You are on page 1of 17

On February 3, 1998, petitioners as heirs of Salas, Jr.

HEIRS OF AUGUSTO L. SALAS, JR., namely: TERESITA D. filed in the Regional Trial Court of Lipa City a Complaint[6] for
SALAS for herself and as legal guardian of the declaration of nullity of sale, reconveyance, cancellation of
minor FABRICE CYRILL D. SALAS, MA. CRISTINA
contract, accounting and damages against herein respondents
S. LESACA, and KARINA TERESA D. which was docketed as Civil Case No. 98-0047.
SALAS, petitioners, vs. LAPERAL REALTY
CORPORATION, ROCKWAY REAL ESTATE On April 24, 1998, respondent Laperal Realty filed a
CORPORATION, SOUTH RIDGE VILLAGE, INC., Motion to Dismiss[7]on the ground that petitioners failed to
MAHARAMI DEVELOPMENT CORPORATION, submit their grievance to arbitration as required under Article
Spouses THELMA D. ABRAJANO and GREGORIO VI of the Agreement which provides:
ABRAJANO, OSCAR DACILLO, Spouses
VIRGINIA D. LAVA and RODEL LAVA, EDUARDO ARTICLE VI. ARBITRATION.
A. VACUNA, FLORANTE DE LA CRUZ, JESUS
VICENTE B. CAPELLAN, and the REGISTER OF All cases of dispute between CONTRACTOR and OWNERS
DEEDS FOR LIPA CITY, respondents. representative shall be referred to the committee represented
by:
DECISION
DE LEON, JR., J.: a. One representative of the OWNER;
b. One representative of the CONTRACTOR;
Before us is a petition for review on certiorari of the
Order[1] of Branch 85 of the Regional Trial Court of Lipa c. One representative acceptable to both OWNER
City[2] dismissing petitioners complaint[3] for rescission of and CONTRACTOR.[8]
several sale transactions involving land owned by Augusto L. On May 5, 1998, respondent spouses Abrajano and Lava
Salas, Jr., their predecessor-in-interest, on the ground that and respondent Dacillo filed a Joint Answer with Counterclaim
they failed to first resort to arbitration. and Crossclaim[9] praying for dismissal of petitioners Complaint
Salas, Jr. was the registered owner of a vast tract of land for the same reason.
in Lipa City, Batangas spanning 1,484,354 square meters. On August 9, 1998, the trial court issued the herein
On May 15, 1987, he entered into an Owner-Contractor assailed Order dismissing petitioners Complaint for non-
Agreement[4] (hereinafter referred to as the Agreement) with compliance with the foregoing arbitration clause.
respondent Laperal Realty Corporation (hereinafter referred to Hence this petition.
as Laperal Realty) to render and provide complete (horizontal)
construction services on his land. Petitioners argue, thus:

On September 23, 1988, Salas, Jr. executed a Special The petitioners causes of action did not emanate from the
Power of Attorney in favor of respondent Laperal Realty to Owner-Contractor Agreement.
exercise general control, supervision and management of the
sale of his land, for cash or on installment basis. The petitioners causes of action for cancellation of contract
On June 10, 1989, Salas, Jr. left his home in the morning and accounting are covered by the exception under the
for a business trip to Nueva Ecija. He never returned. Arbitration Law.
On August 6, 1996, Teresita Diaz Salas filed with the Failure to arbitrate is not a ground for dismissal.[10]
Regional Trial Court of Makati City a verified petition for the
declaration of presumptive death of her husband, Salas, Jr.,
In a catena of cases[11] inspired by Justice Malcolms
who had then been missing for more than seven (7) years. It
provocative dissent in Vega v. San Carlos Milling Co.[12], this
was granted on December 12, 1996.[5]
Court has recognized arbitration agreements as valid, binding,
Meantime, respondent Laperal Realty subdivided the enforceable and not contrary to public policy so much so that
land of Salas, Jr. and sold subdivided portions thereof to when there obtains a written provision for arbitration which is
respondents Rockway Real Estate Corporation and South not complied with, the trial court should suspend the
Ridge Village, Inc. on February 22, 1990; to respondent proceedings and order the parties to proceed to arbitration in
spouses Abrajano and Lava and Oscar Dacillo on June 27, accordance with the terms of their agreement[13] Arbitration is
1991; and to respondents Eduardo Vacuna, Florante de la the wave of the future in dispute resolution.[14] To brush aside a
Cruz and Jesus Vicente Capalan on June 4, 1996 (all of whom contractual agreement calling for arbitration in case of
are hereinafter referred to as respondent lot buyers). disagreement between parties would be a step backward.[15]
Nonetheless, we grant the petition.
A submission to arbitration is a contract.[16] As such, the WHEREFORE, the instant petition is hereby
Agreement, containing the stipulation on arbitration, binds the GRANTED. The Order dated August 19, 1998 of Branch 85 of
parties thereto, as well as their assigns and heirs.[17] But only the Regional Trial Court of Lipa City is hereby NULLIFIED and
they. Petitioners, as heirs of Salas, Jr., and respondent Laperal SET ASIDE. Said court is hereby ordered to proceed with the
Realty are certainly bound by the Agreement. If respondent hearing of Civil Case No. 98-0047.
Laperal Realty, had assigned its rights under the Agreement to
a third party, making the former, the assignor, and the latter, Costs against private respondents.
the assignee, such assignee would also be bound by the SO ORDERED.
arbitration provision since assignment involves such transfer of
rights as to vest in the assignee the power to enforce them to Bellosillo, (Chairman), Mendoza, Quisumbing, and
the same extent as the assignor could have enforced them Buena, JJ., concur.
against the debtor[18] or in this case, against the heirs of the
original party to the Agreement. However, respondents
Rockway Real Estate Corporation, South Ridge Village, Inc., G.R. No. 110434 December 13, 1993
Maharami Development Corporation, spouses Abrajano,
spouses Lava, Oscar Dacillo, Eduardo Vacuna, Florante de la HI-PRECISION STEEL CENTER, INC., petitioner,
Cruz and Jesus Vicente Capellan are not assignees of the vs.
rights of respondent Laperal Realty under the Agreement to LIM KIM STEEL BUILDERS, INC., and CONSTRUCTION
develop Salas, Jr.s land and sell the same. They are, rather, INDUSTRY ARBITRATION COMMISSION, respondents.
buyers of the land that respondent Laperal Realty was given
the authority to develop and sell under the Agreement. As Felix Q. Vinluan and Siguion Reyna, Montecillo & Ongsiako for
such, they are not assigns contemplated in Art. 1311 of the petitioner.
New Civil Code which provides that contracts take effect only
between the parties, their assigns and heirs. De Castro & Cagampang Law Offices for Lim Kim teel
Petitioners claim that they suffered lesion of more than Builders, Inc.
one-fourth (1/4) of the value of Salas, Jr.s land when
respondent Laperal Realty subdivided it and sold portions RESOLUTION
thereof to respondent lot buyers.Thus, they instituted
action[19]against both respondent Laperal Realty and
respondent lot buyers for rescission of the sale transactions
and reconveyance to them of the subdivided lots. They argue FELICIANO, J.:
that rescission, being their cause of action, falls under the
exception clause in Sec. 2 of Republic Act No. 876 which On 18 June 1993, a "Petition for Extension to File Petition for
provides that such submission [to] or contract [of arbitration] Review" 1 was filed before the Court, petitioner Hi-Precision
shall be valid, enforceable and irrevocable, save upon such Steel Center, Inc. ("Hi-Precision") stating that it intended to file
grounds as exist at law for the revocation of any contract. a Petition for Review on Certiorari in respect of the 13
The petitioners contention is without merit. For while November 1992 Award 2 and 13 May 1993 Order 3 of public
rescission, as a general rule, is an arbitrable respondent Construction Industry Arbitration Commission
issue,[20] they impleaded in the suit for rescission the ("CIAC") in Arbitration Case No. 13-90. The Petition (really a
respondent lot buyers who are neither parties to the Motion) prayed for an extension of thirty (30) days or until 21
Agreement nor the latters assigns or heirs. Consequently, the July 1993 within which to file a Petition for Review.
right to arbitrate as provided in Article VI of the Agreement was
never vested in respondent lot buyers. An opposition 4 to the Motion was filed by private respondent
Lim Kim Steel Builders, Inc. ("Steel Builders") on 5 July 1993.
Respondent Laperal Realty, as a contracting party to the On the same day, however, the Court issued a
Agreement, has the right to compel petitioners to first arbitrate Resolution 5 granting the Motion with a warning that no further
before seeking judicial relief. However, to split the proceedings extension would be given.
into arbitration for respondent Laperal Realty and trial for the
respondent lot buyers, or to hold trial in abeyance pending The Opposition, the subsequent Reply 6 of petitioner filed on
arbitration between petitioners and respondent Laperal Realty, 20 July 1993 and the Petition for Review 7 dated 21 July 1993,
would in effect result in multiplicity of suits, duplicitous were noted by the Court in its Resolution 8 of 28 July 1993.
procedure and unnecessary delay. On the other hand, it would The Court also required private respondent Steel Builders to
be in the interest of justice if the trial court hears the complaint file a Comment on the Petition for Review and Steel Builders
against all herein respondents and adjudicates petitioners complied.
rights as against theirs in a single and complete proceeding.
The Petition prays for issuance of a temporary restraining In its Award, the Arbitral Tribunal stated that it was guided by
order 9 to stay the execution of the assailed Order and Award Articles 1169, 1192 and 2215 of the Civil Code. With such
in favor of Steel Builders, which application the Court merely guidance, the arbitrators concluded that (a) both parties were
noted, as it did subsequent Urgent Motions for a temporary at fault, though the Tribunal could not point out which of the
restraining order. 10 parties was the first infractor; and (b) the breaches by one
party affected the discharge of the reciprocal obligations of the
Petitioner Hi-Precision entered into a contract with private other party. With mutual fault as a principal premise, the
respondent Steel Builders under which the latter as Contractor Arbitral Tribunal denied (a) petitioner's claims for the additional
was to complete a P21 Million construction project owned by costs allegedly incurred to complete the project; and (b) private
the former within a period of 153 days, i.e. from 8 May 1990 to respondent's claim for profit it had failed to earn because of
8 October 1990. The project completion date was first moved petitioner's take over of the project.
to 4 November 1990. On that date, however, only 75.8674% of
the project was actually completed. Petitioner attributed this The Tribunal then proceeded to resolve the remaining specific
non-completion to Steel Builders which allegedly had claims of the parties. In disposing of these multiple, detailed
frequently incurred delays during the claims the Arbitral Tribunal, in respect of one or more of the
original contract period and the extension period. Upon the respective claims of the parties: (a) averaged out the
other hand, Steel Builders insisted that the delays in the conflicting amounts and percentages claimed by the
project were either excusable or due to Hi-Precision's own fault parties; 13 (b) found neither basis nor justification for a
and issuance of change orders. The project was taken over on particular claim; 14 (c) found the evidence submitted in support
7 November 1990, and eventually completed on February of particular claims either weak or non-existent; 15 (d) took
1991, by Hi-Precision. account of the admissions of liability in respect of particular
claims; 16 (e) relied on its own expertise in resolving particular
Steel Builders filed a "Request for Adjudication" with public claims; 17 and (f) applied a "principle of equity" in requiring
respondent CIAC. In its Complaint filed with the CIAC, Steel each party to bear its own loss resulting or arising from mutual
Builders sought payment of its unpaid progress buildings, fault or delay (compensation morae). 18
alleged unearned profits and other receivables. Hi-Precision,
upon the other hand, in its Answer and Amended Answer, Petitioner Hi-Precision now asks this Court to set aside the
claimed actual and liquidated damages, reimbursement of Award, contending basically that it was the contractor Steel
alleged additional costs it had incurred in order to complete the Builders who had defaulted on its contractual undertakings and
project and attorney's fees. so could not be the injured party and should not be allowed to
recover any losses it may have incurred in the project.
The CIAC formed an Arbitral Tribunal with three (3) members, Petitioner Hi-Precision insists it is still entitled to damages, and
two (2) being appointed upon nomination of Hi-Precision and claims that the Arbitral Tribunal committed grave abuse of
Steel Builders, respectively; the third member (the Chairman) discretion when it allowed certain claims by Steel Builders and
was appointed by the CIAC as a common nominee of the two offset them against claims of Hi-Precision.
(2) parties. On the Chairman was a lawyer. After the arbitration
proceeding, the Arbitral Tribunal rendered a unanimous Award A preliminary point needs to be made. We note that the Arbitral
dated 13 November 1992, the dispositive portion of which Tribunal has not been impleaded as a respondent in the
reads as follows: Petition at bar. The CIAC has indeed been impleaded;
however, the Arbitral Award was not rendered by the CIAC, but
WHEREFORE, premises considered, the rather by the Arbitral Tribunal. Moreover, under Section 20 of
Owner [petitioner Hi-Precision] is ordered to Executive Order No. 1008, dated 4 February 1985, as
pay the Contractor [private respondent Steel amended, it is the Arbitral Tribunal, or the single Arbitrator,
Builders] the amount of P6,400,717.83 and with the concurrence of the CIAC, which issues the writ of
all other claims of the parties against each execution requiring any sheriff or other proper officer to
other are deemed compensated and offset. execute the award. We consider that the Arbitral Tribunal
No pronouncement as to costs. which rendered the Award sought to be reviewed and set
aside, should be impleaded even though the defense of its
The Parties are enjoined to abide by the Award would presumably have to be carried by the prevailing
award. 11 party.

