069,646.07
4 Pas. Kunci Pintu Royal besar J.1 3.00 Bh 458,276.10 1,374,828.30
5 Pas. Engsel Pintu J.3 6.00 Bh 86,097.98 516,587.88
6 Pas. Engsel Jendela J.4 6.00 Bh 66,033.40 396,200.40
7 Pas. Grendel Jendela J.8 3.00 Bh 87,272.03 261,816.09
8 Pas. Hak/Kait angin jendela J.5 6.00 Bh 96,657.98 579,947.88
9 Pas. Handel jendela J.6 3.00 Bh 57,977.27 173,931.81
Sub Total 21,852,407.460
H PEKERJAAN PENGECATAN
1 Pek. Pengecatan Kosen (cat minyak) K.1 7.60 M 100,380.26 762,889.98

EE ILU THP I - 9
Uraian Pekerjaan Analisa Volume Sat. Harga Satuan (Rp) Jumlah Harga (Rp)

2 Pek. Pengecatan Daun Pintu Panil (cat minyak) K.1 11.84 M 100,380.26 1,188,502.28
3 Pek. Pengecatan Daun Jendela panil kaca (cat minyak) K.1 1.29 M 100,380.26 129,490.54
4 Pek. Pengecatan teralis jendela (cat besi) K.5 2.94 M 51,730.25 152,086.94
5 Pek. Pengecatan Plafond (cat tembok) K.3 65.55 M 45,536.31 2,984,905.12
6 Pek. Pengecatan Dinding Tembok (cat minyak) K.1 129.60 M 100,380.26 13,009,281.70
7 Pek. Pengecatan balok pengikat kolom (cat minyak) K.1 3.60 M 100,380.26 361,368.94
8 Pek. Pengecatan listplank (cat minyak) K.1 6.56 M 100,380.26 658,494.51
9 Pek. Pengecatan Dinding Kap (cat minyak) K.1 12.70 M 100,380.26 1,274,829.30
10 Pek. Pengecatan tiang teras (cat minyak) K.1 1.80 M 100,380.26 180,684.47
11 Pek. Pengecatan atap (cat atap) K.2 69.42 M 53,562.14 3,718,283.76
Sub Total 24,420,817.540

EE ILU THP I - 10
Uraian Pekerjaan Analisa Volume Sat. Harga Satuan (Rp) Jumlah Harga (Rp)

I PEKERJAAN INSTALASI LISTRIK


1 Pekerjaan instalasi titik lampu dan kotak kontak L.1 11.00 ttk 539,236.61 5,931,602.71
2 Pemasangan Stop Kontak L.2 3.00 bh 80,055.99 240,167.97
3 Pemasangan Saklar Tunggal L.6 2.00 bh 74,500.99 149,001.98
4 Pemasangan Saklar Ganda L.5 2.00 bh 80,055.99 160,111.98
5 Pemasangan Lampu philips 18 w L.3 7.00 bh 221,343.84 1,549,406.88
6 Pemasangan MCB 6 A L.4 1.00 set 122,134.72 122,134.72
Sub Total 8,152,426.240
J PEKERJAAN AKHIR/FINISHING
1 Pembersihan akhir Ditafsir 1.00 Ls 2,500,000.00 2,500,000.00
Sub Total 2,500,000.000
Total 1,032,993,237.440

IX PEKERJAAN MEKANIKAL ELEKTRIKAL


1 Pengadaan Turbin Cross Flow T 15 D500 + Generator 200 KVA + Harga Bahan dan upah
Panel kontrol + Ballast Load + Grounding 1.00 Unit 2,129,807,142.86 2,129,807,142.86
2. Pemasangan Turbin, Generator, Panel kontrol, Ballast Load
dan Grounding termasuk uji coba (5% dari harga) - Pkt 106,490,357.14 -
Sub Total 2,129,807,142.860
Total 2,129,807,142.860

X PEKERJAAN AKHIR
1 Dokumentasi/Pelaporan Ditafsir 1.00 Ls 2,500,000.00 2,500,000.00
2 Pembongkaran dan pembersihan gudang dan bedeng buruh Ditafsir 1.00 Ls 2,500,000.00 2,500,000.00
Sub Total 5,000,000.000
Total 5,000,000.000

EE ILU THP I - 11
ANALISA BIAYA KONSTRUKSI (ABK)
BANGUNAN GEDUNG DAN PERUMAHAN
DISTRIK NIOGA

A. PEKERJAAN PERSIAPAN SNI 2835 - 2002


A.1 SNI 03-2835-2002 (6.4)
1M' Pengukuran dan pemasangan bouwplank (keliling)
6.4.1 Bahan :
Kayu balok 0.0120 M x Rp 5,600,000.00 = Rp 67,200.00
Kayu papan 0.0070 M x Rp 5,600,000.00 = Rp 39,200.00
Paku campur 0.0200 Kg x Rp 73,628.57 = Rp 1,472.57
A. JUMLAH HARGA BAHAN = Rp 107,872.57
6.4.2 Tenaga :
Tukang Kayu 0.1000 OH x Rp 140,000.00 = Rp 14,000.00
Pekerja 0.1000 OH x Rp 100,000.00 = Rp 10,000.00
Kepala Tukang 0.0100 OH x Rp 150,000.00 = Rp 1,500.00
Mandor 0.0050 OH x Rp 165,000.00 = Rp 825.00
B. JUMLAH UPAH = Rp 26,325.00
C. JUMLAH BAHAN DAN UPAH = Rp 134,197.57
D. Overhead + Profit (10%) = Rp 13,419.76
A.1 E. Total = Rp 147,617.33
A.2 SNI 03-2835-2002 (6.7)
1M2 Pembuatan gudang semen dan alat-alat
6.7.1 Bahan :
Kayu balok 0.0600 M x Rp 5,600,000.00 = Rp 336,000.00
Kayu papan 0.2100 M x Rp 5,600,000.00 = Rp 1,176,000.00
Paku campur 0.3000 Kg x Rp 73,628.57 = Rp 22,088.57
Semen PC 10.5000 Kg x Rp 48,028.57 = Rp 504,299.99
Pasir cor 0.0300 M x Rp 2,000,000.00 = Rp 60,000.00
Kerikil pecah 0.0500 M x Rp 2,500,000.00 = Rp 125,000.00
Seng Gelombang BJLS 20 1.5000 Lbr x Rp 205,385.71 = Rp 308,078.57
A. JUMLAH HARGA BAHAN = Rp 2,531,467.12
6.7.2 Tenaga :
Pekerja 1.0000 OH x Rp 100,000.00 = Rp 100,000.00
Tukang kayu 2.0000 OH x Rp 140,000.00 = Rp 280,000.00
Kepala Tukang 0.2000 OH x Rp 150,000.00 = Rp 30,000.00
Mandor 0.0500 OH x Rp 165,000.00 = Rp 8,250.00
B. JUMLAH UPAH = Rp 418,250.00
C. JUMLAH BAHAN DAN UPAH = Rp 2,949,717.12
D. Overhead + Profit (10%) = Rp 294,971.71
E. Total = Rp 3,244,688.83
A.3 SNI 03-2835-2002 (6.8)
1M2 Pembersihan Lapangan dan perataan
6.8.2 Tenaga :
Pekerja 0.1000 OH x Rp 100,000.00 = Rp 10,000.00
Mandor 0.0500 OH x Rp 165,000.00 = Rp 8,250.00
A. JUMLAH UPAH = Rp 18,250.00
B. Overhead + Profit (10%) = Rp 1,825.00
A.3 C. Total = Rp 20,075.00
A.4 SNI 03-2835-2002 (6.10)
1M2 Pembuatan bedeng buruh
6.10.1 Bahan :
Kayu balok 0.0600 M x Rp 5,600,000.00 = Rp 336,000.00
Kayu papan 0.2300 M x Rp 5,600,000.00 = Rp 1,288,000.00
Paku campur 0.3000 Kg x Rp 73,628.57 = Rp 22,088.57
Seng Gelombang BJLS 20 1.5000 Lbr x Rp 205,385.71 = Rp 308,078.57
Tripleks 3 mm 1.3500 Lbr x Rp 317,942.86 = Rp 429,222.86
A. JUMLAH HARGA BAHAN = Rp 2,383,390.00
6.10.2 Tenaga :
Pekerja 1.0000 OH x Rp 100,000.00 = Rp 100,000.00
Tukang kayu 2.0000 OH x Rp 140,000.00 = Rp 280,000.00
Kepala Tukang 0.2000 OH x Rp 150,000.00 = Rp 30,000.00
Mandor 0.0500 OH x Rp 165,000.00 = Rp 8,250.00
B. JUMLAH UPAH = Rp 418,250.00
C. JUMLAH BAHAN DAN UPAH = Rp 2,801,640.00
D. Overhead + Profit (10%) = Rp 280,164.00
E. Total = Rp 3,219,890.00
B. PEKERJAAN TANAH - SNI 2835 - 2008
B.1 SNI 2835 - 2008 (6.1)

EE Analisa Harga - 12
Menggali 1 m3 Tanah biasa
6.1.2 Tenaga :
Pekerja 0.7500 OH x Rp 100,000.00 = Rp 75,000.00
Mandor 0.0250 OH x Rp 165,000.00 = Rp 4,125.00
A. JUMLAH UPAH = Rp 79,125.00
B. Overhead + Profit (10%) = Rp 7,912.50
B.1 C. Total = Rp 87,037.50
B.2 SNI 2835 - 2008 (6.9)
1 M Urugan Kembali
6.9.2 Tenaga :
Pekerja 0.1920 OH x Rp 100,000.00 = Rp 19,200.00
Mandor 0.0190 OH x Rp 165,000.00 = Rp 3,135.00
A. JUMLAH UPAH = Rp 22,335.00
B. Overhead + Profit (10%) = Rp 2,233.50
B.2 C. Total = Rp 24,568.50

EE Analisa Harga - 13
B.3 SNI 2835 - 2008 (6.10)
Memadatkan 1 m3 tanah (per 20 cm)
Tenaga :
6.10.2 Pekerja 0.5000 OH x Rp 100,000.00 = Rp 50,000.00
Mandor 0.0500 OH x Rp 165,000.00 = Rp 8,250.00
A. JUMLAH UPAH = Rp 58,250.00
B. Overhead + Profit (10%) = Rp 5,825.00
B.3 C. Total = Rp 64,075.00
B.4 SNI 2835 - 2008 (6.11)
Mengurug 1 m3 pasir urug
6.11.1 Bahan :
Pasir Urug 1.2000 M x Rp 2,000,000.00 = Rp 2,400,000.00
A. JUMLAH HARGA BAHAN = Rp 2,400,000.00
6.11.2 Tenaga :
Pekerja 0.3000 OH x Rp 100,000.00 = Rp 30,000.00
Mandor 0.0100 OH x Rp 165,000.00 = Rp 1,650.00
B. JUMLAH UPAH = Rp 31,650.00
C. JUMLAH BAHAN DAN UPAH = Rp 2,431,650.00
D. Overhead + Profit (10%) = Rp 243,165.00
B.4 E. Total = Rp 2,674,815.00
B.5 SNI 2835 - 2008 (6.15)
Mengurug 1 m3 Batu Kali
6.15.1 Bahan :
Batu kali 1.2000 M x Rp 2,000,000.00 = Rp 2,400,000.00
A. JUMLAH HARGA BAHAN = Rp 2,400,000.00
6.15..2 Tenaga :
Pekerja 0.3000 OH x Rp 100,000.00 = Rp 30,000.00
Mandor 0.0100 OH x Rp 165,000.00 = Rp 1,650.00
B. JUMLAH UPAH = Rp 31,650.00
C. JUMLAH BAHAN DAN UPAH = Rp 2,431,650.00
D. Overhead + Profit (10%) = Rp 243,165.00
B.5 E. Total = Rp 2,674,815.00
C. PEKERJAAN PONDASI SNI 2836 - 2008
C.1 SNI 2836 - 2008 (6.2)
Memasang 1 M pondasi batu kali, campuran 1 Pc :4 Ps
6.2.1 Bahan :
Batu kali 1.2000 M x Rp 2,000,000.00 = Rp 2,400,000.00
Semen PC 163.0000 Kg x Rp 48,028.57 = Rp 7,828,656.91
Pasir Pasang 0.5200 M x Rp 2,000,000.00 = Rp 1,040,000.00
A. JUMLAH HARGA BAHAN = Rp 11,268,656.91
6.2.2 Tenaga :
Pekerja 1.5000 OH x Rp 100,000.00 = Rp 150,000.00
Tukang batu 0.7500 OH x Rp 140,000.00 = Rp 105,000.00
Kepala Tukang 0.0750 OH x Rp 150,000.00 = Rp 11,250.00
Mandor 0.0750 OH x Rp 165,000.00 = Rp 12,375.00
B. JUMLAH UPAH = Rp 278,625.00
C. JUMLAH BAHAN DAN UPAH = Rp 11,547,281.91
D. Overhead + Profit (10%) = Rp 1,154,728.19
C.1 E. Total = Rp 12,702,010.10
C.2 SNI 2836 - 2008 (6.9)
Memasang 1 M Batu Kosong (Aanstamping)
6.9.1 Bahan :
Batu kali 1.2000 M x Rp 2,000,000.00 = Rp 2,400,000.00
Pasir Pasang 0.4320 M x Rp 2,000,000.00 = Rp 864,000.00
A. JUMLAH HARGA BAHAN = Rp 3,264,000.00
6.9.2 Tenaga :
Pekerja 0.7800 OH x Rp 100,000.00 = Rp 78,000.00
Tukang batu 0.3900 OH x Rp 140,000.00 = Rp 54,600.00
Kepala Tukang 0.0390 OH x Rp 150,000.00 = Rp 5,850.00
Mandor 0.0390 OH x Rp 165,000.00 = Rp 6,435.00
B. JUMLAH UPAH = Rp 144,885.00
C. JUMLAH BAHAN DAN UPAH = Rp 3,408,885.00
D. Overhead + Profit (10%) = Rp 340,888.50
C.2 E. Total = Rp 3,749,773.50
D. PEKERJAAN PLESTERAN SNI 2837 - 2008
D.1 SNI 2837-2008 (6.2)
Membuat 1 m2 plesteran 1 Pc:2 Ps tebal 15 mm
6.2.1 Bahan :
Semen Pc 10.2240 Kg x Rp 48,028.57 = Rp 491,044.10
Pasir Pasang 0.0200 M x Rp 2,000,000.00 = Rp 40,000.00

EE Analisa Harga - 14
A. JUMLAH HARGA BAHAN = Rp 531,044.10
6.2.2 Tenaga :
Pekerja 0.3000 OH x Rp 100,000.00 = Rp 30,000.00
Tukang batu 0.1500 OH x Rp 140,000.00 = Rp 21,000.00
Kepala Tukang 0.0150 OH x Rp 150,000.00 = Rp 2,250.00
Mandor 0.0150 OH x Rp 165,000.00 = Rp 2,475.00
B. JUMLAH UPAH = Rp 55,725.00
C. JUMLAH BAHAN DAN UPAH = Rp 586,769.10
D. Overhead + Profit (10%) = Rp 58,676.91
D.1 E. Total = Rp 645,446.01

EE Analisa Harga - 15
D.2 SNI 2837-2008 (6.4)
Membuat 1 m2 plesteran 1 Pc:4 Ps tebal 15 mm
6.4.1 Bahan :
Semen PC 6.2400 Kg x Rp 48,028.57 = Rp 299,698.28
Pasir Pasang 0.0240 M x Rp 2,000,000.00 = Rp 48,000.00
A. JUMLAH HARGA BAHAN = Rp 347,698.28
6.4.2 Tenaga :
Pekerja 0.3000 OH x Rp 100,000.00 = Rp 30,000.00
Tukang batu 0.1500 OH x Rp 140,000.00 = Rp 21,000.00
Kepala Tukang 0.0150 OH x Rp 150,000.00 = Rp 2,250.00
Mandor 0.0150 OH x Rp 165,000.00 = Rp 2,475.00
B. JUMLAH UPAH = Rp 55,725.00
C. JUMLAH BAHAN DAN UPAH = Rp 403,423.28
D. Overhead + Profit (10%) = Rp 40,342.33
D.2 E. Total = Rp 443,765.60
D.3 SNI 2837-2008 (6.26)
MEMASANG 1 M2 FINISHING SIAR PASANGAN BATU KALI ADUKAN 1 PC : 2 PP
6.26.1 Bahan :
Semen PC 6.3400 Kg x Rp 48,028.57 = Rp 304,501.13
Pasir Pasang 0.0120 M x Rp 2,000,000.00 = Rp 24,000.00
A. JUMLAH HARGA BAHAN = Rp 328,501.13
6.26.2 Tenaga :
Pekerja 0.3000 OH x Rp 100,000.00 = Rp 30,000.00
Tukang batu 0.1400 OH x Rp 140,000.00 = Rp 19,600.00
Kepala Tukang 0.0140 OH x Rp 150,000.00 = Rp 2,100.00
Mandor 0.0150 OH x Rp 165,000.00 = Rp 2,475.00
B. JUMLAH UPAH = Rp 54,175.00
C. JUMLAH BAHAN DAN UPAH = Rp 382,676.13
D. Overhead + Profit (10%) = Rp 38,267.61
D.3 E. Total = Rp 420,943.75
D.4 SNI 2837-2008 (6.27)
MEMASANG 1 M2 ACIAN
6.27.1 Bahan :
Semen PC 3.2500 Kg x Rp 48,028.57 = Rp 156,092.85
A. JUMLAH HARGA BAHAN = Rp 156,092.85
6.27.2 Tenaga :
Pekerja 0.1500 OH x Rp 100,000.00 = Rp 15,000.00
Tukang batu 0.1000 OH x Rp 140,000.00 = Rp 14,000.00
Kepala Tukang 0.0100 OH x Rp 150,000.00 = Rp 1,500.00
Mandor 0.0080 OH x Rp 165,000.00 = Rp 1,320.00
B. JUMLAH UPAH = Rp 31,820.00
C. JUMLAH BAHAN DAN UPAH = Rp 187,912.85
D. Overhead + Profit (10%) = Rp 18,791.29
D.4 E. Total = Rp 206,704.14
E. PEKERJAAN BETON SNI 7394 - 2008
E.1 SNI 2002 . 6.1
Membuat 1 m3 beton tumbuk 1 Pc : 3 Ps : 5 Kr
6.1.1 Bahan :
Semen PC 218.0000 Kg x Rp 48,028.57 = Rp 10,470,228.26
Pasir Cor 0.5200 M x Rp 2,000,000.00 = Rp 1,040,000.00
Kerikil pecah 0.8700 M x Rp 2,500,000.00 = Rp 2,175,000.00
A. JUMLAH HARGA BAHAN = Rp 13,685,228.26
6.1.2 Tenaga :
Pekerja 1.6500 OH x Rp 100,000.00 = Rp 165,000.00
Tukang batu 0.2500 OH x Rp 140,000.00 = Rp 35,000.00
Kepala Tukang 0.0250 OH x Rp 150,000.00 = Rp 3,750.00
Mandor 0.0800 OH x Rp 165,000.00 = Rp 13,200.00
B. JUMLAH UPAH = Rp 216,950.00
C. JUMLAH BAHAN DAN UPAH = Rp 13,902,178.26
D. Overhead + Profit (10%) = Rp 1,390,217.83
E.1 E. Total = Rp 15,292,396.09
E.2 SNI 2002. 6.13
1 M3 Membuat beton bertulang, 1 Pc : 2 Ps : 3 Kr
6.13.1 Bahan
Semen PC 336.0000 Kg x Rp 48,028.57 = Rp 16,137,599.52
Pasir Cor 0.5400 M3 x Rp 2,000,000.00 = Rp 1,080,000.00
Kerikil pecah 0.8100 M3 x Rp 2,500,000.00 = Rp 2,025,000.00
A. JUMLAH HARGA BAHAN = Rp 19,242,599.52
6.13.2 Tenaga

EE Analisa Harga - 16
Pekerja 2.0000 Oh x Rp 100,000.00 = Rp 200,000.00
Tukang Batu 0.3500 Oh x Rp 140,000.00 = Rp 49,000.00
Kepala Tukang 0.0350 Oh x Rp 150,000.00 = Rp 5,250.00
Mandor 1.0000 Oh x Rp 165,000.00 = Rp 165,000.00
B. JUMLAH UPAH = Rp 419,250.00
C. JUMLAH BAHAN DAN UPAH = Rp 19,661,849.52
D. Overhead + Profit (10%) = Rp 1,966,184.95
E. Total = Rp 21,628,034.47

EE Analisa Harga - 17
E.3 PEMBESIAN 1 KG DENGAN BESI POLOS
6.17.1 Bahan :
Besi beton polos 1.0500 Kg x Rp 66,728.57 = Rp 70,065.00
Kawat ikat 0.0150 Kg x Rp 76,728.57 = Rp 1,150.93
A. JUMLAH HARGA BAHAN = Rp 71,215.93
6.17.2 Tenaga :
Pekerja 0.0070 OH x Rp 100,000.00 = Rp 700.00
Tukang besi 0.0070 OH x Rp 140,000.00 = Rp 980.00
Kepala Tukang 0.0007 OH x Rp 150,000.00 = Rp 105.00
Mandor 0.0004 OH x Rp 165,000.00 = Rp 66.00
B. JUMLAH UPAH = Rp 1,851.00
C. JUMLAH BAHAN DAN UPAH = Rp 73,066.93
D. Overhead + Profit (10%) = Rp 7,306.69
### E. Total = Rp 80,373.62
E.4 SNI 7394-2008 (6.20)
MEMASANG 1 M2 BEKESTING UNTUK PONDASI
6.20.1 Bahan :
Kayu papan 0.0400 M3 x Rp 5,600,000.00 = Rp 224,000.00
Paku campur 0.3000 Kg x Rp 73,628.57 = Rp 22,088.57
Minyak bekesting 0.1000 Ltr x Rp 52,428.57 = Rp 5,242.86
A. JUMLAH HARGA BAHAN = Rp 251,331.43
6.20.2 Tenaga :
Pekerja 0.5200 OH x Rp 100,000.00 = Rp 52,000.00
Tukang kayu 0.2600 OH x Rp 140,000.00 = Rp 36,400.00
Kepala Tukang 0.0260 OH x Rp 150,000.00 = Rp 3,900.00
Mandor 0.0260 OH x Rp 165,000.00 = Rp 4,290.00
B. JUMLAH UPAH = Rp 96,590.00
C. JUMLAH BAHAN DAN UPAH = Rp 347,921.43
D. Overhead + Profit (10%) = Rp 34,792.14
E.4 E. Total = Rp 382,713.57
E.5 SNI 7394-2008 (6.21)
MEMASANG 1 M2 BEKESTING UNTUK SLOOF
6.21.1 Bahan :
Kayu papan 0.0450 M3 x Rp 5,600,000.00 = Rp 252,000.00
Paku campur 0.3000 Kg x Rp 73,628.57 = Rp 22,088.57
Minyak Bekesting 0.1000 Ltr x Rp 52,428.57 = Rp 5,242.86
A. JUMLAH HARGA BAHAN = Rp 279,331.43
6.21.2 Tenaga :
Pekerja 0.5200 OH x Rp 100,000.00 = Rp 52,000.00
Tukang kayu 0.2600 OH x Rp 140,000.00 = Rp 36,400.00
Kepala Tukang 0.0260 OH x Rp 150,000.00 = Rp 3,900.00
Mandor 0.0260 OH x Rp 165,000.00 = Rp 4,290.00
B. JUMLAH UPAH = Rp 96,590.00
C. JUMLAH BAHAN DAN UPAH = Rp 375,921.43
D. Overhead + Profit (10%) = Rp 37,592.14
E.5 E. Total = Rp 413,513.57
E.6 SNI 7394-2008 (6.22)
MEMASANG 1 M2 BEKESTING UNTUK KOLOM
6.22.1 Bahan :
Kayu papan 0.0400 M3 x Rp 5,600,000.00 = Rp 224,000.00
Paku campur 0.4000 Kg x Rp 73,628.57 = Rp 29,451.43
Minyak Bekesting 0.2000 ltr x Rp 52,428.57 = Rp 10,485.71
Kayu balok 0.0150 M3 x Rp 5,600,000.00 = Rp 84,000.00
Tripleks 6 mm 0.3500 lbr x Rp 496,828.57 = Rp 173,890.00
Balok 5/10 panjang 3 m 2.0000 btg x Rp 112,000.00 = Rp 224,000.00
A. JUMLAH HARGA BAHAN = Rp 745,827.14
6.22.2 Tenaga :
Pekerja 0.6600 OH x Rp 100,000.00 = Rp 66,000.00
Tukang besi 0.3300 OH x Rp 140,000.00 = Rp 46,200.00
Kepala Tukang 0.0330 OH x Rp 150,000.00 = Rp 4,950.00
Mandor 0.0330 OH x Rp 165,000.00 = Rp 5,445.00
B. JUMLAH UPAH = Rp 122,595.00
C. JUMLAH BAHAN DAN UPAH = Rp 868,422.14
D. Overhead + Profit (10%) = Rp 86,842.21
E.6 E. Total = Rp 955,264.36
E.7 SNI 7394-2008 (6.23)
MEMASANG 1 M2 BEKESTING UNTUK BALOK
6.23.1 Bahan :
Kayu papan 0.0400 M3 x Rp 5,600,000.00 = Rp 224,000.00
Paku campur 0.4000 Kg x Rp 73,628.57 = Rp 29,451.43

EE Analisa Harga - 18
Minyak Bekesting 0.2000 ltr x Rp 52,428.57 = Rp 10,485.71
Kayu balok 0.0150 M3 x Rp 5,600,000.00 = Rp 84,000.00
Tripleks 6 mm 0.3500 lbr x Rp 496,828.57 = Rp 173,890.00
Balok 5/10 panjang 3 m 2.0000 btg x Rp 112,000.00 = Rp 224,000.00
A. JUMLAH HARGA BAHAN = Rp 745,827.14
6.23.2 Tenaga :
Pekerja 0.6600 OH x Rp 100,000.00 = Rp 66,000.00
Tukang besi 0.3300 OH x Rp 140,000.00 = Rp 46,200.00
Kepala Tukang 0.0330 OH x Rp 150,000.00 = Rp 4,950.00
Mandor 0.0330 OH x Rp 165,000.00 = Rp 5,445.00
B. JUMLAH UPAH = Rp 122,595.00
C. JUMLAH BAHAN DAN UPAH = Rp 868,422.14
D. Overhead + Profit (10%) = Rp 86,842.21
E.7 E. Total = Rp 955,264.36

EE Analisa Harga - 19
E.8 SNI 7394-2008 (6.24)
MEMASANG 1 M2 BEKESTING UNTUK LANTAI
6.24.1 Bahan :
Kayu papan 0.0400 M3 x Rp 5,600,000.00 = Rp 224,000.00
Paku campur 0.4000 Kg x Rp 73,628.57 = Rp 29,451.43
Minyak Bekesting 0.2000 ltr x Rp 52,428.57 = Rp 10,485.71
Kayu balok 0.0150 M3 x Rp 5,600,000.00 = Rp 84,000.00
Tripleks 6 mm 0.3500 lbr x Rp 496,828.57 = Rp 173,890.00
Balok 5/10 panjang 3 m 6.0000 btg x Rp 112,000.00 = Rp 672,000.00
A. JUMLAH HARGA BAHAN = Rp 1,193,827.14
6.24.2 Tenaga :
Pekerja 0.6600 OH x Rp 100,000.00 = Rp 66,000.00
Tukang besi 0.3300 OH x Rp 140,000.00 = Rp 46,200.00
Kepala Tukang 0.0330 OH x Rp 150,000.00 = Rp 4,950.00
Mandor 0.0330 OH x Rp 165,000.00 = Rp 5,445.00
B. JUMLAH UPAH = Rp 122,595.00
C. JUMLAH BAHAN DAN UPAH = Rp 1,316,422.14
D. Overhead + Profit (10%) = Rp 131,642.21
E.8 E. Total = Rp 1,448,064.36
E.9 SNI 7394-2008 (6.25)
MEMASANG 1 M2 BEKESTING UNTUK DINDING
6.25.1 Bahan :
Kayu papan 0.0300 M3 x Rp 5,600,000.00 = Rp 168,000.00
Paku campur 0.4000 Kg x Rp 73,628.57 = Rp 29,451.43
Minyak Bekesting 0.2000 ltr x Rp 52,428.57 = Rp 10,485.71
Kayu balok 0.0200 M3 x Rp 5,600,000.00 = Rp 112,000.00
Tripleks 6 mm 0.3500 lbr x Rp 496,828.57 = Rp 173,890.00
Balok 5/10 panjang 3 m 3.0000 btg x Rp 112,000.00 = Rp 336,000.00
Formtie/penjaga Jarak Bekisting/Spacer 4.0000 BH x Rp 16,949.29 = Rp 67,797.16
A. JUMLAH HARGA BAHAN = Rp 897,624.30
6.25.2 Tenaga :
Pekerja 0.6600 OH x Rp 100,000.00 = Rp 66,000.00
Tukang besi 0.3300 OH x Rp 140,000.00 = Rp 46,200.00
Kepala Tukang 0.0330 OH x Rp 150,000.00 = Rp 4,950.00
Mandor 0.0330 OH x Rp 165,000.00 = Rp 5,445.00
B. JUMLAH UPAH = Rp 122,595.00
C. JUMLAH BAHAN DAN UPAH = Rp 1,020,219.30
D. Overhead + Profit (10%) = Rp 102,021.93
E.9 E. Total = Rp 1,122,241.23
E.10 Permen PU No. 11/PRT/M/2013 (B.35)
MEMBONGKAR BEKESTING 1 M2 SECARA BIASA DAN MEMBERESKAN PUING-PUING
Tenaga :
Pekerja 0.0400 OH x Rp 100,000.00 = Rp 4,000.00
Mandor 0.0040 OH x Rp 165,000.00 = Rp 660.00
A. JUMLAH UPAH = Rp 4,660.00
B. Overhead + Profit (10%) = Rp 466.00
E.10 C. Total = Rp 5,126.00
F. PEKERJAAN DINDING SNI 6897 - 2008
F.1 SNI 6897 - 2008 (6.9)
MEMASANG 1 M2 DINDING BATAKO (9 X 14 X 29) CM , CAMPURAN SPESI 1 PC : 4 PP
6.9.1 Bahan :
Batu batako 22.0000 Bh x Rp 50,798.56 = Rp 1,117,568.32
Semen PC 7.9150 Kg x Rp 48,028.57 = Rp 380,146.13
Pasir Pasang 0.0250 M3 x Rp 2,000,000.00 = Rp 50,000.00
A. JUMLAH HARGA BAHAN = Rp 1,547,714.45
6.9.2 Tenaga :
Pekerja 0.6000 OH x Rp 100,000.00 = Rp 60,000.00
Tukang Batu 0.2000 OH x Rp 140,000.00 = Rp 28,000.00
Kepala Tukang 0.0200 OH x Rp 150,000.00 = Rp 3,000.00
Mandor 0.0300 OH x Rp 165,000.00 = Rp 4,950.00
B. JUMLAH UPAH = Rp 95,950.00
C. JUMLAH BAHAN DAN UPAH = Rp 1,643,664.45
D. Overhead + Profit (10%) = Rp 164,366.45
F.1 E. Total = Rp 1,808,030.90

Analisa Harga Batu Batako per buah dibuat di lokasi


Ukuran batako 9 cm x 14 cm x 29 cm
Volume batu batako 1 bh V=0,09x0,14x0,29 0.0037 m3
Jumlah batu batako 1 m3 J = 1/V 273.6727 bh

EE Analisa Harga - 20
Harga 1 m3 beton tumbuk 1:3:5 (non overhead + profit) An E.1 13,902,178.26
Harga 1 bh batako Rp=An E.1/J 50,798.56

EE Analisa Harga - 21
G. PEKERJAAN KAYU SNI 3434 - 2008
G.1 SNI 3434 - 2008 (6.2)
MEMBUAT DAN MEMASANG 1 M3 KOSEN PINTU DAN KOSEN JENDELA KAYU KELAS II DAN III
6.2.1 Bahan :
Kayu Balok 1.2000 M3 x Rp 5,600,000.00 = Rp 6,720,000.00
Paku campur 1.2500 Kg x Rp 73,628.57 = Rp 92,035.71
Lem kayu 1.0000 Kg x Rp 92,828.57 = Rp 92,828.57
A. JUMLAH HARGA BAHAN = Rp 6,904,864.28
6.2.2 Tenaga :
Pekerja 6.0000 OH x Rp 100,000.00 = Rp 600,000.00
Tukang Kayu 18.0000 OH x Rp 140,000.00 = Rp 2,520,000.00
Kepala Tukang 1.8000 OH x Rp 150,000.00 = Rp 270,000.00
Mandor 0.3000 OH x Rp 165,000.00 = Rp 49,500.00
B. JUMLAH UPAH = Rp 3,439,500.00
C. JUMLAH BAHAN DAN UPAH = Rp 10,344,364.28
D. Overhead + Profit (10%) = Rp 1,034,436.43
G.1 E. Total = Rp 11,378,800.71
G.2 SNI 3434 - 2008 (6.2b)
MEMBUAT DAN MEMASANG 1 M3 GELAGAR, KOLOM, DAN RINGBALK KAYU 10/10
6.2b.1 Bahan :
Kayu Balok 1.2000 M3 x Rp 5,600,000.00 = Rp 6,720,000.00
Paku campur 1.2500 Kg x Rp 73,628.57 = Rp 92,035.71
Lem kayu 1.0000 Kg x Rp 92,828.57 = Rp 92,828.57
A. JUMLAH HARGA BAHAN = Rp 6,904,864.28
6.2b.2 Tenaga :
Pekerja 4.0000 OH x Rp 100,000.00 = Rp 400,000.00
Tukang Kayu 12.0000 OH x Rp 140,000.00 = Rp 1,680,000.00
Kepala Tukang 1.2000 OH x Rp 150,000.00 = Rp 180,000.00
Mandor 0.2000 OH x Rp 165,000.00 = Rp 33,000.00
B. JUMLAH UPAH = Rp 2,293,000.00
C. JUMLAH BAHAN DAN UPAH = Rp 9,197,864.28
D. Overhead + Profit (10%) = Rp 919,786.43
G.2 E. Total = Rp 10,117,650.71
G.3 SNI 3434 - 2008 (6.5)
MEMBUAT DAN MEMASANG 1 M2 DAUN PINTU PANEEL KELAS I ATAU II
6.5.1 Bahan :
Kayu Papan 0.0400 M3 x Rp 5,600,000.00 = Rp 224,000.00
Lem kayu 0.5000 Kg x Rp 92,828.57 = Rp 46,414.29
A. JUMLAH HARGA BAHAN = Rp 270,414.29
6.5.2 Tenaga :
Pekerja 1.0000 OH x Rp 100,000.00 = Rp 100,000.00
Tukang Kayu 3.0000 OH x Rp 140,000.00 = Rp 420,000.00
Kepala Tukang 0.3000 OH x Rp 150,000.00 = Rp 45,000.00
Mandor 0.0500 OH x Rp 165,000.00 = Rp 8,250.00
B. JUMLAH UPAH = Rp 573,250.00
C. JUMLAH BAHAN DAN UPAH = Rp 843,664.29
D. Overhead + Profit (10%) = Rp 84,366.43
G.3 E. Total = Rp 928,030.71
G.4 SNI 3434 - 2008 (6.6)
MEMBUAT DAN MEMASANG 1 M2 PINTU DAN JENDELA KACA
6.6.1 Bahan :
Kayu Papan 0.0240 M3 x Rp 5,600,000.00 = Rp 134,400.00
Kaca bening 5 mm 0.7100 M2 x Rp 819,141.43 = Rp 581,590.42
Lem kayu 0.3000 Kg x Rp 92,828.57 = Rp 27,848.57
A. JUMLAH HARGA BAHAN = Rp 743,838.99
6.6.2 Tenaga :
Pekerja 0.8000 OH x Rp 100,000.00 = Rp 80,000.00
Tukang Kayu 2.4000 OH x Rp 140,000.00 = Rp 336,000.00
Kepala Tukang 0.2400 OH x Rp 150,000.00 = Rp 36,000.00
Mandor 0.0400 OH x Rp 165,000.00 = Rp 6,600.00
B. JUMLAH UPAH = Rp 458,600.00
C. JUMLAH BAHAN DAN UPAH = Rp 1,202,438.99
D. Overhead + Profit (10%) = Rp 120,243.90
G.4 E. Total = Rp 1,322,682.88
G.5 SNI 3434 - 2008 (6.13)
MEMASANG 1 M3 KONSTRUKSI KUDA-KUDA KONVENSIONAL
6.13.1 Bahan :
Kayu balok 1.1000 M3 x Rp 5,600,000.00 = Rp 6,160,000.00
Besi strip 15.0000 Kg x Rp = Rp -
Paku campur 5.6000 Kg x Rp 73,628.57 = Rp 412,319.99

EE Analisa Harga - 22
A. JUMLAH HARGA BAHAN = Rp 6,572,319.99
6.13.2 Tenaga :
Pekerja 4.0000 OH x Rp 100,000.00 = Rp 400,000.00
Tukang Kayu 12.0000 OH x Rp 140,000.00 = Rp 1,680,000.00
Kepala Tukang 1.2000 OH x Rp 150,000.00 = Rp 180,000.00
Mandor 0.2000 OH x Rp 165,000.00 = Rp 33,000.00
B. JUMLAH UPAH = Rp 2,293,000.00
C. JUMLAH BAHAN DAN UPAH = Rp 8,865,319.99
D. Overhead + Profit (10%) = Rp 886,532.00
G.5 E. Total = Rp 9,751,851.99

