Professional Documents
Culture Documents
LOGO
Time Calculation
PRECEDENCE DIAGRAM
Sheila Belayutham
LOGO
LEARNING OUTCOME
Introduction
Activity A Activity B
Sheila Belayutham
LOGO
Labelling of Precedence Activity
ES Activity EF
Description
LS (Duration) LF
Sheila Belayutham
LOGO
Basic Elements
Nodes
Represents activities .
Lines
Represents activity links which are used
to represent the dependencies between
activities.
Lag Time
Time period that separates or designates
a waiting period between 2 activities.-a
predecessor & a successor.
Sheila Belayutham
LOGO
Lag Time
Time period that separates or designates
a waiting period between 2 activities.-a
predecessor & a successor.
Typically a positive value.
However, if there is a need to overlap 2
activities, the lag time is assigned as a
negative value and more appropriately
called LEAD time.
Sheila Belayutham
LOGO
Type of Relationship
Finish to Start
A B
Sheila Belayutham
LOGO
Type of Relationship
Start to Start
Applies to schedule the start of a
successor activity at the same time as or
after some lag time to the start of a
predecessor activity.
A B
Sheila Belayutham
LOGO
SS
Example:
If activity A is Pour Concrete for slab &
Activity B is Level and Smooth Concrete,
Activity B cannot start until A has started
but should begin immediately after the
start of A.
Therefore, SS relationship between A and
B is assigned a lag time equals zero.
SS = O
Sheila Belayutham
LOGO
SS with lag
Install Insulation
Finish to Finish
A B
Sheila Belayutham
LOGO
Type of Relationship
Start to Finish
A B
Sheila Belayutham
LOGO
For example:
Activity Duration
Concrete work 1
Curing 3
Strip formwork 1
Sheila Belayutham
LOGO
CPM
A B C
1 3 1
Sheila Belayutham
LOGO
Precedence
A B C
(1) (3) (1)
OR
A C
FS = 3
Sheila Belayutham
LOGO
0 A 1 FS3 0 C 0
0 1 1 0 1 0
Forward pass
Determine ES & EF.
Backward pass
Determine LS & LF.
Sheila Belayutham
LOGO
Advantages of Precedence
Diagram Over CPM
No usage of Dummy.
Ease of changing logic and adding additional
activities.
Planning could be done with less activities.
Code or activity number need not be changed
when logic was to be changed.
Permits other relationships such as FF and SS
whereby CPM only does FS relationship.
Allow for time lag quantities.
Sheila Belayutham
LOGO
CONTINUOUS PRECEDENCE
DIAGRAM
Continuous PD
A continuous duration means that once
an activity begins, it must be worked on
continuously until it is finished.
Q.1
Sheila Belayutham
LOGO
Try this: Draw the network,
calculate the ES, EF, LS and LF.
Q.3
C
6
B
6 G
2
A D
2 1
F
3
E
3
Sheila Belayutham
Q.4
B
5
G
E 10
3
C I
A
6 5
2
F H
8 2
D
4
Sheila Belayutham
LOGO
Float Calculation