ACCOMPLISHMENT REPORT

For the Period of: June 1 to June 15, 2017

Assisted Engineer III for consolidation AutoCAD files for CMMS Project.
Assisted Huawei Personnel for cabling/fiber laying between Taft and Magallanes Station
for free Public Wi-Fi.
Monitored MRT3 Maintenance Provider Power Supply Personnel in their Monthly
Preventive Maintenance, following are activities in Station 3,8,9,5,6,7:
Inspection and cleaning/maintaining UPS Battery
Earth Box
UPS 20kvA
Silicon Rectifier (TPSS 3,5,6,9,11,12,13)
DC 750 Switchgear (TPSS 3,5,6,9,11,12)
Control Battery
Pilot Wire Panel
LV Panel No. LV-1, LV-2
Battery Charger Panel
AC/DC Distribution Panels
Alarm Panel
Checked and Monitored MRT3 Maintenance Provider Power Supply Personnel these
are their following activities in Depot:
Inspection and cleaning/maintaining DC 750 Switchgear (Stabling and
Maintenance Feeder)
DC 750 Switchgear
Monitored MRT3 Maintenance Provider Power Supply Personnel in their Quarterly
Preventive Maintenance, following are activities in Station 3,8,9,5,6,7:
Inspection and cleaning/maintaining UPS Panel 20KVA,30KVA.
UPS Battery (Back-up test)
Control Battery (Back-up test)
Negative Panel ( TPSS 3,5,6,9,11,12,13 )
12KV Switchgear ( SS 1,2,4,7,8,10)
Checked and monitored Control Battery in station 9,cell number 18 pulled out due low
voltage reading also in station 5 cell number 29.

Prepared by: Approved By:

ENGR.ISIDRO R. BAANG.JR ENGR. OSCAR B. BONGON


ENGINEER II, Engineering Division CHIEF, Engineering Division

Reviewed By:

ENGR. JOSE RODANTE SABAYLE


ENGINEER III, Engineering Division