EE Analisa Harga - 23
G.6 SNI 3434 - 2008 (6.15)
MEMASANG 1 M3 KONSTRUKSI GORDING
6.15.1 Bahan :
Kayu balok 1.1000 M3 x Rp 5,600,000.00 = Rp 6,160,000.00
Besi strip tebal 5 mm *) 15.0000 Kg x Rp - = Rp -
Paku campur 3.0000 Kg x Rp 73,628.57 = Rp 220,885.71
A. JUMLAH HARGA BAHAN = Rp 6,380,885.71
6.15.2 Tenaga :
Pekerja 2.4000 OH x Rp 100,000.00 = Rp 240,000.00
Tukang Kayu 7.2000 OH x Rp 140,000.00 = Rp 1,008,000.00
Kepala Tukang 0.7200 OH x Rp 150,000.00 = Rp 108,000.00
Mandor 0.1200 OH x Rp 165,000.00 = Rp 19,800.00
B. JUMLAH UPAH = Rp 1,375,800.00
C. JUMLAH BAHAN DAN UPAH = Rp 7,756,685.71
D. Overhead + Profit (10%) = Rp 775,668.57
G.6 E. Total = Rp 8,532,354.28
G.7 SNI 3434 - 2008 (6.19)
MEMASANG 1 M2 RANGKA LANGIT-LANGIT (60 X 120 CM)
6.19.1 Bahan :
Kayu balok 0.0120 M3 x Rp 5,600,000.00 = Rp 67,200.00
Paku campur 0.1000 Kg x Rp 73,628.57 = Rp 7,362.86
A. JUMLAH HARGA BAHAN = Rp 74,562.86
6.19.2 Tenaga :
Pekerja 0.1500 OH x Rp 100,000.00 = Rp 15,000.00
Tukang Kayu 0.2500 OH x Rp 140,000.00 = Rp 35,000.00
Kepala Tukang 0.0250 OH x Rp 150,000.00 = Rp 3,750.00
Mandor 0.0750 OH x Rp 165,000.00 = Rp 12,375.00
B. JUMLAH UPAH = Rp 66,125.00
C. JUMLAH BAHAN DAN UPAH = Rp 140,687.86
D. Overhead + Profit (10%) = Rp 14,068.79
G.7 E. Total = Rp 154,756.64
G.8 SNI 3434 - 2008 (6.22)
MEMASANG 1 M' LISTPLANK UKURAN (2,5 x 30) CM KAYU KELAS I ATAU II
6.22.1 Bahan :
Kayu Papan 0.0135 M3 x Rp 5,600,000.00 = Rp 75,600.00
Paku campur 0.1000 Kg x Rp 73,628.57 = Rp 7,362.86
A. JUMLAH HARGA BAHAN = Rp 82,962.86
6.22.2 Tenaga :
Pekerja 0.1000 OH x Rp 100,000.00 = Rp 10,000.00
Tukang Kayu 0.2000 OH x Rp 140,000.00 = Rp 28,000.00
Kepala Tukang 0.0200 OH x Rp 150,000.00 = Rp 3,000.00
Mandor 0.0050 OH x Rp 165,000.00 = Rp 825.00
B. JUMLAH UPAH = Rp 41,825.00
C. JUMLAH BAHAN DAN UPAH = Rp 124,787.86
D. Overhead + Profit (10%) = Rp 12,478.79
G.8 E. Total = Rp 137,266.64
G.9 SNI 3434 - 2008 (6.26)
MEMASANG 1 M2 DINDING LAMRIZEERING DARI PAPAN
6.26.1 Bahan :
Kayu Papan 0.0070 M3 x Rp 5,600,000.00 = Rp 39,200.00
Paku campur 0.1000 Kg x Rp 73,628.57 = Rp 7,362.86
A. JUMLAH HARGA BAHAN = Rp 46,562.86
6.26.2 Tenaga :
Pekerja 0.6000 OH x Rp 100,000.00 = Rp 60,000.00
Tukang Kayu 1.8000 OH x Rp 140,000.00 = Rp 252,000.00
Kepala Tukang 0.1800 OH x Rp 150,000.00 = Rp 27,000.00
Mandor 0.0300 OH x Rp 165,000.00 = Rp 4,950.00
B. JUMLAH UPAH = Rp 343,950.00
C. JUMLAH BAHAN DAN UPAH = Rp 390,512.86
D. Overhead + Profit (10%) = Rp 39,051.29
G.9 E. Total = Rp 429,564.14
H. PEKERJAAN PENUTUP ATAP SNI 2002
H.1 SNI 2002 (6.38)
MEMASANG 1 M2 ATAP SENG GELOMBANG
6.38.1 Bahan :
Seng Gelombang BJLS 20 0.7000 Lbr x Rp 205,385.71 = Rp 143,770.00
Paku seng 0.0200 Kg x Rp 79,128.57 = Rp 1,582.57
A. JUMLAH HARGA BAHAN = Rp 145,352.57
6.38.2 Tenaga :
Pekerja 0.1200 OH x Rp 100,000.00 = Rp 12,000.00

EE Analisa Harga - 24
Tukang Kayu 0.0600 OH x Rp 140,000.00 = Rp 8,400.00
Kepala Tukang 0.0060 OH x Rp 150,000.00 = Rp 900.00
Mandor 0.0060 OH x Rp 165,000.00 = Rp 990.00
B. JUMLAH UPAH = Rp 22,290.00
C. JUMLAH BAHAN DAN UPAH = Rp 167,642.57
D. Overhead + Profit (10%) = Rp 16,764.26
H.1 E. Total = Rp 184,406.83

EE Analisa Harga - 25
H.2 SNI 2002 (6.39)
MEMASANG 1 M NOK ATAP SENG
6.39.1 Bahan :
Seng Plat BJLS 20 0.3000 Lbr x Rp 211,985.71 = Rp 63,595.71
Paku seng 0.0400 Kg x Rp 79,128.57 = Rp 3,165.14
A. JUMLAH HARGA BAHAN = Rp 66,760.86
6.39.2 Tenaga :
Pekerja 0.1500 OH x Rp 100,000.00 = Rp 15,000.00
Tukang Kayu 0.0700 OH x Rp 140,000.00 = Rp 9,800.00
Kepala Tukang 0.0080 OH x Rp 150,000.00 = Rp 1,200.00
Mandor 0.0060 OH x Rp 165,000.00 = Rp 990.00
B. JUMLAH UPAH = Rp 26,990.00
C. JUMLAH BAHAN DAN UPAH = Rp 93,750.86
D. Overhead + Profit (10%) = Rp 9,375.09
H.2 E. Total = Rp 103,125.94
I. PEKERJAAN LANGIT-LANGIT SNI 2839 - 2008
I.1 SNI 2839 - 2008 (6.5)
MEMASANG 1 M2 LANGIT-LANGIT TRIPLEKS UKURAN (120 X 240) CM, TEBAL 3 MM
6.5.1 Bahan :
Tripleks 3 mm 0.3750 Lbr x Rp 317,942.86 = Rp 119,228.57
Paku tripleks 0.0300 Kg x Rp 76,228.57 = Rp 2,286.86
A. JUMLAH HARGA BAHAN = Rp 121,515.43
6.5.2 Tenaga :
Pekerja 0.1000 OH x Rp 100,000.00 = Rp 10,000.00
Tukang Kayu 0.1000 OH x Rp 140,000.00 = Rp 14,000.00
Kepala Tukang 0.0100 OH x Rp 150,000.00 = Rp 1,500.00
Mandor 0.0050 OH x Rp 165,000.00 = Rp 825.00
B. JUMLAH UPAH = Rp 26,325.00
C. JUMLAH BAHAN DAN UPAH = Rp 147,840.43
D. Overhead + Profit (10%) = Rp 14,784.04
I.1 E. Total = Rp 162,624.47
I.2 SNI 2839 - 2008 (6.10)
MEMASANG 1 M' LIST LANGIT-LANGIT KAYU PROFIL
6.10.1 Bahan :
List Kayu Profil 1/3 cm pjg 4m 1.0500 m x Rp 19,250.00 = Rp 20,212.50
Paku tripleks 0.0100 Kg x Rp 76,228.57 = Rp 762.29
A. JUMLAH HARGA BAHAN = Rp 20,974.79
6.10.2 Tenaga :
Pekerja 0.0500 OH x Rp 100,000.00 = Rp 5,000.00
Tukang kayu 0.0500 OH x Rp 140,000.00 = Rp 7,000.00
Kepala Tukang 0.0050 OH x Rp 150,000.00 = Rp 750.00
Mandor 0.0030 OH x Rp 165,000.00 = Rp 495.00
B. JUMLAH UPAH = Rp 13,245.00
C. JUMLAH BAHAN DAN UPAH = Rp 34,219.79
D. Overhead + Profit (10%) = Rp 3,421.98
I.2 E. Total = Rp 37,641.76
J. PEKERJAAN KUNCI, ALAT GANTUNGAN DAN KACA SNI 03-3437- 2002
J.1 SNI-03-3437-2002 (6.1)
PASANG 1 BUAH KUNCI TANAM ANTIK
6.1.1 Bahan :
Kunci tanam 2 slaag (besar) 1.0000 Bh x Rp 317,119.64 = Rp 317,119.64
A. JUMLAH HARGA BAHAN = Rp 317,119.64
6.1.2 Tenaga :
Pekerja 0.0600 OH x Rp 100,000.00 = Rp 6,000.00
Tukang kayu 0.6000 OH x Rp 140,000.00 = Rp 84,000.00
Kepala tukang 0.0600 OH x Rp 150,000.00 = Rp 9,000.00
Mandor 0.0030 OH x Rp 165,000.00 = Rp 495.00
B. JUMLAH UPAH = Rp 99,495.00
C. JUMLAH BAHAN DAN UPAH = Rp 416,614.64
D. Overhead + Profit (10%) = Rp 41,661.46
J.1 E. Total = Rp 458,276.10
J.2 SNI-03-3437-2002 (6.2)
PASANG 1 BUAH KUNCI TANAM BIASA
6.2.1 Bahan :
Kunci tanam 2 slaag (kecil) 1.0000 Bh x Rp 251,866.07 = Rp 251,866.07
A. JUMLAH HARGA BAHAN = Rp 251,866.07
6.2.2 Tenaga :
Pekerja 0.0100 OH x Rp 100,000.00 = Rp 1,000.00
Tukang kayu 0.5000 OH x Rp 140,000.00 = Rp 70,000.00
Kepala tukang 0.0100 OH x Rp 150,000.00 = Rp 1,500.00

EE Analisa Harga - 26
Mandor 0.0050 OH x Rp 165,000.00 = Rp 825.00
B. JUMLAH UPAH = Rp 73,325.00
C. JUMLAH BAHAN DAN UPAH = Rp 325,191.07
D. Overhead + Profit (10%) = Rp 32,519.11
J.2 E. Total = Rp 357,710.18

EE Analisa Harga - 27
J.3 SNI-03-3437-2002 (6.5)
PASANG 1 BUAH ENGSEL PINTU
6.5.1 Bahan :
Engsel Pintu 1.0000 Bh x Rp 53,397.14 = Rp 53,397.14
A. JUMLAH HARGA BAHAN = Rp 53,397.14
6.5.2 Tenaga :
Pekerja 0.0150 OH x Rp 100,000.00 = Rp 1,500.00
Tukang kayu 0.1500 OH x Rp 140,000.00 = Rp 21,000.00
Kepala tukang 0.0150 OH x Rp 150,000.00 = Rp 2,250.00
Mandor 0.00075 OH x Rp 165,000.00 = Rp 123.75
B. JUMLAH UPAH = Rp 24,873.75
C. JUMLAH BAHAN DAN UPAH = Rp 78,270.89
D. Overhead + Profit (10%) = Rp 7,827.09
J.3 E. Total = Rp 86,097.98
J.4 SNI-03-3437-2002 (6.6)
PASANG 1 BUAH ENGSEL JENDELA
6.6.1 Bahan :
Engsel jendela 1.0000 Bh x Rp 43,447.86 = Rp 43,447.86
A. JUMLAH HARGA BAHAN = Rp 43,447.86
6.6.2 Tenaga :
Pekerja 0.0100 OH x Rp 100,000.00 = Rp 1,000.00
Tukang kayu 0.1000 OH x Rp 140,000.00 = Rp 14,000.00
Kepala tukang 0.0100 OH x Rp 150,000.00 = Rp 1,500.00
Mandor 0.0005 OH x Rp 165,000.00 = Rp 82.50
B. JUMLAH UPAH = Rp 16,582.50
C. JUMLAH BAHAN DAN UPAH = Rp 60,030.36
D. Overhead + Profit (10%) = Rp 6,003.04
J.4 E. Total = Rp 66,033.40
J.5 SNI-03-3437-2002 (6.9)
PASANG 1 BUAH KAIT ANGIN
6.9.1 Bahan :
Hak/kait angin 1.0000 Bh x Rp 62,997.14 = Rp 62,997.14
A. JUMLAH HARGA BAHAN = Rp 62,997.14
6.9.2 Tenaga :
Pekerja 0.0150 OH x Rp 100,000.00 = Rp 1,500.00
Tukang kayu 0.1500 OH x Rp 140,000.00 = Rp 21,000.00
Kepala tukang 0.0150 OH x Rp 150,000.00 = Rp 2,250.00
Mandor 0.00075 OH x Rp 165,000.00 = Rp 123.75
B. JUMLAH UPAH = Rp 24,873.75
C. JUMLAH BAHAN DAN UPAH = Rp 87,870.89
D. Overhead + Profit (10%) = Rp 8,787.09
J.5 E. Total = Rp 96,657.98
J.6 SNI-03-3437-2002 (6.9)
PASANG 1 BUAH HANDLE JENDELA
6.9.1 Bahan :
Handle jendela 1.0000 Bh x Rp 27,832.86 = Rp 27,832.86
A. JUMLAH HARGA BAHAN = Rp 27,832.86
6.9.2 Tenaga :
Pekerja 0.0150 OH x Rp 100,000.00 = Rp 1,500.00
Tukang kayu 0.1500 OH x Rp 140,000.00 = Rp 21,000.00
Kepala tukang 0.0150 OH x Rp 150,000.00 = Rp 2,250.00
Mandor 0.00075 OH x Rp 165,000.00 = Rp 123.75
B. JUMLAH UPAH = Rp 24,873.75
C. JUMLAH BAHAN DAN UPAH = Rp 52,706.61
D. Overhead + Profit (10%) = Rp 5,270.66
J.6 E. Total = Rp 57,977.27
J.7 SNI-03-3437-2002 (11)
PASANG 1 GRENDEL PINTU
6.11.1 Bahan :
Grendel pintu 1.0000 Bh x Rp 50,047.86 = Rp 50,047.86
A. JUMLAH HARGA BAHAN = Rp 50,047.86
6.11.2 Tenaga :
Pekerja 0.0200 OH x Rp 100,000.00 = Rp 2,000.00
Tukang kayu 0.2000 OH x Rp 140,000.00 = Rp 28,000.00
Kepala tukang 0.0200 OH x Rp 150,000.00 = Rp 3,000.00
Mandor 0.00100 OH x Rp 165,000.00 = Rp 165.00
B. JUMLAH UPAH = Rp 33,165.00
C. JUMLAH BAHAN DAN UPAH = Rp 83,212.86
D. Overhead + Profit (10%) = Rp 8,321.29
J.7 E. Total = Rp 91,534.15

EE Analisa Harga - 28
J.8 SNI-03-3437-2002 (11)
PASANG 1 GRENDEL JENDELA
6.11.1 Bahan :
Grendel Jendela 1.0000 Bh x Rp 46,173.21 = Rp 46,173.21
A. JUMLAH HARGA BAHAN = Rp 46,173.21
6.11.2 Tenaga :
Pekerja 0.0200 OH x Rp 100,000.00 = Rp 2,000.00
Tukang kayu 0.2000 OH x Rp 140,000.00 = Rp 28,000.00
Kepala tukang 0.0200 OH x Rp 150,000.00 = Rp 3,000.00
Mandor 0.00100 OH x Rp 165,000.00 = Rp 165.00
B. JUMLAH UPAH = Rp 33,165.00
C. JUMLAH BAHAN DAN UPAH = Rp 79,338.21
D. Overhead + Profit (10%) = Rp 7,933.82
J.8 E. Total = Rp 87,272.03

EE Analisa Harga - 29
K. PEKERJAAN PENGECATAN DAN FINISHING DINDING SNI 03-2842-2002
K.1 SNI 2842-2002 (6.8)
1 M2 PENGECATAN BIDANG KAYU BARU ( 1 lapis dempul, 1 lapis cat dasar, 2 lapis cat penutup)
6.8.1 Bahan :
Meni kayu 0.2000 Kg x Rp 81,328.57 = Rp 16,265.71
Dempul Kayu 0.1500 Kg x Rp 74,828.57 = Rp 11,224.29
Cat kayu 0.4300 Kg x Rp 126,028.57 = Rp 54,192.29
A. JUMLAH HARGA BAHAN = Rp 81,682.28
6.8.2 Tenaga :
Pekerja 0.0700 OH x Rp 100,000.00 = Rp 7,000.00
Tukang cat 0.0090 OH x Rp 140,000.00 = Rp 1,260.00
Kepala Tukang 0.0060 OH x Rp 150,000.00 = Rp 900.00
Mandor 0.0025 OH x Rp 165,000.00 = Rp 412.50
B. JUMLAH UPAH = Rp 9,572.50
C. JUMLAH BAHAN DAN UPAH = Rp 91,254.78
D. Overhead + Profit (10%) = Rp 9,125.48
K.1 E. Total = Rp 100,380.26
K.2 SNI 2842-2002 (6.13)
1 M2 PENGECATAN ATAP
6.13.1 Bahan :
Cat Atap 0.1000 Kg x Rp 140,428.57 = Rp 14,042.86
A. JUMLAH HARGA BAHAN = Rp 14,042.86
6.13.2 Tenaga :
Pekerja 0.0200 OH x Rp 100,000.00 = Rp 2,000.00
Tukang cat 0.2000 OH x Rp 140,000.00 = Rp 28,000.00
Kepala Tukang 0.0200 OH x Rp 150,000.00 = Rp 3,000.00
Mandor 0.0100 OH x Rp 165,000.00 = Rp 1,650.00
B. JUMLAH UPAH = Rp 34,650.00
C. JUMLAH BAHAN DAN UPAH = Rp 48,692.86
D. Overhead + Profit (10%) = Rp 4,869.29
K.2 E. Total = Rp 53,562.14
K.3 SNI 2842-2002 (6.14)
1 M2 PENGECATAN BIDANG TEMBOK BARU ( 1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup)
6.14.1 Bahan :
Plamur tembok 0.1000 Kg x Rp 66,728.57 = Rp 6,672.86
Cat tembok 0.3600 Kg x Rp 62,628.57 = Rp 22,546.29
A. JUMLAH HARGA BAHAN = Rp 29,219.14
6.14.2 Tenaga :
Pekerja 0.0200 OH x Rp 100,000.00 = Rp 2,000.00
Tukang cat 0.0630 OH x Rp 140,000.00 = Rp 8,820.00
Kepala Tukang 0.0063 OH x Rp 150,000.00 = Rp 945.00
Mandor 0.0025 OH x Rp 165,000.00 = Rp 412.50
B. JUMLAH UPAH = Rp 12,177.50
C. JUMLAH BAHAN DAN UPAH = Rp 41,396.64
D. Overhead + Profit (10%) = Rp 4,139.66
K.3 E. Total = Rp 45,536.31
K.4 SNI 2842-2002 (6.20.a)
1 M2 PENGECATAN PERMUKAAN BESI DENGAN MENI BESI
6.20a.1 Bahan :
Meni besi 0.1000 Kg x Rp 81,328.57 = Rp 8,132.86
Kuas biasa 0.0100 Bh x Rp 44,464.29 = Rp 444.64
A. JUMLAH HARGA BAHAN = Rp 8,577.50
6.20a.2 Tenaga :
Pekerja 0.0200 OH x Rp 100,000.00 = Rp 2,000.00
Tukang cat 0.2000 OH x Rp 140,000.00 = Rp 28,000.00
Kepala Tukang 0.0200 OH x Rp 150,000.00 = Rp 3,000.00
Mandor 0.0100 OH x Rp 165,000.00 = Rp 1,650.00
B. JUMLAH UPAH = Rp 34,650.00
C. JUMLAH BAHAN DAN UPAH = Rp 43,227.50
D. Overhead + Profit (10%) = Rp 4,322.75
K.4 E. Total = Rp 47,550.25
K.5 SNI 2842-2002 (6.20.b)
1 M2 PENGECATAN PERMUKAAN BESI DENGAN CAT BESI
6.20b.1 Bahan :
Cat besi 0.1000 Kg x Rp 119,328.57 = Rp 11,932.86
Kuas biasa 0.0100 Bh x Rp 44,464.29 = Rp 444.64
A. JUMLAH HARGA BAHAN = Rp 12,377.50
6.20b.2 Tenaga :
Pekerja 0.0200 OH x Rp 100,000.00 = Rp 2,000.00
Tukang cat 0.2000 OH x Rp 140,000.00 = Rp 28,000.00

EE Analisa Harga - 30
Kepala Tukang 0.0200 OH x Rp 150,000.00 = Rp 3,000.00
Mandor 0.0100 OH x Rp 165,000.00 = Rp 1,650.00
B. JUMLAH UPAH = Rp 34,650.00
C. JUMLAH BAHAN DAN UPAH = Rp 47,027.50
D. Overhead + Profit (10%) = Rp 4,702.75
K.5 E. Total = Rp 51,730.25

EE Analisa Harga - 31
L. ELECTRIKAL
L.1 1 TITIK PEKERJAAN INSTALASI LAMPU DAN KOTAK KONTAK
Bahan :
Kabel NYM 2 x 2,5 mm 11.0000 M' x Rp 29,258.72 = Rp 321,845.92
Perlengkapan 20% harga material 1.0000 x Rp 64,369.18 = Rp 64,369.18
A. JUMLAH HARGA BAHAN = Rp 386,215.10
Tenaga :
Pekerja 0.2000 OH x Rp 100,000.00 = Rp 20,000.00
Tukang Listrik 0.6000 OH x Rp 140,000.00 = Rp 84,000.00
B. JUMLAH UPAH = Rp 104,000.00
C. JUMLAH BAHAN DAN UPAH = Rp 490,215.10
D. Overhead + Profit (10%) = Rp 49,021.51
L.1 E. Total = Rp 539,236.61
L.2 PASANG 1 BUAH STOP KONTAK
Bahan :
Stop kontak 1.0000 Bh x Rp 55,423.93 = Rp 55,423.93
Perlengkapan 1% harga material 1.0000 x Rp 554.24 = Rp 554.24
A. JUMLAH HARGA BAHAN = Rp 55,978.17
Tenaga :
Tukang Listrik 0.1200 OH x Rp 140,000.00 = Rp 16,800.00
B. JUMLAH UPAH = Rp 16,800.00
C. JUMLAH BAHAN DAN UPAH = Rp 72,778.17
D. Overhead + Profit (10%) = Rp 7,277.82
L.2 E. Total = Rp 80,055.99
L.3 1 BUAH PEKERJAAN LAMPU SL 18 + FITTING
Bahan :
Lampu philips 18 W 1.0000 Bh x Rp 123,697.14 = Rp 123,697.14
Fitting duduk 1.0000 Bh x Rp 58,898.57 = Rp 58,898.57
Perlengkapan 1% harga material 1.0000 x Rp 1,825.96 = Rp 1,825.96
A. JUMLAH HARGA BAHAN = Rp 184,421.67
Tenaga :
Tukang Listrik 0.1200 OH x Rp 140,000.00 = Rp 16,800.00
B. JUMLAH UPAH = Rp 16,800.00
C. JUMLAH BAHAN DAN UPAH = Rp 201,221.67
D. Overhead + Profit (10%) = Rp 20,122.17
L.3 E. Total = Rp 221,343.84
L.4 PASANG 1 BH MCB BOX
Bahan :
MCB 6 A 1.0000 Set x Rp 93,298.57 = Rp 93,298.57
Perlengkapan 1% harga material 1.0000 x Rp 932.99 = Rp 932.99
A. JUMLAH HARGA BAHAN = Rp 94,231.56
Tenaga :
Tukang Listrik 0.1200 OH x Rp 140,000.00 = Rp 16,800.00
B. JUMLAH UPAH = Rp 16,800.00
C. JUMLAH BAHAN DAN UPAH = Rp 111,031.56
D. Overhead + Profit (10%) = Rp 11,103.16
L.4 E. Total = Rp 122,134.72
L.5 PASANG 1 BUAH SAKLAR GANDA
Bahan :
Saklar ganda 1.0000 Set x Rp 55,423.93 = Rp 55,423.93
Perlengkapan 1% harga material 1.0000 x Rp 554.24 = Rp 554.24
A. JUMLAH HARGA BAHAN = Rp 55,978.17
Tenaga :
Tukang Listrik 0.1200 OH x Rp 140,000.00 = Rp 16,800.00
B. JUMLAH UPAH = Rp 16,800.00
C. JUMLAH BAHAN DAN UPAH = Rp 72,778.17
D. Overhead + Profit (10%) = Rp 7,277.82
L.5 E. Total = Rp 80,055.99
L.6 PASANG 1 BUAH SAKLAR TUNGGAL
Bahan :
Saklar tunggal 1.0000 Set x Rp 50,423.93 = Rp 50,423.93
Perlengkapan 1% harga material 1.0000 x Rp 504.24 = Rp 504.24
A. JUMLAH HARGA BAHAN = Rp 50,928.17
Tenaga :
Tukang Listrik 0.1200 OH x Rp 140,000.00 = Rp 16,800.00
B. JUMLAH UPAH = Rp 16,800.00
C. JUMLAH BAHAN DAN UPAH = Rp 67,728.17
D. Overhead + Profit (10%) = Rp 6,772.82

EE Analisa Harga - 32
L.6 E. Total = Rp 74,500.99

EE Analisa Harga - 33
M. PEKERJAAN PIPA DAN SANITER RSNI T-15-2002
M.1 SNI 2002 (6.21)
PEMASANGAN 1 M' PIPA GIP 1,5"
6.21.1 Bahan :
Pipa GIP 1,5" 1.2000 m x Rp 187,750.64 = Rp 225,300.77
Perlengkapan 35% dari harga material 1.0000 x Rp 78,855.27 = Rp 78,855.27
A. JUMLAH HARGA BAHAN = Rp 304,156.04
6.21.2 Tenaga :
Pekerja 0.1080 OH x Rp 100,000.00 = Rp 10,800.00
Tukang las 0.1800 OH x Rp 140,000.00 = Rp 25,200.00
Kepala Tukang 0.0180 OH x Rp 150,000.00 = Rp 2,700.00
Mandor 0.0050 OH x Rp 165,000.00 = Rp 825.00
B. JUMLAH UPAH = Rp 39,525.00
C. JUMLAH BAHAN DAN UPAH = Rp 343,681.04
M.2 SNI 2002 ( 6.28)
MEMASANG 1 M' PIPA PVC 1,5" TIPE AW
6.28.1 Bahan
Pipa PVC 1" 1.0000 Set x Rp 94,428.57 = Rp 94,428.57
Perlengkapan 35% = Rp 33,050.00
A. JUMLAH HARGA BAHAN = Rp 127,478.57
6.28.2 Tenaga
Pekerja 0.0360 OH x Rp 100,000.00 = Rp 3,600.00
Tukang pipa 0.0600 OH x Rp 140,000.00 = Rp 8,400.00
Kepala Tukang 0.0060 OH x Rp 150,000.00 = Rp 900.00
Mandor 0.0018 OH x Rp 165,000.00 = Rp 297.00
B. JUMLAH UPAH = Rp 13,197.00
C. JUMLAH BAHAN DAN UPAH = Rp 140,675.57
D. Overhead + Profit (10%) = Rp 14,067.56
M.2 E. Total = Rp 154,743.13
M.3 SNI 2002 ( 6.29)
MEMASANG 1 M' PIPA PVC 2" TIPE AW
6.29.1 Bahan
Pipa PVC 2" 1.0000 Set x Rp 225,285.71 = Rp 225,285.71
Perlengkapan 35% = Rp 78,850.00
A. JUMLAH HARGA BAHAN = Rp 304,135.71
6.29.2 Tenaga
Pekerja 0.0540 OH x Rp 100,000.00 = Rp 5,400.00
Tukang pipa 0.0900 OH x Rp 140,000.00 = Rp 12,600.00
Kepala Tukang 0.0090 OH x Rp 150,000.00 = Rp 1,350.00
Mandor 0.0027 OH x Rp 165,000.00 = Rp 445.50
B. JUMLAH UPAH = Rp 19,795.50
C. JUMLAH BAHAN DAN UPAH = Rp 323,931.21
D. Overhead + Profit (10%) = Rp 32,393.12
M.3 E. Total = Rp 356,324.33
N. PASANGAN BROJONG SNI 03 - 0009 -1999
N.1 PASANGAN 1 M3 BRONJONG PABRIKASI BENTUK I Type D (L = 2, B = 1, T = 0,5) Kawat sisi 3,4 mm kawat pengikat 2 mm
Bahan :
Batu kali 1.4 m3 x Rp 2,000,000.00 = Rp 2,800,000.00
Kawat bronjong 3 mm 1 kotak x Rp 1,024,500.00 = Rp 1,024,500.00
A. JUMLAH HARGA BAHAN = Rp 3,824,500.00
Tenaga :
Pekerja 0.5 OH x Rp 100,000.00 = Rp 50,000.00
Mandor 0.05 OH x Rp 165,000.00 = Rp 8,250.00
B. JUMLAH UPAH = Rp 58,250.00
C. JUMLAH BAHAN DAN UPAH = Rp 3,882,750.00
D. Overhead + Profit (10%) = Rp 388,275.00
N.1 E. Total = Rp 4,271,025.00

EE Analisa Harga - 34
O. PEKERJAAN BESI DAN ALUMINIUM SNI 7393 - 2008
O.1 SNI 7393 - 2008 (6.1)
MEMASANG 1 KG BESI PROFIL
6.1.1 Bahan :
Besi profil C. 50. 38 mm panjang 6 m (33,42 Kg) 1.1500 Kg x Rp 2,255,850.00 = Rp 2,594,227.50
A. JUMLAH HARGA BAHAN = Rp 2,594,227.50
6.1.2 Tenaga :
Pekerja 0.0600 OH x Rp 100,000.00 = Rp 6,000.00
Tukang besi 0.0600 OH x Rp 140,000.00 = Rp 8,400.00
Kepala Tukang 0.0060 OH x Rp 150,000.00 = Rp 900.00
Mandor 0.0030 OH x Rp 165,000.00 = Rp 495.00
B. JUMLAH UPAH = Rp 15,795.00
C. JUMLAH BAHAN DAN UPAH = Rp 2,610,022.50
D. Overhead + Profit (10%) = Rp 261,002.25
O.1 E. Total = Rp 2,871,024.75
O.2 SNI 7393 - 2008 (6.3)
MENGERJAKAN 100 KG PERAKITAN
6.3.1 Bahan :
Solar 1.0000 Ltr x Rp 55,128.57 = Rp 55,128.57
Minyak pelumas 0.1000 Ltr x Rp 77,428.57 = Rp 7,742.86
A. JUMLAH HARGA BAHAN = Rp 62,871.43
6.3.2 Tenaga :
Pekerja 0.1000 OH x Rp 100,000.00 = Rp 10,000.00
Tukang Las 0.1000 OH x Rp 140,000.00 = Rp 14,000.00
Kepala Tukang 0.0010 OH x Rp 150,000.00 = Rp 150.00
Mandor 0.0050 OH x Rp 165,000.00 = Rp 825.00
B. JUMLAH UPAH = Rp 24,975.00
6.4.3 Peralatan :
sewa genset 0.8000 Jam x Rp 115,000.00 = Rp 92,000.00
C. JUMLAH ALAT = Rp 92,000.00
D. JUMLAH BAHAN, UPAH, DAN ALAT = Rp 179,846.43
E. Total harga untuk 1 kg = Rp 1,798.46

O.3 SNI 7393 - 2008 (6.4)


MEMBUAT 1 M2 PINTU PLAT BAJA TEBAL 2 MM RANGKAP, RANGKA BAJA SIKU
6.4.1 Bahan :
Besi Siku 30.30.3 mm panjang 6 m (8,16 kg) 15.0000 Kg x Rp 73,562.94 = Rp 1,103,444.17
Besi plat 2 mm 32.8000 Kg x Rp 74,133.15 = Rp 2,431,567.28
Kawat las 0.0500 Kg x Rp 95,148.57 = Rp 4,757.43
A. JUMLAH HARGA BAHAN = Rp 3,539,768.88
6.4.2 Tenaga :
Pekerja 1.0500 OH x Rp 100,000.00 = Rp 105,000.00
Tukang Las 1.0500 OH x Rp 140,000.00 = Rp 147,000.00
Kepala Tukang 0.1050 OH x Rp 150,000.00 = Rp 15,750.00
Mandor 0.0520 OH x Rp 165,000.00 = Rp 8,580.00
B. JUMLAH UPAH = Rp 276,330.00
6.4.3 Peralatan :
sewa genset 0.1700 Jam x Rp 115,000.00 = Rp 19,550.00
C. JUMLAH ALAT = Rp 19,550.00
D. JUMLAH BAHAN, UPAH, DAN ALAT = Rp 3,835,648.88
O.4 SNI 7393 - 2008 (6.5)
MENGERJAKAN 10 CM PENGELASAN DENGAN LAS LISTRIK
6.5.1 Bahan :
Kawat las 0.4000 Kg x Rp 95,148.57 = Rp 38,059.43
Solar 0.3000 Ltr x Rp 11,025.71 = Rp 3,307.71
Minyak pelumas 0.0400 Ltr x Rp 15,485.71 = Rp 619.43
A. JUMLAH HARGA BAHAN = Rp 41,986.57
6.5.2 Tenaga :
Pekerja 0.0400 OH x Rp 100,000.00 = Rp 4,000.00
Tukang Las 0.0200 OH x Rp 140,000.00 = Rp 2,800.00
Kepala Tukang 0.0020 OH x Rp 150,000.00 = Rp 300.00
Mandor 0.0020 OH x Rp 165,000.00 = Rp 330.00
B. JUMLAH UPAH = Rp 7,430.00
6.5.3 Peralatan :
sewa genset 0.1700 Jam x Rp 115,000.00 = Rp 19,550.00
C. JUMLAH ALAT = Rp 19,550.00
D. JUMLAH BAHAN, UPAH, DAN ALAT = Rp 68,966.57
O.4 E. Total harga untuk 1 cm = Rp 6,896.66
O.5 SNI 7393 - 2008 (6.18)
MEMASANG 1 M TALANG DATAR/JURAI SENG BJLS 0.25 LEBAR 45 CM

EE Analisa Harga - 35
6.18.1 Bahan :
Seng Plat BJLS 20 1.0500 M x Rp 211,985.71 = Rp 222,585.00
Paku Tripleks 0.0150 Kg x Rp 76,228.57 = Rp 1,143.43
Kayu papan 0.0096 M3 x Rp 5,600,000.00 = Rp 53,760.00
A. JUMLAH HARGA BAHAN = Rp 277,488.42
6.18.2 Tenaga :
Pekerja 0.1500 OH x Rp 100,000.00 = Rp 15,000.00
Tukang Kayu 0.3000 OH x Rp 140,000.00 = Rp 42,000.00
Kepala Tukang 0.0300 OH x Rp 150,000.00 = Rp 4,500.00
Mandor 0.0080 OH x Rp 165,000.00 = Rp 1,320.00
B. JUMLAH UPAH = Rp 62,820.00
C. JUMLAH BAHAN DAN UPAH = Rp 340,308.42
D. Overhead + Profit (10%) = Rp 34,030.84
O.5 E. Total = Rp 374,339.27

EE Analisa Harga - 36
P. ANALISA GABUNGAN
P.1 PASANG 1 BUAH SARINGAN TERALIS BESI BETON
Bahan :
Besi Profil L 50.50.5 mm 33.18 Kg x Rp 58,711.28 = Rp 1,948,040.42
Besi beton dia 12 mm 58.57 Kg x Rp 66,728.57 = Rp 3,908,292.34
O.2 Pekerjaan perakitan 91.75 Kg x Rp 1,798.46 = Rp 165,009.10
O.4 Pengelasan teralis besi dan besi siku 660 cm x Rp 6,896.66 = Rp 4,551,793.72
A. JUMLAH HARGA BAHAN = Rp 10,573,135.58
Tenaga :
Pekerja 1.2000 OH x Rp 100,000.00 = Rp 120,000.00
Tukang Las 1.2000 OH x Rp 140,000.00 = Rp 168,000.00
Kepala Tukang 0.0120 OH x Rp 150,000.00 = Rp 1,800.00
Mandor 0.0120 OH x Rp 165,000.00 = Rp 1,980.00
B. JUMLAH UPAH = Rp 291,780.00
C. JUMLAH BAHAN DAN UPAH = Rp 10,864,915.58
D. Overhead + Profit (10%) = Rp 1,086,491.56
E. Total = Rp 11,951,407.14
P.2 PASANG 1 BUAH TRASHRACK BESI BETON
Bahan :
Besi siku 50.50.5 mm 42.83 Kg x Rp 58,711.28 = Rp 2,514,604.31
Besi beton dia. 12 mm 102.26 Kg x Rp 66,728.57 = Rp 6,823,663.57
O.2 Pekerjaan perakitan 145.09 Kg x Rp 1,798.46 = Rp 260,939.18
O.4 Pengelasan teralis besi dan besi siku 470 cm x Rp 6,896.66 = Rp 3,241,428.86
A. JUMLAH HARGA BAHAN = Rp 12,840,635.92

