Professional Documents
Culture Documents
Construction Management On Set of Design Phase
Construction Management On Set of Design Phase
- Programme Clarification
- Skeptic Process
2
INTRODUCTION
Despite its importance, relatively little research has been made on the
management of the design process, in relation to the research time and
effort which has been dedicated to production management and
project management in general.
To some extent, the fact that design management has been neglected is
understandable. Building design is a very difficult process to manage. It
involves thousands of decisions, sometimes over a period of years, with
numerous interdependencies, under a highly uncertain environment. A
large number of personnel are implicated, such as architects, project
managers, structural engineers, service engineers and marketing
consultants. Each category of professional has a distinct background,
culture and learning style (Powell and Newland 1994).
During this phase the team must continually communicate and consult on
all substantive issues. There should be periodic constructability reviews by
the team. The client and the project manager should agree on the scope
and number of constructability reviews required. The project manager
should also coordinate with any needed Value Engineering and
alternative studies. The goal is to complete a set of documents defining a
4
project which can be bid in the current local marketplace within the
client's budget and time requirements. The design professional has total
responsibility for design implementation and execution. The role of the
project manager during this phase should be to assist the team by
carrying out the activities listed below. Although the designer is
responsible for design decisions to meet the project requirements, the
client as well as project manager and other stakeholders can also have
decision making responsibility.
PROGRAMME CLARIFICATION
initiates the design process and the design is carried out on behalf of the
client by the Design Team. The design team may be internal or external to
the client organisation, depending on the in-house resources and
technical knowledge available. Typically the design team is led by the
architect (building projects) or the engineer (civil engineering projects).
This type of procurement can allow the contractor to carry responsibility
for designing part of the project where this arises it should be explicitly
defined in the contract as specialist work or as a specific type of
temporary works.
It is worthy of note that, there are separate prime contracts for the design
team and the general Contractor. The selected design team prepares a
set of construction documents based on the client's requirements. The
scope of the entire project will typically be included in the bid documents
so that one general Contractor will be responsible for all the requirements
of a project. Therefore, the Project Manager only needs to manage one
contract for construction. Furniture, fixtures, and equipment and/or
telecommunications may be bid as separate contracts if the Project
Manager desires.
Most (if not all) of the design responsibility, however, is transferred to the
contractor. The early involvement and commitment of the construction
contractor in the design process improves buildability and ensures that risk
in the execution of the design and any conflict that might arise between
the designer and the contractor is a matter for those parties and does not
involve the Client. Clients should retain their own technical advisers (for
8
MATERIALS MANAGEMENT
VALUE ANALYSIS
Todays owners are demanding that designers and builders pay more
attention to their clients financial and economic objectives. Owners want
their design and construction team to demonstrate effective
management of cost and, ultimately, of value.
DESIGN REVIEWS
For each design review, you make certain that the design manager will
ensure the following key objectives are accomplished, as applicable to
the particular review:
For Design Review to succeed, it must be carried out using a robust and
defensible process. It must also offer consistently high standards in the
quality of its advice. These standards can be summarized in the following
ten principles.
Advisory: A design review panel does not make decisions, but it offers
impartial advice for the people who do.
Accessible: Its findings and advice are clearly expressed in terms that
design teams, decision makers and clients can all understand and make
use of.
Accountable: The Review Panel and its advice must be clearly seen to
work for the benefit of the public. This should be ingrained within the
panels terms of reference.
The onboard design review in the onset of the design phase ha a principle
that planning should: always seek to secure high quality design and a
good standard of amenity for all existing and future occupants of land
and buildings
The work breakdown structure [WBS] is again the starting point for
schedule control. Work activities are identified for each of the WBS work
package elements and form the building blocks of the project schedule.
For relatively simple projects you can represent the activities using a bar
chart schedule and the time from the beginning of the first bar (start) and
the end of the last bar (finish) is the duration of the project but more
complex projects, such as building construction project require a critical
path method (CPM) schedule.
As with the scope and cost baseline, the schedule baseline should be
developed at the close of conceptual design/preliminary engineering. As
the project progresses through final design and construction the schedule
performance is monitored, the outstanding durations of incomplete
activities estimated, the critical path updated and compared to baseline.
You should then take management action to address schedule slippages
of critical and near critical activities.
RISK MANAGEMENT
According to Smith (2006) the peak of risk impact on the building project
is when the design phase is finished and the construction phase is going to
be started. Then the theory becomes a real structure, and every mistake
made in the previous phase will have an influence on the construction
phase and the service life. To minimize this impact two parts; design and
construction should be overlapped. Very often the final design of the
details takes place during the construction phase duration, with
consultation of contractor engineers. It results in gaining more economical
solutions, enlarges ability of potential need of change in this point without
project disturbances and develops the cooperation between the project
participants.
In a building project and in the service life there are many situations that
cannot be predicted. The execution of the construction process can
become even more difficult than it was assumed before and unexpected
events can take place. This state of lack of information is called
uncertainty.
decision making will not protect the project from uncertainties. The
uncertainties can be related to new critical events, so also to risks that
these events represent. It is important to bear in mind that not only known
critical events exist in building projects, but also these ones that were not
identified and can occur unexpectedly.
CONCLUSION
To ensure that optimal design, value for money and buildability are
achieved, due care and attention need to be given to the proper
management and coordination of all design activities throughout the
design process. In particular, the interaction between the different design
disciplines requires a well-coordinated teamwork structure. Design
management encompasses all of the coordination, analysis and design
testing activities that a project requires. For effective design management
and coordination it is necessary to appoint a manager with appropriate
management skills to ensure the design process operates efficiently. Such
a person is usually the design team leader.
REFERENCES
Bourdon, C.C., and R.W. Levitt, Union and Open Shop Construction,
Lexington Books, D.C. Heath and Co., Lexington, MA, 1980.
http://pmbook.ce.cmu.edu/04_Labor,_Material,_And_Equipment_Utilizati
on.html : Construction and Project Management: Labor, Material and
Equipment Utilization
Lange, J.E., and D.Q. Mills, The Construction Industry, Lexington Books, D.C.
Heath and Co., Lexington, MA, 1979.
24