Professional Documents
Culture Documents
As part of the inquiry into Electricity Network Regulation, the Commission quantitatively explored the relative merits of d
analysis is intended to assist the Commission in drawing out relevant implications for issues of demand management add
recommendations. The purpose of the calculations is to illustrate the effects of different DM strategies and how these m
parameters or use the spreadsheet as the basis for other experiments. It is NOT intended to give precise estimates, whic
As such, the Commission has not independently prepared detailed assumptions concerning the implementation of smar
previous cost benefit analysis and on actual data from the recent roll out of smart meters in Victoria. By using consistent
relative merits of different approaches can still be drawn.
A range of scenarios have been examined, with the cost benefit ratios outlined in the Summary tab. For each scenario, a
case takes assumptions entailing the highest costs and lowest benefits that have been identified (as primarily outlined in
Assumption parameters tab are parameterised variables that will automatically flow through to the scenario calculations
The References tab includes the bibliographical information of studies drawn on for this analysis.
The spreadsheet also includes the (separate) calculations on the size of the subsidy to air conditioning during critical pea
Productivity Commission 2013, The costs and benefits of demand management for households, Supplement to inquiry re
9 April.
ary tab. For each scenario, a low, mid and high case has been developed. The low
fied (as primarily outlined in the Assumption parameters tab). Red boxes on the
h to the scenario calculations.
ysis.
NEM-
wide roll- Direct
Regional
out with load
roll-out in
NEM-wide roll-out with weakly control
peaky
critical peak pricing targeted without
constrain
time of smart
ed areas
use meters
pricing
Cost-benefit ratios
Low 1.1 0.6 0.3 1.2
Medium 2.7 1.2 0.6 2.7
High 6.9 2.7 1.1 6.3
25th and 75th percentile of annuity value per household
25th P ($) 100 -10 -45 65
75th P ($) 200 35 -20 140
Back to the Contents of this spreadsheet
Regional roll-out in
peaky contrained area
with an additional
deferred lumpy
investment
1.15
2.75
7.00
100
200
scenario 1 (not used in TP)
Discount rate (%) 8 Discount factor
Cost of direct load control (mainly labour cost and installation of control devices)
Lowest 160
Mid 210
Highest 260
Lower amount presumed with economies of scale and technology change (and consistent with lower figures
Average of lowest and highest
Deloitte 2011a pp.12-13, pp. 39ff
Estimates based on Oakley Greenwood 2010 p.23 (transitional and ongoing opex of $284m) and Deloitte 201
Delloite 2011a (It suggests $2 per meter per month - so roughly $20 a year especially as costs fall)
Based on a mixture of assumptions and evidence from on trial studies. Selection biases, the lack of compatib
In effect this is households that would have meters installed (outside Victoria)
s of this spreadsheet
y Greenwood AMI Benefits and Costs Report, August 2010)
opex of $284m) and Deloitte 2011a p.45 (NPV of OPEX of $592m over 20 years)
s: All green shaded figures are from Deloitte 2011a, p. 13 and are in $million npv. They include
om the AMI program, efficiencies of network management and other benefits excluding from
and demand management. There are 2.66 million meters. Meters have a 15 year life. A discount
umed. The annuity over the 15 year value is calculated
tion biases, the lack of compatible appliances and the difficulties of recruiting people without intensive marketing across the whole NE
arketing across the whole NEM suggests that the best trial participation rates are over-optimistic.
Max Limited sequential rollout of smart meters with c
Number of meters 10,000
Total peak demand from these households 35.93 Note the 1.5 multiple reflects that a limited rollout
Price ratio (after/before) 8 As per the SP Ausnet strategic pricing trial
3.4926178082
34.0
There is an initial
investment in smart
meters in year 0 and an
upgrade in year 7
Summary
Units low
Smart meters number 10,000
Relevant critical peak demand MWh 28
Up front cost $ per appliance 800
Refresh cost $ per appliance 150
Cost profile Install costs all occur up front. IT refresh after 7 years.