Upon motions for reconsideration filed, respectively, Petitioner Hi-Precision apparently seeks review of both under
by Hi-Precision and Steel Builders, the Arbitral Rule 45 and Rule 65 of the Rules of Court. 19 We do not find it
Tribunal issued an Order dated 13 May 1993 which necessary to rule which of the two: a petition for review under
reduced the net amount due to contractor Steel Rule 45 or a petition for certiorari under Rule 65 is
Builders to P6,115,285.83. 12 necessary under Executive Order No. 1008, as amended; this
issue was, in any case, not squarely raised by either party and The public respondent committed serious
has not been properly and adequately litigated. error in law, if not grave abuse of discretion,
when it found, in the May 13, 1993 Order,
In its Petition, Hi-Precision purports to raise "legal issues," and the petitioner "guilty of estoppel" although it
in presenting these issues, prefaced each with a creative is claimed that the legal doctrine of estoppel
formula: does not apply with respect to the required
written formalities in the issuance of change
(1) order . . .;

The public respondent [should be the (6)


"Arbitral Tribunal'] committed serious error in
law, if not grave abuse of discretion, when it The exceptional circumstances in Remalante
failed to strictly apply Article 1191, New Civil vs. Tibe, 158 SCRA 138, where the
Code, against the Honorable Supreme Court may review
contractor . . .; findings of facts, are present in the instant
case, namely; (a) when the inference made
(2) is manifestly absurd, mistaken or impossible
(Luna vs. Linatoc, 74 Phil. 15); (2) when
The public respondent committee serious there is grave abuse of discretion in the
error in law, if not grave abuse of discretion, appreciation of facts (Buyco vs. People, 95
when it failed to rule in favor of the owner, Phil. 253); (3) when the judgment is
now petitioner herein, all the awards it premised on a misapprehension of facts (De
claimed on arbitration, and when it la Cruz v. Sosing, 94 Phil. 26 and Castillo vs.
nonetheless persisted in its awards of CA, 124 SCRA 808); (4) when the findings of
damages in favor of the fact are conflicting (Casica v. Villaseca, 101
respondent. . . .; Phil. 1205); (5) when the findings are
contrary to the admissions of the parties
(3) (Evangelista v. Alto Surety, 103 Phil. 401),
and therefore, the findings of facts of the
public respondent in the instant case may be
The public respondent committed serious
reviewed by the Honorable Supreme
error in law, if not grave abuse of discretion,
Court. 20 (Emphasis partly applied and partly
for its abject failure to apply the doctrine of
in the original)
waiver, estoppel against the contractor, the
private respondent herein, when it agreed on
November 16, 1990 to award termination of From the foregoing, petitioner Hi-Precision may be seen to be
making two (2) basic arguments:
the contract and the owner's takeover of the
project . . .;
(a) Petitioner asks this Court to correct legal
(4) errors committed by the Arbitral Tribunal,
which at the same time constitute grave
abuse of discretion amounting to lack of
The public respondent committed serious
jurisdiction on the part of the Arbitral
error in law, if not grave abuse of discretion,
Tribunal; and
when it did not enforce the law between the
parties, the "technical specification[s]" which
is one of the contract documents, particularly (b) Should the supposed errors petitioner
to par. (a), sub-part 3.01, part 3, Sec. 2b, asks us to correct be characterized as errors
of fact, such factual errors should
which expressly requires that major site work
nonetheless be reviewed because there was
activities like stripping, removal and
stockpiling of top soil shall be done "prior to "grave abuse of discretion" in the
the start of regular excavation or backfiling misapprehension of facts on the part of the
Arbitral Tribunal.
work", the principal issue in arbitration being
non-compliance with the contract
documents; Executive Order No. 1008, as amended, provides, in its
Section 19, as follows:
(5)
Sec. 19. Finality of Awards. The arbitral other, more relaxed, rule would result in setting at naught the
award shall be binding upon the parties. It basic objective of a voluntary arbitration and would reduce
shall be final and inappealable except on arbitration to a largely inutile institution.
questions of law which shall be appealable
to the Supreme Court. Examination of the Petition at bar reveals that it is essentially
an attempt to re-assert and re-litigate before this Court the
Section 19 makes it crystal clear that questions of fact detailed or itemized factual claims made before the Arbitral
cannot be raised in proceedings before the Supreme Tribunal under a general averment that the Arbitral Tribunal
Court which is not a trier of facts in respect of had "misapprehended the facts" submitted to it. In the present
an arbitral award rendered under the aegis of the Petition, too, Hi-Precision claims that the Arbitral Tribunal had
CIAC. Consideration of the animating purpose of committed grave abuse of discretion amounting to lack of
voluntary arbitration in general, and arbitration under jurisdiction in reaching its factual and legal conclusions.
the aegis of the CIAC in particular, requires us to
apply rigorously the above principle embodied in The first "legal issue" submitted by the Petition is the claimed
Section 19 that the Arbitral Tribunal's findings of fact misapplication by the Arbitral Tribunal of the first and second
shall be final and inappealable. paragraphs of Article 1911 of the Civil Code. 24 Article 1191
reads:
Voluntary arbitration involves the reference of a dispute to an
impartial body, the members of which are chosen by the Art. 1191. The power to rescind obligations
parties themselves, which parties freely consent in advance to is implied in reciprocal ones, in case one of
abide by the arbitral award issued after proceedings where the obligors should not comply with what is
both parties had the opportunity to be heard. The basic incumbent upon him.
objective is to provide a speedy and inexpensive method of
settling disputes by allowing the parties to avoid the formalities, The injured party may choose between the
delay, expense and aggravation which commonly accompany fulfillment and the rescission of the
ordinary litigation, especially litigation which goes through the obligation, with the payment of damages in
entire hierarchy of courts. Executive Order No. 1008 created either case. He may also seek rescission,
an arbitration facility to which the construction industry in the even after he has chosen fulfillment, if the
Philippines can have recourse. The Executive Order was latter should become impossible.
enacted to encourage the early and expeditious settlement of
disputes in the construction industry, a public policy the The court shall decree the rescission
implementation of which is necessary and important for the claimed, unless there be just cause
realization of national development goals. 21 authorizing the fixing of a period.

