Professional Documents
Culture Documents
Power smart
Scott Macdonald
Manager, Freedom of Information and Privacy
16th Floor
Phone: (604) 623-3880
Fax: (604) 623-4556
29 May 2017
I am writing in response to your request under the Act for all agendas, minutes anp
Powerpoint and like presentations for the Site C Project Board Meetings since October 26,
2016, to the date of your request (December 14, 2016).
Response: We have attached 42 responsive pages, some of which have been redacted in
accordance with sections 17, 21, and 22 of the Act.
Section 17 of the Act permits a public body to withhold information the disclosure of which
could reasonably be expected to harm the financial or economic interests of a public body, or
is likely to have information which, if disclosed, could reasonably be expected to harm the
negotiating position of a public body. BC Hydro has redacted certain information on the
basis that disclosure could harm the negotiating position of BC Hydro with third parties
currently working on the Site C project.
Section 21 of the Act requires public bodies to withhold information, the disclosure of which
would reveal trade, commercial, financial, labor relations, scientific or technical information of
or about a third party that is supplied in confidence and if disclosed, could reasonably be
expected to harm significantly the competitive position or negotiating position of the third
party, or result in undue financial loss or gain to any person or organization. In view of its
section 21 obligations, BC Hydro has redacted certain information on the basis that
disclosure could cause undue financial loss or gain to third parties currently working on the
Site C project.
British Columbia Hydro and Power Authority, 333 Dunsmuir Street, Vancouver, BC, V6B 5R3
www.bchydro.com
2
Section 22 of the Act prohibits BC Hydro from disclosing the personal information of an
individual to a third party if the disclosure of that information would be an unreasonable
invasion of the individual's personal privacy, and BC Hydro has therefore redacted names of
third parties that are contained in the material. BC Hydro has also redacted the names of the
evaluators on the basis of section 22(3), which presumes that disclosure of personal
information related to the work history of individuals would be an unreasonable invasion of
their privacy.
If you have any questions regarding our response to your request for records, please call me.
You may also ask the Office of Information and Privacy Commissioner for BC ('the OIPC') to
review our response to your request. You have 30 days from the receipt of this letter to
request a review by writing to:
If you request a review, please provide the OIPC with a copy of this letter and a copy of your
request.
Yours truly,
Scott Macdonald
Attachments
British Columbia Hydro and Power Authority, 333 Dunsmuir Street, Vancouver, BC, V6B 5R3
www.bchydro.com
(I) BC Hydro
Power smart
Site C Clean Energy Project Board
18th Floor Boardroom, BC Hydro, 333 Dunsmuir Street, Vancouver, BC
14 November 2016 -11 :00 a.m. - 1 :00 p.m.
Agenda
Preliminary matters . 11:00
1. Minutes from Prior Meetings ...... ....... .. .......... .. ............ ... ................... .. .... .. . John Knappett Approval
o Overall Project
o Early Works
o Environmental Compliance
o First Nations
o Approvals
2
e BCHydro
Power smart
Overall Projec
3
CI> BC Hydro
Power smart
Key Project Activities to 111eet Project
Milestone for River Diversion Fall 2019
o Main Civil Works 1tw111 ltWi41
o Contractor re-sequence work so contrad milestones maintained for diversion
o Clearing required prior to Diversion - Lower Reservoir to Halfway River complete by March 2019
4 <:) BC Hydro
Power smart
Year 1 Key Milestones
\
Contract award:
Voith Hydro for
Turbines and
Generators
July 2015 December 2015 March 2016 June 2016 August 2016
Contract award: Contract award: Completed on-time Completed on-time Completed on-time
Morgan Construction Peace River Hydro and on-budget: and on-budget: and on budget:
for north bank Partners for main Peace River Phase 2 worker All 1,600 rooms at
site prep civil works Construction Bridge lodge (900 rooms) the worker lodge
[ Early Works
Highlights
o 900 hectares cleared - Ell
o Approximately 2.4 million cubic metres of
material has been excavated
o Bridge Access across Peace River
o Construction power complete
o Worker Accommodation Phase 3 complete
o Access roads substantially complete
o North Bank Road Gully Crossing completed
o Septimus Rail Siding Track completed
o Peace River bridge
o More than - First Nation Commitments
--
Challenges
o Geotechnical conditions
Remaining Work
o
o
o
Lower Reservoir Clearing
Road completion work
North Bank Viewpoint
o Rocky Mountain Fort Protest o South Bank Initial Access Road
o Weather
<:) BC Hydro
Power smart
Early Works & Worker Accommodation
Cost Performance
A s of September 30, 201 6
lt* BI
Early Works*
Worker Accommodation
October 1, 2016
10 C> BCHydro
Power smart
c
,,-..
