Duration

Project Tasks Start Date End Date (Days) 1/30/2017 2/6/2017 2/13/2017 2/20/2017 2/27/2017
Days in class
this time
period 3 2 3 2 2
3.0 Design
Cont. &
Construction 1/30/2017 2/26/2017 28
3.3 Technical
Drawings 1/30/2017 2/5/2017 21
3.5 Cost 1/30/2017 2/5/2017 7
3.6 Tool
Selection 1/30/2017 2/5/2017 7
3.7 Tool Safety 1/30/2017 2/5/2017 7
3.4 Material List 2/13/2017 2/19/2017 7
3.9 Prototype
Build
Construction 2/13/2017 2/26/2017 14
4.0 Testing 1/30/2017 3/19/2017 49
4.2 Developing
Testing
Procedures 1/30/2017 2/12/2017 21
4.2a Cost
Testing
Procedures 1/30/2017 02/05/2017 7
4.2b Size and
Weight Testing
Procedures 1/30/2017 02/05/2017 7
4.2c
Performance
Testing
Procedures 1/30/2017 02/05/2017 7
4.2d Materials
Testing
Procedures 2/6/2017 2/12/2017 7
3/6/2017 3/13/2017 3/20/2017 3/27/2017 4/3/2017 4/10/2017 4/17/2017

2 3 2 3 2 0 2
4.2e Service
Life Testing
Procedures 2/6/2017 2/12/2017 7
4.3 Data
Collection 1/30/2017 2/12/2017 21
4.3a Cost Test 1/30/2017 2/12/2017 14
4.3b Size and
Weight Test 2/6/2017 2/19/2017 14
4.3c
Performance
Test 1/30/2017 2/12/2017 14
4.3d Materials
Test 2/6/2017 2/19/2017 14
4.3e Service
Life Test 2/6/2017 2/19/2017 14
4.4 Record Data 2/20/2017 3/5/2017 14
4.5 Redesign
and Refine 2/20/2017 3/5/2017 14
4.6 Determine
Conclusion 3/6/2017 3/12/2017 7
4.7 Critical
Design Review 3/6/2017 3/19/2017 14
4.8
Recommendati
ons 3/6/2017 3/19/2017 14
5.0
Documentation
and
Presentation 3/20/2017 4/28/2017 42
5.1
Presentation
Development 3/20/2017 4/9/2017 21
5.2 Juried Tech-
Ed
Presentations 4/3/2017 4/16/2017 14