You are on page 1of 6

Understanding the Hospital Planning,

Design, and Construction Process


Introduction Development Facilities Development Division
Californias acute care hospitals are an essential (OSHPD FDD) for the building permit and
health care resource that serve a wide range of subsequent construction observation. See page 5
patients during times of illness or injury. To for descriptions of these agencies.

ISSUE BRIEF
do so properly, they must be well designed,
The third phase covers bidding, construction,
safe, and efficient. Recent hospital construction
licensing, and evaluation. Licensing is provided
planning in response to the seismic safety
by the U.S. Department of Health Services
mandates of SB 1953 will require many hospital
and the California Health and Human Services
boards of directors to oversee major building
Agency. Only with their approval can the
projects. Because such projects are relatively
hospital operate and be eligible for Medicare
infrequent, board members and leaders may
and Medical reimbursement.
have only limited experience with the many
complexities and challenges involved in the Implementation of the hospital planning,
planning, design, and construction of a hospital design, and construction process is depicted on
facility. This issue brief is intended to acquaint the flow chart on page 2. The chart is based
non-experts with the way in which hospital upon major projects or extensive re-builds which
construction projects are developed and typically take seven or eight years to complete.
delivered. Smaller projects, such as interior remodeling,
use the same process but may not require the
Background land use approval activities.
The hospital planning, design, and construction
process takes the form of three distinct phases. Phase 1: Project Definition and
Planning
The first is the definition and planning for the
Project Request: All hospitals should have a
hospital project itself, including the project
process to identify construction projects and
request, strategic plan, facilities needs assess-
requests. Smaller projects are often a part of the
ment, specific program, and concept design.
routine planning and budgeting process; larger
Second is the preparation of schematic projects typically require focused attention and
design, design development, construction consideration within the context of the hospitals
documentation, and securing a building permit. longer range strategic and capital planning
This phase involves two public agencies: the processes.
city or county for land use approval, and
Strategic Plan: Most hospital construction
the Office of Statewide Health Planning and
projects are the result of either changes in
F EBRUARY
2007
Figure 1: Elements of a Hospital Building Project

Land Use Approval Planning, Design, and Construction Building Permit Approval

PHASE 1

Project Request
Strategic Plan
Needs Assessment

Specific Program
Concept Design

PHASE 2

Schematic Development

City Land Use OSHPD Building


Permit Process Permit Process

Conditional Use Permit


and Environmental Preliminary
Design Development
Impact Report Submittal
Submission

Construction Building Permit


Documents Submittal
Public Hearings

Building Permit

PHASE 3
Bidding/Construction Inspection

Licensing/Occupancy

Evaluation

the numbers of patients served, new treatments, patients, physicians, and the board of directors. The
or technologies, or strategic initiatives that further plan should address the patient care and community
the hospitals mission. All hospitals should have a service goals for a period of at least five years. The
strategic plan that has been developed with the partic- proposed building projects encompassed within the
ipation of hospitals administration, professional staff, strategic plan should both allow the hospital to grow

2 | CALIFORNIA HEALTHCARE FOUNDATION


and improve the treatment of patients through the program is then tested against the strategic plan and
introduction of new equipment or services, develop- the facilities needs assessment.
ment of key departments, and compliance with Senate
Depending on the complexity of the project, this
Bill 1953 for seismic upgrades, which may require
is the time to select an architect with appropriate
major additions or even hospital replacement. Any
engineering consultants. Some firms provide the
new project should be reviewed internally to determine
programming services above, but most hospitals
whether it is consistent with the strategic plan.
should select their design team no later than the
Facility Needs Assessment: Intrinsic to the strategic completion of programming. It is essential that the
plan is the facility needs assessment. This evaluates architect be experienced in the design of California
each of the departments in the hospital to determine hospitals and has extensive experience working with
how they are meeting their current and potential future OSHPD FDD.
workloads. These workload forecasts generate space
Concept Design: Upon approval of the specific
requirements that form the basis for future remodel-
program, a concept design is prepared that develops
ing or additions that accommodate changing needs.
the available space into floor plans, interior elevations,
Service lines may need clarification or re-definition. A
stacking and blocking diagrams, building sections,
technology plan should be reviewed and updated. These
exterior elevations, and a site plan. A major addition
needs can then be prioritized to become a road map for
or replacement uses the same process but in a broader
fiscal and building development. The needs assessment
frame of reference. The concept design should be
should also include a master facilities plan. This plan
detailed enough to obtain a general cost-per-square-
can assist in predicting when a proposed project may
foot estimate based upon historical cost factors in the
trigger upgrades of mechanical, electrical, plumbing,
hospitals location. This information, while limited, is
and structural systems as well as assist in determining
often the basis for the development of a total project
where additional sources of power are required. Facility
cost budget. This will be the construction budget
needs assessments should be updated regularly.
that the executive administration and the board may
Specific Program: Once a proposed project has been approve for the entire project. Therefore, its very
identified, a specific program should be developed to important that percentage contingencies for inflation,
define the space needs and major equipment for each unknown existing conditions, cost increases during
of the departments affected. The space requirements the permitting phase, and potential owner changes
are driven by the number of medical procedures or during construction are included in the construction
services in each area, plus the area necessary for circu- cost budget. While the concept construction budget
lation, waiting, handicapped access requirements, is crucial, the project approval will be based upon the
and toilets. A staffing model, material flow diagrams, total project cost.
staff and patient flow diagrams, and related services
Total Project Cost: The total project cost budget
and adjacencies are also considered. Percentage factors
includes architects and engineers fees, medical equip-
are applied for mechanical equipment space, net-
ment, furnishings and fixtures, OSHPD building
to-gross square footage ratios, and exit ways such as
permit fees and project contingencies. A general rule
stairs and elevators. Often, the Department of Health
for total project cost is to multiply the construc-
Services (which will subsequently license the project)
tion cost by 1.5. Loss of business revenue, financing,
reviews the staffing model and program. The specific
conditional use permit fees, non-construction related

