ID Task Name Duration Start Finish Half 1, 2016

N D J F M A M J
0 Engineering Schedule Container Ship 100 TEUs 157 days Tue 8/12/15 Fri 13/05/16
1 Activity Milestone 157 days Tue 8/12/15 Fri 13/05/16
2 Contract 0 days Tue 8/12/15 Tue 8/12/15 8/12
3 Complete Basic Design (Class Approval Drawing) 0 days Mon 22/02/16 Mon 22/02/16 22/02
4 Complete Production Engineering & Information Drawing 0 days Fri 13/05/16 Fri 13/05/16 13/05
5 Basic Design (Class Approval Drawing) 57 days Sun 27/12/15 Mon 22/02/16
6 General Part 0 days Sun 27/12/15 Sun 27/12/15 27/12
7 General Arrrangement 0 days Sun 27/12/15 Sun 27/12/15 27/12
8 Lines Plan 0 days Sun 27/12/15 Sun 27/12/15 27/12
9 Offset Table 0 days Sun 27/12/15 Sun 27/12/15 27/12
10 Hydrostatic Table 0 days Sun 27/12/15 Sun 27/12/15 27/12
11 Cross Curve of Stability 0 days Sun 27/12/15 Sun 27/12/15 27/12
12 Freeboard Calculation 0 days Sun 27/12/15 Sun 27/12/15 27/12
13 Trim & Stability Calculation (Pre & Final) 0 days Sun 27/12/15 Sun 27/12/15 27/12
14 Gross Tonage Calculation 0 days Sun 27/12/15 Sun 27/12/15 27/12
15 DWT Calculation 0 days Sun 27/12/15 Sun 27/12/15 27/12
16 Speed Prediction Calculation 0 days Sun 27/12/15 Sun 27/12/15 27/12
17 Hull Construction 0 days Fri 8/01/16 Fri 8/01/16 8/01
18 Scantling Calculation 0 days Fri 8/01/16 Fri 8/01/16 8/01
19 Midship Section 0 days Fri 8/01/16 Fri 8/01/16 8/01
20 Profile And Deck Plan 0 days Fri 8/01/16 Fri 8/01/16 8/01
21 Shell Expansion 0 days Fri 8/01/16 Fri 8/01/16 8/01
22 Trans & Longitudinal Bulkhead 0 days Fri 8/01/16 Fri 8/01/16 8/01
23 Welding Detail & Procedure 0 days Fri 8/01/16 Fri 8/01/16 8/01
24 Welding Table 0 days Fri 8/01/16 Fri 8/01/16 8/01
25 Docking Table 0 days Fri 8/01/16 Fri 8/01/16 8/01
26 After & ER Contruction 0 days Fri 8/01/16 Fri 8/01/16 8/01
27 Midle Construction 0 days Fri 8/01/16 Fri 8/01/16 8/01
28 Fore Construction 0 days Fri 8/01/16 Fri 8/01/16 8/01
29 Crew & Navigation Deck 0 days Fri 8/01/16 Fri 8/01/16 8/01
30 Funnel Construction 0 days Fri 8/01/16 Fri 8/01/16 8/01
31 Rudder Construction 0 days Fri 8/01/16 Fri 8/01/16 8/01
32 Shaft Struts 0 days Fri 8/01/16 Fri 8/01/16 8/01
33 Deck Machinery & Reinforcement 0 days Fri 8/01/16 Fri 8/01/16 8/01
34 Crane Foundation & Reinforcement 0 days Fri 8/01/16 Fri 8/01/16 8/01
35 Material Estimation 0 days Fri 8/01/16 Fri 8/01/16 8/01
36 X-Ray Plan 0 days Fri 8/01/16 Fri 8/01/16 8/01
37 Hull Outfitting 0 days Sun 31/01/16 Sun 31/01/16 31/01
38 Equipment Number Calculation 0 days Sun 31/01/16 Sun 31/01/16 31/01
39 Deck Machinery Calculation 0 days Sun 31/01/16 Sun 31/01/16 31/01
40 Fire Protection 0 days Sun 31/01/16 Sun 31/01/16 31/01
41 Fire Fit & Safety Plan 0 days Sun 31/01/16 Sun 31/01/16 31/01