0
0
E
E
0
CJ
..
.=..
c
,,-..
0
0
E
E
0
u
u
<C
...
...
Main Civil Works
ltYJI
..
o Permits and Authorizations
o Constructability Reviews
o Schedule
o Contractor Performance
13 C> BCHydro
Power smart
._j
....
111
Ill
.>
-
-.c.a
c
ca
m
..
.c
0
z
Main Civil Work
o Re-sequence Schedule
o Resourcing
15 C> BCHydro
Power smart
Main Civil Works Perforn1ance -
Left Bank &f41 ltYJil
Gmph:PlanvsAcrual
iJ.O,coo ,OOJ
ioo,oco
1)9,COO
100,0CO
>9,COO
0
s' ' ' , ' 11 1), ) ) i 0 0
r
1f i f
; E M b E ; ; ' ' '
i 1 1 11 1 I I f yy y I ; 4I l l l 7
0 =m o 6 I Q
ID
1 '
N
0
rl
q
m = " O ' N Jrl rl w " '
0 " ft N 0
a o
16 C BC Hydro
Power smart
Main Civil Works Perfor111ance -
Left Bank [tW6l ltlI
Wuthrich Quarry Temporary Rip-Rap
Graph: PlanvsActual
"'
3,500
3,000 .
2,500 .
l,000 .
1,SOO .,
1,000 "'
500
!11 ,.;
"I
17
(I) BC Hydro
Power smart
Main Civil Works Perfor111ance -
Right Bank
lt-Sfil ltWlI
Graph:Pion vs Actual
Approach
140,000
Channel 120.000
100i000
00,00D
Ell.000
40,00D
20.000
0
I.
.,
- - "
., I
., .,
11 1 1
IH
18 (I) BC Hydro
Power smart
Main Civil Works Performance
Right Bank ltt'I IM'JI
Graph:PianvsActual
ltWJI
Substation
Excavation -
8 N
J M
3 si - -
O !0 Q - N N
t f ; f 0
6
N
8 .
6roph: PfanvsActual
70
60
Moberly Bridge 50
- Construction !(I
a50
20
10
,0
19
1-'ower sman:
..
c
Ot
I. ro
"D E
,.,_. U)
:c (jj
u3
-a.
ca E
...c
CJ
ca
m
....
CJ
c
0
CJ
..
-a
CJ
( ' .,.
ca ,
a.
E
4
.,
' Ii
0
..
CJ ' ' 'f
-
0
0
N
...
-----
.c
-a::m
....c
0
tn
Cl)
m
-..
-a
m
c
-..u
0
.. :::s
en
co ,
u
, .. - - -
-D::
-.>a.
Cl)
.a
0
:E
N
N
-ftS
u
Otm
._
"1J E
>II)
-
c
.c
:c
u3
E)
Ql
u
Cl)
.. Jil:
0 c
Cl) ftS
'-' m
....0 ..
.c
c ::s
0 0
; tn
.! c
Ci 0
.,
-cen -o .
,, ..B
c c
ftS Cl)
mE
c ::s
-= ..
..
