Professional Documents
Culture Documents
REVISION 01
REVISION 01
REV No.: 01
PSWR-QUALITY
TABLE OF CONTENTS DATE: 05.05.2010
PAGE: 01 OF 01
******
QP NO.: QPE-BR-002
DOCUMENTS REFERRED
IN REV No.: 01
FIEDL QUALITY PLAN
PSWR-QUALITY DATE: 05.05.2010
PAGE: 01 OF 01
S. NO. Reference Document Issuing Authority
2. Wherever log sheet is not called for, suitable record shall be maintained in logbook/protocol.
4. QAE shall witness A category checks. He is also authorized to carry out surveillance in any of
B & C category of checks at his discretion.
5. Concerned agencies shall ensure that instruments having valid calibration are only used for
measurements.
6. Quantum of check shall be 100% for all characteristics unless otherwise mentioned specifically
in Field Quality Plan/ reference documents.
RECORD OF QUALITY CHECKS
PSWR-QUALITY
SHEET NO. OF CHECK NO. RESULTS ACHIEVED REFERENCE DRAWING/ FORMAT OF CHECKED BY ACCEPTED BY REMARKS
QPI OK/ NOT OK DOCUMENT RECORD SIGN. & DATE SIGN. & DATE
Note: Any protocol made is to be numbered & mentioned in Format of Record column.
SYSTEM SUB-SYSTEM AREA DOC NO.: QPE-BR-002
PROJECT REV NO.: 01
UNIT NO. LOG SHEET NO.: L-00
RATING SHEET:
INSTRUMENT REGN.NO.
DATE OF INSPECTION
U ROD MEASUREMENT
LEGEND:
LA Arm Length
R Radius of curvature
As As Measured
Sl.N
Description Per Left (C1) Right (C2) Tolerance
o.
Drg. Axis iv Axis ii Axis iv Axis ii
SIGNATURE &
NAME DOC.NO: QPE-BR-002
DATE
INSPECTED
PROJECT REV.NO. R00
BY
UNIT NO. CLEARED LOG SHEET NO.: L-01
RATING BY
CUSTOMER SHEET: 01 OF 01
INSTRUMENT REGN.NO.
DATE OF INSPECTION
REFERENCE DRG.NO..............................................................................
1. Disposition of Drum axis from centre line of ceiling girder: As per Drg. _____ mm
(Tolerance: 1 mm / M; Max. +/- 5 mm) Actual: A ______mm; B _____mm
DATE OF INSPECTION
DRUM ALIGNMENT
2. Spacing of drum axis with reference to centre line of ceiling As per Drg. ______ mm
Girder (Tolerance: 1 mm / M; Max. +/- 5 mm) Actual: A = _____ mm
B = _____ mm
3. Axial disposition of drum Centre with respect to longitudinal axis Actuals ____ mm
Of boiler. (Tolerance: 5 mm) Towards LHS / RHS
SIGNATURE &
NAME DOC.NO. QPE-BR-002
DATE
PROJECT INSPECTED REV.NO. R00
BY
CLEARED
UNIT NO. LOG SHEET NO.: L-02
BY
RATING CUSTOMER SHEET: 02 OF 02
INSTRUMENT REGN.NO.
DATE OF INSPECTION
2. Spacing : +/-3 mm
SIGNATURE / DATE
NAME DOC.NO. QPE-BR-002
INSPECTED
PROJECT REV. NO. R00
BY
UNIT NO. CLEARED BY LOG SHEET NO.: L-03
2. Spacing : +/- 3 mm
SIGNATURE / DATE
NAME DOC.NO. QPE-BR-002
INSPECTED
PROJECT REV. NO. R00
BY
UNIT NO. CLEARED BY LOG SHEET NO.: L-03
DATE OF INSPECTION
Boiler
Furnace
Front
Front
Back
Rear
Rear
pass
Axis
4 3
Right Right
Front wall Right side wall Rear wall Left side wall
Elevation
L M R F M RR L M R F M RR
SIGNATURE &
NAME DOC.NO. QPE-BR-002
DATE
PROJECT INSPECTED REV.NO. R00
BY
CLEARED
UNIT NO. LOG SHEET NO. L-04
BY
RATING CUSTOMER SHEET: 01 OF 01
INSTRUMENT REGN.NO.
DATE OF INSPECTION
A D2 D1 C A C
Boiler
Furnace
Front
Front
Back
Rear
Rear
pass
Axis
B D D
B
G Right H
G Right H
Below water wall Rear arch Above Water wall Rear arch
Elevation A B C D E F G H D1 D2
Note: At Rear arch elevation depth & width of furnace only to be logged.
DATE OF INSPECTION
A D1 D2 C
Axis
Boiler Axis
Front
Furnace
Rear
B D
G Right side H
Elevation A B C D E F G H D1 D2
As per Drg. -- --
Furnace Top
(near roof)
Actual -- --
As per Drg. -- --
Above LTSH
Actual -- --
As per Drg. -- --
Below Economiser
Actual -- --
As per Drg.
Bottom Header
Actual
SIGNATURE &
NAME DOC.NO. QPE-BR-002
DATE
PROJECT INSPECTED REV.NO. R00
BY
CLEARED
UNIT NO. LOG SHEET NO. L-05
BY
RATING CUSTOMER SHEET: 02 OF 03
INSTRUMENT REGN.NO.