Pekerja 1.2500 OH x Rp 100,000.00 = Rp 125,000.00


Tukang Las 1.2500 OH x Rp 140,000.00 = Rp 175,000.00
Kepala Tukang 0.0125 OH x Rp 150,000.00 = Rp 1,875.00
Mandor 0.0125 OH x Rp 165,000.00 = Rp 2,062.50
B. JUMLAH UPAH = Rp 303,937.50
C. JUMLAH BAHAN DAN UPAH = Rp 13,144,573.42
D. Overhead + Profit (10%) = Rp 1,314,457.34
E. Total = Rp 14,459,030.76
P.3 PASANG 1 SET TERALIS JENDELA BESI BETON
Bahan :
Besi Strip 20.2 mm 1.06 Kg x Rp 73,808.08 = Rp 78,236.57
Besi beton dia. 12 mm 7.58 Kg x Rp 66,728.57 = Rp 505,802.56
O.2 Pekerjaan perakitan 8.64 Kg x Rp 1,798.46 = Rp 15,538.73
O.4 Pengelasan teralis besi dan besi strip 100.36 cm x Rp 6,896.66 = Rp 692,148.51
A. JUMLAH HARGA BAHAN = Rp 1,291,726.37
Tenaga :
Pekerja 0.6000 OH x Rp 100,000.00 = Rp 60,000.00
Tukang besi 0.6000 OH x Rp 140,000.00 = Rp 84,000.00
Kepala Tukang 0.0060 OH x Rp 150,000.00 = Rp 900.00
Mandor 0.0060 OH x Rp 165,000.00 = Rp 990.00
B. JUMLAH UPAH = Rp 145,890.00
C. JUMLAH BAHAN DAN UPAH = Rp 1,437,616.37
D. Overhead + Profit (10%) = Rp 143,761.64
E. Total = Rp 1,581,378.01
P.4 PASANG 1 UNIT SPONING PINTU AIR P1 DARI BESI PROFIL
Bahan :
Besi Profil C 65.42 mm 17.725 Kg x Rp 67,465.91 = Rp 1,195,833.33
Besi angker dia. 12 mm panjang 25 cm 8 bh 1.77 Kg x Rp 66,728.57 = Rp 118,109.57
O.2 Pekerjaan perakitan 19.495 Kg x Rp 1,798.46 = Rp 35,061.06
O.4 Pengelasan angker besi 30.144 cm x Rp 6,896.66 = Rp 207,892.83
A. JUMLAH HARGA BAHAN = Rp 1,556,896.80
Tenaga :
Pekerja 0.6000 OH x Rp 100,000.00 = Rp 60,000.00
Tukang besi 0.6000 OH x Rp 140,000.00 = Rp 84,000.00
Kepala Tukang 0.0060 OH x Rp 150,000.00 = Rp 900.00
Mandor 0.0060 OH x Rp 165,000.00 = Rp 990.00
B. JUMLAH UPAH = Rp 145,890.00
C. JUMLAH BAHAN DAN UPAH = Rp 1,702,786.80
D. Overhead + Profit (10%) = Rp 170,278.68
E. Total = Rp 1,873,065.48
P.5 PASANG 1 UNIT SPONING PINTU AIR P2 DARI BESI PROFIL
Bahan :
Besi Profil C 65.42 mm 13.471 Kg x Rp 67,465.91 = Rp 908,833.33
Besi angker dia. 12 mm panjang 25 cm 8 bh 1.77 Kg x Rp 66,728.57 = Rp 118,109.57
O.2 Pekerjaan perakitan 15.241 Kg x Rp 1,798.46 = Rp 27,410.39

EE Analisa Harga - 37
O.4 Pengelasan angker besi 22.608 cm x Rp 6,896.66 = Rp 155,919.62
A. JUMLAH HARGA BAHAN = Rp 1,210,272.92
Tenaga :
Pekerja 0.6000 OH x Rp 100,000.00 = Rp 60,000.00
Tukang besi 0.6000 OH x Rp 140,000.00 = Rp 84,000.00
Kepala Tukang 0.0060 OH x Rp 150,000.00 = Rp 900.00
Mandor 0.0060 OH x Rp 165,000.00 = Rp 990.00
B. JUMLAH UPAH = Rp 145,890.00
C. JUMLAH BAHAN DAN UPAH = Rp 1,356,162.92
D. Overhead + Profit (10%) = Rp 135,616.29
E. Total = Rp 1,491,779.21

EE Analisa Harga - 38
P.6 PASANG 1 BUAH PINTU AIR P1 dan P2 (121/60)
Bahan :
Besi Profil C 80.45 mm panjang 5.32 m 45.91 Kg x Rp 67,500.00 = Rp 3,098,925.00
Stang pintu air drag + mur 1 set x Rp 5,538,457.14 = Rp 5,538,457.14
O.3 Pintu air plat baja (rangkap), rangka baja siku 0.726 m2 x Rp 3,835,648.88 = Rp 2,784,681.09
O.2 Pekerjaan perakitan 45.91 Kg x Rp 1,798.46 = Rp 82,567.49
O.4 Pengelasan stang pintu dan besi profil 50 cm x Rp 6,896.66 = Rp 344,832.86
A. JUMLAH HARGA BAHAN = Rp 11,849,463.58
Tenaga :
Pekerja 1.2000 OH x Rp 100,000.00 = Rp 120,000.00
Tukang besi 1.2000 OH x Rp 140,000.00 = Rp 168,000.00
Kepala Tukang 0.0120 OH x Rp 150,000.00 = Rp 1,800.00
Mandor 0.0120 OH x Rp 165,000.00 = Rp 1,980.00
B. JUMLAH UPAH = Rp 291,780.00
C. JUMLAH BAHAN DAN UPAH = Rp 12,141,243.58
D. Overhead + Profit (10%) = Rp 1,214,124.36
E. Total = Rp 13,355,367.94
P.7 PENYAMBUNGAN 1 TITIK PIPA PENSTOK DENGAN PENGELASAN (berat 1 btg pipa 93,47 kg)
Bahan :
O.4 Pengelasan pipa 244 cm x Rp 6,896.66 = Rp 1,682,784.35
A. JUMLAH HARGA BAHAN = Rp 1,682,784.35
Tenaga :
Pekerja 1.2000 OH x Rp 100,000.00 = Rp 120,000.00
Kepala Tukang 0.0120 OH x Rp 150,000.00 = Rp 1,800.00
Mandor 0.0120 OH x Rp 165,000.00 = Rp 1,980.00
B. JUMLAH UPAH = Rp 123,780.00
C. JUMLAH BAHAN DAN UPAH = Rp 1,806,564.35
D. Overhead + Profit (10%) = Rp 180,656.43
E. Total = Rp 1,987,220.78
P.8 MEMASANG 1 SET EKSPANTION JOINT
Bahan :
O.4 Pengelasan ekspantion joint 488 cm x Rp 6,896.66 = Rp 3,365,568.69
A. JUMLAH HARGA BAHAN = Rp 3,365,568.69
Tenaga :
Pekerja 1.2500 OH x Rp 100,000.00 = Rp 125,000.00
Mekanik 1.2500 OH x Rp 165,000.00 = Rp 206,250.00
Kepala Tukang 0.0125 OH x Rp 150,000.00 = Rp 1,875.00
Mandor 0.0125 OH x Rp 165,000.00 = Rp 2,062.50
B. JUMLAH UPAH = Rp 335,187.50
C. JUMLAH BAHAN DAN UPAH = Rp 3,700,756.19
D. Overhead + Profit (10%) = Rp 370,075.62
E. Total = Rp 4,070,831.81
P.9 MEMASANG 1 SET FLANGE JOINT
Bahan :
O.4 Pengelasan flange joint 488 cm x Rp 6,896.66 = Rp 3,365,568.69
A. JUMLAH HARGA BAHAN = Rp 3,365,568.69
Tenaga :
Pekerja 0.6250 OH x Rp 100,000.00 = Rp 62,500.00
Mekanik 0.6250 OH x Rp 165,000.00 = Rp 103,125.00
Kepala Tukang 0.0063 OH x Rp 150,000.00 = Rp 945.00
Mandor 0.0063 OH x Rp 165,000.00 = Rp 1,039.50
P.9 B. JUMLAH UPAH = Rp 167,609.50
C. JUMLAH BAHAN DAN UPAH = Rp 3,533,178.19
D. Overhead + Profit (10%) = Rp 353,317.82
E. Total = Rp 3,886,496.01
P.10 PEMASANGAN 1 BH AIR VALVE PIPA GIP 1,5"
Bahan :
M.1 Pemasangan Pipa GIP 1,5" 2.0000 m x Rp 343,681.04 = Rp 687,362.08
O.4 Pengelasan 59.82 cm x Rp 6,896.66 = Rp 240,576.73
A. JUMLAH HARGA BAHAN = Rp 927,938.81
D. Overhead + Profit (10%) = Rp 92,793.88
E. Total = Rp 1,020,732.69
P.11 SNI 7393 - 2008 (6.1)
MEMASANG 1 BH KLEM SADEL BESI STRIP 50.5 MM
Bahan :
Besi strip 50.5 mm panjang 6 m (11,78 kg) 4.2300 Kg x Rp 371,838.13 = Rp 1,572,875.31
baut mur 1/2" 4.0000 bh x Rp 9,506.53 = Rp 38,026.11
A. JUMLAH HARGA BAHAN = Rp 1,610,901.42
Tenaga :
Pekerja 0.2538 OH x Rp 100,000.00 = Rp 25,380.00

EE Analisa Harga - 39
Tukang besi 0.2538 OH x Rp 140,000.00 = Rp 35,532.00
Kepala Tukang 0.0254 OH x Rp 150,000.00 = Rp 3,810.00
Mandor 0.0127 OH x Rp 165,000.00 = Rp 2,095.50
B. JUMLAH UPAH = Rp 66,817.50
C. JUMLAH BAHAN DAN UPAH = Rp 1,677,718.92
D. Overhead + Profit (10%) = Rp 167,771.89
P.11 E. Total = Rp 1,845,490.81

EE Analisa Harga - 40
Biro Konsultan
CV. CENDANA CONSULTANT
Muliambut Mulia
Kabupaten Puncak Jaya

HARGA SATUAN BAHAN DAN UPAH


DISTRIK ILU

NO BAHAN/UPAH TENAGA KERJA KODE Satuan Harga Satuan Keterangan

1 2 3 4 5 6
I MATERIAL NON LOKAL
1 Semen PC Kg 48,028.57
2 Tripleks 3 mm Lbr 317,942.86
3 Tripleks 6 mm Lbr 496,828.57
4 Seng Gelombang BJLS 20 Lbr 205,385.71
5 Seng Plat BJLS 20 Lbr 211,985.71
6 Besi beton polos Kg 66,728.57
7 Besi siku 50.50.5 mm panjang 6 m (22,62 kg) Btg 1,406,037.86 1 m = 3,77 kg
8 Besi Siku 30.30.3 mm panjang 6 m (8,16 kg) Btg 600,273.63 1 m = 1,36 kg
9 Besi strip 50.5 mm panjang 6 m (11,78 kg) Btg 691,618.93 1 m = 1,96 kg
10 Besi strip 20.2 mm panjang 6 m (1,86 kg) Btg 137,283.03 1 m = 0,31 kg
11 baut mur 1/2" Bh 17,682.14
12 Paku seng Kg 79,128.57
13 Paku campur Kg 73,628.57
14 Paku Tripleks Kg 76,228.57
15 Kawat ikat Kg 76,728.57
16 Kawat las dos 475,742.86 1 dos = 5 kg
16 Kaca bening 5 mm m2 819,141.43
17 Kaca riben 5 mm m2 833,941.43
18 Kunci Tanam 2 slaag (besar) bh 317,119.64
19 Kunci Tanam 2 slaag (kecil) bh 251,866.07
20 Engsel pintu bh 53,397.14
21 Engsel Jendela bh 43,447.86
22 Grendel Pintu bh 50,047.86
23 Grendel Jendela bh 46,173.21
24 Hak/Kait Angin bh 62,997.14
25 Handle jendela bh 27,832.86
26 Meni kayu kg 81,328.57
27 Meni besi Kg 81,328.57
28 Cat tembok Kg 62,628.57
29 Cat kayu Kg 126,028.57
30 Cat besi Kg 119,328.57
31 Cat Aluminium Kg 126,028.57
32 Cat Atap Kg 140,428.57
33 Dempul kayu Kg 74,828.57
34 Plamur tembok Kg 66,728.57
35 Formtie bh 16,949.29
36 Lem kayu Kg 92,828.57
37 Lem PVC Tube 13,932.86
38 Kuas biasa bh 44,464.29
39 Kuas roll bh 59,346.43
40 Kabel NYM 2 x 1,5 mm roll 1,243,792.86
41 Kabel NYM 2 x 2,5 mm roll 1,462,936.00
42 Kabel NYM 3 x 2,5 mm roll 1,594,299.43
43 Lampu philips 14W bh 108,697.14
44 Lampu philips 18 W bh 123,697.14
45 Stop kontak bh 55,423.93
46 Saklar tunggal bh 50,423.93
47 Saklar ganda bh 55,423.93

Harga Satuan Bahan dan Upah Kerja - 41


NO BAHAN/UPAH TENAGA KERJA KODE Satuan Harga Satuan Keterangan

1 2 3 4 5 6
48 Fitting duduk bh 58,898.57
49 MCB 6 A bh 93,298.57
50 Pipa PVC 1" btg 94,428.57
51 Pipa PVC 2" btg 225,285.71
52 Pipa GIP 1,5" btg 1,126,503.86
53 Sekring Box bh 109,746.43
54 Kawat Bronjong 3 mm kotak 1,024,500.00
55 Solar Ltr 55,128.57
56 Minyak pelumas Ltr 77,428.57
57 Minyak Bekesting Ltr 52,428.57
58 Besi plat 2 mm Lbr 3,352,300.99 1 lbr = 46,74 kg
59 Besi plat 3 mm Lbr 5,028,401.50 1 lbr = 70,10 kg
60 Batu batako bh 50,798.56
61 Pengadaan Pipa GIP dia 8" btg 15,525,300.00

Harga Satuan Bahan dan Upah Kerja - 42


NO BAHAN/UPAH TENAGA KERJA KODE Satuan Harga Satuan Keterangan

1 2 3 4 5 6
62 Pengadaan Flange + Plat penutup pipa penguras dia 8" set 6,462,550.00
63 Pengadaan Turbin Cross Flow T 15 kapasitas 200 KVA: Unit 2,129,807,142.86
64 Pengadaan Turbin Cross Flow T 15 kapasitas 175 KVA: Unit 1,919,142,857.14
65 Pengadaan Pipa besi dia 30", pjg=1,2 m, tebal = 4 mm Btg 9,132,857.14 1 btg = 93,47 kg
66 Expansion Joint 77,64 cm set 32,832,142.86 1 Set = 125 kg
67 Sambungan pipa (flange + baut + paking karet) dia 77,64 cm psg 10,418,871.43 1 Set = 57,5 kg
68 Besi profil C. 50. 38 mm panjang 6 m (33,42 Kg) Btg 2,255,850.00 1 m = 5,57 kg
69 Besi profil C 65.42 mm panjang 6 m (42,54 kg) Btg 2,870,000.00 1 m = 7,09 kg
70 Besi profil C 80.45 mm panjang 6 m (51,78 kg) Btg 3,495,150.00 1 m = 8,63 kg
71 Stang pintu air drag + mur set 5,538,457.14
72 Kabel Twisted 3x35 + 1x25 mm2 mtr 103,094.29
73 Kabel Twisted 2 x 10 mm2 mtr 42,430.00
74 Tiang listrik 9 meter 150 daN btg 15,729,000.00
75 Lampu Jalan LED 70 Watt unit 5,139,750.00
76 Pengadaan dan pemasangan trafo step up 80 kVA Unit 186,000,000.00
77 Stang lampu jalan + clem stang lampu bh 914,928.57
78 Sensor lampu 6 A bh 89,265.71
79 Strain Wedge Clamp (service Klem /wik besar) bh 115,564.29
80 Service klem / wik kecil bh 75,298.57
81 Kaitan Kabel Twiested bh 80,597.14
82 Suspension Clamp with Chain Link (Gantungan kabel) set 75,431.43
83 Stainless steel strip 20 x 0,7 mm2 (pita pengikat) roll 1,155,742.86
84 Stainless steel strip 20 x 0,7 mm2 (pita pengikat) bh 48,155.95
85 Stoping buckle Stainless steel (pengikat pita baja) bh 9,000.00
86 Tap Connector 35-070/35-70 mm2 bh 100,298.57
87 Tap Konektor Distribusi 1 Baut bh 45,165.71
88 Tension Bracket (Penarik) bh 75,564.29
89 Galvanis steel wire 1/4" mtr 29,922.07
90 Klem Sling 1/4" bh 16,961.04
91 Spancroef 1/4" bh 36,222.07
92 Limit 2 A bh 75,298.57
93 Limit 4 A bh 85,298.57
94 Limit 6 A bh 93,298.57
95 Limit 10 A bh 100,298.57
96 MCB Box bh 91,265.71
97 Kawat BC 50 mm2 mtr 140,000.00
98 Cable schoen 50 mm CU mtr 78,400.00
II MATERIAL LOKAL
1 Batu kali M3 2,000,000.00
2 Pasir pasang M3 2,000,000.00
3 Pasir Cor M3 2,000,000.00
4 Pasir Beton M3 2,000,000.00
5 Pasir Urug M3 2,000,000.00
6 Kerikil pecah M3 2,500,000.00
7 Timbunan biasa M3 550,000.00
8 Kayu balok M3 5,600,000.00
9 Kayu Papan btg 5,600,000.00
10 Kayu cina M3 8,350,000.00
11 Balok 5/10 panjang 3 m M3 112,000.00
12 Papan les 1/4 Btg 7,700.00
13 List Kayu Profil 1/3 cm pjg 4m m' 19,250.00
III UPAH TENAGA KERJA
1 Pekerja L01 OH 100,000.00
2 Tukang Batu L02 OH 140,000.00
3 Tukang Kayu L02 OH 140,000.00
4 Tukang Besi L02 OH 140,000.00
5 Tukang Cat L02 OH 140,000.00
6 Tukang Listrik L02 OH 140,000.00
7 Tukang Las L02 OH 140,000.00

Harga Satuan Bahan dan Upah Kerja - 43


NO BAHAN/UPAH TENAGA KERJA KODE Satuan Harga Satuan Keterangan

1 2 3 4 5 6
8 Tukang pipa L02 OH 140,000.00
9 Kepala Tukang L03 OH 150,000.00
10 Mandor L04 OH 165,000.00
11 Juru ukur L05 OH 140,000.00
12 Pembantu Juru ukur L06 OH 140,000.00
13 Pembantu Mekanik L07b OH 140,000.00
14 Mekanik L07 OH 165,000.00
15 Operator L08 OH 165,000.00
16 Pembantu Operator L09 OH 115,000.00
IV PERALATAN/ANGKUTAN
1 Sewa Excavator Hari 11,843,099.03
2 Sewa Excavator jam 1,691,871.29
3 Sewa Genset jam 115,000.00
4 Biaya angkutan lokasi kg 500.00

Harga Satuan Bahan dan Upah Kerja - 44


I PEKERJAAN PENDAHULUAN
1 Pembuatan Gudang semen dan peralatan panjang lebar
3m 3m
2 Pembuatan bedeng buruh 6m 4m

PEKERJAAN INTAKE
PEKERJAAN PERSIAPAN
1 Pengukuran dan pasang bowplank (profil melintang) Panjang bowplank = P
Jumlah patok bowplank = J
Panjang seluruh bowplank = PxJ
B PEKERJAAN TANAH
1 Galian Tanah Kolam Bak Intake (dengan excavator) Luas galian tanah = L
dalam galian rata-rata = d
volume galian = Lxd

2 Urugan kembali Luas urugan = L


dalam urugan = d
volume urugan = Lxd

C PEKERJAAN PASANGAN BATU/BETON


1 Pek. Pondasi pas. Batu Kali camp. 1 Pc : 4 Ps Hitungan volume dengan 3D autocad
Volume =

2 Pek. Dinding tembok pas. Batu kali camp. 1 Pc : 4 Ps Hitungan volume dengan 3D autocad
volume =

3 Siar mata sapi dinding tembok saluran adukan 1 Pc : 2 Ps asumsi Luas plester/2

4 Plester dinding dalam bak camp. 1 Pc : 2 Ps Luas bidang a 9x0,9


Luas bidang b 5 x 0,9-0,75x1,12-0,65x1,12
Luas bidang c 9,6x0,5+9x0,9-0,5x4,2x2
Luas bidang d 9x0,9
Luas bidang e 10,2x0,6
Luas lubang f 5x0,6
Luas bidang g' 10,2x0,6
Luas bidang h 5x0,6
Total luas bidang plesteran

5 Pas. Batu kosong bawah lantai Luas pasangan 9x5


tebal pasangan 0.20
Volume pasangan

6 Cor lantai bak intake beton 1 Pc : 2 Ps : 3 Kr Luas pasangan 9x5


tebal cor 0.15
Volume pengecoran

7 Pas. Bronjong bentuk I type D (keranjang uk. 2 x 1 x 0,5) Volume Bronjong I 10x1
Volume Bronjong II 8x0,5
Volume total
Luas
3 x 3 = 9 m2
6 x 4 = 24 m2

1.6 m
10 titik
16 m

104.16 m2
1.3 m
135.408 m3

42.24 m2
0.4 m
16.896 m3

22.55 m3

25.87 m3

0 m2 0

= 8.1
0,9-0,75x1,12-0,65x1,12 = 2.932
0,5+9x0,9-0,5x4,2x2 = 8.7
= 8.1
= 6.12
= 3
= 6.12
= 3
= 46.07

= 45
= 0.2
= 9

= 45
= 0.15
= 6.75

= 10
= 4
= 14
Biro Konsultan
CV. CENDANA CONSULTANT
Muliambut Mulia
Kabupaten Puncak Jaya

REKAPITULASI

PEKERJAAN : PEMBANGUNAN DAN PEMASANGAN JARINGAN PLTMH NIOGA


LOKASI : DISTRIK NIOGA KABUPATEN PUNCAK JAYA

NO URAIAN PEKERJAAN JUMLAH HARGA

I PEKERJAAN PERSIAPAN Rp 1,805,220,898.83


II PEKERJAAN PENGECATAN Rp 27,354,756.16
III PEKERJAAN PEMASANGAN TIANG (KONSTRUKSI UTAMA) Rp 293,083,264.69
IV PEMASANGAN JARINGAN TR DAN SR Rp 1,534,415,963.63
V PEKERJAAN AKHIR Rp 2,500,000.00

A. Biaya Real Cost : Rp 3,662,574,883.31


B. PPN 10 % : Rp 366,257,488.33
C. Total Cost : A+B Rp 4,028,832,371.64
D Dibulatkan : Rp 4,028,832,000.00

Terbilang : T

Mulia, Pebruari 2015

Konsultan Perencana
CV. CENDANA CONSULTANT

NATALIA ALLOBUA, S.Sos.


Direktris

Mengetahui : Diperiksa/Disetujui Oleh :


Kepala Dinas Pekerjaan Umum PPTK
Kabupaten Puncak Jaya

PILEMON TABUNI, S.PAK,S.IP,M.Si YOSEPH I.M. RENUW, S.SOS


NIP. 19711105 200112 1 003 NIP. 19680509 199712 1 003
Biro Konsultan
CV. CENDANA CONSULTANT
Muliambut Mulia
Kabupaten Puncak Jaya

ENGINEER'S ESTIMATE (EE)


PEKERJAAN : PENGADAAN DAN PEMASANGAN JARINGAN PLTMH NIOGA
LOKASI : DISTRIK NIOGA KABUPATEN PUNCAK JAYA

:
No. Uraian Pekerjaan Analisa Volume Sat. Harga Satuan (Rp) Jumlah Harga (Rp)
Jumlah Harga (Rp)
I PEKERJAAN PERSIAPAN
A. Material Distribusi Utama (MDU)
1 Pengadaan Tiang listrik 9 m 150 daN Harga bhn & Upah 75.00 btg 15,729,000.00 1,179,675,000.00
2 Pengadaan Kabel Twisted, 3x35+1x25 mm2 Harga bhn & Upah 3,300.00 m 103,094.29 340,211,157.00
3 Pengadaan Kabel Twisted, 2x10 mm2 Harga bhn & Upah 6,250.00 m 42,430.00 265,187,500.00
Sub Total 1,785,073,657.000
B Material Pelengkap
1 Strain Wedge Clamp (service Klem /wik besar) Harga bhn & Upah 76.00 bh 115,564.29 8,782,886.04
2 Suspension Clamp with Chain Link (Gantungan kabel ) Harga bhn & Upah 37.00 bh 75,431.43 2,790,962.91
3 Stainless steel strip 20 x 0,7 mm2 Harga bhn & Upah 150.00 bh 48,155.95 7,223,392.88
4 Stoping buckle Stainless steel Harga bhn & Upah 150.00 bh 9,000.00 1,350,000.00
Sub Total 20,147,241.830
Total 1,805,220,898.830
II PEKERJAAN PENGECATAN
1 Pengecatan Tiang dengan cat meni K.4 275.53 M3 47,550.25 13,101,520.38
2 Pengecatan Tiang dengan cat besi K.5 275.53 M2 51,730.25 14,253,235.78
Total 27,354,756.160
III PEMASANGAN TIANG (KONSTRUKSI UTAMA)
1 Galian Tanah Lubang Tiang Listrik B.1 33.00 M3 87,037.50 2,872,237.50
2 Galian Tanah Lubang angker treck schoor B.1 0.13 M3 87,037.50 11,314.88
3 Pemasangan Tiang R-11 (Jalur Akhir/Adjust Dead End Assembly) Q.1 2.00 bh 238,562.50 477,125.00
5 Pemasangan Tiang R-13 (Jalur Lurus/Suspention Assembly) Q.1 73.00 bh 238,562.50 17,415,062.50
6 Pemasangan Treck Schoor Q.3 2.00 bh 800,470.99 1,600,941.98
7 Timbunan batu kali B.5 24.00 M3 2,674,815.00 64,195,560.00
8 Urugan kembali B.2 8.25 M3 24,568.50 202,690.13
9 Pengecoran pondasi tiang listrik beton mutu K125 Q.2 75.00 Ttk 2,521,990.72 189,149,303.73
10 Pengecoran blok angker trek schoor beton mutu K125 E.2 0.16 M3 800,470.99 128,075.36
11 Pemasangan angker tiang besi dia 12 mm Q.4 75.00 Unit 195,265.90 14,644,942.56
12 Pemasangan Grounding Q.5 1.00 Unit 2,386,011.05 2,386,011.05
Total 293,083,264.690
IV PEKERJAAN PEMASANGAN JARINGAN TR dan SR
1 Pemasangan Kabel Twisted, 3x35+1x25 mm2 Q.6 3.00 Kms 11,407,000.00 34,221,000.00
2 Penyambungan SR Q.7 250.00 SR 2,332,744.57 583,186,143.38
3 Pemasangan Lampu Jalan LED 70 Watt Q.8 75.00 bh 12,226,784.27 917,008,820.25
Total 1,534,415,963.630
V PEKERJAAN AKHIR
1 Dokumentasi/Pelaporan - 1.00 Ls 2,500,000.00 2,500,000.00
Total 2,500,000.000

Mulia, Pebruari 2015

Konsultan Perencana
CV. CENDANA CONSULTANT

NATALIA ALLOBUA, S.Sos.


Direktris

JAR NIOGA - 48
Biro Konsultan
CV. CENDANA CONSULTANT
Muliambut Mulia
Kabupaten Puncak Jaya

REKAPITULASI

PEKERJAAN : PENGADAAN DAN PEMASANGAN JARINGAN PLTMH ILU


LOKASI : DISTRIK ILU KABUPATEN PUNCAK JAYA

NO URAIAN PEKERJAAN JUMLAH HARGA

I PEKERJAAN PERSIAPAN Rp 1,238,942,730.65


II PEKERJAAN PENGECATAN Rp 18,236,835.04
III PEKERJAAN PEMASANGAN TIANG (KONSTRUKSI UTAMA) Rp 202,729,090.44
IV PEMASANGAN JARINGAN TR DAN SR Rp 1,100,702,128.20
V PEKERJAAN AKHIR Rp 2,500,000.00

A. Biaya Real Cost : Rp 2,563,110,784.33


B. PPN 10 % : Rp 256,311,078.43
C. Total Cost : A+B Rp 2,819,421,862.76
D Dibulatkan : Rp 2,819,421,000.00

Terbilang :

Mulia, Pebruari 2015

Konsultan Perencana
CV. CENDANA CONSULTANT

NATALIA ALLOBUA, S.Sos.


Direktris

Mengetahui : Diperiksa/Disetujui Oleh :


Kepala Dinas Pekerjaan Umum PPTK
Kabupaten Puncak Jaya

PILEMON TABUNI, S.PAK,S.IP,M.Si YOSEPH I.M. RENUW, S.SOS


NIP. 19711105 200112 1 003 NIP. 19680509 199712 1 003
Biro Konsultan
CV. CENDANA CONSULTANT
Muliambut Mulia
Kabupaten Puncak Jaya

ENGINEER'S ESTIMATE (EE)


PEKERJAAN : PENGADAAN DAN PEMASANGAN JARINGAN PLTMH ILU
LOKASI : DISTRIK ILU KABUPATEN PUNCAK JAYA

:
No. Uraian Pekerjaan Analisa Volume Sat. Harga Satuan (Rp) Jumlah Harga (Rp)

Jumlah Harga (Rp)


I PEKERJAAN PERSIAPAN
A. Material Distribusi Utama (MDU)
1 Pengadaan Tiang listrik 9 m 150 daN Harga bhn & Upah 50.00 btg 15,729,000.00 786,450,000.00
2 Pengadaan Kabel Twisted, 3x35+1x25 mm2 Harga bhn & Upah 2,200.00 m 103,094.29 226,807,438.00
3 Pengadaan Kabel Twisted, 2x10 mm2 Harga bhn & Upah 5,000.00 m 42,430.00 212,150,000.00
Sub Total 1,225,407,438.000
B Material Pelengkap
1 Strain Wedge Clamp (service Klem /wik besar) Harga bhn & Upah 52.00 bh 115,564.29 6,009,343.08
2 Suspension Clamp with Chain Link (Gantungan kabel ) Harga bhn & Upah 24.00 bh 75,431.43 1,810,354.32
3 Stainless steel strip 20 x 0,7 mm2 (pita stainless) Harga bhn & Upah 100.00 bh 48,155.95 4,815,595.25
4 Stoping buckle Stainless steel (klem pita) Harga bhn & Upah 100.00 bh 9,000.00 900,000.00
Sub Total 13,535,292.650
Total 1,238,942,730.650
II PEKERJAAN PENGECATAN
1 Pengecatan Tiang dengan cat meni K.4 183.69 M3 47,550.25 8,734,505.42
2 Pengecatan Tiang dengan cat besi K.5 183.69 M2 51,730.25 9,502,329.62
Total 18,236,835.040
III PEMASANGAN TIANG (KONSTRUKSI UTAMA)
1 Galian Tanah Lubang Tiang Listrik B.1 22.00 M3 87,037.50 1,914,825.00
2 Galian Tanah Lubang angker treck schoor B.1 0.13 M3 87,037.50 11,314.88
3 Pemasangan Tiang R-11 (Jalur Akhir/Adjust Dead End Assembly) Q.1 2.00 bh 238,562.50 477,125.00
4 Pemasangan Tiang R-13 (Jalur Lurus/Suspention Assembly) Q.1 73.00 bh 238,562.50 17,415,062.50
5 Pemasangan Treck Schoor Q.3 2.00 bh 800,470.99 1,600,941.98
6 Timbunan batu kali B.5 16.00 M3 2,674,815.00 42,797,040.00
7 Urugan kembali B.2 5.53 M3 24,568.50 135,863.81
8 Pengecoran pondasi tiang listrik beton mutu K225 Q.2 50.00 Ttk 2,521,990.72 126,099,535.82
9 Pengecoran blok angker trek schoor beton mutu K 225 E.2 0.16 M3 800,470.99 128,075.36
10 Pemasangan angker tiang besi dia 12 mm Q.4 50.00 unit 195,265.90 9,763,295.04
11 Pemasangan Grounding Q.5 1.00 unit 2,386,011.05 2,386,011.05
Total 202,729,090.440
IV PEKERJAAN PEMASANGAN JARINGAN TR dan SR
1 Pemasangan Kabel Twisted, 3x35+1x25 mm2 Q.6 2.00 Kms 11,407,000.00 22,814,000.00
2 Penyambungan SR Q.7 200.00 SR 2,332,744.57 466,548,914.70
3 Pemasangan Lampu Jalan LED 70 Watt Q.8 50.00 bh 12,226,784.27 611,339,213.50
Total 1,100,702,128.200
V PEKERJAAN AKHIR
1 Dokumentasi/Pelaporan - 1.00 Ls 2,500,000.00 2,500,000.00
Total 2,500,000.000

JARINGAN ILU - 50
No. Uraian Pekerjaan Analisa Volume Sat. Harga Satuan (Rp) Jumlah Harga (Rp)

JARINGAN ILU - 51
Q. ANALISA JARINGAN LISTRIK TEGANGAN RENDAH
Q.1 PASANG 1 BH TIANG LISTRIK
Tenaga :
Pekerja 0.3750 OH x Rp 100,000.00 = Rp 37,500.00
Tukang listrik 0.3750 OH x Rp 140,000.00 = Rp 52,500.00
Kepala Tukang 0.1250 OH x Rp 150,000.00 = Rp 18,750.00
Mandor 0.1250 OH x Rp 165,000.00 = Rp 20,625.00
Biaya angkutan ke titik lokasi 160.0000 Kg x Rp 500.00 = Rp 80,000.00
Pemasangan material pelengkap 1.0000 Ls x Rp 7,500.00 = Rp 7,500.00
B. JUMLAH UPAH = Rp 216,875.00
D. Overhead + Profit (10%) = Rp 21,687.50
E. Total = Rp 238,562.50

Q.2 PENGECORAN 1 TTK PONDASI


E.5 Pasang bekesting 0.4800 m2 x Rp 382,713.57 = Rp 183,702.51
E.2 pengecoran beton 0.1080 m3 x Rp 21,628,034.47 = Rp 2,335,827.72
E.11 bongkar bekesting 0.4800 m2 x Rp 5,126.00 = Rp 2,460.48
E. Total = Rp 2,521,990.72

Q.3 Pasang 1 BH TRECK SCHOOR


Bahan
Galvanis steel wire 1/4" 15.0000 mtr x Rp 29,922.07 = Rp 448,831.05
Klem Sling 1/4" 1.0000 bh x Rp 16,961.04 = Rp 16,961.04
Spancroef 1/4" 1.0000 bh x Rp 36,222.07 = Rp 36,222.07
Besi beton polos 1.1604 kg x Rp 66,728.57 = Rp 77,431.83
A. JUMLAH HARGA BAHAN = Rp 579,445.99
Tenaga :
Pekerja 0.2500 OH x Rp 100,000.00 = Rp 25,000.00
Tukang listrik 0.5000 OH x Rp 140,000.00 = Rp 70,000.00
Kepala Tukang 0.0500 OH x Rp 150,000.00 = Rp 7,500.00
Mandor 0.0167 OH x Rp 165,000.00 = Rp 2,750.00
B. JUMLAH HARGA UPAH = Rp 105,250.00
C. JUMLAH HARGA BAHAN DAN UPAH = Rp 684,695.99
D. Overhead + Profit (10%) = Rp 10,525.00
E. Total = Rp 800,470.99

Q.4 PASANG 1 UNIT ANGKER BESI


Bahan :
Besi beton polos 1.42 kg x Rp 66,728.57 = Rp 94,754.57
O.4 Pengelasan 12 cm x Rp 6,896.66 = Rp 82,759.89
A. JUMLAH HARGA BAHAN = Rp 177,514.46
D. Overhead + Profit (10%) = Rp 17,751.45
E. Total = Rp 195,265.90

Q.5 PASANG GROUNDING 1 UNIT


Bahan :
Kawat BC 50 mm2 2.000 mtr x Rp 140,000.00 = Rp 280,000.00
Pipa PVC 1" 2.000 btg x Rp 94,428.57 = Rp 188,857.14
Tap Connector 35-070/35-70 mm2 1.000 bh x Rp 100,298.57 = Rp 100,298.57
Cable schoen 50 mm CU 8.000 m x Rp 78,400.00 = Rp 627,200.00
Stainless steel strip 20 x 0,7 mm2 (pita pengikat) 8.000 bh x Rp 96,311.91 = Rp 770,495.24
Stoping buckle Stainless steel (pengikat pita baja) 8.000 bh x Rp 9,000.00 = Rp 72,000.00
A. JUMLAH HARGA BAHAN = Rp 2,038,850.95
Tenaga :
Pekerja 0.500 OH x Rp 100,000.00 = Rp 50,000.00
Tukang Listrik 0.500 OH x Rp 140,000.00 = Rp 70,000.00
Kepala Tukang 0.050 OH x Rp 150,000.00 = Rp 7,500.00
Mandor 0.017 OH x Rp 165,000.00 = Rp 2,750.00
Q.5 B. JUMLAH UPAH = Rp 130,250.00
C. JUMLAH BAHAN DAN UPAH = Rp 2,169,100.95
D. Overhead + Profit (10%) = Rp 216,910.10
E. Total = Rp 2,386,011.05