Annual cost $ per appliance per year 30
Value of demand management savings
$/kW per year 271.2728501932
(network/generation)
% of relevant critical peak
Maximum demand management response
demand 19
No demand response in first year. Maximum demand response in year 7 a
Demand management savings profile
Discount rate per cent 8
Discounted costs $ Million (npv) 11
Discounted benefits $ Million (npv) 13
Net benefit $ Million (npv) 1
Net benefit per household $ (npv) 130
Benefit cost ratio ratio 1.1
Annuity in savings per household over 15
$ 14.6
year period
This is used to determine alpha such that it is the median between the high and low values
Inverse beta 50% probability 1370
Inverse beta 75% probability 1889
alpha 1.661
beta 2.000
error from deviation of inverse beta from t 0.00
smart meters with critical peak pricing Back to the Contents of this spreadsheet
ple reflects that a limited rollout would target regions with high peak to average demand
net strategic pricing trial
mid-point high
10,000 10,000
32 36
535 270
125 100
years.
25 20
326.2728501932 381.2728501932
27 34
um demand response in year 7 and subsequently sustained. Linear increase
between years 2 to 7..
8 8
8 5
22 34
14 29
1370 2920
2.7 6.9
154.0 328.3
$ 880 $ 1,889
$ 100 $ 200
ntents of this spreadsheet
Costs -$ 4,938,594
Benefits $ 34,124,820
Net benefit 29,186,225
Benefit-Cost Ratio 6.91
Min
Costs -$ 11,208,781
Benefits $ 12,543,544
Net benefit 1,334,764
Benefit-Cost Ratio 1.119
Middle
Costs
Benefits
Net benefit
Benefit-Cost Ratio
Discounted benefits
$ 383,804
$ 710,749
$ 1,461,511
$ 1,657,928
$ 1,817,226
$ 1,943,827
$ 2,041,702
$ 1,890,465
$ 1,750,430
$ 1,620,769
$ 1,500,712
$ 1,389,548
$ 1,286,619
$ 1,191,313
$ 1,103,068
-$ 8,073,688
$ 21,749,671
13,675,983
2.69
Max National smart meter rollout (phased) with critic
# meters 6,200,000 Phase in years
Total peak demand from these households 14,850 Before-after price ratio
Value of network and generation savings 381
The DM savings, operating costs and savings increase over time until the whole stock of meters are deployed, and then decays over time. This is bec
successive benefits and costs of replacing them. In any real world rollout, as meters died at 15 years, they would be replaced. This would involve a n
successive 19 year periods, the demand management benefits would be realised immediately given that consumers' demand responses would be
bigger net benefits than those shown here. On the other hand, discounting reduces the impact of this effect,. Therefore, the long-run scenario is pr
which has the benefit of being far more tractable numerically.
The reason for low demand response in the initial years reflects t (a) the factors described in the worksheet labelled "One-off" and (b) that the met
occurring between t=0 and t=1. Altogether, the model results relate to 19 periods because the last tranche of meter rollouts occurs between years
Summary
Units low
Smart meters number 6,200,000
Relevant critical peak demand MWh 11550
Up front cost $ per appliance 800
Refresh cost $ per appliance 150
Cost profile Smart meters phased in over five years (1.24 million per year). Refresh of IT com
Annual cost $ per appliance per year 30
Value of demand management savings
$/kW per year 271.2728501932
(network/generation)
% of relevant critical peak
Maximum demand management response 19
demand
No demand management savings for first two years after rollout. Maximum sav
Demand management savings profile
meter.
Discount rate per cent 8
Discounted costs $ Million (npv) 5993
Discounted benefits $ Million (npv) 3311
Net benefit $ Million (npv) -2682
PV of Net benefit per household $ (npv) -433
Benefit cost ratio ratio 0.6
Annuity in savings per household over 15
$
year period -$ 49
This is used to determine alpha such that it is the median between the high and low values
d, and then decays over time. This is because the experiment relates to the benefits and costs of rolling out one full tranche of meters, and not the
ould be replaced. This would involve a new set of costs for investment and operating expenses, and a new set of demand and operating cost savings. In
nsumers' demand responses would be stable at that time (and supported by the diffusion of technology). Accordingly, a long-run model would produce
,. Therefore, the long-run scenario is probably close to a multiple of the one-off scenario shown here and little is lost in adopting a finite horizon model,
abelled "One-off" and (b) that the meter rollout is staged over five years. The outcomes in the first year (shown as t=0) relate to the outcomes
f meter rollouts occurs between years 4 and 5, with this tranche finally fully depreciated by the period between years 18 and 19 (shown as year = 18).
