Professional Documents
Culture Documents
Welcome
Thank you for selecting SSI Logic's PMP Exam Prep Questions, Answers,
and Explanations for your PMP study needs. The goal of this book is to
provide condensed mock exams and practice tests which allow you to
become comfortable with the pace, subject matter, and difficulty of the PMP
exam.
The content in this book is designed to optimize the time you spend studying
in multiple ways.
1. Practice exams in this book are condensed to be completed in one
hour; allowing you to balance your time between practice tests and
offline study.
2. Passing score requirements in this book are slightly higher than the
real exam; allowing you to naturally adjust to a higher test score
requirement.
3. Practice exams included in this book cover the entire scope of the PMP
exam, while shorter quizzes focus only on specific Knowledge Areas
outlined in the PMBOK Guide.
The practice exam content in this book is structured into two general types of
exam preparation:
"Lite" Mock Exams, which allow you to test your knowledge across
condensed versions of the PMP exam; designed to be completed
within one hour.
Knowledge Area Quizzes, which reflect brief practice tests focused on
specific Knowledge Areas outlined in the PMBOK Guide designed to
be completed in 15 minutes.
We wish you the best of luck in your pursuit to become a certified PMP.
To accommodate the updated exam content, this book has been revised
extensively so that exam updates are taken into account. All mock exams
have been revised to account for the new additional domain tasks. Further, an
additional focus on Project Stakeholder Management exists appropriately
throughout the baseline practice exams in this book.
PMP Exam Overview
The PMP practice questions in this book reflect the PMP exam version
updated January 11, 2016; and are based on the content contained within
the PMBOK Guide Fifth Edition.
Additionally, the PMP practice exam content in this book include questions on
the overall Project Management Framework and Professional Responsibility;
reflecting the real PMP exam.
The ten knowledge areas contain a total of 47 processes which are applied to
five basic process groups. These five basic process groups, or "domains", are
common across all projects and listed below along with the percentage of
questions one should expect on the PMP exam:
1. Initiating (13%)
2. Planning (24%)
3. Executing (31%)
4. Controlling and Monitoring (25%)
5. Closing (7%)
PMP Formula Cheat Sheet
PMP Formulas
Open table as spreadsheet
Keywords Formulas
SPI = EV/PV
A) EV = Earned Value
PV = Planned Value
[PMBOK Guide - Fourth Edition -
Page183]
< Project is behind
1 schedule
Schedule Performance
Index (SPI) =
B) Project is on schedule
1
> Project is ahead of
1 schedule
[PMBOK Guide - Fourth Edition -
Page183]
Open table as spreadsheet
CPI = EV/AC
A) EV = Earned Value
AC = Actual Cost
[PMBOK Guide - Fourth Edition -
Page183]
Cost Performance Index <1 Over budget
(CPI) B) =1 On budget
>1 Under budget
[PMBOK Guide - Fourth Edition -
Page183]
Open table as spreadsheet
SV = EV - PV
A) EV = Earned Value
PV = Planned Value
[PMBOK Guide - Fourth Edition -
Schedule Variance (SV) Page182]
Negative Behind schedule
B) Zero On schedule
Positive Ahead of
Keywords Formulas
schedule
[PMBOK Guide - Fourth Edition -
Page182]
Open table as spreadsheet
CV = EV - AC
A) EV = Earned Value
AC = Actual Cost
[PMBOK Guide - Fourth Edition -
Page182]
Negative Over budget
Cost Variance (CV)
B) Zero On budget
Positive Under budget
[PMBOK Guide - Fourth Edition -
Page182]
Open table as spreadsheet
EAC = (BAC/CPI)
BAC = Budget at completion
Estimate at Completion
CPI = Cost performance index
(EAC)
[PMBOK Guide - Fourth Edition -
Page184]
ETC = (EAC - AC)
Estimate to Complete (ETC) EAC = Estimate at completion AC =
when original estimates are Actual cost
flawed [PMBOK Guide - Fourth Edition -
Page184, 185]
ETC = (BAC - EV)/CPI
BAC = Budget at completion
Estimate to Complete (ETC) EV = Earned value
when variances are typical CPI = Cost performance index
[PMBOK Guide - Fourth Edition -
Page184, 185]
ETC = BAC - EV
BAC = Budget at completion
Estimate to Complete (ETC)
EV = Earned value
when variances are atypical
[PMBOK Guide - Fourth Edition -
Page184, 185]
N(N-1)/2
Number of Communication
Where N = Number of project team
Channels
members
Expected Value (EV) or (O+4M+P)/6
PERT Estimation O= Optimistic estimate
Keywords Formulas
M= Most Likely estimate
P= Pessimistic estimate
[PMBOK Guide - Fourth Edition -
Page253]
TCPI = (BAC - EV) / (BAC - AC)
BAC = Budget at completion
To-Complete Performance
AC = Actual cost
Index (TCPI) based on the
EV = Earned value
BAC
[PMBOK Guide - Fourth Edition -
Page185]
TCPI = (BAC - EV) / (EAC - AC)
BAC = Budget at completion
To-Complete Performance AC = Actual cost
Index (TCPI) based on the EV = Earned value
EAC EAC = Estimate at completion
[PMBOK Guide - Fourth Edition -
Page185]
LS-ES (or) LF-EF
LS = Late start
Total Float (or) Total Slack ES = Early start
LF = Late finish
EF = Early finish
(P-O)/6
Standard Deviation of a
P = Pessimistic estimate
Task