Q.6 PEMASANGAN 1 KMS KABEL TWISTED 3X35 MM2 + 25 MM2

AN. JTR -16


Tenaga :
Pekerja 30.000 OH x Rp 100,000.00 = Rp 3,000,000.00
Tukang Listrik 30.000 OH x Rp 140,000.00 = Rp 4,200,000.00
Kepala Tukang 10.000 OH x Rp 150,000.00 = Rp 1,500,000.00
Mandor 10.000 OH x Rp 165,000.00 = Rp 1,650,000.00
Alat Bantu 1.000 Ls x Rp 20,000.00 = Rp 20,000.00
A. JUMLAH HARGA BAHAN = Rp 10,370,000.00
D. Overhead + Profit (10%) = Rp 1,037,000.00
E. Total = Rp 11,407,000.00

AN. JTR -17


Q.7 PEMASANGAN 1 SR
Bahan :
Kabel Twisted 2 x 10 mm2 30.000 m x Rp 42,430.00 = Rp 1,272,900.00
Kaitan Kabel Twiested 1.000 bh x Rp 80,597.14 = Rp 80,597.14
Service klem / wik kecil 2.000 bh x Rp 75,298.57 = Rp 150,597.14
Tap Konektor Distribusi 1 Baut 2.000 bh x Rp 45,165.71 = Rp 90,331.42
Stainless steel strip 20 x 0,7 mm2 (pita pengikat) 2.000 bh x Rp 48,155.95 = Rp 96,311.91
Stoping buckle Stainless steel (pengikat pita baja) 2.000 bh x Rp 9,000.00 = Rp 18,000.00
Limit 2 A 1.000 bh x Rp 75,298.57 = Rp 75,298.57
MCB Box 1.000 bh x Rp 91,265.71 = Rp 91,265.71
A. JUMLAH HARGA BAHAN = Rp 1,875,301.89
Tenaga :
Pekerja 0.750 OH x Rp 100,000.00 = Rp 75,000.00
Tukang Listrik 0.750 OH x Rp 140,000.00 = Rp 105,000.00
Kepala Tukang 0.075 OH x Rp 150,000.00 = Rp 11,250.00
Mandor 0.025 OH x Rp 165,000.00 = Rp 4,125.00
Alat bantu 1.000 Ls x Rp 50,000.00 = Rp 50,000.00
B. JUMLAH UPAH = Rp 245,375.00
C. JUMLAH BAHAN DAN UPAH = Rp 2,120,676.89
D. Overhead + Profit (10%) = Rp 212,067.69
0 E. Total = Rp 2,332,744.57

Q.8 PEMASANGAN 1 BH LAMPU JALAN LED


Bahan :
Lampu Jalan LED 70 Watt 1.000 set x Rp 5,139,750.00 = Rp 5,139,750.00
Stang lampu jalan + clem stang lampu 1.000 bh x Rp 914,928.57 = Rp 914,928.57
Sensor lampu 6 A 1.000 bh x Rp 89,265.71 = Rp 89,265.71
A. JUMLAH HARGA BAHAN = Rp 10,809,433.43
Tenaga :
Pekerja 1.000 OH x Rp 100,000.00 = Rp 100,000.00
Tukang Listrik 1.000 OH x Rp 140,000.00 = Rp 140,000.00
Kepala Tukang 0.100 OH x Rp 150,000.00 = Rp 15,000.00
Mandor 0.005 OH x Rp 165,000.00 = Rp 825.00
Alat Bantu 1.000 Ls x Rp 50,000.00 = Rp 50,000.00
B. JUMLAH UPAH = Rp 305,825.00
C. JUMLAH BAHAN DAN UPAH = Rp 11,115,258.43
D. Overhead + Profit (10%) = Rp 1,111,525.84
E. Total = Rp 12,226,784.27

AN. JTR -18


ITEM PEMBAYARAN NO. : Analisa EI -
JENIS PEKERJAAN : Galian Tanah
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN

No. U RAIAN KODE KOEF. SATUAN KETERANGAN

I. ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Jam kerja efektif per-hari Tk 7.00 jam
3 Faktor pengembangan bahan Fk 1.20 -
4 Berat volume bahan D 1.60 Ton/M3

II. URUTAN KERJA


1 Penggalian dilakukan dengan menggunakan Excavator
2 Selanjutnya Excavator menuangkan material hasil
galian di lokasi tanpa angkutan
3 Sekelompok pekerja akan merapikan hasil galian

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA

1. BAHAN
Tidak ada bahan yang diperlukan

2. ALAT
2.a. EXCAVATOR (E10)
Kapasitas Bucket V 0.93 M3
Faktor Bucket Fb 1.00 - kondisi tanah berbatu
Faktor Efisiensi alat Fa 0.83 - kondisi kerja baik
Faktor Konversi
Waktu siklus = T1 + T2 Ts1 1.80 menit masuk dalam
- Menggali, memuat dan berputar T1 1.00 menit waktu siklus
- Lain lain T2 0.80 menit disesuaikan dgn
Kap. Prod. / jam = V x Fb x Fa x 60 Q1 21.44 M3 lapangan
Ts1 x Fk

Koefisien Alat / M3 = 1 : Q1 - 0.0466 Jam

2.b. ALAT BANTU


Diperlukan alat-alat bantu kecil
- Sekop
- Linggis

3. TENAGA
Produksi menentukan : EXCAVATOR Q1 21.44 M3/Jam
Produksi Galian / hari = Tk x Q1 Qt 150.09 M3
Kebutuhan tenaga :
- Pekerja P 4.00 orang
- Mandor M 1.00 orang

Koefisien tenaga / M3 :
- Pekerja = Tk x P : Qt (L01) 0.1866 OJ
- Mandor = Tk x M : Qt (L03) 0.0466 OJ

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :
Rp. 95,070.66 / M3

6. WAKTU PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan : . . . . . . . . . . . . bulan

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : M3
Analisa EI -

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KEGIATAN : PEMBANGUNAN PLTMH DISTRIK NIOGA


PEKERJAAN : PEMBANGUNAN PLTMH DISTRIK NIOGA
ITEM PEMBAYARAN NO. :
JENIS PEKERJAAN : Galian Tanah
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) OJ 0.1866 14,285.71 2,665.04


2. Mandor (L03) OJ 0.0466 23,571.43 1,099.33

JUMLAH HARGA TENAGA 3,764.37

B. BAHAN

0.32

JUMLAH HARGA BAHAN 0.00

C. PERALATAN

1. Excavator (E10) jam 0.0466 1,691,871.29 78,905.77

3. Alat Bantu Ls 0.00

JUMLAH HARGA PERALATAN 78,905.77

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 82,670.14


E. OVERHEAD & PROFIT 15.0 % x D 12,400.52
F. HARGA SATUAN PEKERJAAN ( D + E ) 95,070.66

Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
ANALISA HARGA SATUAN PEKERJAAN (AHSP)
BIDANG CIPTA KARYA SNI 2002 DAN SNI 2008

A. PEKERJAAN PERSIAPAN SNI 2835 - 2002


HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN INDEKS SATUAN
(Rp) (Rp)

1 SNI 03-2835-2002 (6.4)


1M' Pengukuran dan pemasangan bouwplank (keliling)
Bahan :
Kayu balok 0.0120 M 5,600,000.00 67,200.00
Kayu papan 0.0070 M 5,600,000.00 39,200.00
Paku campur 0.0200 Kg 73,628.57 1,472.57
A. JUMLAH HARGA BAHAN 107,872.57
Tenaga :
Tukang Kayu 0.1000 OH 140,000.00 14,000.00
Pekerja 0.1000 OH 100,000.00 10,000.00
Kepala Tukang 0.0100 OH 150,000.00 1,500.00
Mandor 0.0050 OH 165,000.00 825.00
B. JUMLAH UPAH 26,325.00
C. JUMLAH BAHAN DAN UPAH 134,197.57
D. Overhead + Profit (10%) 13,419.76
E. Total 147,617.33
2 SNI 03-2835-2002 (6.7)
1M2 Pembuatan gudang semen dan alat-alat
Bahan :
Kayu balok 0.0600 M 5,600,000.00 336,000.00
Kayu papan 0.2100 M 5,600,000.00 1,176,000.00
Paku campur 0.3000 Kg 73,628.57 22,088.57
Semen PC 10.5000 Kg 48,028.57 504,299.99
Pasir cor 0.0300 M 2,000,000.00 60,000.00
Kerikil pecah 0.0500 M 2,500,000.00 125,000.00
Seng Gelombang BJLS 20 1.5000 Lbr 205,385.71 308,078.57
A. JUMLAH HARGA BAHAN 2,531,467.12
Tenaga :
Pekerja 1.0000 OH 100,000.00 100,000.00
Tukang kayu 2.0000 OH 140,000.00 280,000.00
Kepala Tukang 0.2000 OH 150,000.00 30,000.00
Mandor 0.0500 OH 165,000.00 8,250.00
B. JUMLAH UPAH 418,250.00
C. JUMLAH BAHAN DAN UPAH 2,949,717.12
D. Overhead + Profit (10%) 294,971.71
E. Total 3,244,688.83
F. Total x 0,5 1,622,344.42
3 SNI 03-2835-2002 (6.8)
1M2 Pembersihan Lapangan dan perataan
Tenaga :
Pekerja 0.1000 OH 100,000.00 10,000.00
Mandor 0.0500 OH 165,000.00 8,250.00
A. JUMLAH UPAH 18,250.00
B. Overhead + Profit (10%) 1,825.00
C. Total 20,075.00
4 SNI 03-2835-2002 (6.10)
1M2 Pembuatan bedeng buruh
Bahan :
Kayu balok 0.0600 M 5,600,000.00 336,000.00
Kayu papan 0.2300 M 5,600,000.00 1,288,000.00
Paku campur 0.3000 Kg 73,628.57 22,088.57
Seng Gelombang BJLS 20 1.5000 Lbr 205,385.71 308,078.57
Tripleks 3 mm 1.3500 Lbr 317,942.86 429,222.86
A. JUMLAH HARGA BAHAN 2,383,390.00
Tenaga :
Pekerja 1.0000 OH 100,000.00 100,000.00
Tukang kayu 2.0000 OH 140,000.00 280,000.00
Kepala Tukang 0.2000 OH 150,000.00 30,000.00
Mandor 0.0500 OH 165,000.00 8,250.00
B. JUMLAH UPAH 418,250.00
C. JUMLAH BAHAN DAN UPAH 2,801,640.00
D. Overhead + Profit (10%) 280,164.00

ARSIP SNI 2008 - 23


HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN INDEKS SATUAN
(Rp) (Rp)
E. Total 3,219,890.00
F. Total x 0,5 1,609,945.00
B. PEKERJAAN TANAH - SNI 2835 - 2008

Analisa Sumber Daya Air T.16


Galian Tanah m3 Menggunakan Excavator
Bahan :
Solar 10,800.000 Ltr -
A. JUMLAH HARGA BAHAN -

Tenaga :
Operator 1.0000 OJ 23,571.43 23,571.43
Mekanik 0.5000 OJ 23,571.43 11,785.71
B. JUMLAH UPAH 35,357.14
Peralatan :
Sewa excavator 0.0120 Jam 1,691,871.29 20,302.46
C. JUMLAH ALAT 20,302.46
D. JUMLAH BAHAN, UPAH, DAN ALAT 55,659.60
E. Overhead + Profit (10%) 5,565.96
F. Total 91,016.74
SNI 2835 - 2008 (6.1)
Menggali 1 m3 Tanah biasa sedalam 1 m
Tenaga :
Pekerja 0.7500 OH 100,000.00 75,000.00
Mandor 0.0250 OH 165,000.00 4,125.00
A. JUMLAH UPAH 79,125.00
B. Overhead + Profit (10%) 7,912.50
C. Total 87,037.50
SNI 2835 - 2008 (6.1)
Menggali 1 m3 Tanah biasa sedalam 2 m
Tenaga :
Pekerja 0.9000 OH 100,000.00 90,000.00
Mandor 0.0450 OH 165,000.00 7,425.00
A. JUMLAH UPAH 97,425.00
B. Overhead + Profit (10%) 9,742.50
C. Total 107,167.50
1 SNI 2835 - 2008 (6.8)
Menggali 1 m3 Tanah keras
Tenaga :
Pekerja 1.2500 OH 100,000.00 125,000.00
Mandor 0.1250 OH 165,000.00 20,625.00
A. JUMLAH UPAH 145,625.00
B. Overhead + Profit (10%) 14,562.50
C. Total 160,187.50
2 SNI 2835 - 2008 (6.9)
1 M Urugan Kembali
Tenaga :
Pekerja 0.1920 OH 100,000.00 19,200.00
Mandor 0.0190 OH 165,000.00 3,135.00
A. JUMLAH UPAH 22,335.00
B. Overhead + Profit (10%) 2,233.50
C. Total 24,568.50
3 SNI 2835 - 2008 (6.10)
Memadatkan 1 m3 tanah (per 20 cm)
Tenaga Kerja
Pekerja 0.5000 OH 100,000.00 50,000.00
Mandor 0.0500 OH 165,000.00 8,250.00
A. JUMLAH UPAH 58,250.00
B. Overhead + Profit (10%) 5,825.00
C. Total 64,075.00
4 SNI 2835 - 2008 (6.11)
Mengurug 1 m3 pasir urug
Bahan :
Pasir Urug 1.2000 M 2,000,000.00 2,400,000.00
A. JUMLAH HARGA BAHAN 2,400,000.00
Tenaga :
Pekerja 0.3000 OH 100,000.00 30,000.00
Mandor 0.0100 OH 165,000.00 1,650.00
B. JUMLAH UPAH 31,650.00

ARSIP SNI 2008 - 24


HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN INDEKS SATUAN
(Rp) (Rp)
C. JUMLAH BAHAN DAN UPAH 2,431,650.00
D. Overhead + Profit (10%) 243,165.00
E. Total 2,674,815.00
SNI 2835 - 2008 (6.15)
5 Mengurug 1 m3 tanah urug
Bahan :
Timbunan biasa 1.2000 M 550,000.00 660,000.00
A. JUMLAH HARGA BAHAN 660,000.00
Tenaga :
Pekerja 0.3000 OH 100,000.00 30,000.00
Mandor 0.0100 OH 165,000.00 1,650.00
B. JUMLAH UPAH 31,650.00
C. JUMLAH BAHAN DAN UPAH 691,650.00
D. Overhead + Profit (10%) 69,165.00
E. Total 760,815.00
C. PEKERJAAN PONDASI SNI 2836 - 2008
1 SNI 2836 - 2008 (6.1)
Memasang 1 M pondasi batu kali, campuran 1 Pc :3 Ps
Bahan :
Batu kali 1.200 M 2,000,000.00 2,400,000.00
Semen PC 202.000 Kg 48,028.57 9,701,771.14
Pasir Pasang 0.485 M 2,000,000.00 970,000.00
A. JUMLAH HARGA BAHAN 13,071,771.14
Tenaga :
Pekerja 1.5000 OH 100,000.00 150,000.00
Tukang batu 0.7500 OH 140,000.00 105,000.00
Kepala Tukang 0.0750 OH 150,000.00 11,250.00
Mandor 0.0750 OH 165,000.00 12,375.00
B. JUMLAH UPAH 278,625.00
C. JUMLAH BAHAN DAN UPAH 13,350,396.14
D. Overhead + Profit (10%) 1,335,039.61
E. Total 14,685,435.75
2 SNI 2836 - 2008 (6.2)

ARSIP SNI 2008 - 25


HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN INDEKS SATUAN
(Rp) (Rp)
Memasang 1 M pondasi batu kali, campuran 1 Pc :4 Ps
Bahan :
Batu kali 1.2000 M 2,000,000.00 2,400,000.00
Semen PC 163.0000 Kg 48,028.57 7,828,656.91
Pasir Pasang 0.5200 M 2,000,000.00 1,040,000.00
A. JUMLAH HARGA BAHAN 11,268,656.91
Tenaga :
Pekerja 1.5000 OH 100,000.00 150,000.00
Tukang batu 0.7500 OH 140,000.00 105,000.00
Kepala Tukang 0.0750 OH 150,000.00 11,250.00
Mandor 0.0750 OH 165,000.00 12,375.00
B. JUMLAH UPAH 278,625.00
C. JUMLAH BAHAN DAN UPAH 11,547,281.91
D. Overhead + Profit (10%) 1,154,728.19
E. Total 12,702,010.10
3 SNI 2836 - 2008 (6.3)
Memasang 1 M pondasi batu kali, campuran 1 Pc :5 Ps
Bahan :
Batu kali 1.2000 M 2,000,000.00 2,400,000.00
Semen PC 136.0000 Kg 48,028.57 6,531,885.52
Pasir Pasang 0.5440 M 2,000,000.00 1,088,000.00
A. JUMLAH HARGA BAHAN 10,019,885.52
Tenaga :
Pekerja 1.5000 OH 100,000.00 150,000.00
Tukang batu 0.7500 OH 140,000.00 105,000.00
Kepala Tukang 0.0750 OH 150,000.00 11,250.00
Mandor 0.0750 OH 165,000.00 12,375.00
B. JUMLAH UPAH 278,625.00
C. JUMLAH BAHAN DAN UPAH 10,298,510.52
D. Overhead + Profit (10%) 1,029,851.05
E. Total 11,328,361.57
SNI 2836 - 2008 (6.9)
4 Memasang 1 M Batu Kosong (Aanstamping)
Bahan :
Batu kali 1.2000 M 2,000,000.00 2,400,000.00
Pasir Pasang 0.4320 M 2,000,000.00 864,000.00
A. JUMLAH HARGA BAHAN 3,264,000.00
Tenaga :
Pekerja 0.7800 OH 100,000.00 78,000.00
Tukang batu 0.3900 OH 140,000.00 54,600.00
Kepala Tukang 0.0390 OH 150,000.00 5,850.00
Mandor 0.0390 OH 165,000.00 6,435.00
B. JUMLAH UPAH 144,885.00
C. JUMLAH BAHAN DAN UPAH 3,408,885.00
D. Overhead + Profit (10%) 340,888.50
E. Total 3,749,773.50
4 SNI 2836 - 2008 (6.10)
Memasang 1 M pondasi cyclop, 60% campuran 1 Pc :2 Ps: 3 Kr dan 40% batu kali
Bahan :
Batu kali 0.4800 M 2,000,000.00 960,000.00
Semen PC 194.0000 Kg 48,028.57 9,317,542.58
Pasir Pasang 0.3120 M 2,000,000.00 624,000.00
Kerikil pecah 0.4680 M 2,500,000.00 1,170,000.00
A. JUMLAH HARGA BAHAN 12,071,542.58
Tenaga :
Pekerja 3.4000 OH 100,000.00 340,000.00
Tukang batu 0.8500 OH 140,000.00 119,000.00
Kepala Tukang 0.0850 OH 150,000.00 12,750.00
Mandor 0.1700 OH 165,000.00 28,050.00
B. JUMLAH UPAH 499,800.00
C. JUMLAH BAHAN DAN UPAH 12,571,342.58
D. Overhead + Profit (10%) 1,257,134.26
E. Total 13,828,476.84
D. PEKERJAAN PLESTERAN SNI 2837 - 2008
1 SNI 2837-2008 (6.2)
Membuat 1 m2 plesteran 1 Pc:2 Ps tebal 15 mm
Bahan :
Semen Pc 10.2240 Kg 48,028.57 491,044.10
Pasir Pasang 0.0200 M 2,000,000.00 40,000.00

ARSIP SNI 2008 - 26


HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN INDEKS SATUAN
(Rp) (Rp)
A. JUMLAH HARGA BAHAN 531,044.10
Tenaga :
Pekerja 0.3000 OH 100,000.00 30,000.00
Tukang batu 0.1500 OH 140,000.00 21,000.00
Kepala Tukang 0.0150 OH 150,000.00 2,250.00
Mandor 0.0150 OH 165,000.00 2,475.00
B. JUMLAH UPAH 55,725.00
C. JUMLAH BAHAN DAN UPAH 586,769.10
D. Overhead + Profit (10%) 58,676.91
E. Total 645,446.01
2 SNI 2837-2008 (6.3)
Membuat 1 m2 plesteran 1 Pc:3 Ps tebal 15 mm
Bahan :
Semen Pc 7.7760 Kg 48,028.57 373,470.16
Pasir Pasang 0.0230 M 2,000,000.00 46,000.00
A. JUMLAH HARGA BAHAN 419,470.16
Tenaga :
Pekerja 0.3000 OH 100,000.00 30,000.00
Tukang batu 0.1500 OH 140,000.00 21,000.00
Kepala Tukang 0.0150 OH 150,000.00 2,250.00
Mandor 0.0150 OH 165,000.00 2,475.00
B. JUMLAH UPAH 55,725.00
C. JUMLAH BAHAN DAN UPAH 475,195.16
D. Overhead + Profit (10%) 47,519.52
E. Total 522,714.68
3 SNI 2837-2008 (6.4)
Membuat 1 m2 plesteran 1 Pc:4 Ps tebal 15 mm
Bahan :
Semen PC 6.2400 Kg 48,028.57 299,698.28
Pasir Pasang 0.0240 M 2,000,000.00 48,000.00
A. JUMLAH HARGA BAHAN 347,698.28
Tenaga :
Pekerja 0.3000 OH 100,000.00 30,000.00
Tukang batu 0.1500 OH 140,000.00 21,000.00
Kepala Tukang 0.0150 OH 150,000.00 2,250.00
Mandor 0.0150 OH 165,000.00 2,475.00
B. JUMLAH UPAH 55,725.00
C. JUMLAH BAHAN DAN UPAH 403,423.28
D. Overhead + Profit (10%) 40,342.33
E. Total 443,765.60
SNI 2837-2008 (6.26)
4 MEMASANG 1 M2 FINISHING SIAR PASANGAN BATU KALI ADUKAN 1 PC : 2 PP
Bahan :
Semen PC 6.3400 Kg 48,028.57 304,501.13
Pasir Pasang 0.0120 M 2,000,000.00 24,000.00
A. JUMLAH HARGA BAHAN 328,501.13
Tenaga :
Pekerja 0.3000 OH 100,000.00 30,000.00
Tukang batu 0.1400 OH 140,000.00 19,600.00
Kepala Tukang 0.0140 OH 150,000.00 2,100.00
Mandor 0.0150 OH 165,000.00 2,475.00
B. JUMLAH UPAH 54,175.00
C. JUMLAH BAHAN DAN UPAH 382,676.13
D. Overhead + Profit (10%) 38,267.61
E. Total 420,943.75
SNI 2837-2008 (6.27)
5 MEMASANG 1 M2 ACIAN
Bahan :
Semen PC 3.2500 Kg 48,028.57 156,092.85
A. JUMLAH HARGA BAHAN 156,092.85
Tenaga :
Pekerja 0.1500 OH 100,000.00 15,000.00
Tukang batu 0.1000 OH 140,000.00 14,000.00
Kepala Tukang 0.0100 OH 150,000.00 1,500.00
Mandor 0.0080 OH 165,000.00 1,320.00
B. JUMLAH UPAH 31,820.00
C. JUMLAH BAHAN DAN UPAH 187,912.85
D. Overhead + Profit (10%) 18,791.29
E. Total 206,704.14

ARSIP SNI 2008 - 27


HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN INDEKS SATUAN
(Rp) (Rp)
E. PEKERJAAN BETON SNI 7394 - 2008
1 SNI 2002 . 6.1
Membuat 1 m3 beton tumbuk 1 Pc : 3 Ps : 5 Krl
Bahan :
Semen PC 218.0000 Kg 48,028.57 10,470,228.26
Pasir Cor 0.5200 M 2,000,000.00 1,040,000.00
Kerikil pecah 0.8700 M 2,500,000.00 2,175,000.00
A. JUMLAH HARGA BAHAN 13,685,228.26
Tenaga :
Pekerja 1.6500 OH 100,000.00 165,000.00
Tukang batu 0.2500 OH 140,000.00 35,000.00
Kepala Tukang 0.0250 OH 150,000.00 3,750.00
Mandor 0.0800 OH 165,000.00 13,200.00
B. JUMLAH UPAH 216,950.00
C. JUMLAH BAHAN DAN UPAH 13,902,178.26
D. Overhead + Profit (10%) 1,390,217.83
E. Total 15,292,396.09

2 SNI 7394-2008 (6.1)


MEMBUAT 1 M3 BETON MUTU F'C = 7,4 MPa (K 100), SLUMP (12 2) CM, W/C = 0,87
Bahan :
Semen PC 247.0000 Kg 48,028.57 11,863,056.79
Pasir Cor 0.6207 m3 2,000,000.00 1,241,400.00
Kerikil pecah 0.7400 m3 2,500,000.00 1,850,000.00
Air kerja 215.0000 ltr - -
A. JUMLAH HARGA BAHAN 14,954,456.79
Tenaga :
Pekerja 1.6500 OH 100,000.00 165,000.00
Tukang batu 0.2500 OH 140,000.00 35,000.00
Kepala Tukang 0.0250 OH 150,000.00 3,750.00
Mandor 0.0800 OH 165,000.00 13,200.00
B. JUMLAH UPAH 216,950.00
C. JUMLAH BAHAN DAN UPAH 15,171,406.79
D. Overhead + Profit (10%) 1,517,140.68
E. Total 16,688,547.47

3 SNI 7394-2008 (6.2)


MEMBUAT 1 M3 BETON MUTU F'C = 9,8 MPa (K 125), SLUMP (12 2) CM, W/C = 0,78 (manual)
Bahan :
Semen PC 276.0000 Kg 48,028.57 13,255,885.32
Pasir Cor 0.5910 m3 2,000,000.00 1,182,000.00
Kerikil pecah 0.7500 m3 2,500,000.00 1,875,000.00
Air kerja 215.0000 ltr - -
A. JUMLAH HARGA BAHAN 16,312,885.32
Tenaga :
Pekerja 1.6500 OH 100,000.00 165,000.00
Tukang batu 0.2500 OH 140,000.00 35,000.00
Kepala Tukang 0.0250 OH 150,000.00 3,750.00
Mandor 0.0800 OH 165,000.00 13,200.00
B. JUMLAH UPAH 216,950.00
C. JUMLAH BAHAN DAN UPAH 16,529,835.32
D. Overhead + Profit (10%) 1,652,983.53
E. Total 18,182,818.85

SNI 7394-2008 (6.2)


MEMBUAT 1 M3 BETON MUTU F'C = 9,8 MPa (K 125), SLUMP (12 2) CM, W/C = 0,78 (dengan alat molen)
Bahan :
Semen PC 276.0000 Kg 48,028.57 13,255,885.32
Pasir Cor 0.5910 m3 2,000,000.00 1,182,000.00
Kerikil pecah 0.7500 m3 2,500,000.00 1,875,000.00
Air kerja 215.0000 ltr - -
A. JUMLAH HARGA BAHAN 16,312,885.32
Tenaga :
Pekerja 1.3200 OH 100,000.00 132,000.00
Tukang batu 0.2050 OH 140,000.00 28,700.00
Kepala Tukang 0.0200 OH 150,000.00 3,000.00
Mandor 0.0600 OH 165,000.00 9,900.00
B. JUMLAH UPAH 173,600.00
Alat :

ARSIP SNI 2008 - 28


HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN INDEKS SATUAN
(Rp) (Rp)
Sewa Molen 0.2000 Hari #N/A #N/A
C. JUMLAH ALAT #N/A
D. JUMLAH BAHAN, UPAH, DAN ALAT #N/A
E. Overhead + Profit (10%) #N/A
F. Total #N/A
4 SNI 7394-2008 (6.3)
MEMBUAT 1 M3 BETON MUTU F'C = 12,2 MPa (K 150), SLUMP (12 2) CM, W/C = 0,72
Bahan :
Semen PC 299.0000 Kg 48,028.57 14,360,542.43
Pasir Cor 0.5710 m3 2,000,000.00 1,142,000.00
Kerikil pecah 0.7530 m3 2,500,000.00 1,882,500.00
Air kerja 215.0000 ltr - -
A. JUMLAH HARGA BAHAN 17,385,042.43
Tenaga :
Pekerja 1.6500 OH 100,000.00 165,000.00
Tukang batu 0.2500 OH 140,000.00 35,000.00
Kepala Tukang 0.0250 OH 150,000.00 3,750.00
Mandor 0.0800 OH 165,000.00 13,200.00
B. JUMLAH UPAH 216,950.00
C. JUMLAH BAHAN DAN UPAH 17,601,992.43
D. Overhead + Profit (10%) 1,760,199.24
E. Total 19,362,191.67
5 SNI 7394-2008 (6.4)
MEMBUAT 1 M3 LANTAI KERJA BETON MUTU F'C = 7,4 MPa (K 100), SLUMP (3-6) CM, W/C = 0,87
Bahan :
Semen PC 230.0000 Kg 48,028.57 11,046,571.10
Pasir Cor 0.6380 m3 2,000,000.00 1,276,000.00
Kerikil pecah 0.7610 m3 2,500,000.00 1,902,500.00
Air kerja 200.0000 ltr - -
A. JUMLAH HARGA BAHAN 14,225,071.10
Tenaga :
Pekerja 1.2000 OH 100,000.00 120,000.00
Tukang batu 0.2000 OH 140,000.00 28,000.00
Kepala Tukang 0.0200 OH 150,000.00 3,000.00
Mandor 0.0600 OH 165,000.00 9,900.00
B. JUMLAH UPAH 160,900.00
C. JUMLAH BAHAN DAN UPAH 14,385,971.10
D. Overhead + Profit (10%) 1,438,597.11
E. Total 15,824,568.21
6 SNI 7394-2008 (6.5)
MEMBUAT 1 M3 BETON MUTU F'C = 14,5 MPa (K 175), SLUMP (12 2) CM, W/C = 0,66
Bahan :
Semen PC 326.0000 Kg 48,028.57 15,657,313.82
Pasir Cor 0.5430 m3 2,000,000.00 1,086,000.00
Kerikil pecah 0.7620 m3 2,500,000.00 1,905,000.00
Air kerja 215.0000 ltr - -
A. JUMLAH HARGA BAHAN 18,648,313.82
Tenaga :
Pekerja 1.6500 OH 100,000.00 165,000.00
Tukang Batu 0.2750 OH 140,000.00 38,500.00
Kepala Tukang 0.0280 OH 150,000.00 4,200.00
Mandor 0.0830 OH 165,000.00 13,695.00
B. JUMLAH UPAH 221,395.00
C. JUMLAH BAHAN DAN UPAH 18,869,708.82
D. Overhead + Profit (10%) 1,886,970.88
E. Total 20,756,679.70

MEMBUAT 1 M3 BETON MUTU F'C = 14,5 MPa (K 175), SLUMP (12 2) CM, W/C = 0,66 (menggunakan molen)
Bahan :
Semen PC 326.0000 Kg 48,028.57 15,657,313.82
Pasir Cor 0.5430 m3 2,000,000.00 1,086,000.00
Kerikil pecah 0.7620 m3 2,500,000.00 1,905,000.00
Air kerja 215.0000 ltr - -
A. JUMLAH HARGA BAHAN 18,648,313.82
Tenaga :
Pekerja 1.3300 OH 100,000.00 133,000.00
Tukang batu 0.1890 OH 140,000.00 26,460.00
Kepala Tukang 0.0190 OH 150,000.00 2,850.00
Mandor 0.0660 OH 165,000.00 10,890.00

ARSIP SNI 2008 - 29


HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN INDEKS SATUAN
(Rp) (Rp)
B. JUMLAH UPAH 173,200.00
Peralatan :
Molen 0.2500 Sewa ha 192,780.00 48,195.00
C. JUMLAH PERALATAN 48,195.00
D. JUMLAH BAHAN, TENAGA DAN ALAT 18,869,708.82
E. Overhead + Profit (10%) 1,886,970.88
F. Total 20,756,679.70

7 SNI 7394-2008 (6.6)


MEMBUAT 1 M3 BETON MUTU F'C = 16,9 MPa (K 200), SLUMP (12 2) CM, W/C = 0,61
Bahan :
Semen PC 352.0000 Kg 48,028.57 16,906,056.64
Pasir Cor 0.5220 m3 2,000,000.00 1,044,000.00
Kerikil pecah 0.7640 m3 2,500,000.00 1,910,000.00
Air kerja 215.0000 ltr - -
A. JUMLAH HARGA BAHAN 19,860,056.64
Tenaga :
Pekerja 1.6500 OH 100,000.00 165,000.00
Tukang batu 0.2750 OH 140,000.00 38,500.00
Kepala Tukang 0.0280 OH 150,000.00 4,200.00
Mandor 0.0830 OH 165,000.00 13,695.00
B. JUMLAH UPAH 221,395.00
C. JUMLAH BAHAN DAN UPAH 20,081,451.64
D. Overhead + Profit (10%) 2,008,145.16
E. Total 22,089,596.80
8 SNI 7394-2008 (6.7)
MEMBUAT 1 M3 BETON MUTU F'C = 19,3 MPa (K 225), SLUMP (12 2) CM, W/C = 0,58
Bahan :
Semen PC 371.0000 Kg 48,028.57 17,818,599.47
Pasir Cor 0.4990 m3 2,000,000.00 998,000.00
Kerikil pecah 0.7760 m3 2,500,000.00 1,940,000.00
Air kerja 215.0000 ltr - -
A. JUMLAH HARGA BAHAN 20,756,599.47
Tenaga :
Pekerja 1.6500 OH 100,000.00 165,000.00
Tukang batu 0.2750 OH 140,000.00 38,500.00
Kepala Tukang 0.0280 OH 150,000.00 4,200.00
Mandor 0.0830 OH 165,000.00 13,695.00
B. JUMLAH UPAH 221,395.00
C. JUMLAH BAHAN DAN UPAH 20,977,994.47
D. Overhead + Profit (10%) 2,097,799.45
E. Total 23,075,793.92
9 SNI 7394-2008 (6.17)
PEMBESIAN 1 KG DENGAN BESI POLOS
Bahan :
Besi beton polos 1.0500 Kg 66,728.57 70,065.00
Kawat ikat 0.0150 Kg 76,728.57 1,150.93
A. JUMLAH HARGA BAHAN 71,215.93
Tenaga :
Pekerja 0.0070 OH 100,000.00 700.00
Tukang besi 0.0070 OH 140,000.00 980.00
Kepala Tukang 0.0007 OH 150,000.00 105.00
Mandor 0.0004 OH 165,000.00 66.00
B. JUMLAH UPAH 1,851.00
C. JUMLAH BAHAN DAN UPAH 73,066.93
D. Overhead + Profit (10%) 7,306.69
E. Total 80,373.62
10 SNI 7394-2008 (6.20)
MEMASANG 1 M2 BEKESTING UNTUK PONDASI
Bahan :
Kayu papan 0.0400 M3 5,600,000.00 224,000.00
Paku campur 0.3000 Kg 73,628.57 22,088.57
Minyak bekesting 0.1000 Ltr - -
A. JUMLAH HARGA BAHAN 246,088.57
Tenaga :
Pekerja 0.5200 OH 100,000.00 52,000.00
Tukang kayu 0.2600 OH 140,000.00 36,400.00
Kepala Tukang 0.0260 OH 150,000.00 3,900.00
Mandor 0.0260 OH 165,000.00 4,290.00

ARSIP SNI 2008 - 30


HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN INDEKS SATUAN
(Rp) (Rp)
B. JUMLAH UPAH 96,590.00
C. JUMLAH BAHAN DAN UPAH 342,678.57
D. Overhead + Profit (10%) 34,267.86
E. Total 376,946.43
11 SNI 7394-2008 (6.21)
MEMASANG 1 M2 BEKESTING UNTUK SLOOF
Bahan :
Kayu papan 0.0450 M3 5,600,000.00 252,000.00
Paku campur 0.3000 Kg 73,628.57 22,088.57
Minyak Bekisting 0.1000 Ltr - -
A. JUMLAH HARGA BAHAN 274,088.57
Tenaga :
Pekerja 0.5200 OH 100,000.00 52,000.00
Tukang kayu 0.2600 OH 140,000.00 36,400.00
Kepala Tukang 0.0260 OH 150,000.00 3,900.00
Mandor 0.0260 OH 165,000.00 4,290.00
B. JUMLAH UPAH 96,590.00
C. JUMLAH BAHAN DAN UPAH 370,678.57
D. Overhead + Profit (10%) 37,067.86
E. Total 407,746.43
12 SNI 7394-2008 (6.22)
MEMASANG 1 M2 BEKESTING UNTUK KOLOM
Bahan :
Kayu papan 0.0400 M3 5,600,000.00 224,000.00
Paku campur 0.4000 Kg 73,628.57 29,451.43
Minyak Bekisting 0.2000 ltr - -
Kayu balok 0.0150 M3 5,600,000.00 84,000.00
Tripleks 6 mm 0.3500 lbr - -
Balok 5/10 panjang 3 m 2.0000 btg 112,000.00 224,000.00
A. JUMLAH HARGA BAHAN 561,451.43
Tenaga :
Pekerja 0.6600 OH 100,000.00 66,000.00
Tukang besi 0.3300 OH 140,000.00 46,200.00
Kepala Tukang 0.0330 OH 150,000.00 4,950.00
Mandor 0.0330 OH 165,000.00 5,445.00
B. JUMLAH UPAH 122,595.00
C. JUMLAH BAHAN DAN UPAH 684,046.43
D. Overhead + Profit (10%) 68,404.64
E. Total 752,451.07
13 SNI 7394-2008 (6.23)
MEMASANG 1 M2 BEKESTING UNTUK BALOK
Bahan :
Kayu papan 0.0400 M3 5,600,000.00 224,000.00
Paku campur 0.4000 Kg 73,628.57 29,451.43
Minyak Bekisting 0.2000 ltr - -
Kayu balok 0.0150 M3 5,600,000.00 84,000.00
Tripleks 6 mm 0.3500 lbr - -
Balok 5/10 panjang 3 m 2.0000 btg 112,000.00 224,000.00
A. JUMLAH HARGA BAHAN 561,451.43
Tenaga :
Pekerja 0.6600 OH 100,000.00 66,000.00
Tukang besi 0.3300 OH 140,000.00 46,200.00
Kepala Tukang 0.0330 OH 150,000.00 4,950.00
Mandor 0.0330 OH 165,000.00 5,445.00
B. JUMLAH UPAH 122,595.00
C. JUMLAH BAHAN DAN UPAH 684,046.43
D. Overhead + Profit (10%) 68,404.64
E. Total 752,451.07
14 SNI 7394-2008 (6.24)
MEMASANG 1 M2 BEKESTING UNTUK LANTAI
Bahan :
Kayu papan 0.0400 M3 5,600,000.00 224,000.00
Paku campur 0.4000 Kg 73,628.57 29,451.43
Minyak Bekisting 0.2000 ltr - -
Kayu balok 0.0150 M3 5,600,000.00 84,000.00
Tripleks 6 mm 0.3500 lbr 496,828.57 173,890.00
Balok 5/10 panjang 3 m 6.0000 btg 112,000.00 672,000.00
A. JUMLAH HARGA BAHAN 1,183,341.43
Tenaga :