mid-point high
6,200,000 6,200,000
13200 14850
535 270
125 100
illion per year). Refresh of IT components 7 years after installation
25 20
326.2728501932 381.2728501932
27 34
years after rollout. Maximum savings achieved 15 years after rollout for each
meter. Linear transition path from 2nd to 15th years
8 8
4317 2641
4968 7126
651 4485
105 723
1.2 2.7
$ 12 $ 81
25 percentage points percent75 percentage points percentile
-$ 98 $ 315
-$ 10 $ 35
ntents of this spreadsheet
Costs -$ 5,993,376,875
Benefits $ 3,311,217,837
Net benefit - 2,682,159,037
Benefit-Cost Ratio 0.55
Middle
# meters 6200000
Total peak demand from 13200
Value of network savi 326.2728501932
Year Transition costs of metDM Savings
0 -$ 663,400,000 $ 370,866
1 -$ 663,400,000 $ 3,482,389
2 -$ 663,400,000 $ 11,930,511
3 -$ 663,400,000 $ 29,477,825
4 -$ 663,400,000 $ 60,648,805
5 $ 109,504,031
6 $ 177,052,338
7 -$ 155,000,000 $ 262,383,803
8 -$ 155,000,000 $ 361,618,842
9 -$ 155,000,000 $ 468,648,256
10 -$ 155,000,000 $ 576,531,688
11 -$ 155,000,000 $ 678,990,087
12 $ 771,447,758
13 $ 851,388,221
14 $ 918,133,432
15 $ 761,023,908
16 $ 587,905,680
17 $ 401,668,421
18 $ 204,945,605
19
Operating costs Operating savings Discount factor Discounted costs
- 31,000,000 0 0.96 -$ 668,186,712
- 62,000,000 0 0.89 -$ 646,311,551
- 93,000,000 71,300,000 0.82 -$ 624,010,836
- 124,000,000 142,600,000 0.76 -$ 601,467,640
- 155,000,000 213,900,000 0.71 -$ 578,840,248
- 155,000,000 285,200,000 0.65 -$ 101,508,180
- 155,000,000 356,500,000 0.61 -$ 93,989,056
- 155,000,000 356,500,000 0.56 -$ 174,053,807
- 155,000,000 356,500,000 0.52 -$ 161,160,933
- 155,000,000 356,500,000 0.48 -$ 149,223,086
- 155,000,000 356,500,000 0.45 -$ 138,169,524
- 155,000,000 356,500,000 0.41 -$ 127,934,744
- 155,000,000 356,500,000 0.38 -$ 59,229,048
- 155,000,000 356,500,000 0.35 -$ 54,841,711
- 155,000,000 356,500,000 0.33 -$ 50,779,362
- 124,000,000 285,200,000 0.30 -$ 37,614,343
- 93,000,000 213,900,000 0.28 -$ 26,121,071
- 62,000,000 142,600,000 0.26 -$ 16,124,118
- 31,000,000 71,300,000 0.24 -$ 7,464,869
0.96 $ -
Costs
Benefits
Net benefit
Benefit-Cost Ratio
Discounted benefits
$ 356,866
$ 3,102,713
$ 68,663,063
$ 131,444,302
$ 194,183,649
$ 258,488,310
$ 323,536,003
$ 347,480,910
$ 373,331,298
$ 397,197,320
$ 415,859,820
$ 427,339,225
$ 431,014,660
$ 427,371,982
$ 417,581,116
$ 317,363,100
$ 225,204,551
$ 141,545,940
$ 66,520,561
$ -
-$ 4,317,030,841
$ 4,967,585,389
650,554,548
1.15
Max National smart meter rollout (phased) with poor
Phase in years 5
Summary
Units low
Direct load control devices million 6,200,000
Relevant critical peak demand MWh 11550
Up front cost $ per appliance 800
Refresh cost $ per appliance 150
Cost profile Smart meters phased in over five years (1.24 million per year). Refres
This is used to determine alpha such that it is the median between the high and low values
Inverse beta 50% probability -302
Inverse beta 75% probability 23
alpha 2.013
beta 2.000
error from deviation of inverse beta from t 0.0
(phased) with poorly targeted time of use tariffs only
mid-point high
6,200,000 6,200,000
13200 14850
535 270
125 100
ars (1.24 million per year). Refresh of IT components 7 years after installation
25 20
326.2728501932 381.2728501932
3 3
years after rollout. Maximum savings achieved 15 years after rollout for each
meter. Linear transition path from 2nd to 15th years.
