You are on page 1of 30

Sheila Belayutham

LOGO

Time Calculation

PRECEDENCE DIAGRAM
Sheila Belayutham
LOGO
LEARNING OUTCOME

Students will be able to:


Understand Precedence Diagram
programming technique.
Calculate the ES, EF, LS, LF, TF and FF
in a Precedence Diagram.
Sheila Belayutham
LOGO

Introduction

Uses the technique of Activity On Node


(AON).

Activity A Activity B
Sheila Belayutham
LOGO
Labelling of Precedence Activity

ES Activity EF
Description

LS (Duration) LF
Sheila Belayutham
LOGO
Basic Elements

Nodes
Represents activities .
Lines
Represents activity links which are used
to represent the dependencies between
activities.
Lag Time
Time period that separates or designates
a waiting period between 2 activities.-a
predecessor & a successor.
Sheila Belayutham
LOGO

Lag Time
Time period that separates or designates
a waiting period between 2 activities.-a
predecessor & a successor.
Typically a positive value.
However, if there is a need to overlap 2
activities, the lag time is assigned as a
negative value and more appropriately
called LEAD time.
Sheila Belayutham
LOGO
Type of Relationship

Finish to Start

A B
Sheila Belayutham
LOGO
Type of Relationship

Start to Start
Applies to schedule the start of a
successor activity at the same time as or
after some lag time to the start of a
predecessor activity.

A B
Sheila Belayutham
LOGO
SS

Example:
If activity A is Pour Concrete for slab &
Activity B is Level and Smooth Concrete,
Activity B cannot start until A has started
but should begin immediately after the
start of A.
Therefore, SS relationship between A and
B is assigned a lag time equals zero.
SS = O
Sheila Belayutham
LOGO
SS with lag

Install Insulation

Install & Finish dry wall


SS = 1
Sheila Belayutham
LOGO
Type of Relationship

Finish to Finish

A B
Sheila Belayutham
LOGO
Type of Relationship

Start to Finish

A B
Sheila Belayutham
LOGO

Logical relationship in Precedence is


more flexible and versatile compared to
CPM.
In CPM, logical relationship shows that an
activity must be completed before you
can proceed with the following activities.
Only F-S relationships.
Sheila Belayutham
LOGO

For example:
Activity Duration
Concrete work 1
Curing 3
Strip formwork 1
Sheila Belayutham
LOGO

CPM

A B C
1 3 1
Sheila Belayutham
LOGO

Precedence

A B C
(1) (3) (1)

OR

A C
FS = 3
Sheila Belayutham
LOGO

Simplified Precedence Diagram

0 A 1 FS3 0 C 0
0 1 1 0 1 0

Means late/ lag 3 days. Therefore, activity B (Curing)


could be eliminated.
Sheila Belayutham
LOGO
Convention

Network could start with more than 1


activities.
Network could end with more than 1
activities.
Sheila Belayutham
LOGO
Forward & Backward Calculation

Forward pass
Determine ES & EF.

Backward pass
Determine LS & LF.
Sheila Belayutham
LOGO
Advantages of Precedence
Diagram Over CPM
No usage of Dummy.
Ease of changing logic and adding additional
activities.
Planning could be done with less activities.
Code or activity number need not be changed
when logic was to be changed.
Permits other relationships such as FF and SS
whereby CPM only does FS relationship.
Allow for time lag quantities.
Sheila Belayutham
LOGO
CONTINUOUS PRECEDENCE
DIAGRAM

Continuous PD
A continuous duration means that once
an activity begins, it must be worked on
continuously until it is finished.
Q.1
Sheila Belayutham
LOGO
Try this: Draw the network,
calculate the ES, EF, LS and LF.

Activity Predecessor Duration


A - 4
B A 8
C A 3
D A 2
E B,C 7
F C,D 5
G E,F 1
Q.2
Sheila Belayutham
LOGO

For the same question, get the ES, EF,


LS and LF date of the activities. Assume
date of commencement will be on 1/7/09.
Working days would be 7 days a week
including public holidays.
Sheila Belayutham

Q.3
C
6
B
6 G
2
A D
2 1
F
3

E
3
Sheila Belayutham

Q.4

B
5
G
E 10
3

C I
A
6 5
2

F H
8 2
D
4
Sheila Belayutham
LOGO
Float Calculation

Total Float (TF)


Same as CPM calculation for TF
Late Start Early Start (LS ES)
OR
Late Finish Early Finish (LF EF)
Sheila Belayutham
LOGO
Float Calculation

Free Float (FF)


For FF calculation, there is no single
formula to calculate FF.
Reason being that there are 4
relationships in the Precedence Diagram
Method (PDM).
Based on the Lowest Float of relationship
with successor.
Therefore, each relationship going to
successors are evaluated.
Sheila Belayutham
LOGO
Q.6 Factory Project Foundation

Activity Precedence Duration Constraints


Precedence Relationship
Establish site (A) - 10 - -

Site clearance A 6 A SS6


(B) FF
Piling (C) B 10 B SS4
FF6
Pile cap & C 8 C SS6
ground beam (D) FF2

Represent the above table in a Precedence Diagram.


* Calculate the ES, EF, LS, LF, TF & FF for each activities.
* Assume working days are from Monday to Saturday. Sunday
will be an off day. Public holiday will remain as working day.
* Project will begin on 1/ 7/ 2009.
Sheila Belayutham
LOGO
Q. 7 FACTORY PROJECT

ACTIVITIES PRECEDENCE DURATION CONSTRAINTS


PRECEDENCE RELATIONSHIP
Set up site (A) - 5 - -
Site clear (B) A 6 A SS2
FF3
Drainage con (C) A 4 - -
Piling (D) B 8 B SS4
FF4
Main Drainage (E) C 8 - -
Caps & g/beam (F) D 10 D SS5
FF4
G. Flr drainage (G) E, B 10 E SS4
FF3
Erect steel work(H) F 5 - -
Grd Flr Slab(I) G, H 8 - -
Sheila Belayutham
LOGO
Q.7 FACTORY PROJECT

For the above table, draw and activity on


node diagram.
Perform the forward and backward pass
for the diagram.
Project will begin on 1/ 7/ 2009.
Assume the working days will be from
Mondays to Saturdays inclusive of any
public holidays.
Sunday will be an off day.

You might also like