Understanding the Hospital Planning, Design, and Construction Process | 3


consultant fees, attorneys fees, and other related The goal of this phase is to obtain all the decisions
costs are separate line items additional to the total necessary to move on to preparing the construction
project cost. Upon approval of the total project cost, documents when this phase is approved. Design
implementation of the schematic design phase can be development is the most labor intensive for hospi-
authorized to start the project delivery process. tal personnel as the rooms require many detail
decisions. At the conclusion of this phase, the design
Phase 2: Design, Documentation, and development package is submitted to OSHPD
Permitting FDD as a preliminary submittal. Completion of
Schematic design is the stage when the building is their review of this submittal is necessary prior
designed in terms of character, materials, the shape to proceeding with construction documents.
and organization of interior spaces, and exterior Additionally, if a public hearing was held, comments
appearance. Major mechanical and electrical equip- that may affect the design should be received from
ment locations as well as the definition of the the local municipality. Also at the end of this phase,
structural system, grading, and building location the cost estimate is updated to confirm if the project
occur during this phase. Hospitals can expect requests is within the budget.
for frequent department and staff interviews to assist
Construction Documents: Following the hospitals
in this process. This is also the time to start the
approval of the design development phase, construc-
remaining two parallel processes; initiate the land use
tion documents are prepared. These are the working
approval process and initiate the OSHPD approval
drawings and specifications necessary to provide
process. Soil Borings should be taken at the project
the general contractor with sufficient information
site and a geotechnical report submitted through
to construct the building. Ideally, all decisions on
OSHPD to the Bureau of Mines and Geology. This
the scope and detailed definition of the project have
review will determine the seismic zone for the site
been made in design development. This allows the
and confirm the criteria for the structural design
architect/engineer team to complete their work with
of the building. Upon completion of the schematic
a minimum of client interface during this phase.
design a more detailed cost estimate can be prepared.
This estimate should confirm that the project is on Building Permit: Upon completion of these
track per the previously approved total project cost. drawings and specifications, they are submitted to
OSHPD FDD for approval and the building permit.
Design Development: This is the process whereby
A typical hospital project will have a minimum of
the schematic design information is developed into
two OSHPD FDD reviews with comments. The first
specific room by room data that includes all the
review comments are usually issued within 90 to 120
medical equipment, HVAC loads, plumbing and
days. Then the architect/engineer team must respond
electrical requirements, detailed floor plans, wall
to those comments and correct the drawings as neces-
elevations, materials, and finishes for each treatment
sary. A second review may also take place with the
room. Also included are the typical types of patient
corresponding response period. This process of review
rooms, public spaces, and food service. The receipt of
comments and resubmitted corrections continue
the approved geotechnical report from OSHPD FDD
until OSHPD FDD is satisfied that all the building
will provide the criteria necessary for the structural
code issues have addressed. Once the final building
design of the project.
corrections and the land use approval in the form of