Aware of the objective of voluntary arbitration in the labor field, This is understood to be without prejudice to
in the construction industry, and in any other area for that the rights of third persons who have
matter, the Court will not assist one or the other or even both acquired the thing, in accordance with
parties in any effort to subvert or defeat that objective for their articles 1385 and 1388 and the Mortgage
private purposes. The Court will not review the factual findings Law.
of an arbitral tribunal upon the artful allegation that such body
had "misapprehended the facts" and will not pass upon issues
Hi-Precision contends energetically that it is the injured party
which are, at bottom, issues of fact, no matter how cleverly
and that Steel Builders was the obligor who did not comply
disguised they might be as "legal questions." The parties here
with what was incumbent upon it, such that Steel Builders was
had recourse to arbitration and chose the arbitrators the party in default and the entity guilty of negligence and
themselves; they must have had confidence in such delay. As the injured party, Hi-Precision maintains that it may
arbitrators. The Court will not, therefore, permit the parties to choose between the fulfillment or rescission of the obligation in
relitigate before it the issues of facts previously presented and accordance with Article 1191, and is entitled to damages in
argued before the Arbitral Tribunal, save only where a very either case. Thus, Hi-Precision continues, when the contractor
clear showing is made that, in reaching its factual conclusions, Steel Builders defaulted on the 153rd day of the original
the Arbitral Tribunal committed an error so egregious and contract period, Hi-Precision opted for specific performance
hurtful to one party as to constitute a grave abuse of discretion and gave Steel Builders a 30-day extension period with which
resulting in lack or loss of jurisdiction. 22 Prototypical examples to complete the project.
would be factual conclusions of the Tribunal which resulted in
deprivation of one or the other party of a fair opportunity to
What petitioner Hi-Precision, in its above argument, disregards
present its position before the Arbitral Tribunal, and an award
is that the determination of whether Hi-Precision or Steel
obtained through fraud or the corruption of arbitrators. 23 Any
Builders was the "injured party" is not to be resolved by an
application of Article 1191. That determination is eminently a is in reality asking this Court to review the physical operations
question of fact, for it requires ascertainment and identification relating, e.g., to site preparation carried out by the contractor
of which the two (2) contending parties had first failed to Steel Builders and to determine whether such operations were
comply with what is incumbent upon it. In other words, the in accordance with the Technical Specifications of the project.
supposed misapplication of Article 1191, while ostensibly a The Arbitral Tribunal resolved Hi-Precision's claim by finding
"legal issue," is ultimately a question of fact, i.e., the that Steel Builders had complied substantially with the
determination of the existence or non-existence of a fact or set Technical Specifications. This Court will not pretend that it has
of facts in respect of which Article 1191 may be properly the technical and engineering capability to review the
applied. Thus, to ask this Court to correct a claimed resolution of that factual issue by the Arbitral Tribunal.
misapplication or non-application of Article 1191 is to compel
this Court to determine which of the two (2) contending parties Finally, the Petition asks this Court to "review serious errors in
was the "injured party" or the "first infractor." As noted earlier, the findings of fact of the [Arbitral Tribunal]." 28 In this section of
the Arbitral Tribunal after the prolonged arbitration proceeding, its Petition,
was unable to make that factual determination and instead Hi-Precision asks us to examine each item of its own claims
concluded that both parties had committed breaches of their which the Arbitral Tribunal had rejected in its Award, and each
respective obligations. We will not review, and much less claim of the contractor Steel Builders which the Tribunal had
reverse, that basic factual finding of the Arbitral Tribunal. granted. In respect of each item of the owner's claims and
each item of the contractor's claims, Hi-Precision sets out its
A second "legal issue" sought to be raised by petitioner Hi- arguments, to all appearances the same arguments it had
Precision relates to the supposed failure of the Arbitral Tribunal raised before the Tribunal. As summarized in the Arbitral
to apply the doctrines of estoppel and waiver as against Steel Award, Contractor's Claims were as follows:
Builders. 25 The Arbitral Tribunal, after declaring that the
parties were mutually at fault, proceeded to enumerate the 12.1. Unpaid Progress Billing 1,812,706.95
faults of each of the parties. One of the faults attributed to
petitioner Hi-Precision is that it had failed to give the contractor 12.2. Change Order 1 0.00
Steel Builders the required 15-day notice for termination of the 12.3. -do- 2 10,014.00
contract. 26 This was clearly a finding of fact on the part of the 12.4. -do- 3 320,000.00
Tribunal, supported by the circumstance that per the record, 12.5. -do- 4 112,300.70
petitioner had offered no proof that it had complied with such 12.6. -do- 5 398,398.00
15-day notice required under Article 28.01 of the General 12.7. -do- 6 353,050.38
Conditions of Contract forming part of the Contract 12.8. -do- 7 503,836.53
Documents. Petitioner Hi-Precision's argument is that a written 12.9. -do- 8 216,138.75
Agreement dated 16 November 1990 with Steel Builders 12.10. -do- 9 101,621.40
concerning the take over of the project by Hi-Precision, 12.11. -do- 10 7,200.00
constituted waiver on the part of the latter of its right to a 15- 12.12. -do- 11 0.00
day notice of contract termination. Whether or not that 12.13. -do- 12 7,800.00
Agreement dated 16 November 1990 (a document not 12.14. -do- 13 49,250.00
submitted to this Court) is properly characterized as 12.15. -do- 14 167,952.00
constituting waiver on the part of Steel Builders, may be 12.16. -do- 15 445,600.00
conceded to be prima facie a question of law; but, if it is, and 12.17. -do- 16 92,457.30
assuming arguendo that the Arbitral Tribunal had erred in 12.18. -do- 17 1,500.00
resolving it, that error clearly did not constitute a grave abuse 12.19. 20,240.00
of discretion resulting in lack or loss of jurisdiction on the part 12.20. 63,518.00
of the Tribunal. 12.21. 0.00
12.22. 0.00
A third "legal issue" posed by Hi-Precision relates to the 12.23. 0.00
supposed failure on the part of the Arbitral Tribunal "to uphold 12.24. 0.00
the supremacy of 'the 12.25. 0.00
law between the parties' and enforce it against private 12.26. 730,201.57
respondent [Steel Builders]." 27 The "law between that parties" 12.27. 1,130,722.70
here involved is the "Technical Specifications" forming part of 12.28. 0.00
the Contract Documents. Hi-Precision asserts that the Arbitral 12.29. 273,991.00
Tribunal did not uphold the "law between the parties," but 12.30. 0.00
instead substituted the same with "its [own] absurd inference
and 'opinion' on mud." Here again, petitioner is merely
disguising a factual question as a "legal issue," since petitioner
12.31. 7,318,499.28 29 b. Cost of money of (a) 873,535.49