Task Milestone External Tasks


Project: Engineering Schedule Contain
Split Summary External Milestone
Date: Tue 17/11/15
Progress Project Summary Deadline

Page 1
ID Task Name Duration Start Finish Half 1, 2016
N D J F M A M J
42 Rudder Stock & Torque Calculation 0 days Sun 31/01/16 Sun 31/01/16 31/01
43 Rudder, Rudder Stock & Fitting Arrangement 0 days Sun 31/01/16 Sun 31/01/16 31/01
44 Accomodation Arrangement 0 days Sun 31/01/16 Sun 31/01/16 31/01
45 Door & Window Arrangement 0 days Sun 31/01/16 Sun 31/01/16 31/01
46 Cathodic Protection Arrangement 0 days Sun 31/01/16 Sun 31/01/16 31/01
47 Draft Mark Arrangement 0 days Sun 31/01/16 Sun 31/01/16 31/01
48 Man Hole & Hatch Arrangement 0 days Sun 31/01/16 Sun 31/01/16 31/01
49 Mooring Arrangement 0 days Sun 31/01/16 Sun 31/01/16 31/01
50 Machinery Outfitting 0 days Mon 22/02/16 Mon 22/02/16 22/02
51 Bilge & Ballast System 0 days Mon 22/02/16 Mon 22/02/16 22/02
52 Fire & Deck System 0 days Mon 22/02/16 Mon 22/02/16 22/02
53 Sounding, Air Pipe, Filling Pipe Arrangement 0 days Mon 22/02/16 Mon 22/02/16 22/02
54 Fuel Oil System 0 days Mon 22/02/16 Mon 22/02/16 22/02
55 Cooling System 0 days Mon 22/02/16 Mon 22/02/16 22/02
56 LO System 0 days Mon 22/02/16 Mon 22/02/16 22/02
57 Capacity Plan 0 days Mon 22/02/16 Mon 22/02/16 22/02
58 Outside Deck Scupper System 0 days Mon 22/02/16 Mon 22/02/16 22/02
59 SW,FW, & Sanitary Supply System 0 days Mon 22/02/16 Mon 22/02/16 22/02
60 Exhaust Gas Piping System 0 days Mon 22/02/16 Mon 22/02/16 22/02
61 Dirty Oil System 0 days Mon 22/02/16 Mon 22/02/16 22/02
62 Compressed Air System 0 days Mon 22/02/16 Mon 22/02/16 22/02
63 Gear System 0 days Mon 22/02/16 Mon 22/02/16 22/02
64 AC & Ventilation System 0 days Mon 22/02/16 Mon 22/02/16 22/02
65 Engine Room Layout 0 days Mon 22/02/16 Mon 22/02/16 22/02
66 Shafting Arrangement 0 days Mon 22/02/16 Mon 22/02/16 22/02
67 Electric Outfitting 0 days Mon 22/02/16 Mon 22/02/16 22/02
68 Electric Power Consumption Table 0 days Mon 22/02/16 Mon 22/02/16 22/02
69 General Electric Diagram 0 days Mon 22/02/16 Mon 22/02/16 22/02
70 Electrical Load Balance 0 days Mon 22/02/16 Mon 22/02/16 22/02
71 Arrangement of Electrical Equipment 0 days Mon 22/02/16 Mon 22/02/16 22/02
72 Battery Calculation 0 days Mon 22/02/16 Mon 22/02/16 22/02
73 Arrangement of Main Cable Way 0 days Mon 22/02/16 Mon 22/02/16 22/02
74 Arrangemnt Of Navigation Light 0 days Mon 22/02/16 Mon 22/02/16 22/02
75 Complete Basic Design (Class Approval Drawing) 0 days Mon 22/02/16 Mon 22/02/16 22/02
76 Production Engineering & Information 137 days Mon 28/12/15 Fri 13/05/16
77 Production Information Hull Structure 71 days Mon 28/12/15 Tue 8/03/16
78 Production Information Stern Bottom Block 13 days Mon 28/12/15 Sun 10/01/16
79 Model 6 days Mon 28/12/15 Sun 3/01/16
80 Working Drawing 4 days Sun 3/01/16 Thu 7/01/16
81 APL 2 days Thu 7/01/16 Sat 9/01/16
82 Nesting Plate 4 days Sun 3/01/16 Thu 7/01/16
83 Cutting Profile 3 days Sun 3/01/16 Wed 6/01/16

