Scope of Works Amount % Wt Start Finish Dur

Civil & Structural 45,000,000.00 56.96% Wk 1 Wk 5 5


Mechanical 14,000,000.00 17.72% Wk 3 Wk 6 4
Electrical 11,000,000.00 13.92% Wk 4 Wk 7 4
Architectural 9,000,000.00 11.39% Wk 5 Wk 8 4
Total Amount 79,000,000.00 100.00%

Weekly Progress Total


Cummulative Progress
Actual Weekly
Actual Commulative

S-Cu
100.00%
90.00%
80.00%
70.00%
60.00%
50.00%
40.00%
30.00%
20.00%
10.00%
0.00%
Wk 1 Wk 2 Wk 3 Wk 4 W
Wk 1 Wk 2 Wk 3 Wk 4 Wk 5 Wk 6 Wk 7 Wk 8
11.39% 11.39% 11.39% 11.39% 11.39%
4.43% 4.43% 4.43% 4.43%
3.48% 3.48% 3.48% 3.48%
2.85% 2.85% 2.85% 2.85%

11.39% 11.39% 15.82% 19.30% 22.15% 10.76% 6.33% 2.85%


11.39% 22.78% 38.61% 57.91% 80.06% 90.82% 97.15% 100.00%
12.00% 15.00% 12.00% 11.00% 14.00% 25.00% 4.00% 7.00%
12.00% 27.00% 39.00% 50.00% 64.00% 89.00% 93.00% 100.00%

S-Curve

Cummulative Progress
Actual Commulative

2 Wk 3 Wk 4 Wk 5 Wk 6 Wk 7 Wk 8