8 8
4,317 2,641
2,445 2849
-1,872 208
-302 34
0.6 1.1
-$ 34 $ 4
25 percentage points percent75 percentage points percentile
-$ 419 -$ 185
-$ 45 -$ 20
Back to the Contents of this spreadsheet
Costs -$ 2,640,684,807
Benefits $ 2,848,841,153
Net benefit 208,156,346
Benefit-Cost Ratio 1.08
Min
Costs -$ 5,993,376,875
Benefits $ 2,025,556,001
Net benefit - 3,967,820,874
Benefit-Cost Ratio 0.34
Middle
Costs
Benefits
Net benefit
Benefit-Cost Ratio
Discounted benefits
$ 35,687
$ 310,271
$ 59,804,931
$ 111,178,919
$ 155,577,378
$ 193,946,378
$ 226,910,946
$ 214,893,782
$ 204,134,695
$ 194,165,626
$ 184,591,439
$ 175,146,383
$ 165,705,596
$ 156,259,541
$ 146,871,392
$ 109,597,999
$ 76,591,073
$ 47,531,518
$ 22,104,336
-$ 4,317,030,841
$ 2,445,357,889
- 1,871,672,952
0.57
Max Direct load control in the absence of sma
Number of DLC devices 1,240,000
Total peak demand from these households outside Vict 4455
Summary
Units
Direct load control devices number
Relevant critical peak demand MWh
Up front cost $ per appliance
Install costs all occur up front for any group of participants. Con
Cost profile
per year) ahead of first three years. Soft
This is used to determine alpha such that it is the median between the high and low values
occur up front for any group of participants. Consumers also receive annual payments (30 to 100
per year) ahead of first three years. Software for direct load control updated after 7 years
25 25 25
15 20 25
um demand management achieved in year 4, with participation in DLC falling to 70% of maximum
participation by year 15
8 8 8
79 162 459
95 437 2875
16 275 2416
131 887 1948
1.2 2.7 6.3
$ 14 $ 96 $ 212
25 percentage points percent75 percentage points percentile
$ 569 $ 1,235
$ 65 $ 140
Costs -$ 458,865,765
Benefits $ 2,874,954,860
Net benefit 2,416,089,094
Benefit-Cost Ratio 6.27
points percentile
Min
# DLC devices 124,000
Total peak demand 346.5
Maximum demand r 15.00
Number of partici 3
-360 124000
Costs -$ 79,170,154
Benefits $ 95,457,105
Net benefit 16,286,952
Benefit-Cost Ratio 1.21
310,000
990
3
Costs -$ 162,352,461
Benefits $ 437,374,601
Net benefit 275,022,140
Benefit-Cost Ratio 2.69
Year 0 1 2 3
kW A/C consumption max 2 2 2 2
Account for not all ac on at the same time or full power ( 1.1475 1.1475 1.1475 1.1475
Total savings in network and generation (LRMC) 374.398096 374.3981 374.3981 374.3981
Discount factor 1 0.925926 0.857339 0.793832
Discounted stream $ 374 $ 347 $ 321 $ 297
Assumes that real cost of network capacity each year rises by the same growth rate as peak to average demand (could be h
As it stands, the $326 is not a net subsidy since the party using the air conditioner does
pay something. However, the bulk of their customer bill is a fixed charge (which will pay
for much of the network capacity at peak) and then a low energy use charge (which will
aslo reflect any marginal costs for retailers, generatrors as well as network businesses).
Properly priced, the true marginal costs of air conditioning at critical peak times will be
very high multiples of the actual marginal energy cost
Back to the Contents of this spreadsheet
4 5 6 7 8 9
2 2 2 2 2 2
1.1475 1.1475 1.1475 1.1475 1.1475 1.1475
374.3981 374.3981 374.3981 374.3981 374.3981 374.3981
0.73503 0.680583 0.63017 0.58349 0.540269 0.500249
$ 275 $ 255 $ 236 $ 218 $ 202 $ 187
326.2729
nditioner does
(which will pay
arge (which will
rk businesses).