============= ID Installation of machinery

Upon the other hand, the petitioner's claims we are asked to a. Foreign exchange loss 11,565,048.37
review and grant are summarized as follows:
b. Cost of money (a) 2,871,987.01
1. Actual Damages
I[E] Raw Materials
Advance Downpayment
[at] signing of Contract a. Foreign exchange loss 4,155,982.18
which is subject to 40% b. Cost of money (a) 821,242.72
deduction every progress c. Additional import levy of 5% 886,513.33
billing (40% of Contract Price) d. Cost of money (c) 170,284.44
P8,406,000.00 e. Cost of money on marginal
deposit on Letter of Credit 561,195.25
Progress Billings 5,582,585.55
IF Cost of money on holding to CRC INTY
Advances made to Lim Kim 3,319,609.63

a) prior to take-over 392,781.45 Total Actual Damages 35,295,927.32


b) after the take-over
2. Liquidated Damages 2,436,000.00
Civil Works 1,158,513.88
Materials 4,213,318.72 3. Attorney's Fees 500,000.00
Labor 2,155,774.79
Equipment Rental 1,448,208.90

P38,231,927.32 30

P8,974,816.45 =============

Total Amount Paid for Construction We consider that in asking this Court to go over each individual
23,650,183.00 claim submitted by it and each individual countering claim
Less: Contract Price (21,000,000.00) submitted by Steel Builders to the Arbitral Tribunal, petitioner
Hi-Precision is asking this Court to pass upon claims which are
IA Excess of amount paid either clearly and directly factual in nature or require previous
over contract price 2,650,163.29 determination of factual issues. This upon the one hand. Upon
the other hand, the Court considers that petitioner Hi-Precision
IB Other items due from Lim has failed to show any serious errors of law amounting to
Kim Steel Builders grave abuse of discretion resulting in lack of jurisdiction on the
part of the Arbitral Tribunal, in either the methods employed or
a. Amount not yet deducted the results reached by the Arbitral Tribunal, in disposing of the
from Downpayment due detailed claims of the respective parties.
to non-completion of Project
(P24.1326%) 2,027,138.40 WHEREFORE, for all the foregoing, the Petition is hereby
DISMISSED for lack of merit. Costs against petitioner.
b. Due to Huey Commercial
used for HSCI Project 51,110.40 SO ORDERED.

IC Additional construction expenses Bidin, Romero, Melo and Vitug, JJ., concur

a. Increases in prices since Oct.


5,272,096.81
HOME BANKERS SAVINGS AND TRUST COMPANY V. CA dispute in arbitration. In the case at bar, private respondent
filed an action for a sum of money with prayer for a writ of
(G.R. NO. 115412) preliminary attachment. Undoubtedly, such action involved the
same subject matter as that in arbitration, i.e., the sum of
P25,200,000.00 which was allegedly deprived from private
Facts: respondent in what is known in banking as a kiting scheme.
Victor Tancuan issued Petitioner Home Bankers Savings and However, the civil action was not a simple case of a money
Trust Company a check while Eugene Arriesgado issued claim since private respondent has included a prayer for a writ
Private Respondent Far East Bank and Trust Company three of preliminary attachment, which is sanctioned by section 14 of
checks; both checks totaling the amount of P25,250,000.00. the Arbitration Law.
Tancuan and Arriesgado exchanged each others checks and Simply put, participants in the regional clearing operations of
deposited them with their respective banks for collection. the Philippine Clearing House Corporation cannot bypass the
When FEBTC presented Tancuans HBSTC check for clearing, arbitration process laid out by the body and seek relief directly
it was dishonored for being DAIF. Meanwhile, HBSTC sent from the courts. In the case at bar, undeniably, private
Arriesgados 3 FEBTC checks through the Philippine Clearing respondent has initiated arbitration proceedings as required by
House Corporation (PCHC) to FEBTC but was returned for the PCHC rules and regulations, and pending arbitration has
being DAIF. HBSTC receive the notice of dishonor but refused sought relief from the trial court for measures to safeguard
to accept the checks and returned them to FEBTC through the and/or conserve the subject of the dispute under arbitration, as
PCHC for the reason Beyond Reglementary Period, implying sanctioned by section 14 of the Arbitration Law, and otherwise
that HBSTC already treated the 3 checks as cleared and not shown to be contrary to the PCHC rules and regulations.
allowed the proceeds thereof to be withdrawn. FEBTC At this point, we emphasize that arbitration, as an alternative
demanded reimbursement for the returned checks and method of dispute resolution, is encouraged by this Court.
inquired from HBSTC whether it had permitted any withdrawal Aside from unclogging judicial dockets, it also hastens
of funds against the unfunded checks. HBSTC, however solutions especially of commercial disputes. The Court looks
refused to make any reimbursement and to provide FEBTC with favor upon such amicable arrangement and will only
with the needed information. Thus, FEBTC submitted the interfere with great reluctance to anticipate or nullify the action
dispute for arbitration before the PCHC Arbitration Committee, of the arbitrator. Wherefore, premises considered, the petition
under its Supplementary Rules on Regional Clearing to which is hereby dismissed and the decision of the court a quo is
FEBTC and HBSTC are bound as participants in the regional affirmed.
clearing operations administered by the PCHC. While the
arbitration proceeding was still pending, FEBTC filed an action
for sum of money and damages with preliminary attachment LM POWER ENGINEERING CORPORATION, petitioner,
against HBSTC. HBSTC moved to dismiss on the ground that vs. CAPITOL INDUSTRIAL CONSTRUCTION GROUPS,
there is no cause of action and because it seeks to enforce an INC., respondent.
arbitral award which as yet does not exist. The trial court
denied the motion to dismiss and the motion for
DECISION
reconsideration. Petitioner then filed a petition for certiorari
with respondent CA to which it had dismissed. PANGANIBAN, J.:
Issue:
Whether or not private respondent which commenced an Alternative dispute resolution methods or ADRs -- like
arbitration proceeding under the auspices of the PCHC may arbitration, mediation, negotiation and conciliation -- are
subsequently file a separate case in court over the same encouraged by the Supreme Court. By enabling parties to
subject matter despite the pendency of that arbitration, simply resolve their disputes amicably, they provide solutions that are
to obtain the provisional remedy of attachment against the less time-consuming, less tedious, less confrontational, and
adverse party in the arbitration proceeding. more productive of goodwill and lasting relationships.[1]
Ruling:
We find no merit in the petition. Section 14 of Republic Act
876, otherwise known as the Arbitration Law, allows any party
The Case
to the arbitration proceeding to petition the court to take
measures to safeguard and/or conserve any matter which is
the subject of the dispute in arbitration. Before us is a Petition for Review on Certiorari[2] under
Petitioners exposition of the foregoing provision deserves Rule 45 of the Rules of Court, seeking to set aside the January
scant consideration. Section 14 simply grants an arbitrator the 28, 2000 Decision of the Court of Appeals[3] (CA) in CA-GR CV
power to issue subpoena and subpoena duces tecum at any No. 54232. The dispositive portion of the Decision reads as
time before rendering the award. The exercise of such power follows:
is without prejudice to the right of a party to file a petition in
court to safeguard any matter which is the subject of the
WHEREFORE, the judgment appealed from is REVERSED under the warranty clause of the Agreement, and whether it
and SET ASIDE. The parties are ORDERED to present their should reimburse respondent for the work the latter had taken
dispute to arbitration in accordance with their Sub-contract over.[15]
Agreement. The surety bond posted by [respondent] is
[d]ischarged.[4] Hence, this Petition.[16]

