TENDER ESTIMATE

TENDER ESTIMATE FOR ELECTRICAL SERVICES

Item
Preliminaries n/a

General Conditions of Contract including one day surveying 200

Ensuring the adjacent areas and ancillary accommodation remain fully


operational, without disruption or loss of supply throughout the contract
works inc temporaries and diversion supply authority

Isolation, disconnection and removal of redundant equipment,


materials, accessories and cable etc. Strip out works general 1000

20 Steel street lamps 18,000

2no Ground workers including materials Concrete 4,900

Hire of Hiab / concret mixers (2weeks) 2,640

2No Qualified JIB Electrician

Luminaires & Lamps


Lighting installation 3,200
Final inspection 200
Site Foreman 2,400
Overheads 2000

As-fitted drawings & operation & maintenance manuals 200

Any item not included above (please specify) 1000


Storing of old street lamps
Delivery of new street lamps

Provisional Sums

Electrical Works created by works in adjacent areas risk 1500

Note :
Allowance for any jointing of armored cable underground( provisional sum only )

1 OF 3
TENDER ESTIMATE

Provisional 1500
Total to form tender 37240
Cost plus 22% 45432.8

SignedC.STEWART

For and on Behalf of NEW STREET LAMPS.

Date 27/03/15.

Notes

2no of Electricians have been allocated for this project , along with 2no Ground workers.

Site Foreman to oversee the project from start to finish has been allowed in case of any unforeseen
circumstances.

Hiab will be kept on site and hired out for the full duration of the project, we believe this is the most
easiest and practical solution to be implemented.