-
.. cen
Q_
I")
N
Generating Station and Spillways
(Civil Works, Hydro-mechanical,
Powerhouse Bridae Crane
Highlights ltfrJil -
o Board approved selection of four proponents to respond to Request for Proposal for civil works
o Issued Request for Proposals on September 23, 2016
Challenges
Upcoming Activities
o Collaborative meeting held
0 Request for Proposals will close March 2017 with final contract award in July 2017
24 C> BCHydro
Power smart
Transmission
-
Highlights
o Procurement activities underway: ltw111
o Peace Canyon 500kV Gas Insulated Switchgear
o Substation 500Kv shunt reactor
o Transmission steel lattice towers ltfrJll
o Transmission access road upgrade contract awarded to
Challenges
o Mitigation of transmission line induction hazards
o Right-of-Way clearing cost and schedule
Upcoming Activities
o Award contract for transmission line right-of-way clearing in December 2016
o Select preferred propOnent for Peace Canyon 500kV gas insulated switchgear in January 2017
o Award contract for substation 500kV shunt reactor in December 2016
25 CI> BC Hydro
Power smart
2017 Key Milestones
Milestone Plan Date Forecast Date Variance Status
(months)
Complete I
L - - I
Tender Design for 5L5 Complete February 2017 February 2017 0 On Track
Moberly Bridge Complete November December 2016 -1 At Risk
2016 11:
'
Powerhouse Excavation Complete April 2017 April 2017 0 On Track
Transmission Peace Canyon Gas February 2017 February 2017 0 On Track
Insulated Switchgear Contract Award
Transmission 5L5 & 5L6 Tower Contract February 2017 February 2017 0 On Track
Award
Generating Station & Spillways Civil July 2017 July 2017 0 On.Track
Contract Award
Cache Creek Roads Contract Award June 2017 June 2017 0 On Track
26 CI> BC Hydro
Power smart
.[ Highway 29
Highlights
o
o
Heritage Program for Cache Creek/Bear Flat - completed in October
Geotechnical Investigations for Cache Creek/Bear Flat - completed in September
-
o 50% Detailed Design for Cache Creek/Bear Flat - completed
Challenges
o Archaeology
o Properties
Upcoming Activities
o Commence clearing at Cache Creek/Bear Flat early 2017
o Ministry of Transportation and Infrastructure tender period for procurement of construction contractor
April to June 2017
o Construction for Cache Creek/Bear Flat to commence July 2017
27 (I) BC Hydro
Power smart
2016 Properties Update
o Cache Creek I Bear Flat Agreements: discussions
continue with Owners Permanent Land Tenure Requirements
for Life of Project
o Conveyor corridor (Dam Site Area) Agreements: Private ....Fee
Complete Simple
435 ha
o Transmission Line: Temporary access on two
properties. Complete
--+
Conveyor
(3)
-+ Transmission
I
Line (2)
Mar
=+
28 C> BC Hydro
Power smart
Litigation - Active Proceedings
Outcome Date
Federal Court : Federal Environmental Approval
Prophet River First Nation August 28, 2015
West Moberly First Nations September 30, 2015
September 12, 2016
Prophet River First Nation Injunction .application dism issed August 28, 2015
West Moberly First Nations Hearing of Petition complete Nov 17-23 2015; Feb 2 2016
Petition dismissed Oct31, 2016
Sierra Club Petition filed July 20, 2016
Filing of written materials Sept 23 - Oct 14, 2016
Hearing date January 27 , 2017
West Moberly and Prophet River Two water license appeals filed
First Nations; and London Procedural Conference
Tentative hearing date set
29
Regulatory &
Environ111ental Challenges
o Environmental Compliance
30 C> BCHydro
Power smart
Key Per111it.s an.d Regulatory Bodies
LEGEND
Provincial
EAC
--
(77 Condi*.ions) (SS Cona otions)
lrul
(12 Ccncfitions)
Water
can. Emrircmne:nta1
Assessment
Dept. o f Fishe:ries
and Oceans CilnuSa
s
(132.Conditions) ; t 131 Condit:ionsJ
cp___ [!c=1
Comptroltti" of \Vater
:WR
c
111
a:
8 I
8 8 I I !lights fMRO)
Tnnsport
I
I - - - - - - - - - - - - - - - - . . , , expeaed
- - I Fl1'1RO I Fcirests1 Lands ;u:!d
Namral
.. I 7 wr - --u tces
'- expected I I -o/IEM J
Operations
Independent Engin.u/
In dependent
EtlvStonmenG:I M oni'.tor
Fisheries Act
INpection Authorization
I I
I LCC: Leave t o Commence
I -, - ::; I Construction
u
Cl.I I
MCW: Major Civil Works
u I
I NPA: Navigation Protection
Act
,Jar Compliance Checks
I
C>Qcr;un For
OCT14 NOV14 JUN15 OCT 15 NOV 15 FEB16 APR 16 JUL16 NOV16
Purpmes Only
31 <I> BC Hydro
Power smart
I
I
,,..