ARSIP SNI 2008 - 31


HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN INDEKS SATUAN
(Rp) (Rp)
Pekerja 0.6600 OH 100,000.00 66,000.00
Tukang besi 0.3300 OH 140,000.00 46,200.00
Kepala Tukang 0.0330 OH 150,000.00 4,950.00
Mandor 0.0330 OH 165,000.00 5,445.00
B. JUMLAH UPAH 122,595.00
C. JUMLAH BAHAN DAN UPAH 1,305,936.43
D. Overhead + Profit (10%) 130,593.64
E. Total 1,436,530.07
15 SNI 7394-2008 (6.25)
MEMASANG 1 M2 BEKESTING UNTUK DINDING
Bahan :
Kayu papan 0.0300 M3 5,600,000.00 168,000.00
Paku campur 0.4000 Kg 73,628.57 29,451.43
Minyak Bekisting 0.2000 ltr - -
Kayu balok 0.0200 M3 5,600,000.00 112,000.00
Tripleks 6 mm 0.3500 lbr 496,828.57 173,890.00
Balok 5/10 panjang 3 m 3.0000 btg 112,000.00 336,000.00
Formite/penjaga Jarak Bekisting/Spacer 4.0000 BH - -
A. JUMLAH HARGA BAHAN 819,341.43
Tenaga :
Pekerja 0.6600 OH 100,000.00 66,000.00
Tukang besi 0.3300 OH 140,000.00 46,200.00
Kepala Tukang 0.0330 OH 150,000.00 4,950.00
Mandor 0.0330 OH 165,000.00 5,445.00
B. JUMLAH UPAH 122,595.00
C. JUMLAH BAHAN DAN UPAH 941,936.43
D. Overhead + Profit (10%) 94,193.64
E. Total 1,036,130.07
16 Permen PU No. 11/PRT/M/2013 (B.35)
MEMBONGKAR BEKESTING 1 M2 SECARA BIASA DAN MEMBERESKAN PUING-PUING
Tenaga :
Pekerja 0.0400 OH 100,000.00 4,000.00
Mandor 0.0040 OH 165,000.00 660.00
A. JUMLAH UPAH 4,660.00
B. Overhead + Profit (10%) 466.00
C. Total 5,126.00
17 Permen PU No. 11/PRT/M/2013 (B.36)
MEMBONGKAR BEKESTING 1 M2 SECARA HATI-HATI ( UNTUK PENGGUNAAN KEMBALI)
Tenaga :
Pekerja 0.1000 OH 100,000.00 10,000.00
Mandor 0.0100 OH 165,000.00 1,650.00
A. JUMLAH UPAH 11,650.00
B. Overhead + Profit (10%) 1,165.00
C. Total 12,815.00
18 SNI 7394-2008 (6.35)
MEMBUAT 1 M' KOLOM PRAKTIS BETON BERTULANG (10 X 10 CM)
Bahan :
Kayu papan 0.0020 M3 5,600,000.00 11,200.00
Paku campur 0.0100 Kg 73,628.57 736.29
Besi Beton polos 3.0000 Kg 66,728.57 200,185.71
Kawat ikat 0.4500 Kg 76,728.57 34,527.86
Semen PC 4.0000 Kg 48,028.57 192,114.28
Pasir cor 0.0060 M3 2,000,000.00 12,000.00
Kerikil pecah 0.0090 M3 2,500,000.00 22,500.00
A. JUMLAH HARGA BAHAN 473,264.13
Tenaga :
Pekerja 0.1800 OH 100,000.00 18,000.00
Tukang batu 0.0200 OH 140,000.00 2,800.00
Tukang Kayu 0.0200 OH 140,000.00 2,800.00
Tukang Besi 0.0200 OH 140,000.00 2,800.00
Kepala Tukang 0.0060 OH 150,000.00 900.00
Mandor 0.0090 OH 165,000.00 1,485.00
B. JUMLAH UPAH 28,785.00
C. JUMLAH BAHAN DAN UPAH 502,049.13
D. Overhead + Profit (10%) 50,204.91
E. Total 552,254.05
19 SNI 7394-2008 (6.35)
MEMBUAT 1 M' RINGBALOK BETON BERTULANG (10 X 15 CM)
Bahan :

ARSIP SNI 2008 - 32


HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN INDEKS SATUAN
(Rp) (Rp)
Kayu papan 0.0030 M3 5,600,000.00 16,800.00
Paku campur 0.0200 Kg 73,628.57 1,472.57
Besi Beton polos 3.6000 Kg 66,728.57 240,222.85
Kawat ikat 0.0500 Kg 76,728.57 3,836.43
Semen PC 5.5000 Kg 48,028.57 264,157.14
Pasir cor 0.0090 M3 2,000,000.00 18,000.00
Kerikil pecah 0.0150 M3 2,500,000.00 37,500.00
A. JUMLAH HARGA BAHAN 581,988.99
Tenaga :
Pekerja 0.2970 OH 100,000.00 29,700.00
Tukang batu 0.0330 OH 140,000.00 4,620.00
Tukang Kayu 0.0330 OH 140,000.00 4,620.00
Tukang Besi 0.0330 OH 140,000.00 4,620.00
Kepala Tukang 0.0100 OH 150,000.00 1,500.00
Mandor 0.0150 OH 165,000.00 2,475.00
B. JUMLAH UPAH 47,535.00
C. JUMLAH BAHAN DAN UPAH 629,523.99
D. Overhead + Profit (10%) 62,952.40
E. Total 692,476.39
F. PEKERJAAN DINDING SNI 6897 - 2008
1 SNI 6897 - 2008 (6.7)
MEMASANG 1 M2 DINDING BATA MERAH UKURAN (5 X 11 X 22) CM TEBAL 1 BATA, CAMPURAN SPESI 1 PC : 2 PP
Bahan :
Bata Merah 140.0000 Bh #N/A #N/A
Semen PC 43.5000 Kg 48,028.57 2,089,242.80
Pasir Pasang 0.0800 M3 2,000,000.00 160,000.00
A. JUMLAH HARGA BAHAN #N/A
Tenaga :
Pekerja 0.3000 OH 100,000.00 30,000.00
Tukang Batu 0.1000 OH 140,000.00 14,000.00
Kepala Tukang 0.0100 OH 150,000.00 1,500.00
Mandor 0.0150 OH 165,000.00 2,475.00
B. JUMLAH UPAH 47,975.00
C. JUMLAH BAHAN DAN UPAH #N/A
D. Overhead + Profit (10%) #N/A
E. Total #N/A
2 SNI 6897 - 2008 (6.8)
MEMASANG 1 M2 DINDING BATA MERAH UKURAN (5 X 11 X 22) CM TEBAL 1 BATA, CAMPURAN SPESI 1 PC : 3 PP
Bahan :
Bata Merah 140.0000 Bh #N/A #N/A
Semen PC 32.9500 Kg 48,028.57 1,582,541.38
Pasir Pasang 0.0910 M3 2,000,000.00 182,000.00
A. JUMLAH HARGA BAHAN #N/A
Tenaga :
Pekerja 0.6000 OH 100,000.00 60,000.00
Tukang Batu 0.2000 OH 140,000.00 28,000.00
Kepala Tukang 0.0200 OH 150,000.00 3,000.00
Mandor 0.0300 OH 165,000.00 4,950.00
B. JUMLAH UPAH 95,950.00
C. JUMLAH BAHAN DAN UPAH #N/A
D. Overhead + Profit (10%) #N/A
E. Total #N/A
3 SNI 6897 - 2008 (6.9)
MEMASANG 1 M2 DINDING BATAKO (9 X 14 X 29) CM , CAMPURAN SPESI 1 PC : 4 PP
Bahan :
Batu batako 25.0000 Bh 50,798.56 1,269,964.00
Semen PC 7.9150 Kg 48,028.57 380,146.13
Pasir Pasang 0.0250 M3 2,000,000.00 50,000.00
A. JUMLAH HARGA BAHAN 1,700,110.13
Tenaga :
Pekerja 0.6000 OH 100,000.00 60,000.00
Tukang Batu 0.2000 OH 140,000.00 28,000.00
Kepala Tukang 0.0200 OH 150,000.00 3,000.00
Mandor 0.0300 OH 165,000.00 4,950.00
B. JUMLAH UPAH 95,950.00
C. JUMLAH BAHAN DAN UPAH 1,796,060.13
D. Overhead + Profit (10%) 179,606.01
E. Total 1,975,666.14

ARSIP SNI 2008 - 33


HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN INDEKS SATUAN
(Rp) (Rp)
G. PEKERJAAN KAYU SNI 3434 - 2008

1 SNI 3434 - 2008 (6.2)


MEMBUAT DAN MEMASANG 1 M3 KOSEN PINTU DAN KOSEN JENDELA KAYU KELAS II DAN III
Bahan :
Kayu Balok 1.2000 M3 5,600,000.00 6,720,000.00
Paku campur 1.2500 Kg 73,628.57 92,035.71
Lem kayu 1.0000 Kg 92,828.57 92,828.57
A. JUMLAH HARGA BAHAN 6,904,864.28
Tenaga :
Pekerja 6.0000 OH 100,000.00 600,000.00
Tukang Kayu 18.0000 OH 140,000.00 2,520,000.00
Kepala Tukang 1.8000 OH 150,000.00 270,000.00
Mandor 0.3000 OH 165,000.00 49,500.00
B. JUMLAH UPAH 3,439,500.00
C. JUMLAH BAHAN DAN UPAH 10,344,364.28
D. Overhead + Profit (10%) 1,034,436.43
E. Total 11,378,800.71
2 SNI 3434 - 2008 (6.5)
MEMBUAT DAN MEMASANG 1 M2 DAUN PINTU PANEEL KELAS I ATAU II
Bahan :
Kayu Papan 0.0400 M3 5,600,000.00 224,000.00
Lem kayu 0.5000 Kg 92,828.57 46,414.29
A. JUMLAH HARGA BAHAN 270,414.29
Tenaga :
Pekerja 1.0000 OH 100,000.00 100,000.00
Tukang Kayu 3.0000 OH 140,000.00 420,000.00
Kepala Tukang 0.3000 OH 150,000.00 45,000.00
Mandor 0.0500 OH 165,000.00 8,250.00
B. JUMLAH UPAH 573,250.00
C. JUMLAH BAHAN DAN UPAH 843,664.29
D. Overhead + Profit (10%) 84,366.43
E. Total 928,030.71
3 SNI 3434 - 2008 (6.6)
MEMBUAT DAN MEMASANG 1 M2 PINTU DAN JENDELA KACA
Bahan :
Kayu Papan 0.0240 M3 5,600,000.00 134,400.00
Kaca bening 5 mm 0.7100 M2 819,141.43 581,590.42
Lem kayu 0.3000 Kg 92,828.57 27,848.57
A. JUMLAH HARGA BAHAN 743,838.99
Tenaga :
Pekerja 0.8000 OH 100,000.00 80,000.00
Tukang Kayu 2.4000 OH 140,000.00 336,000.00
Kepala Tukang 0.2400 OH 150,000.00 36,000.00
Mandor 0.0400 OH 165,000.00 6,600.00
B. JUMLAH UPAH 458,600.00
C. JUMLAH BAHAN DAN UPAH 1,202,438.99
D. Overhead + Profit (10%) 120,243.90
E. Total 1,322,682.88
SNI 3434 - 2008 (6.10)
MEMASANG 1 M2 JALUSI KOSEN, KAYU KELAS I ATAU II
Bahan :
Kayu Papan 0.0600 M3 5,600,000.00 336,000.00
Paku tripleks 0.1500 Kg 76,228.57 11,434.29
A. JUMLAH HARGA BAHAN 347,434.29
Tenaga :
Pekerja 0.6700 OH 100,000.00 67,000.00
Tukang Kayu 2.0000 OH 140,000.00 280,000.00
Kepala Tukang 0.2000 OH 150,000.00 30,000.00
Mandor 0.3350 OH 165,000.00 55,275.00
B. JUMLAH UPAH 432,275.00
C. JUMLAH BAHAN DAN UPAH 779,709.29
D. Overhead + Profit (10%) 77,970.93
E. Total 857,680.21
4 SNI 3434 - 2008 (6.13)
MEMASANG 1 M3 KONSTRUKSI KUDA-KUDA KONVENSIONAL
Bahan :
Kayu balok 1.1000 M3 5,600,000.00 6,160,000.00
Besi strip tebal 5 mm *) 15.0000 Kg - -

ARSIP SNI 2008 - 34


HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN INDEKS SATUAN
(Rp) (Rp)
Paku campur 5.6000 Kg 73,628.57 412,319.99
A. JUMLAH HARGA BAHAN 6,572,319.99
Tenaga :
Pekerja 4.0000 OH 100,000.00 400,000.00
Tukang Kayu 12.0000 OH 140,000.00 1,680,000.00
Kepala Tukang 1.2000 OH 150,000.00 180,000.00
Mandor 0.2000 OH 165,000.00 33,000.00
B. JUMLAH UPAH 2,293,000.00
C. JUMLAH BAHAN DAN UPAH 8,865,319.99
D. Overhead + Profit (10%) 886,532.00
E. Total 9,751,851.99
5 SNI 3434 - 2008 (6.15)
MEMASANG 1 M3 KONSTRUKSI GORDING
Bahan :
Kayu balok 1.1000 M3 5,600,000.00 6,160,000.00
Besi strip tebal 5 mm *) 15.0000 Kg - -
Paku campur 3.0000 Kg 73,628.57 220,885.71
A. JUMLAH HARGA BAHAN 6,380,885.71
Tenaga :
Pekerja 2.4000 OH 100,000.00 240,000.00
Tukang Kayu 7.2000 OH 140,000.00 1,008,000.00
Kepala Tukang 0.7200 OH 150,000.00 108,000.00
Mandor 0.1200 OH 165,000.00 19,800.00
B. JUMLAH UPAH 1,375,800.00
C. JUMLAH BAHAN DAN UPAH 7,756,685.71
D. Overhead + Profit (10%) 775,668.57
E. Total 8,532,354.28
6 SNI 3434 - 2008 (6.19)
MEMASANG 1 M2 RANGKA LANGIT-LANGIT (50 X 100 CM)
Bahan :
Kayu balok 0.0120 M3 5,600,000.00 67,200.00
Paku campur 0.1000 Kg 73,628.57 7,362.86
A. JUMLAH HARGA BAHAN 74,562.86
Tenaga :
Pekerja 0.1500 OH 100,000.00 15,000.00
Tukang Kayu 0.2500 OH 140,000.00 35,000.00
Kepala Tukang 0.0250 OH 150,000.00 3,750.00
Mandor 0.0750 OH 165,000.00 12,375.00
B. JUMLAH UPAH 66,125.00
C. JUMLAH BAHAN DAN UPAH 140,687.86
D. Overhead + Profit (10%) 14,068.79
E. Total 154,756.64
7 SNI 3434 - 2008 (6.20)
MEMASANG 1 M2 RANGKA LANGIT-LANGIT (60 X 60 CM)
Bahan :
Kayu balok 0.0163 M3 5,600,000.00 91,280.00
Paku campur 0.2500 Kg 73,628.57 18,407.14
A. JUMLAH HARGA BAHAN 109,687.14
Tenaga :
Pekerja 0.2000 OH 100,000.00 20,000.00
Tukang Kayu 0.3000 OH 140,000.00 42,000.00
Kepala Tukang 0.0300 OH 150,000.00 4,500.00
Mandor 0.0100 OH 165,000.00 1,650.00
B. JUMLAH UPAH 68,150.00
C. JUMLAH BAHAN DAN UPAH 177,837.14
D. Overhead + Profit (10%) 17,783.71
E. Total 195,620.86
8 SNI 3434 - 2008 (6.21)
MEMASANG 1 M' LISTPLANK UKURAN (3 x 20) CM KAYU KELAS I ATAU II
Bahan :
Kayu Papan 0.0108 M3 5,600,000.00 60,480.00
Paku campur 0.1000 Kg 73,628.57 7,362.86
A. JUMLAH HARGA BAHAN 67,842.86
Tenaga :
Pekerja 0.1000 OH 100,000.00 10,000.00
Tukang Kayu 0.2000 OH 140,000.00 28,000.00
Kepala Tukang 0.0200 OH 150,000.00 3,000.00
Mandor 0.0050 OH 165,000.00 825.00
B. JUMLAH UPAH 41,825.00

ARSIP SNI 2008 - 35


HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN INDEKS SATUAN
(Rp) (Rp)
C. JUMLAH BAHAN DAN UPAH 109,667.86
D. Overhead + Profit (10%) 10,966.79
E. Total 120,634.64
SNI 3434 - 2008 (6.22)
MEMASANG 1 M' LISTPLANK UKURAN (2,5 x 30) CM KAYU KELAS I ATAU II
Bahan :
Kayu Papan 0.0135 M3 5,600,000.00 75,600.00
Paku campur 0.1000 Kg 73,628.57 7,362.86
A. JUMLAH HARGA BAHAN 82,962.86
Tenaga :
Pekerja 0.1000 OH 100,000.00 10,000.00
Tukang Kayu 0.2000 OH 140,000.00 28,000.00
Kepala Tukang 0.0200 OH 150,000.00 3,000.00
Mandor 0.0050 OH 165,000.00 825.00
B. JUMLAH UPAH 41,825.00
C. JUMLAH BAHAN DAN UPAH 124,787.86
D. Overhead + Profit (10%) 12,478.79
E. Total 137,266.64
SNI 3434 - 2008 (6.22)
MEMASANG 1 M' LISTPLANK UKURAN (3x30) CM
Bahan :
Kayu Papan 0.0162 M3 5,600,000.00 90,720.00
Paku campur 0.1000 Kg 73,628.57 7,362.86
A. JUMLAH HARGA BAHAN 98,082.86
Tenaga :
Pekerja 0.1000 OH 100,000.00 10,000.00
Tukang Kayu 0.2000 OH 140,000.00 28,000.00
Kepala Tukang 0.0200 OH 150,000.00 3,000.00
Mandor 0.0050 OH 165,000.00 825.00
B. JUMLAH UPAH 41,825.00
C. JUMLAH BAHAN DAN UPAH 139,907.86
D. Overhead + Profit (10%) 13,990.79
E. Total 153,898.64
SNI 3434 - 2008 (6.26)
MEMASANG 1 M2 DINDING LAMRIZEERING DARI PAPAN
Bahan :
Kayu Papan 0.0070 M3 5,600,000.00 39,200.00
Paku campur 0.1000 Kg 73,628.57 7,362.86
A. JUMLAH HARGA BAHAN 46,562.86
Tenaga :
Pekerja 0.6000 OH 100,000.00 60,000.00
Tukang Kayu 1.8000 OH 140,000.00 252,000.00
Kepala Tukang 0.1800 OH 150,000.00 27,000.00
Mandor 0.0300 OH 165,000.00 4,950.00
B. JUMLAH UPAH 343,950.00
C. JUMLAH BAHAN DAN UPAH 390,512.86
D. Overhead + Profit (10%) 39,051.29
E. Total 429,564.14
SNI 3434 - 2008 (6.26)
MEMASANG 1 M2 DINDING PAPAN 2/20
Bahan :
Kayu Papan 0.0063 M3 5,600,000.00 35,000.00
Paku campur 0.1000 Kg 73,628.57 7,362.86
A. JUMLAH HARGA BAHAN 42,362.86
Tenaga :
Pekerja 0.6000 OH 100,000.00 60,000.00
Tukang Kayu 1.8000 OH 140,000.00 252,000.00
Kepala Tukang 0.1800 OH 150,000.00 27,000.00
Mandor 0.0300 OH 165,000.00 4,950.00
B. JUMLAH UPAH 343,950.00
C. JUMLAH BAHAN DAN UPAH 386,312.86
D. Overhead + Profit (10%) 38,631.29
E. Total 424,944.14
H. PEKERJAAN PENUTUP ATAP SNI 2002
1 SNI 2002 (6.38)
MEMASANG 1 M2 ATAP SENG GELOMBANG
Bahan :
Seng Gelombang BJLS 20 0.7000 Lbr 205,385.71 143,770.00
Paku seng 0.0200 Kg 79,128.57 1,582.57

ARSIP SNI 2008 - 36


HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN INDEKS SATUAN
(Rp) (Rp)
A. JUMLAH HARGA BAHAN 145,352.57
Tenaga :
Pekerja 0.1200 OH 100,000.00 12,000.00
Tukang Kayu 0.0600 OH 140,000.00 8,400.00
Kepala Tukang 0.0060 OH 150,000.00 900.00
Mandor 0.0060 OH 165,000.00 990.00
B. JUMLAH UPAH 22,290.00
C. JUMLAH BAHAN DAN UPAH 167,642.57
D. Overhead + Profit (10%) 16,764.26
E. Total 184,406.83
2 SNI 2002 (6.39)
MEMASANG 1 M NOK ATAP SENG
Bahan :
Seng Plat BJLS 20 0.3000 Lbr 211,985.71 63,595.71
Paku seng 0.0400 Kg 79,128.57 3,165.14
A. JUMLAH HARGA BAHAN 66,760.86
Tenaga :
Pekerja 0.1500 OH 100,000.00 15,000.00
Tukang Kayu 0.0700 OH 140,000.00 9,800.00
Kepala Tukang 0.0080 OH 150,000.00 1,200.00
Mandor 0.0060 OH 165,000.00 990.00
B. JUMLAH UPAH 26,990.00
C. JUMLAH BAHAN DAN UPAH 93,750.86
D. Overhead + Profit (10%) 9,375.09
E. Total 103,125.94
I. PEKERJAAN LANGIT-LANGIT SNI 2839 - 2008
1 SNI 7395 - 2008 (6.5)
MEMASANG 1 M2 LANGIT-LANGIT TRIPLEKS UKURAN (120 X 240) CM, TEBAL 3 MM
Bahan :
Tripleks 3 mm 0.3750 Lbr 317,942.86 119,228.57
Paku tripleks 0.0300 Kg 76,228.57 2,286.86
A. JUMLAH HARGA BAHAN 121,515.43
Tenaga :
Pekerja 0.1000 OH 100,000.00 10,000.00
Tukang Kayu 0.1000 OH 140,000.00 14,000.00
Kepala Tukang 0.0100 OH 150,000.00 1,500.00
Mandor 0.0050 OH 165,000.00 825.00
B. JUMLAH UPAH 26,325.00
C. JUMLAH BAHAN DAN UPAH 147,840.43
D. Overhead + Profit (10%) 14,784.04
E. Total 162,624.47
2 SNI 7395 - 2008 (6.5)
MEMASANG 1 M' LIST LANGIT-LANGIT KAYU PROFIL
Bahan :
List Kayu Profil 1/3 cm pjg 4m 1.0500 m 19,250.00 20,212.50
Paku tripleks 0.0100 Kg 76,228.57 762.29
A. JUMLAH HARGA BAHAN 20,974.79
Tenaga :
Pekerja 0.0500 OH 100,000.00 5,000.00
Tukang kayu 0.0500 OH 140,000.00 7,000.00
Kepala Tukang 0.0050 OH 150,000.00 750.00
Mandor 0.0030 OH 165,000.00 495.00
B. JUMLAH UPAH 13,245.00
C. JUMLAH BAHAN DAN UPAH 34,219.79
D. Overhead + Profit (10%) 3,421.98
E. Total 37,641.76
J. PEKERJAAN BESI DAN ALUMINIUM SNI 7393 - 2008

1 SNI 7393 - 2008 (6.1)


MEMASANG 1 KG BESI POLOS
Bahan :
Besi beton polos 1.1500 Kg 66,728.57 76,737.86
A. JUMLAH HARGA BAHAN 76,737.86
Tenaga :
Pekerja 0.0600 OH 100,000.00 6,000.00
Tukang Las 0.0600 OH 140,000.00 8,400.00
Kepala Tukang 0.0060 OH 150,000.00 900.00
Mandor 0.0030 OH 165,000.00 495.00
B. JUMLAH UPAH 15,795.00

ARSIP SNI 2008 - 37


HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN INDEKS SATUAN
(Rp) (Rp)
C. JUMLAH BAHAN DAN UPAH 92,532.86
D. Overhead + Profit (10%) 9,253.29
E. Total 101,786.14
2 SNI 7393 - 2008 (6.1)
MEMASANG 1 KG BESI STRIP
Bahan :
Besi strip 20.2 mm panjang 6 m (1,86 kg) 1.1500 Kg 73,808.08 84,879.29
A. JUMLAH HARGA BAHAN 84,879.29
Tenaga :
Pekerja 0.0600 OH 100,000.00 6,000.00
Tukang Las 0.0600 OH 140,000.00 8,400.00
Kepala Tukang 0.0060 OH 150,000.00 900.00
Mandor 0.0030 OH 165,000.00 495.00
B. JUMLAH UPAH 15,795.00
C. JUMLAH BAHAN DAN UPAH 100,674.29
D. Overhead + Profit (10%) 10,067.43
E. Total 110,741.72
3 SNI 7393 - 2008 (6.1)
MEMASANG 1 KG BESI PROFIL C 65.42 MM
Bahan :
Besi profil C 65.42 mm panjang 6 m (42,54 kg) 1.1500 Kg 67,465.91 77,585.80
A. JUMLAH HARGA BAHAN 77,585.80
Tenaga :
Pekerja 0.0600 OH 100,000.00 6,000.00
Tukang Las 0.0600 OH 140,000.00 8,400.00
Kepala Tukang 0.0060 OH 150,000.00 900.00
Mandor 0.0030 OH 165,000.00 495.00
B. JUMLAH UPAH 15,795.00
C. JUMLAH BAHAN DAN UPAH 93,380.80
D. Overhead + Profit (10%) 9,338.08
E. Total 102,718.88

4 SNI 7393 - 2008 (6.1)


MEMASANG 1 KG BESI PROFIL L 50.50.5 MM
Bahan :
Besi siku 50.50.5 mm panjang 6 m (22,62 kg) 1.1500 Kg 62,159.06 71,482.92
A. JUMLAH HARGA BAHAN 71,482.92
Tenaga :
Pekerja 0.0600 OH 100,000.00 6,000.00
Tukang Las 0.0600 OH 140,000.00 8,400.00
Kepala Tukang 0.0060 OH 150,000.00 900.00
Mandor 0.0030 OH 165,000.00 495.00
B. JUMLAH UPAH 15,795.00
C. JUMLAH BAHAN DAN UPAH 87,277.92
D. Overhead + Profit (10%) 8,727.79
E. Total 96,005.71

5 SNI 7393 - 2008 (6.1)


MEMASANG 1 KG BESI PROFIL C 80.50 MM
Bahan :
Besi profil C 80.50 mm panjang 6 m (51,78 kg) 1.1500 Kg #N/A #N/A
A. JUMLAH HARGA BAHAN #N/A
Tenaga :
Pekerja 0.0600 OH 100,000.00 6,000.00
Tukang Las 0.0600 OH 140,000.00 8,400.00
Kepala Tukang 0.0060 OH 150,000.00 900.00
Mandor 0.0030 OH 165,000.00 495.00
B. JUMLAH UPAH 15,795.00
C. JUMLAH BAHAN DAN UPAH #N/A
D. Overhead + Profit (10%) #N/A
E. Total #N/A

6 SNI 7393 - 2008 (6.3)


MENGERJAKAN 100 KG PERAKITAN
Bahan :
Solar 1.0000 Ltr 55,128.57 55,128.57
Minyak pelumas 0.1000 Ltr 77,428.57 7,742.86
A. JUMLAH HARGA BAHAN 62,871.43
Tenaga :

ARSIP SNI 2008 - 38


HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN INDEKS SATUAN
(Rp) (Rp)
Pekerja 0.1000 OH 100,000.00 10,000.00
Tukang Las 0.1000 OH 140,000.00 14,000.00
Kepala Tukang 0.0010 OH 150,000.00 150.00
Mandor 0.0050 OH 165,000.00 825.00
B. JUMLAH UPAH 24,975.00
sewa genset 0.8000 Jam 115,000.00 92,000.00
C. JUMLAH ALAT 92,000.00
D. JUMLAH BAHAN, UPAH, DAN ALAT 179,846.43
E. Overhead + Profit (10%) 17,984.64
F. Total 197,831.07
G. Total harga untuk 1 kg 1,978.31
7 SNI 7393 - 2008 (6.4)
MEMBUAT 1 M2 PINTU PLAT BAJA TEBAL 2 MM RANGKAP, RANGKA BAJA SIKU
Bahan :
Besi Siku 30.30.3 mm panjang 6 m (8,16 kg) 15.0000 Kg 73,562.94 1,103,444.17
Besi plat 2 mm 32.8000 Kg 74,133.15 2,431,567.28
Kawat las 0.0500 Kg 95,148.57 4,757.43
A. JUMLAH HARGA BAHAN 3,539,768.88
Tenaga :
Pekerja 1.0500 OH 100,000.00 105,000.00
Tukang Las 1.0500 OH 140,000.00 147,000.00
Kepala Tukang 0.1050 OH 150,000.00 15,750.00
Mandor 0.0520 OH 165,000.00 8,580.00
B. JUMLAH UPAH 276,330.00
sewa mesin las listrik 0.1700 Jam #N/A #N/A
C. JUMLAH ALAT #N/A
D. JUMLAH BAHAN, UPAH, DAN ALAT #N/A
E. Overhead + Profit (10%) #N/A
F. Total #N/A
8 SNI 7393 - 2008 (6.5)
MENGERJAKAN 10 CM PENGELASAN DENGAN LAS LISTRIK
Bahan :
Kawat las 0.4000 Kg 95,148.57 38,059.43
Solar 0.3000 Ltr - -
Minyak pelumas 0.0400 Ltr - -
A. JUMLAH HARGA BAHAN 38,059.43
Tenaga :
Pekerja 0.0400 OH 100,000.00 4,000.00
Tukang Las 0.0200 OH 140,000.00 2,800.00
Kepala Tukang 0.0020 OH 150,000.00 300.00
Mandor 0.0020 OH 165,000.00 330.00
B. JUMLAH UPAH 7,430.00
Sewa mesin las listrik 0.1700 Jam #N/A #N/A
C. JUMLAH ALAT #N/A
D. JUMLAH BAHAN, UPAH, DAN ALAT #N/A
E. Overhead + Profit (10%) #N/A
F. Total #N/A
G. Total harga untuk 1 cm #N/A
9 SNI 7393 - 2008 (6.12)
MEMASANG 1 M2 KAWAT HARMONIKA
Bahan :
Kawat Harmonika lbr 1,5 m 0.7500 M' #N/A #N/A
Paku Tripleks 0.0200 Kg 76,228.57 1,524.57
Kayu papan 0.0018 M3 5,600,000.00 10,080.00
A. JUMLAH HARGA BAHAN #N/A
Tenaga :
Pekerja 0.1000 OH 100,000.00 10,000.00
Tukang Kayu 0.1000 OH 140,000.00 14,000.00
Kepala Tukang 0.0100 OH 150,000.00 1,500.00
Mandor 0.0005 OH 165,000.00 82.50
B. JUMLAH UPAH 25,582.50
C. JUMLAH BAHAN DAN UPAH #N/A
D. Overhead + Profit (10%) #N/A
E. Total #N/A
10 SNI 7393 - 2008 (6.18)
MEMASANG 1 M TALANG DATAR/JURAI SENG BJLS 0.25 LEBAR 45 CM
Bahan :
Seng Plat BJLS 20 1.0500 M 211,985.71 222,585.00
Paku Tripleks 0.0150 Kg 76,228.57 1,143.43

ARSIP SNI 2008 - 39


HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN INDEKS SATUAN
(Rp) (Rp)
Kayu papan 0.0096 M3 5,600,000.00 53,760.00
A. JUMLAH HARGA BAHAN 277,488.42
Tenaga :
Pekerja 0.1500 OH 100,000.00 15,000.00
Tukang Kayu 0.3000 OH 140,000.00 42,000.00
Kepala Tukang 0.0300 OH 150,000.00 4,500.00
Mandor 0.0080 OH 165,000.00 1,320.00
B. JUMLAH UPAH 62,820.00
C. JUMLAH BAHAN DAN UPAH 340,308.42
D. Overhead + Profit (10%) 34,030.84
E. Total 374,339.27
K. PEKERJAAN KUNCI, ALAT GANTUNGAN DAN KACA SNI 03-3437- 2002
SNI-03-3437-2002 (1)
1 PASANG 1 BUAH KUNCI TANAM ANTIK
Bahan :
Kunci tanam 2 slaag (besar) 1.0000 Bh 317,119.64 317,119.64
A. JUMLAH HARGA BAHAN 317,119.64
Tenaga :
Pekerja 0.0600 OH 100,000.00 6,000.00
Tukang kayu 0.6000 OH 140,000.00 84,000.00
Kepala tukang 0.0600 OH 150,000.00 9,000.00
Mandor 0.0030 OH 165,000.00 495.00
B. JUMLAH UPAH 99,495.00
C. JUMLAH BAHAN DAN UPAH 416,614.64
D. Overhead + Profit (10%) 41,661.46
E. Total 458,276.10
2 SNI-03-3437-2002 (2)
PASANG 1 BUAH KUNCI TANAM BIASA
Bahan :
Kunci tanam 2 slaag (kecil) 1.0000 Bh 251,866.07 251,866.07
A. JUMLAH HARGA BAHAN 251,866.07
Tenaga :
Pekerja 0.0100 OH 100,000.00 1,000.00
Tukang kayu 0.5000 OH 140,000.00 70,000.00
Kepala tukang 0.0100 OH 150,000.00 1,500.00
Mandor 0.0050 OH 165,000.00 825.00
B. JUMLAH UPAH 73,325.00
C. JUMLAH BAHAN DAN UPAH 325,191.07
D. Overhead + Profit (10%) 32,519.11
E. Total 357,710.18
3 SNI-03-3437-2002 (5)
PASANG 1 BUAH ENGSEL PINTU
Bahan :
Engsel Pintu 1.0000 Bh 53,397.14 53,397.14
A. JUMLAH HARGA BAHAN 53,397.14
Tenaga :
Pekerja 0.0150 OH 100,000.00 1,500.00
Tukang kayu 0.1500 OH 140,000.00 21,000.00
Kepala tukang 0.0150 OH 150,000.00 2,250.00
Mandor 0.00075 OH 165,000.00 123.75
B. JUMLAH UPAH 24,873.75
C. JUMLAH BAHAN DAN UPAH 78,270.89
D. Overhead + Profit (10%) 7,827.09
E. Total 86,097.98
4 SNI-03-3437-2002 (6)
PASANG 1 BUAH ENGSEL JENDELA
Bahan :
Engsel jendela 1.0000 Bh 43,447.86 43,447.86
A. JUMLAH HARGA BAHAN 43,447.86
Tenaga :
Pekerja 0.0100 OH 100,000.00 1,000.00
Tukang kayu 0.1000 OH 140,000.00 14,000.00
Kepala tukang 0.0100 OH 150,000.00 1,500.00
Mandor 0.0005 OH 165,000.00 82.50
B. JUMLAH UPAH 16,582.50
C. JUMLAH BAHAN DAN UPAH 60,030.36
D. Overhead + Profit (10%) 6,003.04
E. Total 66,033.40
5 SNI-03-3437-2002 (9)

