Sir, our company Messrs. Liberty Overseas was awarded contract for
the installations of 1x15MVA, 33/11kv Injection substation at Agba
Dam on the 12th December, 2008 at a total contract sum of One
Hundred and Sixty Two Million, Five Hundred and Fifty Eight Thousand
Nine Kobo (N162, 558,964.092) only. Attached as Annexure I is the
photocopy of the letter of award for your certification please.
(MD/CEO)
4thJanuary, 2016
Ministry of Energy
Ilorin.
Our company has been paid a total sum of Twenty Four Million One
Hundred and Two Thousand, Five Hundred and Seventy Two Naira Four
Kobo (N24, 102,572.40) only. The project is about 60% completed. The
reason why the project was abandoned was as a result of under
estimation of the actual cost that could complete the project.
In view of this observation we wish to demand for additional sum of
Thirty Eight Million, Six Hundred and Fifty Thousand, Five Hundred
Naira (N38, 650,500.00) only to enable us complete the job.