k times will be
(1) LRMC
Distribution businesses LRMC estimates
$ per KW per annum
CSIRO 197
CRA (low) 87
CRA (high) 110
Ernst & Young (low) 79
Ernst & Young (high) 264
Ausgrid proposal 163
ActewAGL proposal 158
Jemena proposal 189
United Energy proposal 168
ETSA proposal 169
Ausgrid alternative low estimat 86
Ausgrid Alternative high estima 157
Energex 157
Energex 220
Ergon 291
Ausgrid 212
Essential Energy 259
ActewAGL 228
Powercor 165
SP AusNet Distr 173
United Energy 212
Citipower 259
Jemena 173
ETSA Utilities 275
Aurora Energy 377
Average 193
The value of avoided augmentation to meet peak demand has been valued
as per the previous benefit between $130/kW per year and $240/kW per
Futura 2009 year p.73)
The $240/kW per year figure has been developed up from more recent
information from DBs and other sources (cf the $130 estimate - which we
accordingly ignore). It comprises $120/kW per year for distribution and
transmission augmentation, and up to $120/kW per year for generation
augmentation cost.
Sub 23 based on the DelLRMC OCGT (generation) $129.2 - $155.9 /kW/pa (p. 22)
Energex shares of investment savings (p. 19) $2 billion from Distribution, 0.7 from Transmission, an
0.5714285714
0.2
0.2285714286
2.8571428571
0.7407407407
0.75
Network only
CSIRO $223 per kVA pa
CRA 2008 $98-124 kVA per annum
Ernst & Young $90-$300 per kVA per annum
Convert above to $/kW per annum using a load factor of 0.85 (as in Ausgrid 2012)
CSIRO $262 per kW per annum
CRA 2008 $116- $146 per kW per annum
Ernst & Young $105-$352 per kVA per annum
Average from LRMC from NEM distributors (excluding Endeavour) $144 per kVA per annum fo
Range excluding Endeavour $134-$160 per kVA per annum for LV
Range for distribution in $/kW pa $158-$189
Oakley Greenwood Review of AMI Benefits 2010 Report for Vic DPI
We believe a value of $200/kW/year is a more accurate estimate of the
combined deferral value of generation and network infrastructure.
Ausgrid (derived, with assumptions, from personal communication and Power of Choice submissio
Distribution 2011 $1.1 - 2.0m/MW. Produced by converting the cost of network assets required to deliver 1MW of pe
Transmission 2011 $0.4 - 1.0m/MW. Produced by converting the cost of network assets required to deliver 1MW of pe
Implied distribution $ per kW per annum with 50 year asset life and discoun
Implied transmission $ per kW per annum with 50 year asset life and discou
Generation
OCGT LRMC min
OCGT LRMC max
CSIRO
CRA (low)
CRA (high)
Ernst & Young (low)
Ernst & Young (high)
Ausgrid proposal
ActewAGL proposal
Jemena proposal
United Energy proposal
ETSA proposal
Ausgrid low estimate
Ausgrid high estimate
Energex
Average
variance
alpha
beta
Skewness
Low
High
0.08
Date
2009
2012
ribution, 0.7 from Transmission, and 0.8 for Generation
D 2011
T 2011
G 2011
Ratio of D to T 2011
Ratio of D to network costs 2011
s in Ausgrid 2012)
Source is Department of
Employment, Economic
development and
Innovation, 2011,
Queensland Energy
Management Plan, May, p. 4
or sub. 23 700 Energex TNSP SRMC $ per KW
800 Energex Generayion SRMC $ per KW
157
55
Original data $ per kW per ye Transformed to 0,1 interval This is used to determine alpha and beta using the m
197 0.6356275304 low 78.75
87 0.044534413 high 264
110 0.1659919028 Sample Ave152.60241
79 0 Average as 152.6024
264 1 Inverse bet 194 190
163 0.4563785028 Inverse bet 106.50649 110
158 0.4301500357 alpha 0.818
189 0.5943796142 beta 1.234
168 0.4794951179 error from 0
169 0.4894022386
86 0.0412059933
157 0.4227300724
157 0.4227300724
153 0.399
2696 0.0785468638
0.8180873721 0.8180873721