ARSIP SNI 2008 - 40


HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN INDEKS SATUAN
(Rp) (Rp)
PASANG 1 BUAH KAIT ANGIN
Bahan :
Hak/kait angin 1.0000 Bh 62,997.14 62,997.14
A. JUMLAH HARGA BAHAN 62,997.14
Tenaga :
Pekerja 0.0150 OH 100,000.00 1,500.00
Tukang kayu 0.1500 OH 140,000.00 21,000.00
Kepala tukang 0.0150 OH 150,000.00 2,250.00
Mandor 0.00075 OH 165,000.00 123.75
B. JUMLAH UPAH 24,873.75
C. JUMLAH BAHAN DAN UPAH 87,870.89
D. Overhead + Profit (10%) 8,787.09
E. Total 96,657.98
6 SNI-03-3437-2002 (9)
PASANG 1 BUAH HANDLE JENDELA
Bahan :
Handle jendela 1.0000 Bh 27,832.86 27,832.86
A. JUMLAH HARGA BAHAN 27,832.86
Tenaga :
Pekerja 0.0150 OH 100,000.00 1,500.00
Tukang kayu 0.1500 OH 140,000.00 21,000.00
Kepala tukang 0.0150 OH 150,000.00 2,250.00
Mandor 0.00075 OH 165,000.00 123.75
B. JUMLAH UPAH 24,873.75
C. JUMLAH BAHAN DAN UPAH 52,706.61
D. Overhead + Profit (10%) 5,270.66
E. Total 57,977.27
7 SNI-03-3437-2002 (11)
PASANG 1 GRENDEL PINTU
Bahan :
Grendel pintu 1.0000 Bh 50,047.86 50,047.86
A. JUMLAH HARGA BAHAN 50,047.86
Tenaga :
Pekerja 0.0200 OH 100,000.00 2,000.00
Tukang kayu 0.2000 OH 140,000.00 28,000.00
Kepala tukang 0.0200 OH 150,000.00 3,000.00
Mandor 0.00100 OH 165,000.00 165.00
B. JUMLAH UPAH 33,165.00
C. JUMLAH BAHAN DAN UPAH 83,212.86
D. Overhead + Profit (10%) 8,321.29
E. Total 91,534.15
8 SNI-03-3437-2002 (11)
PASANG 1 GRENDEL JENDELA
Bahan :
Grendel Jendela 1.0000 Bh 46,173.21 46,173.21
A. JUMLAH HARGA BAHAN 46,173.21
Tenaga :
Pekerja 0.0200 OH 100,000.00 2,000.00
Tukang kayu 0.2000 OH 140,000.00 28,000.00
Kepala tukang 0.0200 OH 150,000.00 3,000.00
Mandor 0.00100 OH 165,000.00 165.00
B. JUMLAH UPAH 33,165.00
C. JUMLAH BAHAN DAN UPAH 79,338.21
D. Overhead + Profit (10%) 7,933.82
E. Total 87,272.03
9 SNI-03-3437-2002 (16)
1 M2 PASANG KACA POLOS TEBAL 3 MM
Bahan :
Kaca bening 3 mm 1.1000 M2 #N/A #N/A
A. JUMLAH HARGA BAHAN #N/A
Tenaga :
Pekerja 0.1500 OH 100,000.00 15,000.00
Tukang kayu 0.1500 OH 140,000.00 21,000.00
Kepala tukang 0.0150 OH 150,000.00 2,250.00
Mandor 0.00075 OH 165,000.00 123.75
B. JUMLAH UPAH 38,373.75
C. JUMLAH BAHAN DAN UPAH #N/A
D. Overhead + Profit (10%) #N/A
E. Total #N/A

ARSIP SNI 2008 - 41


HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN INDEKS SATUAN
(Rp) (Rp)
10 SNI-03-3437-2002 (17)
1 M2 PASANG KACA POLOS TEBAL 5 MM
Bahan :
Kaca bening 5 mm 1.1000 M2 819,141.43 901,055.57
A. JUMLAH HARGA BAHAN 901,055.57
Tenaga :
Pekerja 0.1500 OH 100,000.00 15,000.00
Tukang kayu 0.1500 OH 140,000.00 21,000.00
Kepala tukang 0.0150 OH 150,000.00 2,250.00
Mandor 0.00075 OH 165,000.00 123.75
B. JUMLAH UPAH 38,373.75
C. JUMLAH BAHAN DAN UPAH 939,429.32
D. Overhead + Profit (10%) 93,942.93
E. Total 1,033,372.26
L. PEKERJAAN PENGECATAN DAN FINISHING DINDING SNI 03-2842-2002

1 SNI 2842-2002 (6.8)


1 M2 PENGECATAN BIDANG KAYU BARU ( 1 lapis dempul, 1 lapis cat dasar, 2 lapis cat penutup)
Bahan :
Meni kayu 0.2000 Kg 81,328.57 16,265.71
Dempul Kayu 0.1500 Kg 74,828.57 11,224.29
Cat kayu 0.4300 Kg 126,028.57 54,192.29
A. JUMLAH HARGA BAHAN 81,682.28
Tenaga :
Pekerja 0.0700 OH 100,000.00 7,000.00
Tukang cat 0.0090 OH 140,000.00 1,260.00
Kepala Tukang 0.0060 OH 150,000.00 900.00
Mandor 0.0025 OH 165,000.00 412.50
B. JUMLAH UPAH 9,572.50
C. JUMLAH BAHAN DAN UPAH 91,254.78
D. Overhead + Profit (10%) 9,125.48
E. Total 100,380.26
2 SNI 2842-2002 (6.14)
1 M2 PENGECATAN BIDANG TEMBOK BARU ( 1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup)
Bahan :
Plamur tembok 0.1000 Kg 66,728.57 6,672.86
Cat tembok 0.3600 Kg 62,628.57 22,546.29
A. JUMLAH HARGA BAHAN 29,219.14
Tenaga :
Pekerja 0.0200 OH 100,000.00 2,000.00
Tukang cat 0.0630 OH 140,000.00 8,820.00
Kepala Tukang 0.0063 OH 150,000.00 945.00
Mandor 0.0025 OH 165,000.00 412.50
B. JUMLAH UPAH 12,177.50
C. JUMLAH BAHAN DAN UPAH 41,396.64
D. Overhead + Profit (10%) 4,139.66
E. Total 45,536.31

3 SNI 2842-2002 (6.20.a)


1 M2 PENGECATAN PERMUKAAN BESI DENGAN MENI BESI
Bahan :
Meni besi 0.1000 Kg 81,328.57 8,132.86
Kuas biasa 0.0100 Bh 44,464.29 444.64
A. JUMLAH HARGA BAHAN 8,577.50
Tenaga :
Pekerja 0.0200 OH 100,000.00 2,000.00
Tukang cat 0.2000 OH 140,000.00 28,000.00
Kepala Tukang 0.0200 OH 150,000.00 3,000.00
Mandor 0.0100 OH 165,000.00 1,650.00
B. JUMLAH UPAH 34,650.00
C. JUMLAH BAHAN DAN UPAH 43,227.50
D. Overhead + Profit (10%) 4,322.75
E. Total 47,550.25
4 SNI 2842-2002 (6.20.b)
1 M2 PENGECATAN PERMUKAAN BESI DENGAN CAT BESI
Bahan :
Cat besi 0.1000 Kg 119,328.57 11,932.86
Kuas biasa 0.0100 Bh 44,464.29 444.64
A. JUMLAH HARGA BAHAN 12,377.50

ARSIP SNI 2008 - 42


HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN INDEKS SATUAN
(Rp) (Rp)
Tenaga :
Pekerja 0.0200 OH 100,000.00 2,000.00
Tukang cat 0.2000 OH 140,000.00 28,000.00
Kepala Tukang 0.0200 OH 150,000.00 3,000.00
Mandor 0.0100 OH 165,000.00 1,650.00
B. JUMLAH UPAH 34,650.00
C. JUMLAH BAHAN DAN UPAH 47,027.50
D. Overhead + Profit (10%) 4,702.75
E. Total 51,730.25

ARSIP SNI 2008 - 43


HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN INDEKS SATUAN
(Rp) (Rp)
M. ELECTRIKAL
1 1 TITIK PEKERJAAN INSTALASI LAMPU DAN KOTAK KONTAK
Bahan
Kabel NYM 3 x 2,5 mm 11.0000 M' 31,885.99 350,745.87
A. JUMLAH HARGA BAHAN 350,745.87
Tenaga
Pekerja 0.4800 OH 100,000.00 48,000.00
Tukang Listrik 0.0480 OH 140,000.00 6,720.00
Kepala Tukang 0.0480 OH 150,000.00 7,200.00
B. JUMLAH UPAH 61,920.00
C. JUMLAH BAHAN DAN UPAH 412,665.87
D. Overhead + Profit (10%) 41,266.59
E. Total 453,932.46
2 PASANG 1 BUAH STOP KONTAK
Bahan
Stop kontak 1.0000 Bh 55,423.93 55,423.93
A. JUMLAH HARGA BAHAN 55,423.93
Tenaga
Pekerja 0.2000 OH 100,000.00 20,000.00
Tukang Listrik 0.0200 OH 140,000.00 2,800.00
Kepala Tukang 0.0200 OH 150,000.00 3,000.00
B. JUMLAH UPAH 25,800.00
C. JUMLAH BAHAN DAN UPAH 81,223.93
D. Overhead + Profit (10%) 8,122.39
E. Total 89,346.32
3 1 BUAH PEKERJAAN LAMPU SL 18 + FITTING
Bahan
Lampu philips 18 W 1.0000 Bh 123,697.14 123,697.14
Fitting duduk 1.0000 Bh 58,898.57 58,898.57
A. JUMLAH HARGA BAHAN 182,595.71
Tenaga
Pekerja 0.2000 OH 100,000.00 20,000.00
Tukang Listrik 0.0200 OH 140,000.00 2,800.00
Kepala Tukang 0.0200 OH 150,000.00 3,000.00
B. JUMLAH UPAH 25,800.00
C. JUMLAH BAHAN DAN UPAH 208,395.71
D. Overhead + Profit (10%) 20,839.57
E. Total 229,235.28
4 PASANG 1 BH MCB BOX
Bahan
MCB 6 A 1.0000 Set 93,298.57 93,298.57
A. JUMLAH HARGA BAHAN 93,298.57
Tenaga
Pekerja 0.2000 OH 100,000.00 20,000.00
Tukang Listrik 0.0200 OH 140,000.00 2,800.00
Kepala Tukang 0.0200 OH 150,000.00 3,000.00
B. JUMLAH UPAH 25,800.00
C. JUMLAH BAHAN DAN UPAH 119,098.57
D. Overhead + Profit (10%) 11,909.86
E. Total 131,008.43
PASANG 1 BUAH SAKLAR GANDA
Bahan
Saklar ganda 1.0000 Set 55,423.93 55,423.93
A. JUMLAH HARGA BAHAN 55,423.93
Tenaga
Pekerja 0.4000 OH 100,000.00 40,000.00
Tukang Listrik 0.0400 OH 140,000.00 5,600.00
Kepala Tukang 0.0400 OH 150,000.00 6,000.00
B. JUMLAH UPAH 51,600.00
C. JUMLAH BAHAN DAN UPAH 107,023.93
D. Overhead + Profit (10%) 10,702.39
E. Total 117,726.32
5 PASANG 1 BUAH SAKLAR TUNGGAL
Bahan
Saklar tunggal 1.0000 Set 50,423.93 50,423.93
A. JUMLAH HARGA BAHAN 50,423.93

ARSIP SNI 2008 - 44


HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN INDEKS SATUAN
(Rp) (Rp)
Tenaga
Pekerja 0.4000 OH 100,000.00 40,000.00
Tukang Listrik 0.0400 OH 140,000.00 5,600.00
Kepala Tukang 0.0400 OH 150,000.00 6,000.00
B. JUMLAH UPAH 51,600.00
C. JUMLAH BAHAN DAN UPAH 102,023.93
D. Overhead + Profit (10%) 10,202.39
E. Total 112,226.32

O PASANGAN BROJONG SNI 03 - 0009 -1999


1 PASANGAN BRONJONG PABRIKASI BENTUK I Type D (L = 2, B = 1, T = 0,5)
Bahan :
Batu kali 1.4 m3 2,000,000.00 2,800,000.00
Kawat bronjong 1 bh #N/A #N/A
A. JUMLAH HARGA BAHAN #N/A
Tenaga :
Pekerja 0.5 OH 100,000.00 50,000.00
Mandor 0.05 OH 165,000.00 8,250.00
B. JUMLAH UPAH 58,250.00
C. JUMLAH BAHAN DAN UPAH #N/A
D. Overhead + Profit (10%) #N/A
E. Total #N/A

N. ANALISA TAMBAHAN

1 PASANG 1 BUAH TERALIS BESI BETON


J.4 Pasang Besi siku 50.50.5 mm 33.18 Kg 110,741.72 3,674,410.27
J.1 Pasang Besi beton dia. 12 mm 58.57 Kg 101,786.14 5,961,614.22
J.8 Pengelasan teralis besi 660 cm #N/A #N/A
A. JUMLAH HARGA BAHAN #N/A
2 PASANG 1 BUAH TERALIS TRASHRACK BESI BETON
J.4 Pasang Besi siku 50.50.5 mm 42.83 Kg 110,741.72 4,743,067.87
J.1 Pasang Besi beton dia. 12 mm 102.26 Kg 101,786.14 10,408,650.68
J.8 Pengelasan teralis besi 470 cm #N/A #N/A
A. JUMLAH HARGA BAHAN #N/A
3 PASANG 1 UNIT SPONING PINTU AIR P1 DARI BESI PROFIL
J.3 Besi profil C 65.42 mm 21.98 kg 102,718.88 2,257,760.98
J.1 pasang angker besi dia 12 mm panjang 20 cm 8 bh 1.42 kg 101,786.14 144,536.32
J.8 Pengelasan 10 titik 30.14 cm #N/A #N/A
A. JUMLAH #N/A

4 PASANG 1 UNIT SPONING PINTU AIR P2 DARI BESI PROFIL


J.3 Besi profil C 65.42 mm 19.85 kg 102,718.88 2,038,969.77
J.1 pasang angker besi dia 10 mm panjang 20 cm 12 bh 1.42 kg 101,786.14 144,536.32
J.8 Pengelasan 12 titik 30.14 cm #N/A #N/A
A. JUMLAH #N/A
5 PASANG 1 BUAH PINTU AIR P1 (120/100)
J.5 Pasang Besi profil C 80.45 mm panjang 4,32 m 37.28 kg #N/A #N/A
Stang pintu air drag + mur 1 set 5,538,457.14 5,538,457.14
J.7 Pintu air plat baja (rangkap), rangka baja siku 1.2 m2 #N/A #N/A
J.8 Pengelasan stang dan besi profil 50.000 cm #N/A #N/A
A. JUMLAH #N/A
6 PASANG 1 BUAH PINTU AIR P2 (112/85)
J.5 Pasang Besi profil C 80.45 mm panjang 4,32 m 35.56 kg #N/A #N/A
Stang pintu air drag + mur 1 set 5,538,457.14 5,538,457.14
J.7 Pintu air plat baja (rangkap), rangka baja siku 0.952 m2 #N/A #N/A
J.8 Pengelasan 50.000 cm #N/A #N/A
A. JUMLAH #N/A
7 SNI 7393 - 2008 (6.1)
MEMASANG 1 KG PIPA PENSTOK
Tenaga :
Pekerja 0.0600 OH 100,000.00 6,000.00
Tukang Las 0.0600 OH 140,000.00 8,400.00
Kepala Tukang 0.0060 OH 150,000.00 900.00
Mandor 0.0030 OH 165,000.00 495.00
B. JUMLAH UPAH 15,795.00
D. Overhead + Profit (10%) 1,579.50
E. Total 17,374.50
SNI 7393 - 2008 (6.1)

ARSIP SNI 2008 - 45


HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN INDEKS SATUAN
(Rp) (Rp)
8 MEMASANG 1 KG EKSPANTION JOINT
Tenaga :
Pekerja 0.0600 OH 100,000.00 6,000.00
Tukang Las 0.0600 OH 140,000.00 8,400.00
Kepala Tukang 0.0060 OH 150,000.00 900.00
Mandor 0.0030 OH 165,000.00 495.00
B. JUMLAH UPAH 15,795.00
D. Overhead + Profit (10%) 1,579.50
E. Total 17,374.50
9 SNI 7393 - 2008 (6.1)
MEMASANG 1 KG FLANGE JOINT
Tenaga :
Pekerja 0.0600 OH 100,000.00 6,000.00
Tukang Las 0.0600 OH 140,000.00 8,400.00
Kepala Tukang 0.0060 OH 150,000.00 900.00
Mandor 0.0030 OH 165,000.00 495.00
B. JUMLAH UPAH 15,795.00
D. Overhead + Profit (10%) 1,579.50
E. Total 17,374.50
10 MEMASANG 1 BTG PIPA PENSTOK
P.7 Pasang 1 bh pipa penstok 74.9300 kg 17,374.50 1,301,871.29
K.8 Pengelasan penyambungan pipa (luar dalam) 477.2800 cm #N/A #N/A
A. JUMLAH #N/A

11 MEMASANG 1 SET EKSPANTION JOINT


P.8 Pasang 1 set ekspantion joint 125.0000 kg 17,374.50 2,171,812.50
K.8 Pengelasan penyambungan pipa (luar dalam) 477.2800 cm #N/A #N/A
Pemasangan baut mur (Tukang las) 0.2000 OH 140,000.00 28,000.00
A. JUMLAH #N/A

12 MEMASANG 1 SET FLANGE JOINT


P.9 Pasang 1 set puddle flange joint 62.5000 kg 17,374.50 1,085,906.25
K.8 Pengelasan penyambungan pipa (luar dalam) 477.2800 cm #N/A #N/A
Pemasangan baut mur 0.1000 OH 140,000.00 14,000.00
A. JUMLAH #N/A

SNI 2002 (6.21)


13 PEMASANGAN 1 M' PIPA GIP 1,5"
Bahan :
Pipa GIP 1,5" 1.2000 m 10,438.10 12,525.71
Perlengkapan 35 % 4,384.00
A. JUMLAH HARGA BAHAN 16,909.71
Tenaga :
Pekerja 0.1080 OH 100,000.00 10,800.00
Tukang las 0.1800 OH 140,000.00 25,200.00
Kepala Tukang 0.0180 OH 150,000.00 2,700.00
Mandor 0.0050 OH 165,000.00 825.00
B. JUMLAH UPAH 39,525.00
C. JUMLAH BAHAN DAN UPAH 56,434.71
D. Overhead + Profit (10%) 5,643.47
E. Total 62,078.19

14 PEMASANGAN 1 BH' AIR VALVE PIPA GIP 1,5"


Bahan :
P.14 Pemasangan Pipa GIP 1,5" 2.0000 m 62,078.19 124,156.38
Pengelasan 59.82 cm #N/A 43,454.73
A. JUMLAH HARGA BAHAN 167,611.11

ARSIP SNI 2008 - 46


Tabel 1 Ukuran Baja Tulangan Polos
Ukuran Nomimal
Penamaa Diame Luas
No Urut Berat
n ter Penampang
(Kg/m')
(mm) (cm2)
1 P-6 6 0.283 0.222 0.222
2 P-8 8 0.503 0.395
3 P-10 10 0.785 0.617
4 P-12 12 1.131 0.888
5 P-14 14 1.539 1.208 7850 kg
6 P-16 16 2.011 1.578
7 P-19 19 2.835 2.226
8 P-22 22 3.801 2.984
9 P-25 25 4.909 3.853
10 P-28 28 6.158 4.834
BESI SIKU L.40.40.4 6 2.42 14.52
SELIMUT BETON DITETAPKAN 0.02 m'
Sumber :Buku Struktur Beton Bertulang Standar Baru SNI
T-15-1991-03, Lampiran 2, Ir. L.Wahyudi dan Ir. Syahril
A.Rahim, M.Eng, Gramedia Jakarta,1999

SLOOF 60/15 60 / 15
BESI POKOK : 10.00 mm
BEGEL : 6.00 mm
SELIMUT BETON : 0.04 m
TINGGI BETON : 15.00 cm
LEBAR BETON : 60.00 cm

PERHITUNGAN BESI BEGEL 6 mm


` LUAS DIMENSI ### X 0.15 = 0.090
PANJANG DARI 1M3 = 11.111
SELIMUT BETON = 0.040

PANJANG I BUAH BEUGEL = 1.280


JRK ANTAR BEUGEL = 0.170
JML BEUGEL YANG DI BUTUHKAN / 1M3 = 66.359
PANJANG TOTAL BEUGEL = 84.940
BERAT BESI BEUGEL = 18.857

PERHITUNGAN TULANGAN POKOK 10 mm


JUMLAH BESI = 8.000
PANJANG BESI /m3 = 88.889
BERAT BESI TUL. POKOK = 54.844
TOTAL BERAT BESI BETON/M3 = 73.701

PERHITUNGAN BEKISTING
LUAS BEKISTING/M3 = 1.667

KOLOM 20/20 20 / 20
BESI POKOK : 10.00 mm
BEGEL : 6.00 mm
SELIMUT BETON : 0.04 m
TINGGI BETON : 20.00 cm
LEBAR BETON : 20.00 cm

PERHITUNGAN BESI BEGEL 6 mm


` LUAS DIMENSI 0.20 X 0.20 = 0.040
PANJANG DARI 1M3 = 25.000
SELIMUT BETON = 0.040

PANJANG I BUAH BEUGEL = 0.580


JRK ANTAR BEUGEL = 0.17
JML BEUGEL YANG DI BUTUHKAN / 1M3 = 148.059
PANJANG TOTAL BEUGEL = 85.874
TOTAL BERAT BEUGEL = 19.064

PERHITUNGAN TULANGAN POKOK 10 mm


JUMLAH BESI = 8.000
PANJANG BESI /m3 = 200.000
TOTAL BERAT BESI = 123.400
TOTAL BERAT BESI = 149.587
Luas Tulangan = 0.0006
Rasio Tulangan = 0.016
PERHITUNGAN BEKISTING
LUAS BEKISTING/M3 = 10.000

RINGBALOK 30/30 30 / 30
BESI POKOK : 12.00 mm
BEGEL : 8.00 mm
SELIMUT BETON : 0.04 m
TINGGI BETON : 30.00 cm
LEBAR BETON : 30.00 cm

PERHITUNGAN BESI BEGEL 8 mm


` LUAS DIMENSI ### X 0.30 = 0.090
PANJANG DARI 1M3 = 11.111
SELIMUT BETON = 0.040

PANJANG I BUAH BEUGEL = 0.980


JRK ANTAR BEUGEL = 0.170
JML BEUGEL YANG DI BUTUHKAN / 1M3 = 66.359
PANJANG TOTAL BEUGEL = 65.032
TOTAL BERAT BEUGEL = 25.688

PERHITUNGAN TULANGAN POKOK 12 mm


JUMLAH BESI = 8.000
PANJANG BESI /m3 = 88.889
TOTAL BERAT BESI = 78.933
TOTAL BERAT BESI = 104.621
PERHITUNGAN BEKISTING
LUAS BEKISTING/M3 = 5.000

RINGPLAT 0.12 / 0.8 M2


BESI POKOK ARAH X : 10.00 mm
BESI POKOK ARAH Y : 10.00 mm
SELIMUT BETON : 0.04 m
TEBAL BETON : 0.00 m
ARAH X : 0.80 m
ARAH Y : 1.00 m

PERHITUNGAN TULANGAN POKOK X 10 mm

JARAK ANTAR TULANGAN = 0.150


JUMLAH BESI = 13.333
PANJANG BESI /m2 = 21.333

TOTAL BERAT BESI = 13.163

PERHITUNGAN TULANGAN POKOK Y 10 mm


JARAK ANTAR TULANGAN = 0.150
JUMLAH BESI = 10.667
PANJANG BESI /m2 = 21.333

TOTAL BERAT BESI = 13.163

PERHITUNGAN BEKISTING
LUAS BEKISTING/M3 = 1.232

PONDASI FOOTPLATE 60 / 20
BESI POKOK : 10.00 mm
BEGEL : 10.00 mm
SELIMUT BETON : 0.04 m
TINGGI BETON : 20.00 cm
LEBAR BETON : 60.00 cm

PERHITUNGAN BESI BEGEL 10.00 mm


` LUAS DIMENSI 0.60 X 0.20 = 0.120
PANJANG DARI 1M3 = 8.333
SELIMUT BETON = 0.040

PANJANG I BUAH BEUGEL = 1.360


JRK ANTAR BEUGEL = 0.125
JML BUGEL YANG DI BUTUHKAN / 1M3 = 66.667
PANJANG TOTAL BEUGEL = 90.667
TOTAL BERAT BEUGEL = 55.941
PERHITUNGAN TULANGAN POKOK 10 mm
JUMLAH BESI = 12.000
PANJANG BESI /m3 = 100.000
TOTAL BERAT BESI = 61.700

PERHITUNGAN BEKISTING
LUAS BEKISTING/M3 = 3.333

PLAT LANTAI TEBAL 30 CM


BESI POKOK : 10.00 mm
BESI PEMBAGI : 10.00 mm
SELIMUT BETON : 0.04 m
TINGGI BETON : 0.30 m
LEBAR PLAT : 1.00 m
PANJANG PLAT : 1.00 m
VOLUME PLAT : 0.30 m3
PERHITUNGAN TULANGAN POKOK X 10 mm
JARAK ANTAR TULANGAN = 0.150
JUMLAH BESI = 3.667
PANJANG BESI = 7.333
TOTAL BERAT BESI = 6.512
BERAT BESI / M3 = 21.707

PERHITUNGAN TULANGAN POKOK Y 10 mm


JARAK ANTAR TULANGAN = 0.150
JUMLAH BESI = 3.667
PANJANG BESI = 7.333
TOTAL BERAT BESI = 6.512
BERAT BESI / M3 = 21.707

TOTAL BERAT BESI = 43.413

DINDING TEBAL 30 CM
BESI POKOK : 12.00 mm
BESI PEMBAGI : 10.00 mm
SELIMUT BETON : 0.04 m
TINGGI BETON : 0.30 m
LEBAR BETON : 1.57 m
PERHITUNGAN

JARAK ANTAR TULANGAN = 0.150


DIMENSI = 0.471
PANJANG DARI 1 M3 = 2.123

TULANGAN POKOK 12 mm
JUMLAH BESI = 14.154
PANJANG BESI = 22.222
TOTAL BERAT BESI = 19.733

TULANGAN PEMBAGI 10 mm
JARAK ANTAR TULANGAN = 0.150
JUMLAH BESI = 10.467
PANJANG BESI = 22.222
TOTAL BERAT BESI = 13.711

TOTAL BERAT BESI = 33.444


PERHITUNGAN BEKISTING
LUAS BEKISTING/M3 = 7.609

BLOK ANGKER
BESI POKOK : 10.00 mm
PANJANG BESI / bh : 0.93 m
JUMLAH BESI : 12.00 bh

BESI BEGEL : 8.00 mm


PANJANG BEGEL/Bh : 3.20 m
JUMLAH BEGEL : 7.00 bh
PERHITUNGAN

TULANGAN POKOK 10 mm
JUMLAH BESI = 12.000
PANJANG BESI TOTAL = 11.160
TOTAL BERAT BESI = 6.886

TULANGAN PEMBAGI 8 mm
JUMLAH BESI = 7.000
PANJANG BESI = 22.400
TOTAL BERAT BESI = 8.848

TOTAL BERAT BESI = 16.520


PERHITUNGAN BEKISTING
LUAS BEKISTING/M3 = #REF!
SLOOF 30/30 30 / 30
BESI POKOK : 12.00 mm
BEGEL : 8.00 mm
SELIMUT BETON : 0.04 m
TINGGI BETON : 30.00 cm
LEBAR BETON : 30.00 cm

PERHITUNGAN BESI BEGEL 8 mm


m ` LUAS DIMENSI ### X 0.30 =
m' PANJANG DARI 1M3 =
m' SELIMUT BETON =

m' PANJANG I BUAH BEUGEL =


m' JRK ANTAR BEUGEL =
bh JML BEUGEL YANG DI BUTUHKAN / 1M3 =
m PANJANG TOTAL BEUGEL =
kg BERAT BESI BEUGEL =

PERHITUNGAN TULANGAN POKOK 12 mm


bh JUMLAH BESI =
m PANJANG BESI /m3 =
kg BERAT BESI TUL. POKOK =
kg TOTAL BERAT BESI BETON/M3 =

PERHITUNGAN BEKISTING
m LUAS BEKISTING/M3 =

KOLOM 30/30 30 / 30
BESI POKOK : 12 mm
BEGEL : 6 mm
SELIMUT BETON : 0.04 m
TINGGI BETON : 30 cm
LEBAR BETON : 30 cm

PERHITUNGAN BESI BEGEL 6 mm


m ` LUAS DIMENSI 0.30 X 0.30 =
m' PANJANG DARI 1M3 =
m' SELIMUT BETON =

m' PANJANG I BUAH BEUGEL =


m' JRK ANTAR BEUGEL =
bh JML BEUGEL YANG DI BUTUHKAN / 1M3 =
m PANJANG TOTAL BEUGEL =
kg TOTAL BERAT BEUGEL =

PERHITUNGAN TULANGAN POKOK 12 mm


bh JUMLAH BESI =
m PANJANG BESI /m3 =
kg TOTAL BERAT BESI =
kg TOTAL BERAT BESI =
m Luas Tulangan =
Rasio Tulangan =
PERHITUNGAN BEKISTING
m LUAS BEKISTING/M3 =

RINGBALOK 40/20 40 / 20
BESI POKOK : 12.00 mm
BEGEL : 6.00 mm
SELIMUT BETON : 0.04 m
TINGGI BETON : 20.00 cm
LEBAR BETON : 40.00 cm

PERHITUNGAN BESI BEGEL 6 mm


m ` LUAS DIMENSI ### X 0.20 =
m' PANJANG DARI 1M3 =
m' SELIMUT BETON =

m' PANJANG I BUAH BEUGEL =


m' JRK ANTAR BEUGEL =
bh JML BEUGEL YANG DI BUTUHKAN / 1M3 =
m PANJANG TOTAL BEUGEL =
kg TOTAL BERAT BEUGEL =

PERHITUNGAN TULANGAN POKOK 12 mm


bh JUMLAH BESI =
m PANJANG BESI /m3 =
kg TOTAL BERAT BESI =
kg TOTAL BERAT BESI/M3 =
PERHITUNGAN BEKISTING
m LUAS BEKISTING/M3 =

PONDASI PLAT BETON BERTULANG 30 / 1 M2


BESI POKOK ARAH X : 10.00 mm
BESI POKOK ARAH Y : 10.00 mm
SELIMUT BETON : 0.04 m
TEBAL BETON : 0.30 m
ARAH X : 1.00 m
ARAH Y : 1.00 m

PERHITUNGAN TULANGAN POKOK X 10 mm

m JARAK ANTAR TULANGAN =


bh JUMLAH BESI =
m PANJANG BESI /m2 =

kg TOTAL BERAT BESI =

PERHITUNGAN TULANGAN POKOK Y 10 mm


m JARAK ANTAR TULANGAN =
bh JUMLAH BESI =
m PANJANG BESI /m2 =

kg TOTAL BERAT BESI =

PERHITUNGAN BEKISTING
m LUAS BEKISTING/M3 =

m
m'
m'

m'
m'
bh
m
kg
bh
m
kg

m
bh
m
kg
kg

m
bh
m
kg
kg

kg

m
m2
m

bh
m
kg

m
bh
m
kg

kg

bh
m
kg

bh
m
kg

kg 15.734 0.787 16.520

m
SLOOF 20/25 20 / 25
BESI POKOK : 10.00 mm
BEGEL : 6.00 mm
SELIMUT BETON : 0.04 m
TINGGI BETON : 25.00 cm
LEBAR BETON : 20.00 cm

PERHITUNGAN BESI BEGEL 6


0.090 m ` LUAS DIMENSI ### X
11.111 m' PANJANG DARI 1M3
0.040 m' SELIMUT BETON

0.980 m' PANJANG I BUAH BEUGEL


0.170 m' JRK ANTAR BEUGEL
66.359 bh JML BEUGEL YANG DI BUTUHKAN / 1M3
65.032 m PANJANG TOTAL BEUGEL
25.688 kg TOTAL BERAT BEUGEL

PERHITUNGAN TULANGAN POKOK 10


8.000 bh JUMLAH BESI
88.889 m PANJANG BESI /m3
78.933 kg TOTAL BERAT BESI
104.621 kg TOTAL BERAT BESI

PERHITUNGAN BEKISTING
3.333 m LUAS BEKISTING/M3

KOLOM 40/40 40 / 40
BESI POKOK : 12 mm
BEGEL : 6 mm
SELIMUT BETON : 0.04 m
TINGGI BETON : 40 cm
LEBAR BETON : 40 cm

PERHITUNGAN BESI BEGEL 6


0.090 m ` LUAS DIMENSI 0.40 X
11.111 m' PANJANG DARI 1M3
0.04 m' SELIMUT BETON

0.980 m' PANJANG I BUAH BEUGEL


0.17 m' JRK ANTAR BEUGEL
66.359 bh JML BEUGEL YANG DI BUTUHKAN / 1M3
65.032 m PANJANG TOTAL BEUGEL
14.437 kg TOTAL BERAT BEUGEL

PERHITUNGAN TULANGAN POKOK 12


8.000 bh JUMLAH BESI
88.889 m PANJANG BESI /m3
54.844 kg TOTAL BERAT BESI
69.282 kg TOTAL BERAT BESI/M3
0.0009 m Luas Tulangan
0.010 Rasio Tulangan
PERHITUNGAN BEKISTING
6.667 m LUAS BEKISTING/M3

RINGBALOK 50/20 50 / 20
BESI POKOK : 12.00 mm
BEGEL : 8.00 mm
SELIMUT BETON : 0.04 m
TINGGI BETON : 20.00 cm
LEBAR BETON : 50.00 cm

PERHITUNGAN BESI BEGEL 8


0.080 m ` LUAS DIMENSI ### X
12.500 m' PANJANG DARI 1M3
0.04 m' SELIMUT BETON

0.980 m' PANJANG I BUAH BEUGEL


0.17 m' JRK ANTAR BEUGEL
74.529 bh JML BEUGEL YANG DI BUTUHKAN / 1M3
73.039 m PANJANG TOTAL BEUGEL
16.215 kg TOTAL BERAT BEUGEL

PERHITUNGAN TULANGAN POKOK 12


6.000 bh JUMLAH BESI
75.000 m PANJANG BESI /m3
66.600 kg TOTAL BERAT BESI
82.815 kg TOTAL BERAT BESI/M3
PERHITUNGAN BEKISTING
2.500 m LUAS BEKISTING/M3

PLAT BETON BERTULANG 10 / 1 M2


BESI POKOK ARAH X: 12.00 mm
BESI POKOK ARAH Y: 10.00 mm
SELIMUT BETON : 0.04 m
TEBAL BETON : 0.10 m
ARAH X : 1.00 m
ARAH Y : 1.00 m
TEBAL BETON : 0.12 m
PERHITUNGAN TULANGAN POKOK X 12

0.150 m JARAK ANTAR TULANGAN


13.333 bh JUMLAH BESI
30.667 m PANJANG BESI /m2

18.921 kg TOTAL BERAT BESI

PERHITUNGAN TULANGAN POKOK Y 10


0.150 m JARAK ANTAR TULANGAN
13.333 bh JUMLAH BESI
30.667 m PANJANG BESI /m2

18.921 kg TOTAL BERAT BESI


TOTAL BERAT BESI
BERAT BESI/M3
PERHITUNGAN BEKISTING
1.200 m LUAS BEKISTING/M3

1 m2 9.461
0.12
8.33333333 78.84167
SLOOF 40/20 40 / 20
BESI POKOK : 12.00 mm
BEGEL : 6.00 mm
SELIMUT BETON : 0.04 m
TINGGI BETON : 20.00 cm
LEBAR BETON : 40.00 cm

mm PERHITUNGAN BESI BEGEL


0.25 = 0.050 m ` LUAS DIMENSI ###
= 20.000 m' PANJANG DARI 1M3
= 0.020 m' SELIMUT BETON

= 0.680 m' PANJANG I BUAH BEUGEL


= 0.170 m' JRK ANTAR BEUGEL
= 118.647 bh JML BEUGEL YANG DI BUTUHKAN / 1M3
= 80.680 m PANJANG TOTAL BEUGEL
= 17.911 kg TOTAL BERAT BEUGEL

mm PERHITUNGAN TULANGAN POKOK


= 8.000 bh JUMLAH BESI
= 160.000 m PANJANG BESI /m3
= 98.720 kg BERAT BESI TUL. POKOK
= 122.463 kg TOTAL BERAT BESI BETON/M3

PERHITUNGAN BEKISTING
= 5.000 m LUAS BEKISTING/M3

KOLOM 45/50 45 / 50
BESI POKOK : 12 mm
BEGEL : 6 mm
SELIMUT BETON : 0.04 m
TINGGI BETON : 50 cm
LEBAR BETON : 45 cm

mm PERHITUNGAN BESI BEGEL


0.40 = 0.160 m ` LUAS DIMENSI 0.45
= 6.250 m' PANJANG DARI 1M3
= 0.04 m' SELIMUT BETON

= 1.380 m' PANJANG I BUAH BEUGEL


= 0.17 m' JRK ANTAR BEUGEL
= 37.765 bh JML BEUGEL YANG DI BUTUHKAN / 1M3
= 52.115 m PANJANG TOTAL BEUGEL
= 11.570 kg TOTAL BERAT BEUGEL

mm PERHITUNGAN TULANGAN POKOK


= 8.000 bh JUMLAH BESI
= 50.000 m PANJANG BESI /m3
= 44.400 kg BERAT BESI TULANGAN
= 55.970 kg TOTAL BERAT BESI/M3
= 0.0009 m Luas Tulangan
= 0.006 Rasio Tulangan
PERHITUNGAN BEKISTING
= 5.000 m LUAS BEKISTING/M3

RINGBALOK 60/15 60 / 15
BESI POKOK : 10.00 mm
BEGEL : 6.00 mm
SELIMUT BETON : 0.04 m
TINGGI BETON : 15.00 cm
LEBAR BETON : 60.00 cm

mm PERHITUNGAN BESI BEGEL


0.20 = 0.100 m ` LUAS DIMENSI ###
= 10.000 m' PANJANG DARI 1M3
= 0.040 m' SELIMUT BETON

= 1.180 m' PANJANG I BUAH BEUGEL


= 0.170 m' JRK ANTAR BEUGEL
= 59.824 bh JML BEUGEL YANG DI BUTUHKAN / 1M3
= 70.592 m PANJANG TOTAL BEUGEL
= 27.884 kg TOTAL BERAT BEUGEL

mm PERHITUNGAN TULANGAN POKOK


= 10.000 bh JUMLAH BESI
= 100.000 m PANJANG BESI /m3
= 88.800 kg TOTAL BERAT BESI
= 122.518 kg TOTAL BERAT BESI/M3
PERHITUNGAN BEKISTING
= 2.000 m LUAS BEKISTING/M3

