Professional Documents
Culture Documents
R.Seshadri
Larsen & Toubro Limited
Mysore Works
Grid Islanding and Load shedding Schemes
Grid
Incomer
6 MW Transformer
import
Incomer
Breaker
Incomer Bus
DG
Breaker
Plant Loads
DG
(9 MW)
3 MW Fig.-1
..2
-2-
Please see fig.-2 . Here the plant load is 2 MW. The DG capacity is
3 MW. The DG is connected to the bus where the grid supply is also
connected. The DG delivers 2 MW to plant load. The DG has a spare 1
MW available from its generation it delivers this 1 MW back into the
grid. In this case the plant is said to be exporting power.
Grid
1 MW Incomer
Export Transformer
Incomer
Breaker
Incomer Bus
DG Braker
DG Plant Loads
2 MW
3 MW Fig.-2
In both cases , the DG owner should obtain special permission from the
local Electricity board to connect his DG in parallel to the grid. The local
EB will permit DG paralleling, subject to the condition that the DG
owner installs a Grid Islanding Scheme at the incomer of the plant.
.3
-3-
In our country, due to several reasons, the grid is not stable and is always
fluctuating with respect to voltage and frequency. In addition, Grid
failures are frequent.
Benefits to EB :
The EB, who have the responsibility to maintain the grid, normally do
not want an additional independent power source (like the DG) in their
grid network, when the grid is disturbed. Since the power source is not in
their control, it will complicate EBs methods of dealing with the
disturbed grid. While the EB are in the process of solving the grid
disturbance, they do not like to have another power source which they do
not control and which may add to the disturbance. Once the DG (non EB
power source) is disconnected from the grid, it becomes easier for the EB
to locate the source of disturbance and rectify the same. The main idea is
that the EB eliminates the possibility of the DG feeding the disturbance.
Hence the local EB will insist on installing the Grid islanding scheme in
the DG owners premises, before allowing the DG to be connected to
grid.
Benefits to DG owner:
It is strongly advisable to disconnect the DG from the grid, when the grid
is disturbed. The main reason is that the DG or the TG may get spoilt due
to grid disturbances resulting in heavy repair costs and shut downs. It is
necessary to protect the DG from grid disturbances.
Hence the user will also insist for the islanding scheme when the DG has
to operate in parallel with the grid.
4
-4-
It may also happen that the DG may experience a reverse power flow
when operating in parallel with grid, without any of the above listed
symptoms. This is due to changing PF conditions in the grid. This is not
a major problem for the EB, but it is harmful to the DG. DGs may not
be able to operate below a certain PF. If compelled to work with low PF,
the DG will experience a reverse reactive power flow - this can damage
the DG.
It should be noted that that there can be two conditions of grid paralleling
of DG sets.
a) Case 1
DG in parallel with grid, plant is importing power :
Refer fig.1. Let us say that the incomer is opened by grid islanding
scheme, when the plant load of 9 MW was fed by DG (3 MW) and
EB(6MW). The moment incomer opens, the DG will have all the
plant load coming onto it there would be an overload of 6 MW.
The generator protection relay will trip the DG, causing a total
black out. This is not desirable what we should have is that :
.6
-6-
b) Case-2
DG in parallel with grid , plant is exporting power :
c) Case 3
The DG has islanded on EB failure
Let us now say that the EB power has come back. At this time it is
desirable to restore the original condition of DG set parallel
connection with grid, without wasting any time.
.7
-7-
The dF/dT can be anded through software with any of the 4 U/F
elements. Wit this feature the user can reliably detect a rapidly
falling frequency in the bus , without any spurious triggers.
The dE/dT element helps to detect a fault in the grid ( a fault in the
grid will result in rapid fall of voltage)
..8
-8-
a) The UFD34 relay, which was used for islanding, can also be
provide contacts for load shedding.
Load shading is provided buy the relay RRS this measures the power
out of the DG it also receives an auxiliary contact from the incomer
breaker. If incomer opens, this relay immediately give decrease pulses to
exciter and governor to bring the power levels of the DG to the required
levels of plant load.
.9
-9-
L&T offers all the above relays as a single source solution. The user can
now select any of the relays to suit his requirements at a given site .
--ooO&Ooo--