1.2339875561 1.2339875561
0.33 0.33
110
190
Original data
65.5
29
36.5
26.25
88
31
79
55
51
577.5505006507
0.48
30
60
Original data Transformed to 0,1 interval This is used to determine alpha such that it is the m
65.5 0.6356275304 low 26.25
29.0 0.044534413 high 88
36.5 0.1659919028 Sample Ave 51
26.3 0 Average as 51
88.0 1 Inverse bet 77 80
31.4 0.0835975576 Inverse bet 27 30
78.5 0.8466457159 alpha 0.240
55.0 0.4651216368 beta 0.352
51 0.405 error from 0.00
577.5505006507 0.1514663084
0.2395424698 0.2395424698
0.3516432991 0.3516432991
0.48 0.48
30
80
90 From sub 23
110
method (Method 1)
262
116
146
105
352
217.7254901961
211.2470588235
251.8117647059
223.4352941176
225.8823529412
118
236
212
206
4833.9923654916
0.23
140
230
230
340
RMC $ per KW
Source: Table 27, p. 59 of AECOM 2012, Impact of Electric Vehicles and Natural Gas Vehicles on the Energy Market, Final Ad
TNSPs
Estimated capex growth ($m LRMC assuming 50 year asset life $ per kW per year
Powerlink (qld) 0.85 67
Transgrid (nsw) 0.9 71
SP Ausnet (Act) 0.9 71
SP Ausnet (VIC) 0.47 37
ElectraNet (SA) 0.37 29
Transend (TAS) 1.66 130
AusGrid low estimate 0.4 31
AusGrid high estimate 1.1 86
Capacity wieghted average 0.66 52
Average 0.831 65.278
Variance 0.185 1143.619
alpha 0.379 0.4
beta 0.682 0.7
Source: Table 28, p. 60 of AECOM 2012, Impact of Electric Vehicles and Natural Gas Vehicles on the Energy Market, Final Ad
The cost of transmission growth was estimated to be between $0.37 and $1.66 million per MW, with a
weighted average of $0.66 million. Again, the range was consistent with the estimate reported by
AusGrid (2011) of $0.4 to $1.1 million per MW, with the exception of Transend (again in Tasmania),
which had the most expensive growth. It is worth noting that Transend owns many distribution assets
which may influence their cost estimates.
Generation
Estimated capex growth ($m LRMC assuming 50 year asset life $ per kW per year
All Australia 0.94 74
Source: Table 29, p. 61 of AECOM 2012, Impact of Electric Vehicles and Natural Gas Vehicles on the Energy Market, Final Ad
Summary
SRMC $ per kw
Low High
Distribution 2330 3600
Transmission 430 1200
Generation 940 940
Total 3700 5740
2012
rom a single report.
mand (based on AER Regulatory Determinat
ly, consultants' and businesses' direct
W. This range is
$4 million per
mple Aurora
o be less
f better data, the weighted average of $2.9
Year Max
0 $ 3,095,437
1 $ 25,970,373
2 $ 70,512,385
3 $ 146,458,930
4 $ 260,169,067
5 $ 410,866,337
6 $ 589,763,357
7 $ 782,732,779
8 $ 974,725,722
9 $ 1,153,491,727
10 $ 1,311,317,073
11 $ 1,444,933,969
12 $ 1,554,432,163
13 $ 1,641,950,029
14 $ 1,710,581,665
l case when all smart meters were rolled out simultaneously
Min Medium
6,200,000 6200000
11550 13200
8 8
$ 588,251,058 $ 1,154,038,297
DM Savings
Min Medium
$ 945,212 $ 1,854,329
$ 7,930,225 $ 15,557,614
$ 21,531,421 $ 42,240,612
$ 44,722,199 $ 87,736,571
$ 79,444,339 $ 155,854,900
$ 125,460,744 $ 246,130,459
$ 180,088,128 $ 353,299,146
$ 239,012,612 $ 468,897,938
$ 297,638,923 $ 583,911,768
$ 352,226,301 $ 691,001,970
$ 400,419,310 $ 785,547,620
$ 441,220,110 $ 865,591,140
$ 474,656,105 $ 931,186,294
$ 501,380,262 $ 983,614,081
$ 522,337,385 $ 1,024,728,026
(c) DM savings only occur if there are network savings, which are
the result of planned deferral of investment. Such planning
requires some certainty about the nature of the demand
response, which only becomes apparent over time. The benefit of
the targeted approach described in scenario (1) is that the meters
are only rolled out when there is such certainty.