The Facts The Issues

On February 22, 1983, Petitioner LM Power Engineering In its Memorandum, petitioner raises the following issues
Corporation and Respondent Capitol Industrial Construction for the Courts consideration:
Groups Inc. entered into a Subcontract Agreement involving A
electrical work at the Third Port of Zamboanga.[5]
On April 25, 1985, respondent took over some of the Whether or not there exist[s] a controversy/dispute between
work contracted to petitioner.[6] Allegedly, the latter had failed petitioner and respondent regarding the interpretation and
to finish it because of its inability to procure materials.[7] implementation of the Sub-Contract Agreement dated
February 22, 1983 that requires prior recourse to voluntary
Upon completing its task under the Contract, petitioner arbitration;
billed respondent in the amount of P6,711,813.90.[8] Contesting
the accuracy of the amount of advances and billable B
accomplishments listed by the former, the latter refused to
pay. Respondent also took refuge in the termination clause of In the affirmative, whether or not the requirements provided in
the Agreement.[9] That clause allowed it to set off the cost of Article III [1] of CIAC Arbitration Rules regarding request for
the work that petitioner had failed to undertake -- due to arbitration ha[ve] been complied with[.][17]
termination or take-over -- against the amount it owed the
latter.
Because of the dispute, petitioner filed with the Regional The Courts Ruling
Trial Court (RTC) of Makati (Branch 141) a Complaint[10] for the
collection of the amount representing the alleged balance due
it under the Subcontract. Instead of submitting an Answer, The Petition is unmeritorious.
respondent filed a Motion to Dismiss,[11] alleging that the
Complaint was premature, because there was no prior
recourse to arbitration. First Issue:
Whether Dispute Is Arbitrable
In its Order[12] dated September 15, 1987, the RTC
denied the Motion on the ground that the dispute did not
involve the interpretation or the implementation of the Petitioner claims that there is no conflict regarding the
Agreement and was, therefore, not covered by the arbitral interpretation or the implementation of the Agreement. Thus,
clause.[13] without having to resort to prior arbitration, it is entitled to
After trial on the merits, the RTC[14] ruled that the take- collect the value of the services it rendered through an ordinary
over of some work items by respondent was not equivalent to action for the collection of a sum of money from
a termination, but a mere modification, of the Subcontract. The respondent. On the other hand, the latter contends that there is
latter was ordered to give full payment for the work completed a need for prior arbitration as provided in the Agreement. This
by petitioner. is because there are some disparities between the parties
positions regarding the extent of the work done, the amount of
advances and billable accomplishments, and the set off of
expenses incurred by respondent in its take-over of petitioners
Ruling of the Court of Appeals work.
We side with respondent. Essentially, the dispute arose
On appeal, the CA reversed the RTC and ordered the from the parties ncongruent positions on whether certain
referral of the case to arbitration. The appellate court held as provisions of their Agreement could be applied to the
arbitrable the issue of whether respondents take-over of some facts. The instant case involves technical discrepancies that
work items had been intended to be a termination of the are better left to an arbitral body that has expertise in those
original contract under Letter K of the Subcontract. It ruled areas. In any event, the inclusion of an arbitration clause in a
likewise on two other issues: whether petitioner was liable contract does not ipso facto divest the courts of jurisdiction to
pass upon the findings of arbitral bodies, because the awards WORK in accordance with this Agreement,
are still judicially reviewable under certain conditions.[18] or persistently or flagrantly neglects to carry
out [its] obligations under this Agreement.[21]
In the case before us, the Subcontract has the following
arbitral clause:
Supposedly, as a result of the take-over, respondent
incurred expenses in excess of the contracted price. It sought
6. The Parties hereto agree that any dispute or to set off those expenses against the amount claimed by
conflict as regards to interpretation and petitioner for the work the latter accomplished, pursuant to the
implementation of this Agreement which cannot be following provision:
settled between [respondent] and [petitioner]
amicably shall be settled by means of arbitration x x
If the total direct and indirect cost of completing the remaining
x.[19]
part of the WORK exceed the sum which would have been
payable to [petitioner] had it completed the WORK, the amount
Clearly, the resolution of the dispute between the parties of such excess [may be] claimed by [respondent] from either of
herein requires a referral to the provisions of their the following:
Agreement. Within the scope of the arbitration clause are
discrepancies as to the amount of advances and billable
1. Any amount due [petitioner] from [respondent] at the time of
accomplishments, the application of the provision on
the termination of this Agreement.[22]
termination, and the consequent set-off of expenses.
A review of the factual allegations of the parties reveals The issue as to the correct amount of petitioners
that they differ on the following questions: (1) Did a take- advances and billable accomplishments involves an evaluation
over/termination occur? (2) May the expenses incurred by of the manner in which the parties completed the work, the
respondent in the take-over be set off against the amounts it extent to which they did it, and the expenses each of them
owed petitioner? (3) How much were the advances and billable incurred in connection therewith. Arbitrators also need to look
accomplishments? into the computation of foreign and local costs of materials,
foreign and local advances, retention fees and letters of credit,
The resolution of the foregoing issues lies in the
and taxes and duties as set forth in the Agreement. These data
interpretation of the provisions of the Agreement. According to
can be gathered from a review of the Agreement, pertinent
respondent, the take-over was caused by petitioners delay in
portions of which are reproduced hereunder:
completing the work. Such delay was in violation of the
provision in the Agreement as to time schedule:
C. CONTRACT PRICE AND TERMS OF PAYMENT
G. TIME SCHEDULE
xxxxxxxxx
[Petitioner] shall adhere strictly to the schedule
related to the WORK and complete the WORK within All progress payments to be made by [respondent]
the period set forth in Annex C hereof. NO time to [petitioner] shall be subject to a retention sum of
extension shall be granted by [respondent] to ten percent (10%) of the value of the approved
[petitioner] unless a corresponding time extension is quantities. Any claims by [respondent] on [petitioner]
granted by [the Ministry of Public Works and may be deducted by [respondent] from the progress
Highways] to the CONSORTIUM.[20] payments and/or retained amount. Any excess from
the retained amount after deducting [respondents]
claims shall be released by [respondent] to
Because of the delay, respondent alleges that it took over
[petitioner] after the issuance of [the Ministry of
some of the work contracted to petitioner, pursuant to the
Public Works and Highways] of the Certificate of
following provision in the Agreement:
Completion and final acceptance of the WORK by
[the Ministry of Public Works and Highways].
K. TERMINATION OF AGREEMENT
xxxxxxxxx
[Respondent] has the right to terminate and/or take
over this Agreement for any of the following
D. IMPORTED MATERIALS AND EQUIPMENT
causes:
[Respondent shall open the letters of credit for the
xxxxxxxxx
importation of equipment and materials listed in
Annex E hereof after the drawings, brochures, and
6. If despite previous warnings by other technical data of each items in the list have
[respondent], [petitioner] does not execute the
been formally approved by [the Ministry of Public SECTION. 1. Submission to Arbitration -- Any party to a
Works and Highways]. However, petitioner will still construction contract wishing to have recourse to arbitration by
be fully responsible for all imported materials and the Construction Industry Arbitration Commission (CIAC) shall
equipment. submit its Request for Arbitration in sufficient copies to the
Secretariat of the CIAC; PROVIDED, that in the case of
All expenses incurred by [respondent], both in government construction contracts, all administrative remedies
foreign and local currencies in connection with the available to the parties must have been exhausted within 90
opening of the letters of credit shall be deducted days from the time the dispute arose.
from the Contract Prices.
Tesco was promulgated by this Court, using the
xxxxxxxxx foregoing provision as reference.
On the other hand, Section 1 of Article III of
N. OTHER CONDITIONS the new Rules of Procedure Governing Construction
Arbitration has dispensed with this requirement and recourse
xxxxxxxxx to the CIAC may now be availed of whenever a contract
contains a clause for the submission of a future controversy to
2. All customs duties, import duties, contractors arbitration, in this wise:
taxes, income taxes, and other taxes that may be
required by any government agencies in connection SECTION 1. Submission to CIAC Jurisdiction An arbitration
with this Agreement shall be for the sole account of clause in a construction contract or a submission to arbitration
[petitioner].[23] of a construction dispute shall be deemed an agreement to
submit an existing or future controversy to CIAC jurisdiction,
Being an inexpensive, speedy and amicable method of notwithstanding the reference to a different arbitration
settling disputes,[24] arbitration -- along with mediation, institution or arbitral body in such contract or
conciliation and negotiation -- is encouraged by the Supreme submission. When a contract contains a clause for the
Court. Aside from unclogging judicial dockets, arbitration also submission of a future controversy to arbitration, it is not
hastens the resolution of disputes, especially of the necessary for the parties to enter into a submission agreement
commercial kind.[25] It is thus regarded as the wave of the before the claimant may invoke the jurisdiction of CIAC.
future in international civil and commercial
disputes. Brushing aside a contractual agreement calling for
[26]
The foregoing amendments in the Rules were formalized
arbitration between the parties would be a step backward.[27] by CIAC Resolution Nos. 2-91 and 3-93.[31]
Consistent with the above-mentioned policy of The difference in the two provisions was clearly explained
encouraging alternative dispute resolution methods, courts in China Chang Jiang Energy Corporation (Philippines) v.
