A CIVIL WORK
1 DIGGING AND BACKFILLING OF 45 NOS 1,500.00
HOLE 600MMX900MM TO
ACCOMADATE CONCRETE POLE
BASE
SUB-TOTAL(A)
B CABLES & OTHER ACCESSORIES
1 4X25MM2 PVC/SWA/PVC 200 MTRS 3,500.00
CABLE[NIGERCHIN]
2 4X16MM2 PVC/SWA/PVC CABLE 1090 MTRS 2,750.00
[NIGERCHIN]
SUB-TOTAL(B)
C POLES/FITTINGS&ACCESSORIES
I 250W CHOKE[THORN]
II 250-400W IGNITOR
III 25UF CAPACITOR
7 60A PVC CONNECTOR 20 ROLLS 500
SUB-TOTAL(C)
D 100KVA,33/0.415
TRANSFORMER SUB-STATION
SUB-TOTAL (D)
SUB-TOTAL(E)
COLLECTION
A CIVIL WORKS
F TOTAL
LABOUR (30%)
CONTIGENCY (5%)
TAX (13%)
GRAND TOTAL
METER LIGHT AT KWARA
TOTAL
67,500.00
627,000.00
990,000.00
125,000.00
35,000.00
25,000.00
90,000.00
1,959,500.00
700,000.00
2,997,500.00
179,000.00
600.00
3,877,100.00
2,210,000.00
715,000.00
1,575,000.00
10,000.00
75,000.00
200,000.00
4,785,000.00
1,500,000.00
35,000.00
20,000.00
30,000.00
10,000.00
90,000.00
40,000.00
50,000.00
16,000.00
17,500.00
44,000.00
100,000.00
400,000.00
800,000,00
1,600,000.00
3,952,500.00
500,000.00
20,000.00
520,000.00
1,959,500.00
3,877,100.00
4,785,000.00
3,952,500.00
520,000.00
15,094,100.00
4,528,230.00
754,705.00
1,962,233.00
22,339,268.00
BILL OF ENGINEERING MEASUREMENT AND EVALUATION
PROJECT TITLE:EXTERNAL ELECTRICAL SERVICES OF PROPOSED RESIDENTIAL DEVELOP-
FOR ENGR. SHERIFF BADAMOSI ,IPE ROAD ,GRA,OFFA
S/NO DESCRIPTION QTY UNIT
SUB-TOTAL (A -J)
TOTAL [ TO COLLECTION]
2 DISTRIBUTION PANELS:MAIN/SUB-
PANEL
SUB- PANEL
C Construction of purpose built low 1 SET
voltage Distribution panel
(Mechanically inter-locked)
comprising the following: -6
Nox 100A TP&N moulded case circuit
breaker (MCCB) [ Schneider or ABB]
as incomer - 6 No x 63A TP&N
MCCB -1 No x 100A digital
Ammeter -1 No x 415A digital
volteter - 1 No x 50Hz frequecy
Meter -Power ON indicator Lamps
- 3 No-Phase prepaid Energy
Meter. All the above shall be
enclosed in 4.0mm thick fabricated
iron sheet of 1800x900x450mm
cubicle ,with satisfactory
1A31:F3
2
- 1 No x 100A T&N MCCB (ABB) as
incomer
3
- 2 No x 100A TP&N contractor (ABB)
4
-Metering/voltage meter relay
5
-Off/Auto selectors switch
8
-Sets of Auxiliary contractor
9
-Sets of pin relay
10
-Sets of Timer
11
-Sets of pilot lamps
12
-Digital ammeter
13
-Digital voltmeter
14
-Digital wattmeter
15
- Digital voltmeter
- Digital Ammeter
RATE TOTAL
3,900.00 312,000.00
2,750.00 173,250.00
1,350.00 105,300.00
1,350.00 45,900.00
650.00 34,450.00
1,200.00 18,000.00
3,500.00 17,500.00
3,750.00 225,000.00
15,000.00 30,000.00
961,400.00
200.00 59,200.00
75,000.00
1,095,600.00
75,000
BILL OF ENGINEERING MEASUREMENT AND EVALUATION
PROJECT TITLE:SUPPLY AND INSTALLATION OF STREET LIGHT AT
ERIN-ILE TOWNSHIP
S/NO DESCRIPTION QTY UNIT RATE
A CIVIL WORK
1 DIGGING AND 220 NOS 1,500.00
BACKFILLING OF
HOLE
600MMX900MM TO
ACCOMADATE
CONCRETE POLE
BASE
SUB-TOTAL(A)
B CABLES & OTHER
ACCESSORIES
1 4X25MM2 500 MTRS 3,500.00
PVC/SWA/PVC
CABLE[NIGERCHIN]
2 4X16MM2 6800 MTRS 2,750.00
PVC/SWA/PVC CABLE
[NIGERCHIN]
3 2.5MM2 75 COILS 8,950.00
TWIN+EARTH PVC
CABLE
4 PVC INSULATION 95 ROLLS 60.00
TAPE
SUB-TOTAL
C POLES/FITTINGS&AC
CESSORIES
1 9.0M SINGLE ARM 220 NOS 65,000
STREET LIGHT POLE
2 1X250W HIGH 220 NOS 35,000.00
PRESSURE SODIUM
LAMP FITTINGS
COMPLETE WITH
I 250W
CHOKE[THORN]
II 250-400W IGNITOR
III 25UF CAPACITOR
6 60A PVC CONNECTOR 150 ROLLS 500
SUB-TOTAL
D 100KVA,11/0.415
TRANSFORMER SUB-
STATION