Back to the Contents of this spreadsheet
Generalised logistic
a_val -0.007
K_val 1
b_val 0.3
V_val 0.2
Q_val 0.5
M_val 1.55
$ 3,095,437 0.0016068176 1
$ 25,970,373 0.0134810206
0.9
$ 70,512,385 0.0366024353
$ 146,458,930 0.0760257017 0.8
$ 260,169,067 0.1350517574 0.7
$ 410,866,337 0.2132775488 0.6
$ 589,763,357 0.3061416129
0.5
$ 782,732,779 0.4063105523
$ 974,725,722 0.505972609 0.4
$ 1,153,491,727 0.5987686645 0.3
$ 1,311,317,073 0.680694585 0.2
$ 1,444,933,969 0.7500540857
0.1
$ 1,554,432,163 0.8068937544
0
$ 1,641,950,029 0.852323604
1 2 3 4 5 6 7 8 9 10
$ 1,710,581,665 0.8879497575
6 7 8 9 10 11 12 13 14 15
Max Limited smart meter with critical peak demand m
This (SEE NOTE) model is identical to scenario 1, except that it includes a given lumpy project that isdeferred by one year (s
# meters 10,000
Total peak demand from these households 35.93 The 1.5 factor is used because regions where defer
Value ($) of avoided network and generati 381.2728501932
Absolute value of long-run elasticity 0.2
Before-after price ratio 8 As per the SP Ausnet strategic pricing trial
SRMC savings (=1 if option is on, and 0 if n 1
Note: p1 and p0 are prices after and before cost-reflective pricing. Given q0 is starting value of demand, and q1 the level
network saving from reductions in peak energy use is equal to (q0-q1)* the value of network savings from each MW of lo
dlog(q)/dlog(p) so that log(q1/q0) = e*log(p1/p0). Accordingly q1/q0 = exp(e*log(p1/p0)) and the MW savings = q0-q1 =
multiplied by the value of network and generation savings per unit of energy reduced. Note the elasticity shown as elasti
whereas the e used in the calculation is the negative of that value. It is assumed that it takes 7 years before there is a full
power after and before price changes.
Summary
Units low
Smart meters number 10,000
Relevant critical peak demand MWh 28
Up front cost $ per appliance 800
Refresh cost $ per appliance 150
Cost profile Install costs all occur up front. IT refresh after 7 years.
Annual cost $ per appliance per year 30
Value of demand management savings $/kW per year all other
271.2728501932
(network/generation) years
% of relevant critical peak
Maximum demand management response
demand 19
Seven years to get full demand response, with little demand response in first ye
Demand management savings profile
subsequently sustained. Line
Discount rate per cent 8
Discounted costs $ Million (npv) 11
Discounted benefits $ Million (npv) 13
Net benefit $ Million (npv) 2
Net benefit per household $ (npv) 168
Benefit cost ratio ratio 1.1
Annuity in savings per household over 15
$
year period $ 19
This is used to determine alpha such that it is the median between the high and low values
Inverse beta 50% probability 1412
Inverse beta 75% probability 1932
alpha 1.663
beta 2.000
error from deviation of inverse beta from t 0 Must be zero
Total demand reduction (MWDM savings from deferredOperating costs $ Operating savings $
1.7463089041 0- 200,000 0
3.4926178082 25000000 - 200,000 0
5.2389267123 -25000000 - 200,000 650,000
6.9852356164 0- 200,000 650,000
8.7315445205 0- 200,000 650,000
10.4778534246 0- 200,000 650,000
12.2241623287 0- 200,000 650,000
12.2241623287 0- 200,000 650,000
12.2241623287 0- 200,000 650,000
12.2241623287 0- 200,000 650,000
12.2241623287 0- 200,000 650,000
12.2241623287 0- 200,000 650,000
12.2241623287 0- 200,000 650,000
12.2241623287 0- 200,000 650,000
12.2241623287 0- 200,000 650,000
lue of demand, and q1 the level of demand following the price change, the Costs
work savings from each MW of lower demand. Now e = elasticity = Benefits
and the MW savings = q0-q1 = q0(1-exp(e*log(p1/p0))). This needs to be Net benefit
ote the elasticity shown as elasticity_high is the absolute value of the elasticity,
Benefit-Cost Ratio
kes 7 years before there is a full demand response. q1 and q0 are quantities of
326.2728501932 381.2728501932
27 34
little demand response in first year. Maximum demand response is
subsequently sustained. Linear increase in response over time
8 8
8 5
22 35
14 30
1412 2965
2.7 7.0
$ 159 $ 333
25 percentage points percent75 percentage points percentile
$ 921 $ 1,932
$ 100 $ 200
Medium High
$ 1,410 $ 2,960
istribution network infrastructure Back to the Contents of this spreadsheet
-$ 4,938,594
$ 34,588,314
29,649,719
Note:
7.00 In this calculation, there is a benefit from deferring a large lumpy inves
that the value of any given reduction of kVA is worth more than its LRM
Balgowlah zone substation build, which would have cost $25m, and fou
would defer the supply-side proposal by one year.