O = Optimistic estimate
PV = FV/ (1 + r/100)n
Present Value (PV) N = Number of years
r = Discount rate
Net Present Value (NPV) The higher the better
Internal Rate of Return
The higher the better
(IRR)
The Payback Period The lower the better
The Life Cycle Cost The lower the better
The Benefit to Cost Ratio
The higher the better
(BCR)
Critical Path Path with longest duration
Rough Order of Magnitude Estimated value + or - 50% [PMBOK
(ROM) Estimate Guide -Fourth Edition - Page 168]
(Standard Deviation) * (Standard
Variance
Deviation)
Additional Resources
Exam Taking Tips
The PMP exam is a multiple choice test that asks one to recognize correct
answers among a set of four options. The extra options that are not the
correct answer are called the "distracters"; and their purpose, unsurprisingly,
is to distract the test taker from the actual correct answer among the bunch.
Students usually consider multiple choice exams as much easier than other
types of exams; this is not necessarily true with the PMP exam. Among these
reasons are:
Most multiple choice exams ask for simple, factual information; unlike
the PMP exam which often requires the student to apply knowledge
and make a best judgment.
The majority of multiple choice exams involve a large quantity of
different questions so even if you get a few incorrect, it's still okay.
The PMP exam covers a broad set of material, often times in greater
depth than other certification exams.
Although four hours may seem like more than enough time for a multiple
choice exam, when faced with 200 questions, time management is one of the
most crucial factors in succeeding and doing well. You should always try and
answer all of the questions you are confident about first, and then go back
about to those items you are not sure about afterwards. Always
read carefullythrough the entire test as well, and do your best to not leave any
question blank upon submission even if you do not readily know the answer.
Many people do very well with reading through each question and not looking
at the options before trying to answer. This way, they can steer clear (usually)
of being fooled by one of the "distracter" options or get into a tug-of-war
between two choices that both have a good chance of being the actual
answer.
Never assume that "all of the above" or "none of the above" answers are the
actual choice. Many times they are, but in recent years they have been used
much more frequently as distracter options on standardized tests. Typically
this is done in an effort to get people to stop believing the myth that they are
always the correct answer.
If you ever narrow down a question to two possible answers, then try and slow
down your thinking and think about how the two different options/answers
differ. Look at the question again and try to apply how this difference between
the two potential answers relates to the question. If you are convinced there is
literally no difference between the two potential answers (you'll more than
likely be wrong in assuming this), then take another look at the answers that
you've already eliminated. Perhaps one of them is actually the correct one
and you'd made a previously unforeseen mistake.
Although you should always take each question individually, "none of the
above" answers are usually less likely to be the correct selection than "all of
the above" is. Keep this in mind with the understanding that it is not an
absolute rule, and should be analyzed on a case-by-case (or "question-by-
question") basis.
Looking for grammatical errors can also be a huge clue. If the stem ends with
an indefinite article such as "an" then you'll probably do well to look for an
answer that begins with a vowel instead of a consonant. Also, the longest
response is also oftentimes the correct one, since whoever wrote the question
item may have tended to load the answer with qualifying adjectives or phrases
in an effort to make it correct. Again though, always deal with these on a
question-by-question basis, because you could very easily be getting a
question where this does not apply.
Just because you have finished a practice test, be aware that you are not
done working. After you have graded your test with all of the necessary
corrections, review it and try to recognize what happened in the answers that
you got wrong. Did you simply not know the qualifying correct information?
Perhaps you were led astray by a solid distracter answer? Going back
through your corrected test will give you a leg up on your next one by
revealing your tendencies as to what you may be vulnerable with, in terms of
multiple choice tests.
It may be a lot of extra work, but in the long run, going through your corrected
multiple choice tests will work wonders for you in preparation for the real
exam. See if you perhaps misread the question or even missed it because
you were unprepared. Think of it like instant replays in professional sports.
You are going back and looking at what you did on the big stage in the past
so you can help fix and remedy any errors that could pose problems for you
on the real exam.