Task Milestone External Tasks


Project: Engineering Schedule Contain
Split Summary External Milestone
Date: Tue 17/11/15
Progress Project Summary Deadline

Page 2
ID Task Name Duration Start Finish Half 1, 2016
N D J F M A M J
84 Check 1 day Sat 9/01/16 Sun 10/01/16
85 Production Information Stern Top Block 12 days Wed 13/01/16 Mon 25/01/16
86 Model 6 days Wed 13/01/16 Tue 19/01/16
87 Working Drawing 3 days Tue 19/01/16 Fri 22/01/16
88 APL 2 days Fri 22/01/16 Sun 24/01/16
89 Nesting Plate 4 days Tue 19/01/16 Sat 23/01/16
90 Cutting Profile 3 days Tue 19/01/16 Fri 22/01/16
91 Check 1 day Sun 24/01/16 Mon 25/01/16
92 Production Information Bow Block 12 days Wed 20/01/16 Mon 1/02/16
93 Model 6 days Wed 20/01/16 Tue 26/01/16
94 Working Drawing 3 days Tue 26/01/16 Fri 29/01/16
95 APL 2 days Fri 29/01/16 Sun 31/01/16
96 Nesting Plate 4 days Tue 26/01/16 Sat 30/01/16
97 Cutting Profile 3 days Tue 26/01/16 Fri 29/01/16
98 Check 1 day Sun 31/01/16 Mon 1/02/16
99 Production Information Void Block-1 Bottom 11 days Wed 20/01/16 Sun 31/01/16
100 Model 4 days Wed 20/01/16 Sun 24/01/16
101 Working Drawing 3 days Sun 24/01/16 Wed 27/01/16
102 APL 3 days Wed 27/01/16 Sat 30/01/16
103 Nesting Plate 2 days Sun 24/01/16 Tue 26/01/16
104 Cutting Profile 2 days Sun 24/01/16 Tue 26/01/16
105 Check 1 day Sat 30/01/16 Sun 31/01/16
106 Production Information Void Block-1 Top 11 days Wed 27/01/16 Sun 7/02/16
107 Model 5 days Wed 27/01/16 Mon 1/02/16
108 Working Drawing 3 days Mon 1/02/16 Thu 4/02/16
109 APL 2 days Thu 4/02/16 Sat 6/02/16
110 Nesting Plate 4 days Mon 1/02/16 Fri 5/02/16
111 Cutting Profile 3 days Mon 1/02/16 Thu 4/02/16
112 Check 1 day Sat 6/02/16 Sun 7/02/16
113 Production Information Void Block-2 11 days Mon 1/02/16 Fri 12/02/16
114 Model 5 days Mon 1/02/16 Sat 6/02/16
115 Working Drawing 3 days Sat 6/02/16 Tue 9/02/16
116 APL 2 days Tue 9/02/16 Thu 11/02/16
117 Nesting Plate 4 days Sat 6/02/16 Wed 10/02/16
118 Cutting Profile 3 days Sat 6/02/16 Tue 9/02/16
119 Check 1 day Thu 11/02/16 Fri 12/02/16
120 Production Information Void Block-3 11 days Tue 2/02/16 Sat 13/02/16
121 Model 5 days Tue 2/02/16 Sun 7/02/16
122 Working Drawing 3 days Sun 7/02/16 Wed 10/02/16
123 APL 2 days Wed 10/02/16 Fri 12/02/16
124 Nesting Plate 4 days Sun 7/02/16 Thu 11/02/16
125 Cutting Profile 3 days Sun 7/02/16 Wed 10/02/16

Task Milestone External Tasks


Project: Engineering Schedule Contain
Split Summary External Milestone
Date: Tue 17/11/15
Progress Project Summary Deadline

