ID Task Name Duration Start May 2017 September 2017 January 2018

1 May 1 June 21 August 11 October 1 November 21 January 11 March 1 April


3/26 4/16 5/7 5/28 6/18 7/9 7/30 8/20 9/10 10/1 10/22 11/12 12/3 12/24 1/14 2/4 2/25 3/18 4/8
1 PROPOSEDTRAININGFACILITY 235days Fri5/12/17

2 ARCHITECTURALWORK 51days Fri5/12/17

6 PRELIMINARYWORKS 30days Mon6/12/17

10 PROCUREMENT 60days Fri7/21/17

16 MAINBUILDING 155days Fri9/1/17

17 CIVILWORKS 100days Fri9/1/17

21 INTERNALS 95days Fri11/24/17

26 MECHANICAL 30days Fri1/12/18

29 HOSTELBUILDING 85days Fri9/1/17

30 CIVILWORKS 70days Fri9/1/17

34 INTERNALS 45days Fri10/27/17

41 RECREATIONALAREA 60days Fri11/17/17

45 UTILITIES 94days Fri9/15/17

46 SEWAGETREATMENTFACILITY 75days Fri9/15/17

50 WATERTREATMENTPLANT 60days Fri9/15/17

54 POWER&GENERATORFACILITY 39days Fri12/1/17

58 INTERNALROAD&PAVEMENT 30days Fri11/17/17

Task Project Summary Manual Task Start-only Deadline

Project: TRAINING MODU- MS Split Inactive Task Duration-only Finish-only Progress


Date: Sun 6/11/17 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress