Tabel 1.

Activity and activity duration

Activity
Task_Name Start_Date Duration Finish_Date
Code

Kegiatan persiapan 7 days

A Persiapan 20 Februari 2017 1 day 21 Februari 2017


B Survey Lokasi 22 Februari 2017 2 days 24 Februari 2017
C Pembelian Bahan 25 Februari 2017 3 days 28 Februari 2017
Pembuatan Sistem Planning
D 29 Februari 2017 2 days 30 Februari 2017
dan Peta Petak
Kegiatan eksekusi 5 days
E Eksekusi Pemasangan 1 April 2017 3 days 4 April 2017
F Pemeriksaan alat 1 April 2017 3 days 4 April 2017
G Pemasangan tiang TL 1 April 2017 3 days 4 April 2017
H Pengecekan Receiver TL 5 April 2017 1 day 6 April 2017
I Pengecekan Jaringan TL 5 April 2017 1 day 6 April 2017
J Pemasangan Countdown 7 April 2017 1 day 8 April 2017
Tabel 2. Precedence Relationship Chart

Estimed
Immediate
Activity Completion
Predecessor
Time
A - 1 day
B - 2 days
C A,B 3 days
D C 2 days
E D 3 days
F E 3 days
G F 3 days
H G 1 day
I G,H 1 day
J H,I 1 day
A
1 H
1

Start C D E F G J
Finish
3 2 3 3 3 1

I
1
B
2