Cl)
C\1
a.
::>
en
c
-..
0
C\1
<O
......
0
N
......-
..z
en
('I')
.....:.
Q)
..c
0
t5
-...
0
+-'
co
(/)
<(
.II.
Site C Employment Statistics
(September 2016)
BC Workers vs Total Workers
2,000
1,800
Total of BC Primary Residents
Peace River Regional #of PRRD
1,600 Residents
Total V\l:Jrl<ers District Primary September
1,400
Residents 2016
1,200
200
Construction Contractors
(including some subcontractors) 1,066 1,345 . 1,200 1,401 1,035 1,345
and Environmental Contractors*
Engineers and Project Team** 345 376 380 415 357 406
- J
I
- ---- -
jL_
1,411 1,580 1,392
TOTAL 1,721 1,816 1,750
(82%) (87%) (80%)
33
Q BCHydro
Power smart
..
Q)
ftS
-a
a. ""
:)
-
-uftS 1
c::)'
c !
ftS
2-
-u.c ,a ">
ui' .
CJ .at:
-..tn
Q) :::::
M
Contingency Update RBI
35 C> BCHydro
Power smart
Ernst & Young Recommendations
Finding I Recommendation BC Hydro Action
Recommendation 1: An interface manager and team
BC Hyd.ro will develop an interface management plan between
should be considered as part of the overall project
major contracts and implement an interface register.
organization.
As the project progresses, BC Hydro will commission an
Recommendation 2: Site C would benefit from an
independent review to ensure sufficient capacity and capability
independent review of the capacity and capability of the
with regards to contract management and reporting
project team to deliver upon evolving project needs.
requirements.
36
C} BCHydro
Power smart
Ernst & Young Recommendations
(c ont'd)'
Recommendation 9: Continue to refine the project BC Hydro will develop a Project Controls Handbook customized
controls processes on the project. for the Site C project team .
Recommendation 10: Continue proactive management of BC Hydro has embedded a monthly review of Estimate at
cost drivers. Completion in the Site C Progression process.
37 C> BCHydro
Power smart
\ I .
-:@n
I I
en
ca
>
0
a.
a.
a.
cc
Resolution:
Quarterly Progress Report No. 5
Site C Project Board Resolution
RESOLVED THAT the resolution pertaining to the Site C Clean Energy Project
Quarterly Progress Report for the period from July .to September 2016, as it appears
in the materials filed for reference with the meeting record, is recommended to the
Board of Directors for approval.
39 C> BCHydro
Power smart
Resolution:
Site C Annual Report 2016
Site C Project Board Resolution
RESOLVED THAT the resolution pertaining to the Site C Clean Energy Project
Annual Report for the period from July 2015 to September 2016, as it appears in the
materials filed for reference with the meeting record, is recommended to the Board of
Directors for approval.
40 <:) BC Hydro
Power smart