Page 3
ID Task Name Duration Start Finish Half 1, 2016
N D J F M A M J
126 Check 1 day Fri 12/02/16 Sat 13/02/16
127 Production Information Void Block-4 11 days Fri 5/02/16 Tue 16/02/16
128 Model 5 days Fri 5/02/16 Wed 10/02/16
129 Working Drawing 3 days Wed 10/02/16 Sat 13/02/16
130 APL 2 days Sat 13/02/16 Mon 15/02/16
131 Nesting Plate 4 days Wed 10/02/16 Sun 14/02/16
132 Cutting Profile 3 days Wed 10/02/16 Sat 13/02/16
133 Check 1 day Mon 15/02/16 Tue 16/02/16
134 Production Information Void Block-5 11 days Wed 10/02/16 Sun 21/02/16
135 Model 5 days Wed 10/02/16 Mon 15/02/16
136 Working Drawing 3 days Mon 15/02/16 Thu 18/02/16
137 APL 2 days Thu 18/02/16 Sat 20/02/16
138 Nesting Plate 4 days Mon 15/02/16 Fri 19/02/16
139 Cutting Profile 3 days Mon 15/02/16 Thu 18/02/16
140 Check 1 day Sat 20/02/16 Sun 21/02/16
141 Production Information Void Superstructure Block 24 days Sat 13/02/16 Tue 8/03/16
142 Model 10 days Sat 13/02/16 Tue 23/02/16
143 Working Drawing 8 days Tue 23/02/16 Wed 2/03/16
144 APL 4 days Wed 2/03/16 Sun 6/03/16
145 Nesting Plate 6 days Tue 23/02/16 Mon 29/02/16
146 Cutting Profile 3 days Tue 23/02/16 Fri 26/02/16
147 Check 2 days Sun 6/03/16 Tue 8/03/16
148 Complete Production Information Hull Sructure 0 days Tue 8/03/16 Tue 8/03/16 8/03
149 Production Information Hull Outfitting 90 days Sat 13/02/16 Fri 13/05/16
150 Equipment Foundations 44 days Sat 13/02/16 Mon 28/03/16
151 Foundation Auxilary Engine 4 days Sat 13/02/16 Wed 17/02/16
152 Foundation Harbour Generator 4 days Mon 15/02/16 Fri 19/02/16
153 Foundation FO Transfer Pump 4 days Wed 17/02/16 Sun 21/02/16
154 Foundation Bilge Pump 4 days Fri 19/02/16 Tue 23/02/16
155 Foundation Ballast Pump 4 days Sun 21/02/16 Thu 25/02/16
156 Foundation Fire & GS Pump 4 days Tue 23/02/16 Sat 27/02/16
157 Foundation Hydropore SW Pump 4 days Thu 25/02/16 Mon 29/02/16
158 Foundation Hydropore FW Pump 4 days Sat 27/02/16 Wed 2/03/16
159 Foundation Oil Water Separotor Pump 4 days Mon 29/02/16 Fri 4/03/16
160 Foundation Air Compressor 5 days Wed 2/03/16 Mon 7/03/16
161 Foundation Fresh Water Generator 5 days Sat 5/03/16 Thu 10/03/16
162 Foundation Sewage Treatment Plant 5 days Tue 8/03/16 Sun 13/03/16
163 Foundation Steering Gear 5 days Fri 11/03/16 Wed 16/03/16
164 Foundation Emergency Fire Pump 5 days Mon 14/03/16 Sat 19/03/16
165 Foundation Capstain 5 days Thu 17/03/16 Tue 22/03/16
166 Foundation AHU 5 days Sun 20/03/16 Fri 25/03/16
167 Foundation Emergency Generator 5 days Wed 23/03/16 Mon 28/03/16

Task Milestone External Tasks


Project: Engineering Schedule Contain
Split Summary External Milestone
Date: Tue 17/11/15
Progress Project Summary Deadline