should liberally construe arbitration clauses. Provided such Rosal Infrastructure Builders et al.[32] (an extended unsigned
clause is susceptible of an interpretation that covers the Resolution) and reiterated in National Irrigation Administration
asserted dispute, an order to arbitrate should be v. Court of Appeals,[33] from which we quote thus:
granted.[28] Any doubt should be resolved in favor of
arbitration.[29] Under the present Rules of Procedure, for a particular
construction contract to fall within the jurisdiction of CIAC, it is
merely required that the parties agree to submit the same to
Second Issue: voluntary arbitration Unlike in the original version of Section 1,
Prior Request for Arbitration as applied in the Tesco case, the law as it now stands does
not provide that the parties should agree to submit disputes
arising from their agreement specifically to the CIAC for the
According to petitioner, assuming arguendo that the latter to acquire jurisdiction over the same. Rather, it is plain
dispute is arbitrable, the failure to file a formal request for and clear that as long as the parties agree to submit to
arbitration with the Construction Industry Arbitration voluntary arbitration, regardless of what forum they may
Commission (CIAC) precluded the latter from acquiring choose, their agreement will fall within the jurisdiction of the
jurisdiction over the question. To bolster its position, petitioner CIAC, such that, even if they specifically choose another
even cites our ruling in Tesco Services Incorporated v. forum, the parties will not be precluded from electing to submit
Vera.[30] We are not persuaded. their dispute before the CIAC because this right has been
Section 1 of Article II of the old Rules of Procedure vested upon each party by law, i.e., E.O. No. 1008.[34]
Governing Construction Arbitration indeed required the
submission of a request for arbitration, as follows:
Clearly, there is no more need to file a request with the Consequently, on May 30, 1991, petitioner and SPI
CIAC in order to vest it with jurisdiction to decide a entered into a written agreement denominated as Agreement
construction dispute. for the Execution of Builders Work for the EDSA Plaza
Project. Said agreement would cover the construction work on
The arbitral clause in the Agreement is a commitment on said project as of May 1, 1991 until its eventual completion.
the part of the parties to submit to arbitration the disputes
covered therein. Because that clause is binding, they are According to SPI, petitioner failed to complete the
expected to abide by it in good faith.[35] And because it covers construction works and abandoned the project.[3] This resulted
the dispute between the parties in the present case, either of in disagreements between the parties as regards their
them may compel the other to arbitrate.[36] respective liabilities under the contract. On July 12, 1993, upon
SPIs initiative, the parties respective representatives met in
Since petitioner has already filed a Complaint with the RTC conference but they failed to come to an agreement.[4]
without prior recourse to arbitration, the proper procedure to
enable the CIAC to decide on the dispute is to request the stay or Barely two days later or on July 14, 1993, petitioner filed
suspension of such action, as provided under RA 876 [the with the Regional Trial Court of Pasig a complaint for collection
Arbitration Law].[37] of the balance due under the construction agreement. Named
defendants therein were SPI and members of its board of
WHEREFORE, the Petition is DENIED and the assailed directors namely, Alfredo C. Ramos, Rufo B. Colayco, Antonio
Decision AFFIRMED. Costs against petitioner. B. Olbes, Gerardo O. Lanuza, Jr., Maximo G. Licauco III and
SO ORDERED. Benjamin C. Ramos.
Puno, (Chairman), Sandoval-Gutierrez, On August 3, 1993, SPI and its co-defendants filed a
Corona and Carpio-Morales, JJ., concur. motion to suspend proceedings instead of filing an
answer. The motion was anchored on defendants allegation
that the formal trade contract for the construction of the project
BF CORPORATION, petitioner, vs. COURT OF APPEALS, provided for a clause requiring prior resort to arbitration before
SHANGRI-LA PROPERTIES, COLAYCO, ALFREDO judicial intervention could be invoked in any dispute arising
C. RAMOS, INC., RUFO B. from the contract.The following day, SPI submitted a copy of
MAXIMO G.LICAUCO III and BENJAMIN C. the conditions of the contract containing the arbitration clause
RAMOS, respondents. that it failed to append to its motion to suspend proceedings.
Petitioner opposed said motion claiming that there was
DECISION no formal contract between the parties although they entered
ROMERO, J.: into an agreement defining their rights and obligations in
undertaking the project. It emphasized that the agreement did
The basic issue in this petition for review on certiorari is not provide for arbitration and therefore the court could not be
whether or not the contract for the construction of the EDSA deprived of jurisdiction conferred by law by the mere allegation
Plaza between petitioner BF Corporation and respondent of the existence of an arbitration clause in the agreement
Shangri-la Properties, Inc. embodies an arbitration clause in between the parties.
case of disagreement between the parties in the In reply to said opposition, SPI insisted that there was
implementation of contractual provisions. such an arbitration clause in the existing contract between
Petitioner and respondent Shangri-la Properties, Inc. petitioner and SPI. It alleged that suspension of proceedings
(SPI) entered into an agreement whereby the latter engaged would not necessarily deprive the court of its jurisdiction over
the former to construct the main structure of the EDSA Plaza the case and that arbitration would expedite rather than delay
Project, a shopping mall complex in the City of Mandaluyong. the settlement of the parties respective claims against each
other.
The construction work was in progress when SPI decided
to expand the project by engaging the services of petitioner In a rejoinder to SPIs reply, petitioner reiterated that there
again. Thus, the parties entered into an agreement for the was no arbitration clause in the contract between the parties. It
main contract works after which construction work began. averred that granting that such a clause indeed formed part of
the contract, suspension of the proceedings was no longer
However, petitioner incurred delay in the construction proper. It added that defendants should be declared in default
work that SPI considered as serious and substantial.[1] On the for failure to file their answer within the reglementary period.
other hand, according to petitioner, the construction works
progressed in faithful compliance with the First Agreement until In its sur-rejoinder, SPI pointed out the significance of
a fire broke out on November 30, 1990 damaging Phase I of petitioners admission of the due execution of the Articles of
the Project.[2] Hence, SPI proposed the re-negotiation of the Agreement. Thus, on page D/6 thereof, the signatures of Rufo
agreement between them. B. Colayco, SPI president, and Bayani Fernando, president of
petitioner appear, while page D/7 shows that the agreement is
a public document duly notarized on November 15, 1991 by and Reynaldo M. de la Cruz) without the initials
Notary Public Nilberto R. Briones as document No. 345, page thereon of any representative of Shangri-La
70, book No. LXX, Series of 1991 of his notarial register.[5] Properties, Inc.
Thereafter, upon a finding that an arbitration clause Considering the insistence of the plaintiff that the
indeed exists, the lower court[6] denied the motion to suspend said Conditions of Contract was not duly executed or
proceedings, thus: signed by the parties, and the failure of the
defendants to submit any signed copy of the said
It appears from the said document that in the letter- document, this Court entertains serious doubt
agreement dated May 30, 1991 (Annex C, whether or not the arbitration clause found in the
Complaint), plaintiff BF and defendant Shangri-La said Conditions of Contract is binding upon the
Properties, Inc. agreed upon the terms and parties to the Articles of Agreement. (Underscoring
conditions of the Builders Work for the EDSA Plaza supplied.)
Project (Phases I, II and Carpark), subject to the
execution by the parties of a formal trade contract. The lower court then ruled that, assuming that the
Defendants have submitted a copy of the alleged arbitration clause was valid and binding, still, it was too late in
trade contract, which is entitled `Contract the day for defendants to invoke arbitration. It quoted the
Documents For Builders Work Trade Contractor following provision of the arbitration clause:
dated 01 May 1991, page 2 of which is entitled
`Contents of Contract Documents with a list of the Notice of the demand for arbitration of a dispute
documents therein contained, and Section A thereof shall be filed in writing with the other party to the
consists of the abovementioned Letter-Agreement contract and a copy filed with the Project
dated May 30, 1991. Section C of the said Contract Manager. The demand for arbitration shall be made
Documents is entitled `Articles of Agreement and within a reasonable time after the dispute has arisen
Conditions of Contract which, per its Index, consists and attempts to settle amicably have failed; in no
of Part A (Articles of Agreement) and B (Conditions case, however, shall the demand he made be later
of Contract). The said Articles of Agreement appears than the time of final payment except as otherwise
to have been duly signed by President Rufo B. expressly stipulated in the contract.
Colayco of Shangri-La Properties, Inc. and President Against the above backdrop, the lower court found that
Bayani F. Fernando of BF and their witnesses, and per the May 30, 1991 agreement, the project was to be
was thereafter acknowledged before Notary Public completed by October 31, 1991. Thereafter, the contractor
Nilberto R. Briones of Makati, Metro Manila on would pay P80,000 for each day of delay counted from
November 15, 1991. The said Articles of Agreement November 1, 1991 with liquified (sic) damages up to a
also provides that the `Contract Documents' therein maximum of 5% of the total contract price.
listed `shall be deemed an integral part of this
Agreement, and one of the said documents is the The lower court also found that after the project was
`Conditions of Contract which contains the completed in accordance with the agreement that contained a
Arbitration Clause relied upon by the defendants in provision on progress payment billing, SPI took possession
their Motion to Suspend Proceedings. and started operations thereof by opening the same to the
public in November, 1991. SPI, having failed to pay for the
This Court notes, however, that the `Conditions of works, petitioner billed SPI in the total amount
