INSTALLATION OF CABLE TRAY, TRUNKING & LADDER

Project: IR No.:
Owner: Building No.:
Project Manager: Level:
Consultant: Date:
Main Contractor :

CHECKED BY
NO. DESCRIPTION
REMARKS

1 Approved Material used (MIR)

2 Shopdrawing is approved

Installed hanger and supports are inspected and


3
approved
Distances between supports are as per approved
4 drawing.
Installed cable tray, trunking or ladder are levelled and
5 straight .
Spring knot is used to connect cable tray or trunking to
6 channel.

7 Approved and correct fittings are used.

8 Bonding jumper is installed.

9 Expansion fitiings are used as required.

10 Painting is applied to cut ends

11 Tagging/labelling is provided

Installed containments are free of damages and


12 scratches.

Remarks/Comments (if any):