131

PS
Pg. 122 refers please.
2. The contractors (Messrs. Stomberg Power Limited) performance is
justifiable to the payment received as at the time maintenance work
stopped on the site.
3. Pg. 123 128 is the comprehensive status report of the site with a
view to carrying out necessary repairs/replacement of damaged electrical
accessories so that the installation can be made functional again.
4. The cost implication of the site analysis carried out is N7,206,700.00
(pg. 129 130 relevant)
5. Net balance available is N3,132,000.00 which will not be able to carry
out all the items of work listed on the status report as a result of long time
of abandonment.
6. Walk-in-cubicle and garden light will not be considered for
rehabilitation at the moment because of limitation of available fund.
7. All efforts will be made to ensure that the overhead street light and
ground mounted street lights are functional with the available sum of
N3,132,000.00 pending the time when total review of rehabilitation of
street light within Ilorin metropolis will be carried out.
8. You may wish to approve the release of the sum of N3,132,000.00 to
enable us mobilise to the site as directed please.