1 SUPPLY AND 2 NOS ###
INSTALLATION OF
100KVA,11/0.415
TRANSFORMER
(ELCO)
SUB-TOTAL (D)
E STREET LIGHTING
KIOSK
1 CONSTRUCTION OF 2 SETS ###
PURPOSE BUILT
STREET
LIGHING KIOSK
WHICH SHALL BE
MECANICAL STRONG
AND ELECTRICALLY
INSULATED
WITHPROVISION FOR
TOP & BOTTOM
CABLE ENTRY
COMPRISING THE
FOLLOWING :
(i) 2NO X 100-120A
CONTACTOR (MERLIN
GERIN)
(ii) 1NO X 100A MCCB
(MG) AS INCOMER
E STREET LIGHTING
KIOSK
F TOTAL
LABOUR (30%)
CONTIGENCY (5%)
TAX (13%)
GRAND TOTAL
ND EVALUATION
T LIGHT AT
TOTAL
330,000.00
3,960,000.00
4,840,000.00
1,250,000.00
70,000.00
50,000.00
1,800,000.00
12,300,000.00
1,750,000.00
18,700,000.00
671,250.00
5,700.00
21,126,950.00
14,300,000.00
7,700,000.00
75,000.00
330,000.00
500,000.00
22,905,000.00
2,600,000.00
70,000.00
40,000.00
60,000.00
20,000.00
180,000.00
80,000.00
50,000.00
32,000.00
17,500.00
88,000.00
500,000.00
400,000.00
800,000,00
1,600,000.00
5,737,500.00
500,000.00
20,000.00
520,000.00
12,300,000.00
21,126,950.00
22,905,000.00
5,737,500.00
520,000.00
62,589,450.00
18,776,835.00
3,129,472.50
8,136,628.50
92,632,386.00
BILL OF ENGINEERING MEASUREMENT AND EVALUATION
PROJECT TITLE:EXTERNAL ELECTRICAL SERVICES OF PROPOSED RESIDENTIAL DEVELOP-
FOR ENGR. SHERIFF BADAMOSI ,IPE ROAD ,GRA,OFFA
S/NO DESCRIPTION QTY UNIT
1 LOAD CABLES/OTHER INSTALLATION
ACCESSORIES
A 4 core x 50.0mm2 PVC/SWA/PVC underground 80 MTRS
armoured cable from the Low tension pole to
Generator House [ KABEL METAL OR APPROVED
EQUAL]
SUB-TOTAL (A -J)
K Digging of Cable trench 296 MTRS
L Labour / Attendance for Laying of / termination LOT SUM
of armoured cable 0f varying sizes.
TOTAL [ TO COLLECTION]
2 DISTRIBUTION PANELS:MAIN/SUB-PANEL
A 200A TP&N Fused switch Complete with 1 NOS
installation accessories [ HAVELL OR APPROVED
EQUAL]
B Construction of purpose built low voltage Main 1 SET
Distribution panel (Mechanically inter-locked)
comprising the following: -2
Nox 200Amp TP&N moulded case circuit breaker
(MCCB) [ Schneider or ABB] as incomer
- 1 No x 100A 4- poles
MCCB -2 No x 63A 4- poles
MCCB -2 No. x 63A 2-poles
MCB as outgoings -1 No x
200A digital Ammeter -1 No x
200A digital volteter - 1 No x
50Hz frequecy Meter -Power
ON indicator Lamps
-1 No 3 -Phase prepaid Energy Meter. All the
above shall be enclosed in 4.0mm thick
fabricated iron sheet of 1800x900x450mm
cubicle which shall be mechanically stable and
electrically insulated to Engineers specifications
C Construction of purpose built low voltage Sub 1 SET
Distribution panel (Mechanically inter-locked)
comprising the following: -6
Nox 100A TP&N moulded case circuit breaker
(MCCB) [ Schneider or ABB] as incomer
TOTAL [ TO COLLECTION]
TOTAL [ TO COLLECTION]
COLLECTIONS
1 LOAD CABLES/OTHER INSTALLATION
ACCESSORIES
2 DISTRIBUTION PANELS:MAIN/SUB-PANEL
3 STREET LIGHTING KIOSK
4 REPRODUCTION OF AS INSTALLED
ELECTRICAL/MECHANICAL SERVICES
DRAWINGS BOTH SOFT AND HARD COPIES
GRAND TOTAL
REMENT AND EVALUATION
L DEVELOP-
RATE TOTAL
3,900.00 312,000.00
2,750.00 173,250.00
1,350.00 105,300.00
1,350.00 45,900.00
650.00 34,450.00
1,200.00 18,000.00
3,500.00 17,500.00
3,750.00 225,000.00
15,000.00 30,000.00
961,400.00
200.00 59,200.00
75,000.00
1,095,600.00
75,000 75,000.00
495,000.00 495,000.00
650,000.00 650,000.00
20,000 20,000.00
1,165,000.00
185,000.00 185,000.00
10,000 10,000.00
195,000.00
1,095,600.00
1,165,000.00
195,000.00
275,000.00
2,730,600.00