1 LAPIS TEBAL 12 CM PLAT BETON BERTULANG 12 / 1


BESI POKOK ARAH X: 10.00 mm
BESI POKOK ARAH Y: 10.00 mm
SELIMUT BETON : 0.04 m
TEBAL BETON : 0.12 m
ARAH X : 1.00 m
ARAH Y : 1.00 m

mm PERHITUNGAN TULANGAN POKOK X

= 0.150 m JARAK ANTAR TULANGAN


= 7.667 bh JUMLAH BESI
= 7.667 m PANJANG BESI /m2
PANJANG BESI /m3
= 4.730 kg TOTAL BERAT BESI

mm PERHITUNGAN TULANGAN POKOK Y


= 0.150 m JARAK ANTAR TULANGAN
= 7.667 bh JUMLAH BESI
= 7.667 m PANJANG BESI /m2
PANJANG BESI /m3
= 4.730 kg TOTAL BERAT BESI
= 9.461 kg TOTAL BERAT BESI (XY)
= 78.839
PERHITUNGAN BEKISTING
= 0.400 m LUAS BEKISTING/M3
6 mm
X 0.20 = 0.080 m
= 12.500 m'
= 0.020 m'

= 0.980 m'
= 0.170 m'
= 74.529 bh
= 73.039 m
= 16.215 kg

### mm
= 6.000 bh
= 75.000 m
= 66.600 kg
= 82.815 kg

= 2.500 m

KOLOM 50/60 60 /
BESI POKOK : 12 mm
BEGEL : 6 mm
SELIMUT BETON : 0.04 m
TINGGI BETON : 60 cm
LEBAR BETON : 60 cm

6 mm PERHITUNGAN BESI BEGEL


X 0.50 = 0.225 m ` LUAS DIMENSI
= 4.444 m' PANJANG DARI 1M3
= 0.04 m' SELIMUT BETON

= 1.680 m' PANJANG I BUAH BEUGEL


= 0.17 m' JRK ANTAR BEUGEL
= 27.144 bh JML BEUGEL YANG DI BUTUHKAN / 1M3
= 45.602 m PANJANG TOTAL BEUGEL
= 10.124 kg TOTAL BERAT BEUGEL

12 mm PERHITUNGAN TULANGAN POKOK


= 16.000 bh JUMLAH BESI
= 71.111 m PANJANG BESI /m3
= 63.147 kg BERAT BESI TULANGAN
= 76.934 kg TOTAL BERAT BESI/M3
= 0.0018 m Luas Tulangan
= 0.008 Rasio Tulangan
PERHITUNGAN BEKISTING
= 4.222 m LUAS BEKISTING/M3

RINGBALOK 80/12 80 /
BESI POKOK : 10.00 mm
BEGEL : 8.00 mm
SELIMUT BETON : 0.04 m
TINGGI BETON : 12.00 cm
LEBAR BETON : 80.00 cm

6 mm PERHITUNGAN BESI BEGEL


X 0.15 = 0.090 m ` LUAS DIMENSI
= 11.111 m' PANJANG DARI 1M3
= 0.040 m' SELIMUT BETON

= 1.280 m' PANJANG I BUAH BEUGEL


= 0.170 m' JRK ANTAR BEUGEL
= 66.359 bh JML BEUGEL YANG DI BUTUHKAN / 1M3
= 84.940 m PANJANG TOTAL BEUGEL
= 18.857 kg TOTAL BERAT BEUGEL

10 mm PERHITUNGAN TULANGAN POKOK


= 8.000 bh JUMLAH BESI
= 88.889 m PANJANG BESI /m3
= 78.933 kg TOTAL BERAT BESI
= 97.790 kg TOTAL BERAT BESI/M3
PERHITUNGAN BEKISTING
= 1.667 m LUAS BEKISTING/M3

M2 2 lapis

### mm

= 0.170 m
= 6.882 bh
= 13.765 m
= 114.706 m 0.12
= 70.774 kg 8.33333333
1

10 mm
= 0.170 m
= 6.882 bh
= 13.765 m
= 114.706 m
= 70.774 kg
= 141.547 kg

= 12.413 m
60
BESI BEGEL 6 mm
0.60 X 0.60 = 0.360 m
= 2.778 m'
= 0.04 m'

= 2.180 m'
= 0.17 m'
= 17.340 bh
= 37.801 m
= 14.931 kg

12 mm
= 12.000 bh
= 33.333 m
= 29.600 kg
= 44.531 kg
= 0.0014 m
= 0.004

= 3.333 m

12

BESI BEGEL 8 mm
### X 0.12 = 0.096 m
= 10.417 m'
= 0.040 m'

= 1.620 m'
= 0.200 m'
= 53.083 bh
= 85.995 m
= 33.968 kg

10 mm
= 11.000 bh
= 114.583 m
= 70.698 kg
= 109.899 kg
= 5.417 m
ANALISA HARGA SATUAN PEKERJAAN (AHSP)
BIDANG SUMBER DAYA AIR RSNI 2008

DAFTAR AHSP BIDANG SUMBER DAYA AIR

A. PEKERJAAN TANAH SECARA MANUAL


a. AHSP pembersihan dan pengupasan permukaan tanah

T.01 1 m2 Pembersihan dan striping/kosrekan


No Uraian Kode Satuan Koefisien Harga Satuan Jumlah
A Tenaga Kerja
Pekerja L.01 OH 0.0600 100,000 6,000.00
Mandor L.04 OH 0.0060 165,000 990.00
Jumlah Harga Tenaga 6,990.00
B Bahan

Jumlah Harga Bahan 0.00


C Peralatan

Jumlah Harga Peralatan 0.00


D Jumlah harga tenaga, Bahan, dan Peralatan (A+B+C) 6,990.00
E Overhead + Profit (10%) 10% xD 699.00

F Harga satuan pekerjaan 7,689.00

T.02 1 m2 Tebas tebang memotong berupa memotong dan membersihkan lokasi dari tanaman/
tumbuhan diameter < 15cm
No Uraian Kode Satuan Koefisien Harga Satuan Jumlah
A Tenaga Kerja
Pekerja L.01 OH 0.0750 100,000 7,500.00
Mandor L.04 OH 0.0075 165,000 1,237.50
Jumlah Harga Tenaga 8,737.50
B Bahan

Jumlah Harga Bahan 0.00


C Peralatan

Jumlah Harga Peralatan 0.00


D Jumlah harga tenaga, Bahan, dan Peralatan (A+B+C) 8,737.50
E Overhead + Profit (10%) 10% xD 873.75

F Harga satuan pekerjaan 9,611.25

T.03 Cabut 1 tunggul pohon tanaman keras diameter >15 cm dan membuang sisa tunggul kayu
dan akar-akar nya
No Uraian Kode Satuan Koefisien Harga Satuan Jumlah
A Tenaga Kerja
Pekerja L.01 OH 0.2000 100,000 20,000.00
Mandor L.04 OH 0.0200 165,000 3,300.00
Jumlah Harga Tenaga 23,300.00
B Bahan
Jumlah Harga Bahan 0.00
C Peralatan
Chainsaw E.06 Sewa-hari 0.1000

Jumlah Harga Peralatan 0.00


D Jumlah harga tenaga, Bahan, dan Peralatan (A+B+C) 23,300.00
E Overhead + Profit (10%) 10% xD 2330

F Harga satuan pekerjaan 25,630.00

b Uitzet trase saluran dan pasang profil melintang penampang


T.04 1muitset trase saluran
No Uraian Kode Satuan Koefisien Harga Satuan Jumlah
A Tenaga Kerja
Pekerja L.01 OH 0.0120 100,000 1,200.00
Pembantu Juru Ukur L.06 OH 0.0040 140,000 560.00
Juru Ukur L.05 OH 0.0040 140,000 560.00
Jumlah Harga Tenaga 2,320.00
B Bahan

Jumlah Harga Bahan


C Peralatan
Waterpass E.50 Sewa-hari 0.0040 200000 800.00
Theodolith E.41 Sewa-hari 0.0040 0 -
Jumlah Harga Peralatan 800.00
D Jumlah harga tenaga, Bahan, dan Peralatan (A+B+C) 6,240.00
E Overhead + Profit (10%) 10% xD 624.00

F Harga satuan pekerjaan 6,864.00

T.05 Pasang 1 m' profil melintang galian tanah


No Uraian Kode Satuan Koefisien Harga Satuan Jumlah
A Tenaga Kerja
Pekerja L.01 OH 0.0600 100,000 6,000.00
Tukang kayu L.02 OH 0.0200 140,000 2,800.00
Mandor L.04 OH 0.0060 165,000 990.00
Juru Ukur L.05 OH 0.0200 140,000 2,800.00
Pembantu juru ukur L.06 OH 0.0200 140,000 2,800.00
Jumlah Harga Tenaga 15,390.00
B Bahan
Kayu balok M.33.d m3 0.0025 5,600,000 14,000.00
Kayu papan M.35.e m3 0.0042 5,600,000 23,520.00
Paku campur M.65.b kg 0.2000 73,629 14,725.71
Jumlah Harga Bahan 52,245.71
C Peralatan

Jumlah Harga Peralatan


D Jumlah harga tenaga, Bahan, dan Peralatan (A+B+C) 67,635.71
E Overhead + Profit (10%) 10% xD 6,763.57
F Harga satuan pekerjaan 74,399.29

c. Pekerjaan Tanah Secara Manual ( T.06 s/d T.11, galian tanah sudah termasuk pembuangan hasil
galian dengan jarak angkut L < 3m serta perataan dan perapihan )
T.06 1 M3 Galian Tanah Biasa sedalam < 1 m
No Uraian Kode Satuan Koefisien Harga Satuan Jumlah
A Tenaga Kerja
Pekerja L.01 OH 0.5630 100,000 56,300.00
Mandor L.04 OH 0.0563 165,000 9,289.50
Jumlah Harga Tenaga
B Bahan
Jumlah Harga Bahan
C Peralatan

Jumlah Harga Peralatan


D Jumlah harga tenaga, Bahan, dan Peralatan (A+B+C) 65,589.50
E Overhead + Profit (10%) 10% xD 6,558.95

F Harga satuan pekerjaan 72,148.45

T.06 a. Galian Tanah Biasa sedalam 1 m < 2 m


No Uraian Kode Satuan Koefisien Harga Satuan Jumlah
A Tenaga Kerja
Pekerja L.01 OH 0.6750 100,000 67,500.00
Mandor L.04 OH 0.0675 165,000 11,137.50
Jumlah Harga Tenaga
B Bahan
Jumlah Harga Bahan 0
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah harga tenaga, Bahan, dan Peralatan (A+B+C) 78,637.50
E Overhead + Profit (10%) 10% xD 7,863.75

F Harga satuan pekerjaan 86,501.25

T.06 b. Galian Tanah Biasa sedalam 2 m < 3 m


No Uraian Kode Satuan Koefisien Harga Satuan Jumlah
A Tenaga Kerja
Pekerja L.01 OH 0.7600 100,000 76,000.00
Mandor L.04 OH 0.0760 165,000 12,540.00
Jumlah Harga Tenaga
B Bahan
Jumlah Harga Bahan 0
C Peralatan
Jumlah Harga Peralatan
D Jumlah harga tenaga, Bahan, dan Peralatan (A+B+C) 88,540.00
E Overhead + Profit (10%) 10% xD 8,854.00

F Harga satuan pekerjaan 97,394.00


T.06 c. Galian Tanah Biasa sedalam > 3 m tambahan koefisien untuk setiap penambahan
kedalaman 1 m
No Uraian Kode Satuan Koefisien Harga Satuan Jumlah
A Tenaga Kerja
Pekerja L.01 OH 0.0700 100,000 7,000.00
Mandor L.04 OH 0.0070 165,000 1,155.00
Jumlah Harga Tenaga
B Bahan
Jumlah Harga Bahan 0
C Peralatan
Jumlah Harga Peralatan 0
D Jumlah harga tenaga, Bahan, dan Peralatan (A+B+C) 8,155.00
E Overhead + Profit (10%) 10% xD 815.50

F Harga satuan pekerjaan 8,970.50

T.07 a. Galian Tanah Berbatu sedalam < 1 m


No Uraian Kode Satuan Koefisien Harga Satuan Jumlah
A Tenaga Kerja
Pekerja L.01 OH 1.3510 100,000 135,100.00
Mandor L.04 OH 0.1351 165,000 22,291.50
Jumlah Harga Tenaga
B Bahan
Jumlah Harga Bahan
C Peralatan
Jack hammer E.14 sewa-hari 0.1500

Jumlah Harga Peralatan


D Jumlah harga tenaga, Bahan, dan Peralatan (A+B+C) 157,391.50
E Overhead + Profit (10%) 10% xD 15,739.15

F Harga satuan pekerjaan 173,130.65

T.07 b. Galian Tanah Berbatu sedalam 1 m < 2 m


No Uraian Kode Satuan Koefisien Harga Satuan Jumlah
A Tenaga Kerja
Pekerja L.01 OH 1.5000 100,000 150,000.00
Mandor L.04 OH 0.1500 165,000 24,750.00
Jumlah Harga Tenaga 174,750.00
B Bahan
Jumlah Harga Bahan
C Peralatan
Jack hammer E.14 sewa-hari 0.1500
Jumlah Harga Peralatan
D Jumlah harga tenaga, Bahan, dan Peralatan (A+B+C) 174,750.00
E Overhead + Profit (10%) 10% xD 17,475.00

F Harga satuan pekerjaan 192,225.00


T.07 c. Galian Tanah Berbatu sedalam 2 m < 3 m
No Uraian Kode Satuan Koefisien Harga Satuan Jumlah
A Tenaga Kerja
Pekerja L.01 OH 1.6500 100,000 165,000.00
Mandor L.04 OH 0.1650 165,000 27,225.00
Jumlah Harga Tenaga
B Bahan
Jumlah Harga Bahan
C Peralatan
Jack hammer E.14 sewa-hari 0.1500

Jumlah Harga Peralatan


D Jumlah harga tenaga, Bahan, dan Peralatan (A+B+C) 192,225.00
E Overhead + Profit (10%) 10% xD 19,222.50

F Harga satuan pekerjaan 211,447.50

T.07 Galian Tanah Berbatu sedalam > 3 m, tambahan koefisien untuk setiap penambahan
kedalaman 1 m
No Uraian Kode Satuan Koefisien Harga Satuan Jumlah
A Tenaga Kerja
Pekerja L.01 OH 0.1500 100,000 15,000.00
Mandor L.04 OH 0.0150 165,000 2,475.00
Jumlah Harga Tenaga
B Bahan
Jumlah Harga Bahan
C Peralatan
Jack hammer E.14 sewa-hari 0.1500

Jumlah Harga Peralatan


D Jumlah harga tenaga, Bahan, dan Peralatan (A+B+C) 17,475.00
E Overhead + Profit (10%) 10% xD 1,747.50

F Harga satuan pekerjaan 19,222.50

T.08 Galian Batu sedalam <= 1 m


No Uraian Kode Satuan Koefisien Harga Satuan Jumlah
A Tenaga Kerja
Pekerja L.01 OH 3.3780 100,000 337,800.00
Mandor L.04 OH 0.3378 165,000 55,737.00
Jumlah Harga Tenaga
B Bahan
Jumlah Harga Bahan
C Peralatan
Jack hammer E.14 sewa-hari 0.3300

Jumlah Harga Peralatan


D Jumlah harga tenaga, Bahan, dan Peralatan (A+B+C) 393,537.00
E Overhead + Profit (10%) 10% xD 39,353.70

F Harga satuan pekerjaan 432,890.70


T.08 Galian Batu sedalam s/d 2 m
No Uraian Kode Satuan Koefisien Harga Satuan Jumlah
A Tenaga Kerja
Pekerja L.01 OH 3.7500 100,000 375,000.00
Mandor L.04 OH 0.3750 165,000 61,875.00
Jumlah Harga Tenaga
B Bahan
Jumlah Harga Bahan
C Peralatan
Jack hammer E.14 sewa-hari 0.3300

Jumlah Harga Peralatan


D Jumlah harga tenaga, Bahan, dan Peralatan (A+B+C) 436,875.00
E Overhead + Profit (10%) 10% xD 43,687.50

F Harga satuan pekerjaan 480,562.50

T.08 Galian Batu sedalam s/d3 m


No Uraian Kode Satuan Koefisien Harga Satuan Jumlah
A Tenaga Kerja
Pekerja L.01 OH 4.1250 100,000 412,500.00
Mandor L.04 OH 0.4130 165,000 68,145.00
Jumlah Harga Tenaga
B Bahan
Jumlah Harga Bahan
C Peralatan
Jack hammer E.14 sewa-hari 0.3300

Jumlah Harga Peralatan


D Jumlah harga tenaga, Bahan, dan Peralatan (A+B+C) 480,645.00
E Overhead + Profit (10%) 10% xD 48,064.50

F Harga satuan pekerjaan 528,709.50

T.08 Galian Batu dengan kedalaman >3 m, tambahan koefisien setiap penambahan kedalaman 1 m
No Uraian Kode Satuan Koefisien Harga Satuan Jumlah
A Tenaga Kerja
Pekerja L.01 OH 0.3750 100,000 37,500.00
Mandor L.04 OH 0.0375 165,000 6,187.50
Jumlah Harga Tenaga
B Bahan
Jumlah Harga Bahan
C Peralatan
Jack hammer *) E.14 sewa-hari 0.3300

Jumlah Harga Peralatan


D Jumlah harga tenaga, Bahan, dan Peralatan (A+B+C) 43,687.50
E Overhead + Profit (10%) 10% xD 4,368.75
F Harga satuan pekerjaan 48,056.25

T.09 Galian Tanah Cadas atau tanah keras <= 1 m


No Uraian Kode Satuan Koefisien Harga Satuan Jumlah
A Tenaga Kerja
Pekerja L.01 OH 1.2500 100,000 125,000.00
Mandor L.04 OH 0.1250 165,000 20,625.00
Jumlah Harga Tenaga
B Bahan
Jumlah Harga Bahan
C Peralatan
Jack hammer *) E.14 sewa-hari 0.1250

Jumlah Harga Peralatan


D Jumlah harga tenaga, Bahan, dan Peralatan (A+B+C) 145,625.00
E Overhead + Profit (10%) 10% xD 14,562.50

F Harga satuan pekerjaan 160,187.50

T.09 Galian Tanah Cadas atau tanah keras s/d 2 m


No Uraian Kode Satuan Koefisien Harga Satuan Jumlah
A Tenaga Kerja
Pekerja L.01 OH 1.3920 100,000 139,200.00
Mandor L.04 OH 0.1392 165,000 22,968.00
Jumlah Harga Tenaga
B Bahan
Jumlah Harga Bahan
C Peralatan
Jack hammer *) E.14 sewa-hari 0.1250

Jumlah Harga Peralatan


D Jumlah harga tenaga, Bahan, dan Peralatan (A+B+C) 162,168.00
E Overhead + Profit (10%) 10% xD 16,216.80

F Harga satuan pekerjaan 178,384.80

T.09 Galian Tanah Cadas atau tanah keras s/d 3 m


No Uraian Kode Satuan Koefisien Harga Satuan Jumlah
A Tenaga Kerja
Pekerja L.01 OH 1.5000 100,000 150,000.00
Mandor L.04 OH 0.1500 165,000 24,750.00
Jumlah Harga Tenaga
B Bahan
Jumlah Harga Bahan
C Peralatan
Jack hammer *) E.14 sewa-hari 0.1250

Jumlah Harga Peralatan


D Jumlah harga tenaga, Bahan, dan Peralatan (A+B+C) 174,750.00
E Overhead + Profit (10%) 10% xD 17,475.00
F Harga satuan pekerjaan 192,225.00

T.09 Galian Tanah Cadas atau tanah keras > 3 m, tambahan koefisien setiap penambahan kedalaman 1 m
No Uraian Kode Satuan Koefisien Harga Satuan Jumlah
A Tenaga Kerja
Pekerja L.01 OH 0.1000 100,000 10,000.00
Mandor L.04 OH 0.0100 165,000 1,650.00
Jumlah Harga Tenaga
B Bahan
Jumlah Harga Bahan
C Peralatan
Jack hammer *) E.14 sewa-hari 0.1250

Jumlah Harga Peralatan


D Jumlah harga tenaga, Bahan, dan Peralatan (A+B+C) 11,650.00
E Overhead + Profit (10%) 10% xD 1,165.00

F Harga satuan pekerjaan 12,815.00

T.10 Galian Lumpur sedalam < = 1 m


No Uraian Kode Satuan Koefisien Harga Satuan Jumlah
A Tenaga Kerja
Pekerja L.01 OH 0.8330 100,000 83,300.00
Mandor L.04 OH 0.0833 165,000 13,744.50
Jumlah Harga Tenaga
B Bahan
Jumlah Harga Bahan
C Peralatan

Jumlah Harga Peralatan


D Jumlah harga tenaga, Bahan, dan Peralatan (A+B+C) 97,044.50
E Overhead + Profit (10%) 10% xD 9,704.45

F Harga satuan pekerjaan 106,748.95

T.10 Galian Lumpur sedalam s/d 2 m


No Uraian Kode Satuan Koefisien Harga Satuan Jumlah
A Tenaga Kerja
Pekerja L.01 OH 1.2200 100,000 122,000.00
Mandor L.04 OH 0.1220 165,000 20,130.00
Jumlah Harga Tenaga
B Bahan
Jumlah Harga Bahan
C Peralatan

Jumlah Harga Peralatan


D Jumlah harga tenaga, Bahan, dan Peralatan (A+B+C) 142,130.00
E Overhead + Profit (10%) 10% xD 14,213.00

F Harga satuan pekerjaan 156,343.00

T.10 1 m3 Galian Lumpur sedalam s/d 3 m


No Uraian Kode Satuan Koefisien Harga Satuan Jumlah
A Tenaga Kerja
Pekerja L.01 OH 1.5500 100,000 155,000.00
Mandor L.04 OH 0.1550 165,000 25,575.00
Jumlah Harga Tenaga
B Bahan
Jumlah Harga Bahan
C Peralatan

Jumlah Harga Peralatan


D Jumlah harga tenaga, Bahan, dan Peralatan (A+B+C) 180,575.00
E Overhead + Profit (10%) 10% xD 18,057.50

F Harga satuan pekerjaan 198,632.50

T.10 1 m3 Galian Lumpur sedalam > 3 m, tambahan koefisien untuk setiap penambahan kedalaman 1 m
No Uraian Kode Satuan Koefisien Harga Satuan Jumlah
A Tenaga Kerja
Pekerja L.01 OH 0.1000 100,000 10,000.00
Mandor L.04 OH 0.0100 165,000 1,650.00
Jumlah Harga Tenaga
B Bahan
Jumlah Harga Bahan
C Peralatan

Jumlah Harga Peralatan


D Jumlah harga tenaga, Bahan, dan Peralatan (A+B+C) 11,650.00
E Overhead + Profit (10%) 10% xD 1,165.00

F Harga satuan pekerjaan 12,815.00

T.11 1 m3 Galian Pasir untuk pondasi bangunan sedalam s/d 1 m


No Uraian Kode Satuan Koefisien Harga Satuan Jumlah
A Tenaga Kerja
Pekerja L.01 OH 0.6630 100,000 66,300.00
Mandor L.04 OH 0.0660 165,000 10,890.00
Jumlah Harga Tenaga
B Bahan
Jumlah Harga Bahan
C Peralatan

Jumlah Harga Peralatan


D Jumlah harga tenaga, Bahan, dan Peralatan (A+B+C) 77,190.00
E Overhead + Profit (10%) 10% xD 7,719.00

F Harga satuan pekerjaan 84,909.00

T.11 1 m3 Galian Pasir untuk pondasi bangunan sedalam s/d 2 m


No Uraian Kode Satuan Koefisien Harga Satuan Jumlah
A Tenaga Kerja
Pekerja L.01 OH 0.7950 100,000 79,500.00
Mandor L.04 OH 0.0800 165,000 13,200.00
Jumlah Harga Tenaga
B Bahan
Jumlah Harga Bahan
C Peralatan

Jumlah Harga Peralatan


D Jumlah harga tenaga, Bahan, dan Peralatan (A+B+C) 92,700.00
E Overhead + Profit (10%) 10% xD 9,270.00

F Harga satuan pekerjaan 101,970.00

T.11 1 m3 Galian Pasir untuk pondasi bangunan sedalam s/d 3 m


No Uraian Kode Satuan Koefisien Harga Satuan Jumlah
A Tenaga Kerja
Pekerja L.01 OH 0.9000 100,000 90,000.00
Mandor L.04 OH 0.0900 165,000 14,850.00
Jumlah Harga Tenaga
B Bahan
Jumlah Harga Bahan
C Peralatan

Jumlah Harga Peralatan


D Jumlah harga tenaga, Bahan, dan Peralatan (A+B+C) 104,850.00
E Overhead + Profit (10%) 10% xD 10,485.00

F Harga satuan pekerjaan 115,335.00

T.11 1 m3 Galian Pasir untuk pondasi bangunan sedalam > 3 m, tambahan koefisien setiap penambahan kedalaman 1 m
No Uraian Kode Satuan Koefisien Harga Satuan Jumlah
A Tenaga Kerja
Pekerja L.01 OH 0.1000 100,000 10,000.00
Mandor L.04 OH 0.0100 165,000 1,650.00
Jumlah Harga Tenaga
B Bahan
Jumlah Harga Bahan
C Peralatan
Jumlah Harga Peralatan
D Jumlah harga tenaga, Bahan, dan Peralatan (A+B+C) 11,650.00
E Overhead + Profit (10%) 10% xD 1,165.00

F Harga satuan pekerjaan 12,815.00

T.14 1 m3 Timbunan tanah atau urugan tanah kembali


No Uraian Kode Satuan Koefisien Harga Satuan Jumlah
A Tenaga Kerja
Pekerja L.01 OH 0.3300 100,000 33,000.00
Mandor L.04 OH 0.0330 165,000 5,445.00
Jumlah Harga Tenaga
B Bahan
Jumlah Harga Bahan
C Peralatan

Jumlah Harga Peralatan


D Jumlah harga tenaga, Bahan, dan Peralatan (A+B+C) 38,445.00
E Overhead + Profit (10%) 10% xD 3,844.50

F Harga satuan pekerjaan 42,289.50

T.14 1 m3 Pemadatan tanah


No Uraian Kode Satuan Koefisien Harga Satuan Jumlah
A Tenaga Kerja
Pekerja L.01 OH 0.5000 100,000 50,000.00
Mandor L.04 OH 0.0500 165,000 8,250.00
Jumlah Harga Tenaga
B Bahan
Jumlah Harga Bahan
C Peralatan
Pemadat timbunan (stamper) E.31 Sewa-hari 0.0500

Jumlah Harga Peralatan


D Jumlah harga tenaga, Bahan, dan Peralatan (A+B+C) 58,250.00
E Overhead + Profit (10%) 10% xD 5,825.00

F Harga satuan pekerjaan 64,075.00

T.14 1 m3 Timbunan pasir sebagai bahan pengisi


No Uraian Kode Satuan Koefisien Harga Satuan Jumlah
A Tenaga Kerja
Pekerja L.01 OH 0.4000 100,000 40,000.00
Mandor L.04 OH 0.0400 165,000 6,600.00
Jumlah Harga Tenaga
B Bahan
Pasir pasang M.14.b m3 1.2000 M3
Jumlah Harga Bahan
C Peralatan
Jumlah Harga Peralatan
D Jumlah harga tenaga, Bahan, dan Peralatan (A+B+C) 46,600.00
E Overhead + Profit (10%) 10% xD 4,660.00

F Harga satuan pekerjaan 51,260.00

T.14 1 m3 Pemadatan pasir sebagai bahan pengisi


No Uraian Kode Satuan Koefisien Harga Satuan Jumlah
A Tenaga Kerja
Pekerja L.01 OH 0.1000 100,000 10,000.00
Mandor L.04 OH 0.0100 165,000 1,650.00
Jumlah Harga Tenaga
B Bahan

Jumlah Harga Bahan


C Peralatan
Pemadat Timbunan (stamper) E.31 Sewa-hari 0.1000

Jumlah Harga Peralatan


D Jumlah harga tenaga, Bahan, dan Peralatan (A+B+C) 11,650.00
E Overhead + Profit (10%) 10% xD 1,165.00

F Harga satuan pekerjaan 12,815.00

T.15 Mengangkut 1 m3 hasil galian dengan jarak angkut > 3 m s/d 5 m


No Uraian Kode Satuan Koefisien Harga Satuan Jumlah
A Tenaga Kerja
Pekerja L.01 OH 0.2400 100,000 24,000.00
Mandor L.04 OH 0.0124 165,000 2,046.00
Jumlah Harga Tenaga
B Bahan

Jumlah Harga Bahan


C Peralatan

Jumlah Harga Peralatan


D Jumlah harga tenaga, Bahan, dan Peralatan (A+B+C) 26,046.00
E Overhead + Profit (10%) 10% xD 2,604.60

F Harga satuan pekerjaan 28,650.60

T.15 Mengangkut 1 m3 hasil galian dengan jarak angkut 5 m


No Uraian Kode Satuan Koefisien Harga Satuan Jumlah
A Tenaga Kerja
Pekerja L.01 OH 0.2680 100,000 26,800.00
Mandor L.04 OH 0.0134 165,000 2,211.00
Jumlah Harga Tenaga
B Bahan

Jumlah Harga Bahan


C Peralatan

Jumlah Harga Peralatan


D Jumlah harga tenaga, Bahan, dan Peralatan (A+B+C) 29,011.00
E Overhead + Profit (10%) 10% xD 2,901.10

F Harga satuan pekerjaan 31,912.10

T.15 Mengangkut 1 m3 hasil galian dengan jarak angkut 10 m


No Uraian Kode Satuan Koefisien Harga Satuan Jumlah
A Tenaga Kerja
Pekerja L.01 OH 0.2860 100,000 28,600.00
Mandor L.04 OH 0.0143 165,000 2,359.50
Jumlah Harga Tenaga
B Bahan

Jumlah Harga Bahan


C Peralatan

Jumlah Harga Peralatan


D Jumlah harga tenaga, Bahan, dan Peralatan (A+B+C) 30,959.50
E Overhead + Profit (10%) 10% xD 3,095.95

F Harga satuan pekerjaan 34,055.45

T.15 Mengangkut 1 m3 hasil galian dengan jarak angkut 30 m


No Uraian Kode Satuan Koefisien Harga Satuan Jumlah
A Tenaga Kerja
Pekerja L.01 OH 0.3560 100,000 35,600.00
Mandor L.04 OH 0.0178 165,000 2,937.00
Jumlah Harga Tenaga
B Bahan

Jumlah Harga Bahan


C Peralatan

Jumlah Harga Peralatan


D Jumlah harga tenaga, Bahan, dan Peralatan (A+B+C) 38,537.00
E Overhead + Profit (10%) 10% xD 3,853.70

F Harga satuan pekerjaan 42,390.70

T.15 Mengangkut 1 m3 hasil galian dengan jarak angkut 50 m


No Uraian Kode Satuan Koefisien Harga Satuan Jumlah
A Tenaga Kerja
Pekerja L.01 OH 0.4220 100,000 42,200.00
Mandor L.04 OH 0.0211 165,000 3,481.50
Jumlah Harga Tenaga
B Bahan

Jumlah Harga Bahan


C Peralatan

Jumlah Harga Peralatan


D Jumlah harga tenaga, Bahan, dan Peralatan (A+B+C) 45,681.50
E Overhead + Profit (10%) 10% xD 4,568.15

F Harga satuan pekerjaan 50,249.65

T.15 Mengangkut 1 m3 hasil galian dengan jarak angkut 100 m


No Uraian Kode Satuan Koefisien Harga Satuan Jumlah
A Tenaga Kerja
Pekerja L.01 OH 0.6000 100,000 60,000.00
Mandor L.04 OH 0.0300 165,000 4,950.00
Jumlah Harga Tenaga
B Bahan

Jumlah Harga Bahan


C Peralatan

Jumlah Harga Peralatan


D Jumlah harga tenaga, Bahan, dan Peralatan (A+B+C) 64,950.00
E Overhead + Profit (10%) 10% xD 6,495.00

F Harga satuan pekerjaan 71,445.00

T.15 Mengangkut 1 m3 hasil galian dengan jarak angkut 200 m


No Uraian Kode Satuan Koefisien Harga Satuan Jumlah
A Tenaga Kerja
Pekerja L.01 OH 0.9500 100,000 95,000.00
Mandor L.04 OH 0.0475 165,000 7,837.50
Jumlah Harga Tenaga
B Bahan

Jumlah Harga Bahan


C Peralatan

Jumlah Harga Peralatan


D Jumlah harga tenaga, Bahan, dan Peralatan (A+B+C) 102,837.50
E Overhead + Profit (10%) 10% xD 10,283.75

F Harga satuan pekerjaan 113,121.25


T.15 Mengangkut 1 m3 hasil galian dengan jarak angkut 300 m
No Uraian Kode Satuan Koefisien Harga Satuan Jumlah
A Tenaga Kerja
Pekerja L.01 OH 1.3000 100,000 130,000.00
Mandor L.04 OH 0.0650 165,000 10,725.00
Jumlah Harga Tenaga
B Bahan

Jumlah Harga Bahan


C Peralatan

Jumlah Harga Peralatan


D Jumlah harga tenaga, Bahan, dan Peralatan (A+B+C) 140,725.00
E Overhead + Profit (10%) 10% xD 14,072.50

F Harga satuan pekerjaan 154,797.50

T.15 Mengangkut 1 m3 hasil galian dengan jarak angkut 400 m


No Uraian Kode Satuan Koefisien Harga Satuan Jumlah
A Tenaga Kerja
Pekerja L.01 OH 1.6500 100,000 165,000.00
Mandor L.04 OH 0.0825 165,000 13,612.50
Jumlah Harga Tenaga
B Bahan

Jumlah Harga Bahan


C Peralatan

Jumlah Harga Peralatan


D Jumlah harga tenaga, Bahan, dan Peralatan (A+B+C) 178,612.50
E Overhead + Profit (10%) 10% xD 17,861.25

F Harga satuan pekerjaan 196,473.75

T.15 Mengangkut 1 m3 hasil galian dengan jarak angkut 500 m


No Uraian Kode Satuan Koefisien Harga Satuan Jumlah
A Tenaga Kerja
Pekerja L.01 OH 1.9500 100,000 195,000.00
Mandor L.04 OH 0.0975 165,000 16,087.50
Jumlah Harga Tenaga
B Bahan

Jumlah Harga Bahan


C Peralatan

Jumlah Harga Peralatan


D Jumlah harga tenaga, Bahan, dan Peralatan (A+B+C) 211,087.50
E Overhead + Profit (10%) 10% xD 21,108.75

F Harga satuan pekerjaan 232,196.25

T.15 Mengangkut 1 m3 hasil galian dengan jarak angkut 500 m


No Uraian Kode Satuan Koefisien Harga Satuan Jumlah
A Tenaga Kerja
Pekerja L.01 OH 1.9500 100,000 195,000.00
Mandor L.04 OH 0.0975 165,000 16,087.50
Jumlah Harga Tenaga
B Bahan

Jumlah Harga Bahan


C Peralatan

Jumlah Harga Peralatan


D Jumlah harga tenaga, Bahan, dan Peralatan (A+B+C) 211,087.50
E Overhead + Profit (10%) 10% xD 21,108.75

F Harga satuan pekerjaan 232,196.25


No No Tenaga Kerja Kode
1 Pekerja L.01 1
2 Tukang L.02
Tukang gali
Tukang batu/tembok
Tukang kayu
Tukang besi/besi beton
Tukang cat/pelitur
Tukang pipa/operator pompa
Tukang penganyam bronjong
Tukang tebas
Tukang las
3 Kepala Tukang L.03
4 Mandor L.04
5 Juru ukur L.05
6 Pembantu juru ukur L.06
7 Ahli alat berat L.07
8 Operator Alat Berat L.08
9 Pembantu operator L.09

10 Supir truk L.10


11 kenek truk L.11
12 Penjaga malam L.12
13 Juru gambar (drafter) L.13
14 Design Engineer L.14
15 Operator printer/ploter L.15
16 Lainnya L.16
0.0096 2.083333
1.05
1.532
2.347024
0.239492
0.489379
0.3720
0.0372

0.3750
0.0380
Kode
Ganco/Balincong T.01
Cangkul T.02
Sekop T.03
Sabit T.04
Sapu lidi T.05
Ekrak/Pengki T.06
Kereta Dorong T.07
Cetok/Sendok Tembok T.08
Ember/Timba T.09
Garu T.10
Sikat ijuk T.11
Hammer/Martil T.12
Parang T.13
Palu T.14
Linggis T.15
Kereta Dorong Besar T.16
Alat Perata T.17
Tempat Penggorengan Aspal T.18

Kuas T.19
Ampelas T.20
Sikat Baja T.21
Gunting Potong Baja T.22
Kunci Pembengkok T.23
Helmet T.24
Rompi T.25
Sepatu T.26
Roskam T.27
DAFTAR PERHITUNGAN BIAYA PE

B IAYA PE M I LI KAN
OPERASI (OWNERSHIP COST)
UMUR PER HARGA CRF B IAYA
KODE JENIS PERALATAN TENAGA ALAT TAHUN SETEMPAT i = 20 % DEPRESIASI ASURANSI PEMILIKAN
ALAT ( HP ) ( TAHUN ) ( JAM ) /JAM
(A) (W) (B) (C) (D) (E) (F)
i(1+i) ^A (90 % x B) x C (3 % + (3% x 10 %))xB (D)+(E)
(1+i)^A-1 W W
( Rp.) ( Rp.) ( Rp.)
1 2 3 4 5 6 7 8 9 10