Contract referred to, contains the following of P110,883,101.52, contained in a demand letter sent by it to
provisions: SPI on February 17, 1993. Instead of paying the amount
`3. Contract Document. demanded, SPI set up its own claim of P220,000,000.00 and
scheduled a conference on that claim for July 12, 1993. The
Three copies of the Contract conference took place but it proved futile.
Documents referred to in the
Articles of Agreement shall be Upon the above facts, the lower court concluded:
signed by the parties to the Considering the fact that under the supposed
contract and distributed to the Arbitration Clause invoked by defendants, it is
Owner and the Contractor for required that `Notice of the demand for arbitration of
their safe keeping. a dispute shall be filed in writing with the other party
(underscoring supplied) x x x x in no case x x x x later than the time of final
And it is significant to note further that the said payment x x x x which apparently, had elapsed, not
`Conditions of Contract is not duly signed by the only because defendants had taken possession of
parties on any page thereof --- although it bears the the finished works and the plaintiffs billings for the
initials of BFs representatives (Bayani F. Fernando payment thereof had remained pending since
November, 1991 up to the filing of this case on July
14, 1993, but also for the reason that defendants de la Cruz, without that of the representative of petitioner
have failed to file any written notice of any demand Shangri-La Properties, Inc. does not militate against its
for arbitration during the said long period of one year effectivity. Said petitioner having categorically admitted that the
and eight months, this Court finds that it cannot stay document, Annex A to its reply dated August 26, 1993 (Annex
the proceedings in this case as required by Sec. 7 of G, petition), is the agreement between the parties, the initial or
Republic Act No. 876, because defendants are in signature of said petitioners representative to signify
default in proceeding with such arbitration. conformity to arbitration is no longer necessary. The parties,
therefore, should be allowed to submit their dispute to
The lower court denied SPIs motion for reconsideration arbitration in accordance with their agreement.
for lack of merit and directed it and the other defendants to file
their responsive pleading or answer within fifteen (15) days
2. The respondent Court held that petitioners `are in default in
from notice.
proceeding with such arbitration. It took note of `the fact that
Instead of filing an answer to the complaint, SPI filed a under the supposed Arbitration Clause invoked by defendants,
petition for certiorari under Rule 65 of the Rules of Court it is required that Notice of the demand for arbitration of a
before the Court of Appeals. Said appellate court granted the dispute shall be filed in writing with the other party x x x in no
petition, annulled and set aside the orders and stayed the case x x x later than the time of final payment, which
proceedings in the lower court. In so ruling, the Court of apparently, had elapsed, not only because defendants had
Appeals held: taken possession of the finished works and the plaintiffs
billings for the payment thereof had remained pending since
The reasons given by the respondent Court in November, 1991 up to the filing of this case on July 14, 1993,
denying petitioners motion to suspend proceedings but also for the reason that defendants have failed to file any
are untenable. written notice of any demand for arbitration during the said
long period of one year and eight months, x x x.
1. The notarized copy of the articles of agreement attached as
Annex A to petitioners reply dated August 26, 1993, has been Respondent Court has overlooked the fact that under the
submitted by them to the respondent Court (Annex G, petition). arbitration clause
It bears the signature of petitioner Rufo B. Colayco, president
of petitioner Shangri-La Properties, Inc., and of Bayani
Notice of the demand for arbitration dispute shall be filed in
Fernando, president of respondent Corporation (Annex G-1,
writing with the other party to the contract and a copy filed with
petition). At page D/4 of said articles of agreement it is
the Project Manager. The demand for arbitration shall be made
expressly provided that the conditions of contract are `deemed
within a reasonable time after the dispute has arisen and
an integral part thereof (page 188, rollo). And it is at pages
attempts to settle amicably had failed; in no case, however,
D/42 to D/44 of the conditions of contract that the provisions
shall the demand be made later than the time of final payment
for arbitration are found (Annexes G-3 to G-5, petition, pp. 227-
except as otherwise expressly stipulated in the contract
229). Clause No. 35 on arbitration specifically provides:
(underscoring supplied)
Provided always that in case any dispute or difference shall
quoted in its order (Annex A, petition). As the respondent Court
arise between the Owner or the Project Manager on his behalf
there said, after the final demand to pay the amount
and the Contractor, either during the progress or after the
of P110,883,101.52, instead of paying, petitioners set up its
completion or abandonment of the Works as to the
own claim against respondent Corporation in the amount
construction of this Contract or as to any matter or thing of
of P220,000,000.00 and set a conference thereon on July 12,
whatsoever nature arising thereunder or in connection
1993. Said conference proved futile. The next day, July 14,
therewith (including any matter or being left by this Contract to
1993, respondent Corporation filed its complaint against
the discretion of the Project Manager or the withholding by the
petitioners. On August 13, 1993, petitioners wrote to
Project Manager of any certificate to which the Contractor may
respondent Corporation requesting arbitration. Under the
claim to be entitled or the measurement and valuation
circumstances, it cannot be said that petitioners resort to
mentioned in clause 30 (5) (a) of these Conditions or the rights
arbitration was made beyond reasonable time. Neither can
and liabilities of the parties under clauses 25, 26, 32 or 33 of
they be considered in default of their obligation to respondent
these Conditions), the Owner and the Contractor hereby agree
Corporation.
to exert all efforts to settle their differences or dispute
amicably. Failing these efforts then such dispute or difference
shall be referred to Arbitration in accordance with the rules and Hence, this petition before this Court. Petitioner assigns
procedures of the Philippine Arbitration Law. the following errors:
A.
The fact that said conditions of contract containing the
arbitration clause bear only the initials of respondent THE COURT OF APPEALS ERRED IN
Corporations representatives, Bayani Fernando and Reynaldo ISSUING THE EXTRAORDINARY WRIT
OF CERTIORARI ALTHOUGH THE REMEDY ordinary course of law x x x. That is why they are referred to as
OF APPEAL WAS AVAILABLE TO `extraordinary. x x x.
RESPONDENTS.
The Court has likewise ruled that certiorari will not be
B.
issued to cure errors in proceedings or correct erroneous
THE COURT OF APPEALS ERRED IN conclusions of law or fact. As long as a court acts within its
FINDING GRAVE ABUSE OF DISCRETION jurisdiction, any alleged errors committed in the exercise of its
IN THE FACTUAL FINDINGS OF THE TRIAL jurisdiction will amount to nothing more than errors of judgment
COURT THAT: which are reviewable by timely appeal and not by a special
civil action of certiorari.[9]v. Court of Appeals, 327 Phil. 1, 41-42
(i) THE PARTIES DID NOT ENTER (1996).9
INTO AN AGREEMENT
TO ARBITRATE. This is not exactly so in the instant case. While this Court
does not deny the eventual jurisdiction of the lower court over
(ii) ASSUMING THAT THE the controversy, the issue posed basically is whether the lower
PARTIES DID ENTER court prematurely assumed jurisdiction over it. If the lower
INTO THE AGREEMENT court indeed prematurely assumed jurisdiction over the case,
TO ARBITRATE, then it becomes an error of jurisdiction which is a proper
RESPONDENTS ARE subject of a petition for certiorari before the Court of
ALREADY IN DEFAULT Appeals. And if the lower court does not have jurisdiction over
IN INVOKING THE the controversy, then any decision or order it may render may
AGREEMENT TO be annulled and set aside by the appellate court.
ARBITRATE.
However, the question of jurisdiction, which is a question
On the first assigned error, petitioner contends that the of law depends on the determination of the existence of the
Order of the lower court denying the motion to suspend arbitration clause, which is a question of fact. In the instant
proceedings is a resolution of an incident on the merits. As case, the lower court found that there exists an arbitration
such, upon the continuation of the proceedings, the lower court clause. However, it ruled that in contemplation of law, said
would appreciate the evidence adduced in their totality and arbitration clause does not exist.
thereafter render a decision on the merits that may or may not
sustain the existence of an arbitration clause. A decision The issue, therefore, posed before the Court of Appeals
containing a finding that the contract has no arbitration clause in a petition for certiorari is whether the Arbitration Clause does
can then be elevated to a higher court in an ordinary appeal not in fact exist. On its face, the question is one of fact which is
where an adequate remedy could be obtained. Hence, to not proper in a petition for certiorari.
petitioner, the Court of Appeals should have dismissed the
The Court of Appeals found that an Arbitration Clause
petition for certiorari because the remedy of appeal would still
does in fact exist. In resolving said question of fact, the Court
be available to private respondents at the proper time.[7]
of Appeals interpreted the construction of the subject contract
The above contention is without merit. documents containing the Arbitration Clause in accordance
with Republic Act No. 876 (Arbitration Law) and existing
The rule that the special civil action of certiorari may not jurisprudence which will be extensively discussed
be invoked as a substitute for the remedy of appeal is hereunder. In effect, the issue posed before the Court of
succinctly reiterated in Ongsitco v. Court of Appeals[8] as Appeals was likewise a question of law. Being a question of
follows: law, the private respondents rightfully invoked the special civil
action of certiorari.
x x x. Countless times in the past, this Court has held that
`where appeal is the proper remedy, certiorari will not lie. The It is that mode of appeal taken by private respondents
writs of certiorari and prohibition are remedies to correct lack before the Court of Appeals that is being questioned by the
or excess of jurisdiction or grave abuse of discretion equivalent petitioners before this Court. But at the heart of said issue is
