A Cluster is a non-electric initiation system which is
designed for use in surface mines. The unit consists of a trunk line delay detonator housed in a cluster connector block.
Technical Specifications Mining Method
Appearance Surface A length of green shock tubing that incorporates a short period Opencast; Open Pit; Quarrying; Construction delay detonator. The detonator includes sleeve that has been Application crimped on one end with a given length of shock tubing. The Trenching; Open Pit; Quarrying; Civils free end of the shock tube is sealed and incorporates a colour coded connector clip. The delay period is also printed along Product Range the length of the detonator. The detonator is fitted into a Nominal delay (ms) 0 17 25 33 42 75 100 colour-coded cluster connector block. Colour code Turquiose Blue Orange Dark Green Yellow Red Brown Nominal delay (ms) 125 150 175 200 225 250 Colour code Light Green Light Blue Beige Clear Grey Dark Pink Benefits & Features Benefits Packaging Accurate delay timing Description Case Rugged, abrasion-resistant tubing Dimensions (LxBxH) 565x295x270mm Easy to use Gross weight 22kg Flexible blast design Initiates detonating cord or shock tube Units per case/bag Length (m) Units per NEQ (kg) Length (m) Units per NEQ (kg) Features case case Thirteen different delays 2 250 0.2 6 150 0.1 Colour-coded connector clip and cluster connector block 3 200 0.2 10-15 75 0.1 indicates delay time 4-5 175 0.2
Green coloured shock tubing
18kg minimum break load on shock tubing Transport (UN Classification) Immune to hazards of radio frequency radiation, stray Class 1.1B UN No 0360, DETONATOR ASSEMBLIES, NON-ELECTRIC currents and electro-static discharge