12.2241623287 Given it is usually growth in max demand that creates the need for augm
34% unlikely to defer a project by one full year (though perhaps by some sho
Since the model is illustrative, we have assumed that the size of the def
MW saving from DM.
Min
# meters 10,000
Total peak demand from these house 27.94
Value of Network and generation s 271.2728501932
Absolute value of elasticity 0.1
a benefit from deferring a large lumpy investment by one year, with the potential
reduction of kVA is worth more than its LRMC. For example, Ausgrid examined its
build, which would have cost $25m, and found that a 2.7MVA load reduction
e proposal by one year.
n max demand that creates the need for augmentation, small DM savings are
by one full year (though perhaps by some shorter period).
tive, we have assumed that the size of the deferred project is $25 million per 3.492
DM savings on SRMC distribOperating costsOperating savings Discount factor
0 - 300,000 0 0.96
$ 10,729,435 - 300,000 0 0.89
-$ 10,729,435 - 300,000 500,000 0.82
0 - 300,000 500,000 0.76
0 - 300,000 500,000 0.71
0 - 300,000 500,000 0.65
0 - 300,000 500,000 0.61
0 - 300,000 500,000 0.56
0 - 300,000 500,000 0.52
0 - 300,000 500,000 0.48
0 - 300,000 500,000 0.45
0 - 300,000 500,000 0.41
0 - 300,000 500,000 0.38
0 - 300,000 500,000 0.35
0 - 300,000 500,000 0.33
Middle
# meters
Total peak demand fro
Value of Network and
Absolute value of elasti
Costs -$ 11,208,781
Benefits $ 12,889,373
Net benefit 1,680,593
Benefit-Cost Ratio 1.15
10000
31.935483871
326.2728501932
0.15
Costs -$ 8,073,688
Benefits $ 22,193,944
Net benefit 14,120,257
Benefit-Cost Rat 2.75
ounted benefits
Back to the Contents of this spreadsheet
References
AECOM 2012, Impact of Electric Vehicles and Natural Gas Vehicles on the Energy Markets, Report for
AEMC, 22 June.
AEMC (Australian Energy Market Commission) 2012, Fact Sheet: Enabling Technology (Meteri
30 November.
AER (Australian Energy Regulator) 2011, Victorian Advanced Metering Infrastructure Review, 2012
budget and charges applications, final determination, October.
2012, Determination, Advanced Metering Infrastructure, 2013 revised charges, October 2012.
Ausgrid 2012, Ausgrid Network Pricing Proposal for the Financial Year Ending June 2013, May 2012.
2013, Meter Upgrades, accessed on 25 March 2013 from http://www.ausgrid.com.au/Common/O
network/Metering/Meter-upgrades.aspx.
CRA (Charles River Associates) 2007, Cost Benefit Analysis of Smart Metering and Direct Load Con
Stream 2, Network Benefits and Recurring Costs, prepared for the Department of Industry, Tourism
Resources, Phase 1 Report, September.
2008a, Cost benefit analysis of smart metering and direct load control, Report to the Ministe
Council on Energy, Work stream 2: Network benefits and recurrent costs.
2008b, Cost benefit analysis of smart metering and direct load control, Report to the Ministe
Council on Energy, Work stream 5: Economic Impacts on wholesale electricity market and greenhouse
emission outcomes.
Deloitte 2011a, Advanced metering infrastructure cost benefit analysis, Final Report to the Victo
Department of Treasury and Finance, 2 August.
2011b, Advanced metering infrastructure customer impact study, Final Report, 2 volumes, repor
the Victorian Department of Primary Industries, October.
2012, Analysis of initiatives to lower peak demand, Report for Energy Supply Association of Austr
April.
EMCa (Energy Market Consulting Associates) 2008, Cost benefit analysis of smart metering and direct l
control, Report to the Ministerial Council on Energy, Work stream 6: Transitional implementation costs.