4 | CALIFORNIA HEALTHCARE FOUNDATION


Key Regulatory Approvals environmental impact report. By initiating the CUP
As the planning, design, and construction of a approval process at the completion of schematic
hospital move into the schematic development design, most of the required documentation has
stage, two regulatory processes must be coordi- been completed and is ready to submit to the local
nated with the projects schedule: local land use municipality. However, design review may involve
approval, and OSHPD permitting and inspection. changes to the project during the design develop-
ment phase.
Land Use Approval by City or County: In
California, no property is zoned for hospitals. As a Office of Statewide Health Planning and
result, all hospitals require discretionary approvals Development (OSHPD)
from municipalities or counties when they choose
The Office of Statewide Health Planning and
to build new buildings or additions to existing build-
Development Facilities Development Division
ings. These approvals take the form of conditional
(OSHPD FDD), the building permitting agency for all
use permits that include environmental review. A
California hospitals, cannot issue a building permit
conditional use permit (CUP) grants the hospital
until the conditional use permit has been granted.
land use approval for a specific project. In most
The goal is to have the time frames for discretionary
cases these projects are additions or replacements
approvals and OSHPD permitting track together. No
that alter only the exteriors of the buildings. A CUP
municipality or county can issue a building permit for
requires the submission of the appearance and size
a hospital since the Hospital Seismic Safety Act in
of the project along with an extensive application
1983. In this capacity, OSHPD is responsible for the
that includes traffic demands, parking, handicapped
development and implementation of all applicable
access points, access to public transportation, noise,
building codes and state mandates. This includes
exterior lighting and other effects upon the surround-
the development of regulations and the implementa-
ing neighborhood. This is an inclusive process. Public
tion of Senate Bill 1953. Hospitals are very complex
hearings will be required as will design review by an
buildings and California has its own building code
appointed board, the city planning commission, or
for hospitals. This code includes codes for structural
the city council.
integrity following an earthquake as well as quality
The city planning staff has two options for and performance requirements in other areas that
environmental review: a negative declaration or are superior to the national codes. Therefore it is
an environmental impact report. If the project is a very important to select architects and engineers
minor addition or a small free standing building, staff who have experience in the design of hospitals in
may determine the project needs only a negative California.
declaration. New hospitals will always require a full

a conditional use permit are obtained, the building tals select a construction manager at the same time
permit will be issued. A final detailed cost estimate they select the architect/engineer. The construction
will also be prepared during this period. manager becomes part of the project delivery team
and advises the hospital on construction systems and
Phase 3: Bidding, Licensing, and techniques that may by incorporated in the design.
Evaluation They may also provide each of the cost estimates
The bidding and construction of a hospital project prior to the start of construction as well as manage
can take several forms. The first is to have pre-quali- the project delivery schedule.
fied general contractors bid competitively based
In some instances the construction manager is
on the permitted construction documents. This is
directly involved in the construction process by
the traditional way to select a contractor, and most
managing all the major sub-contractors and guaran-
publicly funded projects use it. However, some hospi-
teeing a maximum price. This more sophisticated

Understanding the Hospital Planning, Design, and Construction Process | 5


process is often used for hospital replacement or from staff and patients who use the facility on a daily
complex remodeling or renovation projects. Upon basis. Criteria should include whether the original
receiving successful bids, the hospital can proceed intent of the project has been met; impact on opera-
with construction and the ordering of medical equip- tions; ease of operations; heating and air conditioning
ment, furniture, fixtures and major/minor equipment. performance; items needing completion or correc-
OSHPD FDD also contributes to the construc- tion; and general satisfaction with the program and
tion phase by requiring state certified inspector(s) process.
of record who must document the progress of the
construction. This information is reviewed periodi-
cally by OSHPD FDD field staff to confirm that
the project is constructed according to the approved F O R M O R E I N F O R M AT I O N :
construction documents. More information regarding hospital planning,
design and construction can be found in the report
Invariably, there are modifications to the project
Best Practices for Project Management, Design and
during construction. Often hospital personnel or
Construction of Buildings under OSHPD Jurisdiction,
policies have changed during the time elapsed from
available on the CHCF Web site at www.chcf.org/
construction document decisions to the construction
topics/hospitals/index.cfm?itemID=119899.
phase. These change orders may require modifica-
tions to the construction that can add significant cost
to the project. These changes need careful evaluation
by hospital administration.
AUTHOR:
Beneficial Occupancy: Upon completion of
construction, the architect and the contractor will John E. Millsap, AIA, is a former vice president
contact OSHPD FDD to request approval of for facilities development at the California Pacific
beneficial occupancy so the hospital can staff and Medical Center. He also served as a member of the
stock the facility. Upon receipt of the approval, the California Hospital Building Safety Board.
hospital can install equipment and furnishings as well
as provide and train staff in preparation for licensing
and certification.

Licensing: The licensing section of the Department


of Health Services will request final fire safety
approval from OSHPD FDD in preparation for the
hospital to be eligible for Medicare certification.
Upon approval, the hospital will be granted a certifi-
cate of occupancy recognizing that it is now complete
and ready to receive patients.

Evaluation: Engaging the hospital in an evaluation


process following the first six months of occupancy
can be very beneficial to the new users as well as
design team. This evaluation should include input

CALIFORNIA HEALTHCARE FOUNDATION | 476 Ninth Street, Oakland, CA 94607 | tel: 510.238.1040 | fax: 510.238.1388 | www.chcf.org

You might also like