Page 4
ID Task Name Duration Start Finish Half 1, 2016
N D J F M A M J
168 Vertical Ladder in Tanks Detail 4 days Sat 26/03/16 Wed 30/03/16
169 Platform & Handrails 4 days Mon 28/03/16 Fri 1/04/16
170 Grating Arrangement 4 days Wed 30/03/16 Sun 3/04/16
171 Ladder, Stairs, Handrails 4 days Fri 1/04/16 Tue 5/04/16
172 Engine Room Flooring (Chequer Plate) 4 days Sun 3/04/16 Thu 7/04/16
173 Lifesaving & Fire Fighting Plan 4 days Tue 5/04/16 Sat 9/04/16
174 Cathodic Protection Arrangement 4 days Thu 7/04/16 Mon 11/04/16
175 Shaft Support 4 days Sat 9/04/16 Wed 13/04/16
176 Bilge Keel 4 days Mon 11/04/16 Fri 15/04/16
177 Drain Plug Arrangement 4 days Wed 13/04/16 Sun 17/04/16
178 Manhole & Layout Details 4 days Fri 15/04/16 Tue 19/04/16
179 Hawse Pipe 4 days Sun 17/04/16 Thu 21/04/16
180 Bulwark 4 days Tue 19/04/16 Sat 23/04/16
181 Fender Detail 4 days Thu 21/04/16 Mon 25/04/16
182 Rubber Fender Detail 4 days Sat 23/04/16 Wed 27/04/16
183 Mast Contruction 4 days Mon 25/04/16 Fri 29/04/16
184 Hatches Detail 4 days Wed 27/04/16 Sun 1/05/16
185 Watertight Doors 4 days Fri 29/04/16 Tue 3/05/16
186 Windows & Scuttles 4 days Sun 1/05/16 Thu 5/05/16
187 Bollard Details 4 days Tue 3/05/16 Sat 7/05/16
188 Ship's Name 4 days Thu 5/05/16 Mon 9/05/16
189 Plimsol & Draft Marks (Freeboard) 4 days Sat 7/05/16 Wed 11/05/16
190 Anchor Windlass Mooring System 4 days Mon 9/05/16 Fri 13/05/16
191 Complete Production Information Hull Outfitting 0 days Fri 13/05/16 Fri 13/05/16 13/05
192 Production Information Piping 56 days Fri 26/02/16 Fri 22/04/16
193 Ballast System 5 days Fri 26/02/16 Wed 2/03/16
194 Bilge System 5 days Mon 29/02/16 Sat 5/03/16
195 Fuel Oil System 5 days Thu 3/03/16 Tue 8/03/16
196 Fresh Water System 5 days Sun 6/03/16 Fri 11/03/16
197 Sea Water System 5 days Wed 9/03/16 Mon 14/03/16
198 Lube Oil System 5 days Sat 12/03/16 Thu 17/03/16
199 Cooling System 5 days Tue 15/03/16 Sun 20/03/16
200 Oil Water Separator System 5 days Fri 18/03/16 Wed 23/03/16
201 Dirty Oil System 5 days Mon 21/03/16 Sat 26/03/16
202 Air Vent, Sounding & Filling System 5 days Thu 24/03/16 Tue 29/03/16
203 Hydraulic System 5 days Sun 27/03/16 Fri 1/04/16
204 Sanitary System 5 days Wed 30/03/16 Mon 4/04/16
205 Fire Figthing System 5 days Sat 2/04/16 Thu 7/04/16
206 Sea Main Line System 5 days Tue 5/04/16 Sun 10/04/16
207 Scuppers & Discharges System 5 days Fri 8/04/16 Wed 13/04/16
208 Exhaust System 5 days Mon 11/04/16 Sat 16/04/16
209 CO2 System 5 days Thu 14/04/16 Tue 19/04/16

Task Milestone External Tasks


Project: Engineering Schedule Contain
Split Summary External Milestone
Date: Tue 17/11/15
Progress Project Summary Deadline

Page 5
ID Task Name Duration Start Finish Half 1, 2016
N D J F M A M J
210 Compressed Air System 5 days Sun 17/04/16 Fri 22/04/16
211 Complete Production Information Piping 0 days Fri 22/04/16 Fri 22/04/16 22/04
212 Production Information HVAC 15 days Fri 26/02/16 Sat 12/03/16
213 Production Information Electrical 15 days Fri 26/02/16 Sat 12/03/16
214 Drawings & Stability Booklet 15 days Fri 26/02/16 Sat 12/03/16
215 Complete PE & PI 0 days Fri 13/05/16 Fri 13/05/16 13/05