E 020 EXCAVATOR 90.00 8.00 1,500.00 1,113,465,075.00 0.260609 174,107.69 24,496.23 198,603.93

E 010 MOTOR GRADER 100.00 8.00 1,500.00 1,036,234,112.50 0.260609 162,031.42 22,797.15 184,828.57
Produktivitas Alat excavator

V x Fb x Fa x60 V adalah kapasitas Bucket; m


Q= Fb adalah faktor Bucket,
T s x Fk
Fa adalah faktor efisiensi alat (Lihat Tabel 4 Bagian 1),
Fk adalah faktor pengembangan tanah,
Ts adalah waktu siklus; menit,
T1 adalah lama menggali, memuat, lain-lain (Lihat Tabel 6.3); menit
T2 adalah swing kembali dan lain-lain (Lihat Tabel 6.4); menit.
Ts = waktu gali + 2xwaktu putar + waktu buang

Waktu gali
Kondisi/kedalaman gali Ringan sedang agak sulit sulit
0-2m 6 9 15 26
2-4m 7 11 17 28
4 m lebih 8 13 19 30

Faktor efisiensi excavator


Baik 0.83
Sedang 0.75
Agak kurang 0.67
Kurang 0.58

Faktor pengembangan tanah


AYA PERALATAN
HARGA PREMIUM DI LOKASI Rp. 48,000.00
HARGA SOLAR DI LOKASI Rp. 55,128.57
HARGA PELUMAS DILOKASI Rp. 77,428.57
BIAYA OPERASI JUMLAH
( OPERATING COSTS ) BIAYA PROFIT TOTAL
SPARE BAHAN BIAYA PEMILIKAN & BIAYA
PARTS BAKAR PELUMAS OPERASI & OPERASI OVERHEAD / JAM
/ JAM / JAM
(G) (H) (I) (J) (K) (L) (M)
0,6 x D (15 % x HP x (O,6% x HP x (G)+(H)+(I) (J) + (F) 15 % x (K) (K) + (L)
x Harga BBM) Harga Pelumas)
( Rp.) ( Rp.) ( Rp.) (Rp.) (Rp.)
11 12 13 14 15 16 17

104,464.62 744,235.70 41,811.43 890,511.74 1,089,115.66 163,367.35 1,252,483.01

97,218.85 826,928.55 46,457.14 970,604.55 1,155,433.12 138,651.97 1,294,085.10


ANALISA HARGA SATUAN
GALIAN TANAH
(MENGGUNAKAN ALAT)

PROVINSI : PAPUA KABUPATEN : PUNCAK JAYA


KODE : (82)
PROSES : ANGGAPAN :
1. Digali dengan Excavator 1. Menggunakan tenaga alat berat (97,65 m3 / hari)
2. Permukaan Tanah dibentuk dan dirataka2. Galian dibuang dilokasi (tanpa angkutan)
dengan cara manual

TOTAL
A
PEKERJA VOLUME HARI KODE VOL UPAH (Rp / O/H)
.
(O/H)
Mandor 1.00 1.00 1.00 165,000.00
Pekerja 4.00 1.00 4.00 100,000.00

TOTAL HARGA (Rp /


B MATERIAL SATUAN KODE
VOL Unit)
Alat Bantu

HARI JAM HARGA (Rp /


C PERALATAN JUMLAH KODE
KERJA KERJA Jam)
Excavator 1.00 1.00 7.00 1,691,871.29
-

JUMLAH HA
OVERHEAD & PROFIT
HARGA SATUAN PEKERJAAN ( D + E )
Volume : 97.65 M3 Harga Sat 146,127.13
t berat (97,65 m3 / hari)
anpa angkutan)

SUB TOTAL
BIAYA (Rp)
(Rp)
165,000.00
400,000.00

PEKERJA 565,000.00
SUB TOTAL
BIAYA (Rp)
(Rp)

MATERIAL -
SUB TOTAL
BIAYA (Rp)
(Rp)
### 0.142857
-

PERALATAN ###
TOTAL (Rp) ###
1,861,214.85
###
per M3
1 Asphalt mixing plant E01 294 1 Asphalt mixing plant E01 2
2 Asphalt finisher E02 72.4 2 Asphalt finisher E02 72,4 1
3 Asphalt sprayer E03 4 3 Asphalt sprayer E03 4,0 85
4 Bulldozer 100-150 hp E04 155 4 Bulldozer 100-150 hp E04
5 Compressor 4000-6500 l\m E05 60 5 Compressor 4000-6500 l\m
6 Concrete mixer 0.3-0.6 m E06 20 6 Concrete mixer 0.3-0.6 m
7 Crane 10-15 ton E07 138 7 Crane 10-15 ton E07 138,0
8 Dump Truck 3.5 ton E08 100 8 Dump Truck 3.5 ton E08 10
9 Dump Truck 10 ton E09 190 9 Dump Truck 10 ton E09 19
10 Excavator 80-140 hp E10 133 10 Excavator 80-140 hp E10
11 Flat bed truck 3-4 m E11 190 11 Flat bed truck 3-4 m E11
12 Generator set E12 180 12 Generator set E12 180,0
13 Motor grader >100 hp E13 135 13 Motor grader >100 hp E1
14 Track Loader 75-100 hp E14 70 14 Track Loader 75-100 hp E
15 Wheel Loader 1.0-1.6 m E15 96 15 Wheel Loader 1.0-1.6 m
16 Three wheel roller 6-8 t E16 55 16 Three wheel roller 6-8 t E
17 Tandem roller 6-8 t. E17 82 17 Tandem roller 6-8 t. E17 8
18 Tire roller 8-10 t. E18 100.5 18 Tire roller 8-10 t. E18 100
19 Vibratory roller 5-8 t. E19 82 19 Vibratory roller 5-8 t. E19
20 Concrete vibrator E20 5.5 20 Concrete vibrator E20 5,5
21 Stone crusher E21 220 21 Stone crusher E21 220,0
22 Water pump 70-100 mm E22 6 22 Water pump 70-100 mm E
23 Water tanker 3000-4500 l. E23 100 23 Water tanker 3000-4500 l
24 Pedestrian roller E24 8.8 24 Pedestrian roller E24 8,8
25 Tamper E25 4.7 25 Tamper E25 4,7 121,00 T
26 Jack Hammer E26 0 1330 26 Jack Hammer E26 0,0 1.3
27 Fulvi mixer E27 27 Fulvi mixer E27 345,0 2.0
28 Concrete pump E28 28 Concrete pump E28 100,
29 Trailer 20 ton E29 29 Trailer 20 ton E29 175,0 2
30 Pile driver + hammer E30 30 Pile driver + hammer E30
31 Crane on track 35 ton E31 31 Crane on track 35 ton E3
32 Welding set E32 32 Welding set E32 40,0 250
33 Bore pile machine E33 33 Bore pile machine E33 15
34 Asphalt liquid mixer E34 34 Asphalt liquid mixer E34 5
35 Tronton E35 35 Tronton E35 150,0 15,0 T
36 Cold milling E36 36 Cold milling E36 248,0 1.
37 Rock drill breaker E37 37 Rock drill breaker E37 3,0
38 Cold recycler E38 38 Cold recycler E38 900,0 2
39 Hot recycler E39 39 Hot recycler E39 400,0 3,
40 Aggregat (chip) spreader E40 40 Aggregat (chip) spreader
41 Asphalt distributor E41 41 Asphalt distributor E41 11
42 Slip form paver E42 42 Slip form paver E42 105,0
43 Concrete pan mixer E43 43 Concrete pan mixer E43 1
44 Concrete breaker E44 44 Concrete breaker E44 29
45 Aspahlt tanker E45 45 Aspahlt tanker E45 190,0
46 Cement tanker E46 46 Cement tanker E46 190,0
47 Condrete mixer (350) E47 47 Condrete mixer (350) E47
48 Vibrating rammer E48 48 Vibrating rammer E48 4,2
49 Truk mixer (agitator) E49 49 Truk mixer (agitator) E49
50 Bore pile machine E50 50 Bore pile machine E50 12
51 Crane on track 75-100 ton E51 51 Crane on track 75-100 ton
52 Blending equipment E52 52 Blending equipment E52
53 Asphalt liquid mixer E34a 53 Asphalt liquid mixer E34a
54 Water jet E53 54 Water jet E53 - 600 Liter/
1 Asphalt mixing plant E01 294,0 60,0 T/Jam 4.818.593,08 1 Asphalt mixing plant E01 294,0 60,0 T/Jam 4.818.593,08
2 Asphalt finisher E02 72,4 10,0 Ton 820.779,19 2 Asphalt finisher E02 72,4 10,0 Ton 820.779,19
3 Asphalt sprayer E03 4,0 850,0 Liter 3 Asphalt sprayer E03 4,0 850,0 Liter
4 Bulldozer 100-150 hp E04 155,0 - - 402.799,43 4 Bulldozer 100-150 hp E04 155,0 - - 402.799,43
5 Compressor 4000-6500 l\m E05 60,0 5.000,0 CPM/(L/m) 106.890 5 Compressor 4000-6500 l\m E05 60,0 5.000,0 CPM/(L/m) 106.890
6 Concrete mixer 0.3-0.6 m E06 20,0 500,0 Liter 6 Concrete mixer 0.3-0.6 m E06 20,0 500,0 Liter
7 Crane 10-15 ton E07 138,0 15,0 Ton 7 Crane 10-15 ton E07 138,0 15,0 Ton
8 Dump Truck 3.5 ton E08 100,0 3,5 Ton 8 Dump Truck 3.5 ton E08 100,0 3,5 Ton
9 Dump Truck 10 ton E09 190,0 10,0 Ton 420.000.000 212.812,53 9 Dump Truck 10 ton E09 190,0 10,0 Ton 420.000.000 212.812,53
10 Excavator 80-140 hp E10 133,0 0,9 m 934.000.000 383.294,39 10 Excavator 80-140 hp E10 133,0 0,9 m 934.000.000 383.294,39
11 Flat bed truck 3-4 m E11 190,0 10,0 ton 11 Flat bed truck 3-4 m E11 190,0 10,0 ton
12 Generator set E12 180,0 135,0 KVA 277.104,99 12 Generator set E12 180,0 135,0 KVA 277.104,99
13 Motor grader >100 hp E13 135,0 10.800,0 - 327.468,61 13 Motor grader >100 hp E13 135,0 10.800,0 - 327.468,61
14 Track Loader 75-100 hp E14 70,0 0,8 m 14 Track Loader 75-100 hp E14 70,0 0,8 m
15 Wheel Loader 1.0-1.6 m E15 96,0 1,5 m 253.964,94 15 Wheel Loader 1.0-1.6 m E15 96,0 1,5 m 253.964,94
16 Three wheel roller 6-8 t E16 55,0 8,0 Ton 16 Three wheel roller 6-8 t E16 55,0 8,0 Ton
17 Tandem roller 6-8 t. E17 82,0 8,1 Ton 379.339,78 17 Tandem roller 6-8 t. E17 82,0 8,1 Ton 379.339,78
18 Tire roller 8-10 t. E18 100,5 9,0 Ton 335.448,22 18 Tire roller 8-10 t. E18 100,5 9,0 Ton 335.448,22
19 Vibratory roller 5-8 t. E19 82,0 7,1 Ton 316.831,09 19 Vibratory roller 5-8 t. E19 82,0 7,1 Ton 316.831,09
20 Concrete vibrator E20 5,5 25,0 - 18.353,23 20 Concrete vibrator E20 5,5 25,0 - 18.353,23
21 Stone crusher E21 220,0 50,0 T/Jam 21 Stone crusher E21 220,0 50,0 T/Jam
22 Water pump 70-100 mm E22 6,0 - - 22 Water pump 70-100 mm E22 6,0 - -
23 Water tanker 3000-4500 l. E23 100,0 4.000,0 Liter 155.193,02 23 Water tanker 3000-4500 l. E23 100,0 4.000,0 Liter 155.193,02
24 Pedestrian roller E24 8,8 835,00 Ton 24 Pedestrian roller E24 8,8 835,00 Ton
25 Tamper E25 4,7 121,00 Ton 25 Tamper E25 4,7 121,00 Ton
26 Jack Hammer E26 0,0 1.330,00 - 15.795,70 26 Jack Hammer E26 0,0 1.330,00 - 15.795,70
27 Fulvi mixer E27 345,0 2.005,00 - 27 Fulvi mixer E27 345,0 2.005,00 -
28 Concrete pump E28 100,0 8,00 m 155.156,84 28 Concrete pump E28 100,0 8,00 m 155.156,84
29 Trailer 20 ton E29 175,0 20,00 Ton 29 Trailer 20 ton E29 175,0 20,00 Ton
30 Pile driver + hammer E30 25,0 2,50 Ton 30 Pile driver + hammer E30 25,0 2,50 Ton
31 Crane on track 35 ton E31 125,0 35,0 Ton 31 Crane on track 35 ton E31 125,0 35,0 Ton
32 Welding set E32 40,0 250,0 Amp 32 Welding set E32 40,0 250,0 Amp
33 Bore pile machine E33 150,0 2.000,0 Meter 33 Bore pile machine E33 150,0 2.000,0 Meter
34 Asphalt liquid mixer E34 5,0 1.000,0 Liter 34 Asphalt liquid mixer E34 5,0 1.000,0 Liter
35 Tronton E35 150,0 15,0 Ton 35 Tronton E35 150,0 15,0 Ton
36 Cold milling E36 248,0 1.000,0 m 36 Cold milling E36 248,0 1.000,0 m
37 Rock drill breaker E37 3,0 - - 266.452,13 37 Rock drill breaker E37 3,0 - - 266.452,13
38 Cold recycler E38 900,0 2,2 M 38 Cold recycler E38 900,0 2,2 M
39 Hot recycler E39 400,0 3,0 M 39 Hot recycler E39 400,0 3,0 M
40 Aggregat (chip) spreader E40 115,0 3,5 M 40 Aggregat (chip) spreader E40 115,0 3,5 M
41 Asphalt distributor E41 115,0 4.000,0 Liter 41 Asphalt distributor E41 115,0 4.000,0 Liter
42 Slip form paver E42 105,0 2,5 M 426.628,68 42 Slip form paver E42 105,0 2,5 M 426.628,68
43 Concrete pan mixer E43 134,0 600,0 Liter 493.265,26 43 Concrete pan mixer E43 134,0 600,0 Liter 493.265,26
44 Concrete breaker E44 290,0 20,0 m/jam 44 Concrete breaker E44 290,0 20,0 m/jam
45 Aspahlt tanker E45 190,0 4.000,0 liter 45 Aspahlt tanker E45 190,0 4.000,0 liter
46 Cement tanker E46 190,0 4.000,0 liter 46 Cement tanker E46 190,0 4.000,0 liter
47 Condrete mixer (350) E47 20,0 350,0 liter 47 Condrete mixer (350) E47 20,0 350,0 liter
48 Vibrating rammer E48 4,2 80,0 KG 48 Vibrating rammer E48 4,2 80,0 KG
49 Truk mixer (agitator) E49 220,0 5,0 M 449.232,73 49 Truk mixer (agitator) E49 220,0 5,0 M 449.232,73
50 Bore pile machine E50 125,0 60,0 CM 50 Bore pile machine E50 125,0 60,0 CM
51 Crane on track 75-100 ton E51 200,0 75,0 Ton 51 Crane on track 75-100 ton E51 200,0 75,0 Ton
52 Blending equipment E52 50,0 30,0 Ton 52 Blending equipment E52 50,0 30,0 Ton
53 Asphalt liquid mixer E34a 40,0 20.000,0 Liter 53 Asphalt liquid mixer E34a 40,0 20.000,0 Liter
54 Water jet E53 - 600 Liter/Jam 18.534,21 54 Water jet E53 - 600 Liter/Jam 18.534,21
4.818.593,08 1 Asphalt mixing plant E01 294,0 60,0 T/Jam 4.818.593,08 1 Asphalt mixing plant E01 294,0 60,0 T/Jam 4.
2 Asphalt finisher E02 72,4 10,0 Ton 820.779,19 2 Asphalt finisher E02 72,4 10,0 Ton 820.779,1
3 Asphalt sprayer E03 4,0 850,0 Liter 3 Asphalt sprayer E03 4,0 850,0 Liter
4 Bulldozer 100-150 hp E04 155,0 - - 402.799,43 4 Bulldozer 100-150 hp E04 155,0 - - 402.799,4
0,0 CPM/(L/m) 106.890 5 Compressor 4000-6500 l\m E05 60,0 5.000,0 CPM/(L/m) 106.890 5 Compressor 4000-6500 l\m E05 60,0 5.000,0
6 Concrete mixer 0.3-0.6 m E06 20,0 500,0 Liter 6 Concrete mixer 0.3-0.6 m E06 20,0 500,0 Lit
7 Crane 10-15 ton E07 138,0 15,0 Ton 7 Crane 10-15 ton E07 138,0 15,0 Ton
8 Dump Truck 3.5 ton E08 100,0 3,5 Ton 8 Dump Truck 3.5 ton E08 100,0 3,5 Ton
0.000.000 212.812,53 9 Dump Truck 10 ton E09 190,0 10,0 Ton 420.000.000 212.812,53 9 Dump Truck 10 ton E09 190,0 10,0 Ton 420.0
34.000.000 383.294,39 10 Excavator 80-140 hp E10 133,0 0,9 m 934.000.000 383.294,39 10 Excavator 80-140 hp E10 133,0 0,9 m 934.
11 Flat bed truck 3-4 m E11 190,0 10,0 ton 11 Flat bed truck 3-4 m E11 190,0 10,0 ton
12 Generator set E12 180,0 135,0 KVA 277.104,99 12 Generator set E12 180,0 135,0 KVA 277.104
0 - 327.468,61 13 Motor grader >100 hp E13 135,0 10.800,0 - 327.468,61 13 Motor grader >100 hp E13 135,0 10.800,0 -
14 Track Loader 75-100 hp E14 70,0 0,8 m 14 Track Loader 75-100 hp E14 70,0 0,8 m
253.964,94 15 Wheel Loader 1.0-1.6 m E15 96,0 1,5 m 253.964,94 15 Wheel Loader 1.0-1.6 m E15 96,0 1,5 m 2
16 Three wheel roller 6-8 t E16 55,0 8,0 Ton 16 Three wheel roller 6-8 t E16 55,0 8,0 Ton
17 Tandem roller 6-8 t. E17 82,0 8,1 Ton 379.339,78 17 Tandem roller 6-8 t. E17 82,0 8,1 Ton 379.33
18 Tire roller 8-10 t. E18 100,5 9,0 Ton 335.448,22 18 Tire roller 8-10 t. E18 100,5 9,0 Ton 335.448
19 Vibratory roller 5-8 t. E19 82,0 7,1 Ton 316.831,09 19 Vibratory roller 5-8 t. E19 82,0 7,1 Ton 316.8
20 Concrete vibrator E20 5,5 25,0 - 18.353,23 20 Concrete vibrator E20 5,5 25,0 - 18.353,23
21 Stone crusher E21 220,0 50,0 T/Jam 21 Stone crusher E21 220,0 50,0 T/Jam
22 Water pump 70-100 mm E22 6,0 - - 22 Water pump 70-100 mm E22 6,0 - -
00,0 Liter 155.193,02 23 Water tanker 3000-4500 l. E23 100,0 4.000,0 Liter 155.193,02 23 Water tanker 3000-4500 l. E23 100,0 4.000,
24 Pedestrian roller E24 8,8 835,00 Ton 24 Pedestrian roller E24 8,8 835,00 Ton
25 Tamper E25 4,7 121,00 Ton 25 Tamper E25 4,7 121,00 Ton
26 Jack Hammer E26 0,0 1.330,00 - 15.795,70 26 Jack Hammer E26 0,0 1.330,00 - 15.795,70
27 Fulvi mixer E27 345,0 2.005,00 - 27 Fulvi mixer E27 345,0 2.005,00 -
28 Concrete pump E28 100,0 8,00 m 155.156,84 28 Concrete pump E28 100,0 8,00 m 155.156,
29 Trailer 20 ton E29 175,0 20,00 Ton 29 Trailer 20 ton E29 175,0 20,00 Ton
30 Pile driver + hammer E30 25,0 2,50 Ton 30 Pile driver + hammer E30 25,0 2,50 Ton
31 Crane on track 35 ton E31 125,0 35,0 Ton 31 Crane on track 35 ton E31 125,0 35,0 Ton
32 Welding set E32 40,0 250,0 Amp 32 Welding set E32 40,0 250,0 Amp
33 Bore pile machine E33 150,0 2.000,0 Meter 33 Bore pile machine E33 150,0 2.000,0 Meter
34 Asphalt liquid mixer E34 5,0 1.000,0 Liter 34 Asphalt liquid mixer E34 5,0 1.000,0 Liter
35 Tronton E35 150,0 15,0 Ton 35 Tronton E35 150,0 15,0 Ton
36 Cold milling E36 248,0 1.000,0 m 36 Cold milling E36 248,0 1.000,0 m
37 Rock drill breaker E37 3,0 - - 266.452,13 37 Rock drill breaker E37 3,0 - - 266.452,13
38 Cold recycler E38 900,0 2,2 M 38 Cold recycler E38 900,0 2,2 M
39 Hot recycler E39 400,0 3,0 M 39 Hot recycler E39 400,0 3,0 M
40 Aggregat (chip) spreader E40 115,0 3,5 M 40 Aggregat (chip) spreader E40 115,0 3,5 M
41 Asphalt distributor E41 115,0 4.000,0 Liter 41 Asphalt distributor E41 115,0 4.000,0 Liter
42 Slip form paver E42 105,0 2,5 M 426.628,68 42 Slip form paver E42 105,0 2,5 M 426.628,68
r 493.265,26 43 Concrete pan mixer E43 134,0 600,0 Liter 493.265,26 43 Concrete pan mixer E43 134,0 600,0 Liter 4
44 Concrete breaker E44 290,0 20,0 m/jam 44 Concrete breaker E44 290,0 20,0 m/jam
45 Aspahlt tanker E45 190,0 4.000,0 liter 45 Aspahlt tanker E45 190,0 4.000,0 liter
46 Cement tanker E46 190,0 4.000,0 liter 46 Cement tanker E46 190,0 4.000,0 liter
47 Condrete mixer (350) E47 20,0 350,0 liter 47 Condrete mixer (350) E47 20,0 350,0 liter
48 Vibrating rammer E48 4,2 80,0 KG 48 Vibrating rammer E48 4,2 80,0 KG
49 Truk mixer (agitator) E49 220,0 5,0 M 449.232,73 49 Truk mixer (agitator) E49 220,0 5,0 M 449.2
50 Bore pile machine E50 125,0 60,0 CM 50 Bore pile machine E50 125,0 60,0 CM
51 Crane on track 75-100 ton E51 200,0 75,0 Ton 51 Crane on track 75-100 ton E51 200,0 75,0 T
52 Blending equipment E52 50,0 30,0 Ton 52 Blending equipment E52 50,0 30,0 Ton
53 Asphalt liquid mixer E34a 40,0 20.000,0 Liter 53 Asphalt liquid mixer E34a 40,0 20.000,0 Lite
54 Water jet E53 - 600 Liter/Jam 18.534,21 54 Water jet E53 - 600 Liter/Jam 18.534,21
E01 294,0 60,0 T/Jam 4.818.593,08
72,4 10,0 Ton 820.779,19
4,0 850,0 Liter
p E04 155,0 - - 402.799,43
500 l\m E05 60,0 5.000,0 CPM/(L/m) 106.890,74
0.6 m E06 20,0 500,0 Liter
7 138,0 15,0 Ton
E08 100,0 3,5 Ton
E09 190,0 10,0 Ton 420.000.000 212.812,53
hp E10 133,0 0,9 m 934.000.000 383.294,39
m E11 190,0 10,0 ton
180,0 135,0 KVA 277.104,99
hp E13 135,0 10.800,0 - 327.468,61
00 hp E14 70,0 0,8 m
1.6 m E15 96,0 1,5 m 253.964,94
6-8 t E16 55,0 8,0 Ton
. E17 82,0 8,1 Ton 379.339,78
18 100,5 9,0 Ton 335.448,22
t. E19 82,0 7,1 Ton 316.831,09
E20 5,5 25,0 - 18.353,23
220,0 50,0 T/Jam
0 mm E22 6,0 - -
-4500 l. E23 100,0 4.000,0 Liter 155.193,02
24 8,8 835,00 Ton

0,0 1.330,00 - 15.795,70


5,0 2.005,00 -
8 100,0 8,00 m 155.156,84
175,0 20,00 Ton
er E30 25,0 2,50 Ton
ton E31 125,0 35,0 Ton
0,0 250,0 Amp
E33 150,0 2.000,0 Meter
r E34 5,0 1.000,0 Liter

48,0 1.000,0 m
E37 3,0 - - 266.452,13
900,0 2,2 M

eader E40 115,0 3,5 M


E41 115,0 4.000,0 Liter
2 105,0 2,5 M 426.628,68
r E43 134,0 600,0 Liter 493.265,26
E44 290,0 20,0 m/jam
190,0 4.000,0 liter
6 190,0 4.000,0 liter
50) E47 20,0 350,0 liter
E48 4,2 80,0 KG
r) E49 220,0 5,0 M 449.232,73
E50 125,0 60,0 CM
100 ton E51 200,0 75,0 Ton
nt E52 50,0 30,0 Ton
r E34a 40,0 20.000,0 Liter
0 Liter/Jam 18.534,21
Biro Konsultan
CV. CENDANA CONSULTANT
Muliambut Mulia
Kabupaten Puncak Jaya

HARGA SATUAN BAHAN DAN UPAH


DISTRIK NIOGA

NO BAHAN/UPAH TENAGA KERJA KODE Satuan Harga Satuan Keterangan

1 2 3 4 5 6

I MATERIAL NON LOKAL


1 Semen PC M1 Kg 48,028.57
2 Semen warna M2 Kg 64,328.57
3 Tripleks 3 mm M3 Lbr 317,942.86
4 Tripleks 6 mm M4 Lbr 496,828.57
5 Teakwood 3 mm M5 Lbr 404,807.14
6 Seng Gelombang BJLS 20 M6 Lbr 205,385.71
7 Seng Plat BJLS 20 M8 Lbr 211,985.71
8 Keramik 20/20 cm M15 dos 963,414.29
9 Keramik 30/30 cm M16 dos 980,014.29
10 Keramik 40/40 cm M17 dos 1,013,214.29
11 Plint keramik 10/20 cm M19 dos 1,013,214.29
12 Besi beton polos M21 Kg 66,728.57
13 Besi siku 50.50.5 mm panjang 6 m (22,62 kg) M23 Btg 1,406,037.86 1 m = 3,77 kg
14 Besi Siku 30.30.3 mm panjang 6 m (8,16 kg) M24 Btg 600,273.63 1 m = 1,36 kg
15 Besi strip 50.5 mm panjang 6 m (11,78 kg) M25 Btg 691,618.93 1 m = 1,96 kg
16 Besi strip 20.2 mm panjang 6 m (1,86 kg) M26 Btg 137,283.03 1 m = 0,31 kg
17 baut mur 1/2" M27 Bh 17,682.14
17 Paku seng M47 Kg 79,128.57
18 Paku campur M48 Kg 73,628.57
19 Paku Tripleks M49 Kg 76,228.57
20 Kawat ikat M52 Kg 76,728.57
21 Kawat Harmonika lbr 1,5 m M55 M' 141,364.29
22 Kawat las M57 dos 475,742.86 1 dos = 5 kg
21 Kaca bening 5 mm M58 m2 819,141.43
22 Kaca riben 5 mm M59 m2 833,941.43
23 Stang nako 8 klip + kaca + tralis M61 set 1,425,663.00
24 Kunci Tanam 2 slaag (besar) M64 bh 317,119.64
25 Kunci Tanam 2 slaag (kecil) M65 bh 251,866.07
26 Engsel pintu M68 bh 53,397.14
27 Engsel Jendela M69 bh 43,447.86
28 Grendel Pintu M70 bh 50,047.86
29 Grendel Jendela M71 bh 46,173.21
30 Hak/Kait Angin M73 bh 62,997.14
31 Handle jendela M77 bh 27,832.86
32 Meni kayu M78 kg 81,328.57
33 Meni besi M79 Kg 81,328.57
34 Cat tembok M80 Kg 62,628.57
35 Cat kayu M82 Kg 126,028.57
36 Cat besi M83 Kg 119,328.57
37 Dempul kayu M89 Kg 74,828.57
38 Plamur tembok M92 Kg 66,728.57
39 Formtie M96 bh 16,949.29
40 Lem kayu M97 Kg 92,828.57
41 Lem PVC M99 Tube 13,932.86
42 Kuas biasa M100 bh 44,464.29
43 Kuas roll M101 bh 59,346.43
44 Kabel NYM 2 x 1,5 mm M105 roll 1,243,792.86

Harga Satuan Bahan dan Upah Kerja - 139


NO BAHAN/UPAH TENAGA KERJA KODE Satuan Harga Satuan Keterangan

1 2 3 4 5 6
45 Kabel NYM 2 x 2,5 mm M106 roll 1,462,936.00
46 Kabel NYM 3 x 2,5 mm M107 roll 1,594,299.43
47 Lampu philips 14W M112 bh 108,697.14
48 Lampu philips 18 W M113 bh 123,697.14
49 Stop kontak M121 bh 55,423.93
50 Saklar tunggal M122 bh 50,423.93
51 Saklar ganda M123 bh 55,423.93
52 Fitting duduk M124 bh 58,898.57
53 MCB 6 A M125 bh 93,298.57
54 Sekring Box M127 bh 109,746.43
55 Kloset Duduk KIA M128 set 3,881,957.14
56 Kloset Jongkok KIA M130 set 3,064,385.71
57 Washbak stainless steel M133 bh 895,978.57
58 Floor drain M137 bh 79,598.57
59 Kran air 1/2" M138 bh 47,223.93
60 Stop kran GIP dia 1/2" M139 bh 54,665.71

Harga Satuan Bahan dan Upah Kerja - 140


NO BAHAN/UPAH TENAGA KERJA KODE Satuan Harga Satuan Keterangan

1 2 3 4 5 6
61 Stop kran GIP dia 3/4" M140 bh 78,998.57
62 Pipa PVC dia 1/2" M146 Btg 60,364.29
63 Pipa PVC dia 3/4" M147 Btg 77,346.43
64 Seal tape M159 bh 15,463.29
65 Air Valve GIP dia 1" M248 bh 293,085.71
66 Solar M289 Ltr 55,128.57
67 Minyak pelumas M290 Ltr 77,428.57
68 Besi plat 2 mm M292 Lbr 3,352,300.99 1 lbr = 45,22 kg
69 Besi plat 3 mm M293 Lbr 5,028,401.50 1 lbr = 67,82 kg
70 Batu batako bh 25,000.00
71 Pengadaan Turbin Cross Flow T 15 kapasitas 200 KVA: Unit 2,129,807,142.86
72 Pengadaan Pipa besi dia 30", pjg=1,2 m, tebal = 4 mm Btg 9,132,857.14 1 btg = 74,93 kg
73 Expansion Joint 77,64 cm set 32,832,142.86 1 Set = 125 kg
74 Sambungan pipa (flange + baut + paking karet) dia 77,64 cm psg 10,418,871.43 1 Set = 62,5 kg
75 Besi profil C. 50. 38 mm panjang 6 m (33,42 Kg) Btg 2,255,850.00 1 m = 5,57 kg
76 Besi profil C 65.42 mm panjang 6 m (42,54 kg) Btg 2,870,000.00 1 m = 7,09 kg
77 Besi profil C 80.50 mm panjang 6 m (51,78 kg) Btg 3,495,150.00 1 m = 8,63 kg
78 Stang pintu air drag + mur set 5,538,457.14

II MATERIAL LOKAL
1 Batu kali M3 2,000,000.00
2 Pasir pasang M3 2,000,000.00
3 Pasir Cor M3 2,000,000.00
4 Pasir Beton M3 2,000,000.00
5 Pasir Urug M3 2,000,000.00
6 Kerikil pecah M3 2,500,000.00
7 Timbunan biasa M3 550,000.00
8 Kayu balok M3 5,600,000.00
9 Kayu Papan btg 5,600,000.00
10 Kayu cina M3 8,350,000.00
11 Balok 5/10 panjang 3 m M3 112,000.00
12 Papan les 1/4 Btg 7,700.00
13 List Kayu Profil 1/3 cm pjg 4m m' 19,250.00
III UPAH TENAGA KERJA
1 Pekerja L01 OH 100,000.00
2 Tukang Batu L02 OH 140,000.00
3 Tukang Kayu L02 OH 140,000.00
4 Tukang Besi L02 OH 140,000.00
5 Tukang Cat L02 OH 140,000.00
6 Tukang Listrik L02 OH 140,000.00
7 Tukang Las L02 OH 140,000.00
8 Tukang pipa L02 OH 140,000.00
9 Kepala Tukang L03 OH 165,000.00
10 Mandor L04 OH 165,000.00
11 Juru ukur L05 OH 140,000.00
12 Pembantu Juru ukur L06 OH 140,000.00
13 Pembantu Mekanik L07b OH 140,000.00
14 Mekanik L07 OH 165,000.00
15 Operator L08 OH 165,000.00
16 Pembantu Operator L09 OH 115,000.00
IV PERALATAN
1 Sewa Excavator Hari 11,843,099.03
2 Sewa Excavator jam 1,691,871.29
3 Sewa Molen Hari 500,000.00
4 Sewa Theodolit jam
5 Sewa Mesin las listrik jam 75,000.00
6 Sewa Genset jam 40,000.00
7 Sewa Tackel jam 40,000.00

Harga Satuan Bahan dan Upah Kerja - 141


NO BAHAN/UPAH TENAGA KERJA KODE Satuan Harga Satuan Keterangan

1 2 3 4 5 6
Mulia, 1 April 2014

Konsultan Perencana
CV. CENDANA CONSULTANT

NATALIA ALLOBUA, S.Sos.


Direktris

Harga Satuan Bahan dan Upah Kerja - 142


Perbandingan Komposisi Campuran perekat
HL Padat HL air Jumlah
1 bagian semen 0.51 0.25 0.76
1 bagian pasir 0.6 0.075 0.675
Jumlah perekat m3

Campuran 1:2 1:3 1:4 1:5 1:6 1:7 1:8


1 bagian semen 0.7600 0.7600 0.7600 0.7600 0.7600 0.7600 0.7600
1 bagian pasir 1.3500 2.0250 2.7000 3.3750 4.0500 4.7250 5.4000
Jumlah perekat m3 2.1100 2.7850 3.4600 4.1350 4.8100 5.4850 6.1600

Kebutuhan Bahan setiap 1 m3 perekat


Campuran 1:2 1:3 1:4 1:5 1:6 1:7 1:8
Semen (kg) 592.4171 448.8330 361.2717 302.2975 259.8753 227.8943 202.9221
Pasir (m3) 0.9479 1.0772 1.1561 1.2092 1.2474 1.2762 1.2987

Kebutuhan Bahan setiap 1 m2 plesteran tebal 1 cm


Tebal 1 0.01
Campuran 1:2 1:3 1:4 1:5 1:6 1:7 1:8
Semen (kg) 5.9242 4.4883 3.6127 3.0230 2.5988 2.2789 2.0292
Pasir (m3) 0.0095 0.0108 0.0116 0.0121 0.0125 0.0128 0.0130

Kebutuhan Bahan setiap 1 m2 plesteran tebal 1,5 cm


Tebal 1.5 0.015
Campuran 1:2 1:3 1:4 1:5 1:6 1:7 1:8
Semen (kg) 8.8863 6.7325 5.4191 4.5345 3.8981 3.4184 3.0438
Pasir (m3) 0.0142 0.0162 0.0173 0.0181 0.0187 0.0191 0.0195

Kebutuhan Bahan setiap 1 m2 plesteran tebal 2 cm


Tebal 2 0.02
Campuran 1:2 1:3 1:4 1:5 1:6 1:7 1:8
Semen (kg) 11.8483 8.9767 7.2254 6.0459 5.1975 4.5579 4.0584
Pasir (m3) 0.0190 0.0215 0.0231 0.0242 0.0249 0.0255 0.0260

Contoh
Kebutuhan Bahan setiap 1 m3 pas. Batu Batako (29x14x9)
1 m3 Batako dibutuhkan perekat 0.243425 m3
1 m3 Pas. Batu Kali dibutuhkan perekat 0.495 m3 224.01434
1:4 1:3 1:2 1:4 1:3 1:2
batu batako #DIV/0! #DIV/0! #DIV/0! batu batako 300.63 300.63 300.63
Semen (sak) 87.9425578 109.257181 144.209123 Semen (sak) 1.7589 2.19 2.88
Pasir (m3) 0.28141618 0.26221724 0.2307346 Pasir (m3) 0 0 0.0000
1:4 1:3 1:2 1:4 1:3 1:2
Batu Kali 1.20 1.20 1.20 1.20 1.20 1.20
Semen (kg) 178.82948 222.172352 293.246445 Semen (sak) 3.58 4.44 5.86
Pasir (m3) 0.57225434 0.53321364 0.46919431 Pasir (m3) 0 0 0.0000

Batu Kali 1:4 1:3 1:2


1.2 #DIV/0! #DIV/0! #DIV/0!
217.8649237473 #DIV/0! #DIV/0! #DIV/0!

1:4 1:3 1:2 1:4 1:3 1:2


Batako 250 250 250
Semen (kg) 0 0 0 Semen (sak) 0.00 0.00 0.00
Pasir (m3) 0 0 0 Pasir (m3) 0 0 0.0000

1 Kg Paku 1 1/2" 840 bh


beton 2.4
semen 1.5 1 1
pasir 1.6 2 2.1333333
kerikil 1.6 3 3.2
6.3333333

100

0.0520 19.24
0.1995842 3.84

8.23E+010

You might also like