to lack of jurisdiction committed by a lower court. `Where the the question of whether there exists an Arbitration
proper remedy is appeal, the action for certiorari will not be Clause because if an Arbitration Clause does not exist, then
entertained. x x x. Certiorari is not a remedy for errors of private respondents took the wrong mode of appeal before the
judgment. Errors of judgment are correctible by appeal, errors Court of Appeals.
of jurisdiction are reviewable by certiorari. For this Court to be able to resolve the question of
whether private respondents took the proper mode of appeal,
Rule 65 is very clear. The extraordinary remedies of certiorari, which, incidentally, is a question of law, then it has to answer
prohibition and mandamus are available only when `there is no the core issue of whether there exists an Arbitration Clause
appeal or any plain, speedy and adequate remedy in the which, admittedly, is a question of fact.
Moreover, where a rigid application of the rule Act No. 876 provides for the formal requisites of an arbitration
that certiorari cannot be a substitute for appeal will result in a agreement as follows:
manifest failure or miscarriage of justice, the provisions of the
Rules of Court which are technical rules may be relaxed.[10] As Section 4. Form of arbitration agreement. A contract to
we shall show hereunder, had the Court of Appeals dismissed arbitrate a controversy thereafter arising between the parties,
the petition for certiorari, the issue of whether or not an as well as a submission to arbitrate an existing
arbitration clause exists in the contract would not have been controversy, shall be in writing and subscribed by the party
resolved in accordance with evidence extant in the record of sought to be charged, or by his lawful agent.
the case. Consequently, this would have resulted in a judicial
rejection of a contractual provision agreed by the parties to the The making of a contract or submission for arbitration
contract. described in section two hereof, providing for arbitration of any
In the same vein, this Court holds that the question of the controversy, shall be deemed a consent of the parties of the
existence of the arbitration clause in the contract between province or city where any of the parties resides, to enforce
petitioner and private respondents is a legal issue that must be such contract of submission. (Underscoring supplied.)
determined in this petition for review on certiorari.
The formal requirements of an agreement to arbitrate are
Petitioner, while not denying that there exists an therefore the following: (a) it must be in writing and (b) it must
arbitration clause in the contract in question, asserts that in be subscribed by the parties or their representatives. There is
contemplation of law there could not have been one no denying that the parties entered into a written contract that
considering the following points. First, the trial court found that was submitted in evidence before the lower court. To
the conditions of contract embodying the arbitration clause is subscribe means to write underneath, as ones name; to sign at
not duly signed by the parties. Second, private respondents the end of a document.[11] That word may sometimes be
misrepresented before the Court of Appeals that they construed to mean to give consent to or to attest.[12]
produced in the trial court a notarized duplicate original copy of
the construction agreement because what were submitted The Court finds that, upon a scrutiny of the records of this
were mere photocopies thereof. The contract(s) introduced in case, these requisites were complied with in the contract in
court by private respondents were therefore of dubious question. The Articles of Agreement, which incorporates all the
authenticity because: (a) the Agreement for the Execution of other contracts and agreements between the parties, was
Builders Work for the EDSA Plaza Project does not contain an signed by representatives of both parties and duly
arbitration clause, (b) private respondents surreptitiously notarized. The failure of the private respondents representative
attached as Annexes `G-3 to `G-5 to their petition before the to initial the `Conditions of Contract would therefor not affect
Court of Appeals but these documents are not parts of the compliance with the formal requirements for arbitration
Agreement of the parties as there was no formal trade contract agreements because that particular portion of the covenants
executed, (c) if the entire compilation of documents is indeed a between the parties was included by reference in the Articles
formal trade contract, then it should have been duly notarized, of Agreement.
(d) the certification from the Records Management and Petitioners contention that there was no arbitration clause
Archives Office dated August 26, 1993 merely states that the because the contract incorporating said provision is part of a
notarial record of Nilberto Briones x x x is available in the files hodge-podge document, is therefore untenable. A contract
of (said) office as Notarial Registry Entry only, (e) the same need not be contained in a single writing. It may be collected
certification attests that the document entered in the notarial from several different writings which do not conflict with each
registry pertains to the Articles of Agreement only without any other and which, when connected, show the parties, subject
other accompanying documents, and therefore, it is not a matter, terms and consideration, as in contracts entered into
formal trade contract, and (f) the compilation submitted by by correspondence.[13] A contract may be encompassed in
respondents are a mere hodge-podge of documents and do several instruments even though every instrument is not
not constitute a single intelligible agreement. signed by the parties, since it is sufficient if the unsigned
In other words, petitioner denies the existence of the instruments are clearly identified or referred to and made part
arbitration clause primarily on the ground that the of the signed instrument or instruments. Similarly, a written
representatives of the contracting corporations did not sign the agreement of which there are two copies, one signed by each
Conditions of Contract that contained the said clause. Its other of the parties, is binding on both to the same extent as though
contentions, specifically that insinuating fraud as regards the there had been only one copy of the agreement and both had
alleged insertion of the arbitration clause, are questions of fact signed it.[14]
that should have been threshed out below. The flaw in petitioners contentions therefore lies in its
This Court may as well proceed to determine whether the having segmented the various components of the whole
arbitration clause does exist in the parties contract. Republic contract between the parties into several parts. This
notwithstanding, petitioner ironically admits the execution of
the Articles of Agreement. Notably, too, the lower court found
that the said Articles of Agreement also provides that the It should be noted that in this jurisdiction, arbitration has
`Contract Documents therein listed `shall be deemed an been held valid and constitutional. Even before the approval on
integral part of this Agreement, and one of the said documents June 19, 1953 of Republic Act No. 876, this Court has
is the `Conditions of Contract which contains the Arbitration countenanced the settlement of disputes through
Clause. It is this Articles of Agreement that was duly signed by arbitration.[18] Republic Act No. 876 was adopted to
Rufo B. Colayco, president of private respondent SPI, and supplement the New Civil Codes provisions on
Bayani F. Fernando, president of petitioner corporation. The arbitration.[19] Its potentials as one of the alternative dispute
same agreement was duly subscribed before notary public resolution methods that are now rightfully vaunted as the wave
Nilberto R. Briones. In other words, the subscription of the of the future in international relations, is recognized worldwide.
principal agreement effectively covered the other documents To brush aside a contractual agreement calling for arbitration
incorporated by reference therein. in case of disagreement between the parties would therefore
be a step backward.
This Court likewise does not find that the Court of
Appeals erred in ruling that private respondents were not in WHEREFORE, the questioned Decision of the Court of
default in invoking the provisions of the arbitration clause Appeals is hereby AFFIRMED and the petition
which states that (t)he demand for arbitration shall be made for certiorari DENIED. This Decision is immediately
within a reasonable time after the dispute has arisen and executory. Costs against petitioner.
attempts to settle amicably had failed. Under the factual milieu,
private respondent SPI should have paid its liabilities under the SO ORDERED.
contract in accordance with its terms. However, Narvasa, C.J., (Chairman), Kapunan, and Purisima,
misunderstandings appeared to have cropped up between the JJ., concur.
parties ostensibly brought about by either delay in the
completion of the construction work or by force majeure or the
fire that partially gutted the project. The almost two-year delay
in paying its liabilities may not therefore be wholly ascribed to
private respondent SPI.
Besides, private respondent SPIs initiative in calling for a
conference between the parties was a step towards the agreed
resort to arbitration. However, petitioner posthaste filed the
complaint before the lower court. Thus, while private
respondent SPIs request for arbitration on August 13, 1993
might appear an afterthought as it was made after it had filed
the motion to suspend proceedings, it was because petitioner
also appeared to act hastily in order to resolve the controversy
through the courts.
The arbitration clause provides for a reasonable time
within which the parties may avail of the relief under that
clause. Reasonableness is a relative term and the question of
whether the time within which an act has to be done is
reasonable depends on attendant circumstances.[15] This Court
finds that under the circumstances obtaining in this case, a
one-month period from the time the parties held a conference
on July 12, 1993 until private respondent SPI notified petitioner
that it was invoking the arbitration clause, is a reasonable time.
Indeed, petitioner may not be faulted for resorting to the court
to claim what was due it under the contract. However, we find
its denial of the existence of the arbitration clause as an
attempt to cover up its misstep in hurriedly filing the complaint
before the lower court.
In this connection, it bears stressing that the lower court
has not lost its jurisdiction over the case. Section 7 of Republic
Act No. 876 provides that proceedings therein have only been
stayed. After the special proceeding of arbitration[16] has been
pursued and completed, then the lower court may confirm the
award[17] made by the arbitrator.

You might also like