DATE OF INSPECTION
FRONT
4 1
3 2
REAR
AS PER DRAWING:
_________ _________
_________ _________
SIGNATURE &
NAME DOC.NO. QPE-BR-002
DATE
PROJECT INSPECTED REV.NO. R00
BY
CLEARED
UNIT NO. LOG SHEET NO. L-05
BY
RATING CUSTOMER SHEET: 03 OF 03
INSTRUMENT REGN.NO.
DATE OF INSPECTION
SIGNATURE &
NAME DOC.NO. QPE-BR-002
DATE
PROJECT INSPECTED REV.NO. R00
BY
CLEARED
UNIT NO. LOG SHEET NO. L-06
BY
RATING CUSTOMER SHEET: 01 OF 02
INSTRUMENT REGN.NO.
DATE OF INSPECTION
SIGNATURE &
NAME DOC.NO. QPE-BR-002
DATE
PROJECT INSPECTED REV.NO. R00
BY
CLEARED
UNIT NO. LOG SHEET NO. L-06
BY
RATING CUSTOMER SHEET: 02 OF 02
INSTRUMENT REGN.NO.
DATE OF INSPECTION
Tolerance: +/- 10 mm
COIL LEFT RIGHT
Coil end pitch between Centre line of back As per Drawing
pass side wall and end coil assembly FRONT
Actuals
REAR
PITCH OF COILS
As per Drawing: ____ mm Tolerance: +/- 10 mm
DATE OF INSPECTION
SIGNATURE &
NAME DOC.NO. QPE-BR-002
DATE
PROJECT INSPECTED REV.NO. R00
BY
CLEARED
UNIT NO. LOG SHEET NO. L-07
BY
RATING CUSTOMER SHEET: 02 OF 03
INSTRUMENT REGN.NO.
DATE OF INSPECTION
As per Drawing:
Y1 = ____ mm Y2 = ___ mm
A = ____ mm B = ___ mm
Tolerance:
Y1 & Y2 = +/- 3 mm
A & B = +/-20 mm
ECO. Measured values ECO. Measured values
HANGER HANGER
TUBE NO. A Y1 Y2 B TUBE NO. A Y1 Y2 B
A - Spacing between back pass front wall and front ECO hanger tube.
B - Spacing between back pass rear wall and rear ECO hanger tube.
DATE OF INSPECTION
Tolerance: +/- 25 mm
PLATEN SH
COIL
LEFT RIGHT
Coil end pitch between Centre line of side
As per Drawing
wall and end coil assembly
FRONT
Actuals
REAR
DATE OF INSPECTION
Tolerance: +/-25 mm
Final Super Heater
COIL
Coil end pitch between LEFT RIGHT
Centre line of side wall and As per Drawing
end coil assembly FRONT
Actuals
REAR
DATE OF INSPECTION
Tolerance: +/- 10 mm
ECONOMISER
COIL
LEFT RIGHT
Coil end pitch between Centre line of side
As per Drawing
wall and end coil assembly
FRONT
Actuals
REAR
SIGNATURE &
NAME DOC.NO. QPE-BR-002
DATE
PROJECT INSPECTED REV.NO. R00
BY
CLEARED
UNIT NO. LOG SHEET NO. L-10
BY
RATING CUSTOMER SHEET: 01 OF 02
INSTRUMENT REGN.NO.
DATE OF INSPECTION
Tolerance: +/-20 mm
ECONOMISER
Clearance between Centre line of Back pass As per
FRONT REAR
Front / Rear wall and coil ends. Drawing
DATE OF INSPECTION
Tolerance: +/- 10 mm
RH FRONT RH REAR
Coil end pitch between COIL
LEFT RIGHT LEFT RIGHT
Centre line of side wall
and end coil assembly As per Drawing
Actuals
DATE OF INSPECTION
DATE OF INSPECTION
4. Locking of supports.
REMARKS:
DATE OF INSPECTION
REQUIREMENTS:
Reference Document :
OBSERVATION:
Date of test :
Test Witnessed by :
Details of Rectification
REMARKS:
Air test of Boiler at the pressure of ............ Kg / cm2 (g) carried out on ................... and
found satisfactory. The boiler is cleared for Hydraulic test.
SIGNATURE &
NAME DOC.NO. QPE-BR-002
DATE
PROJECT INSPECTED REV.NO. R00
BY
CLEARED
UNIT NO. LOG SHEET NO. L-13
BY
RATING CUSTOMER SHEET: 01 OF 02
INSTRUMENT REGN.NO.
DATE OF INSPECTION
NOTE: Failure at: 1- Butt weld, 2- Seal weld, 3- Attachment weld, 4- Hand hole plate weld, 5- Thermo well weld, 6- Cuts & gouges.
SIGNATURE / DATE
NAME DOC.NO. QPE-BR-002
INSPECTED
PROJECT REV. NO. R00
BY
UNIT NO. CLEARED BY LOG SHEET NO.: L-13
DATE OF INSPECTION
REQUIREMENTS:
Reference Document :
OBSERVATION:
Date of Filling :
Test Witnessed by :
REMARKS:
Hydraulic test of Boiler at the test pressure of ............ Kg / cm2 (g) carried out on
................... and found satisfactory. The boiler is cleared for further operation.
SIGNATURE &
NAME DOC.NO. QPE-BR-002
DATE
PROJECT INSPECTED REV.NO. R00
BY
CLEARED
UNIT NO. LOG SHEET NO. L-14
BY
RATING CUSTOMER SHEET: 01 OF 02