You are on page 1of 4

Mcella G.

Gner,
Can nal
Line Balancing in the Apparel Industry
Using Simulation Techniques
Department of Textile Engineering, Abstract
Faculty of Engineering, University of Ege, Line balancing problems are well-known applications of industrial engineering depart-
Izmir, Turkey ments. Different kinds of line balancing algorithms have been applied for many years in
E-mail: mucella.guner@ege.edu.tr the apparel industry. However manual-operations oriented system of this sector makes it
impossible to gain certain results with the algorithms currently used, and also makes it
difficult to predict upcoming events when the production system is modified. This paper
investigates and demonstrates the application of computer simulation for the design of a
manufacturing process for t-shirt production in a virtual-reality environment. For this pur-
pose, lots of data are collected from the real system and alternative systems are composed
in order to find best one.

Key words: line balancing, simulation technique, apparel mills, modular production, pro-
ductivity.

ferent operations which are done manual- ing how fast each operator should work
ly, the sewing department has to be under in order to continue the process, while at
constant control. Consequently, all line the same time keeping productivity high
balancing processes which determine the and throughput at an acceptable level.
speed of an assembly line are done in this
department. But it is a big mistake not to Therefore, a simulation model is an
consider the relationship of the sewing easier way to build up models to repre-
department with other departments. sent real life scenarios, to identify bot-
tlenecks, to enhance system performance
In the apparel industry, it is essential in terms of productivity, queues, resource
to form a new production line for each utilisation, cycle times, lead times, etc.
order, and also the number of workers A re-configurable assembly line can pro-
is changed according to the complexity vide flexibility for high mix low volume
of the order, the number of operations, manufacturing systems, which can meet
throughput etc. The things which should growing customer demand.
be done during the installation of an as-
sembly line are as follows;
n To define a standard time for each op- n Description of the problem
eration, In many garment assembly plants, stand-
n To balance the production line for ard push production systems with dozens
each order, of workers are being reorganised into
n To keep the utilisation rate at a maxi- straight assembly lines. In sewing de-
mum for each operator, partments the Standard time (St) for each
n To complete all these steps in one operation is calculated by the sum of the
week before production begins. base time (Bt), the fatigue allowances
(Fa) and the idle time (It). The base time
Therefore, to develop a new system, consists of the stopwatch time (Sw) and
n Introduction good observation is needed. However, the performance rating (Pr). It is calcu-
Todays business climate for clothing to observe real manufacturing systems lated as follows;
manufacturers requires low inventory is very expensive and sometimes cum-
and quick response systems that turn out bersome. The rapid rate at which the St = Bt + Fa + It = Sw Pr + Fa + It
a wide variety of products to meet cus- whole process takes place, the interac-
tomer demand. It is especially in the ap- tion between workers, and the different The line balancing problem of sewing
parel industry that managers are trying to transition times between workers make it departments is solved by using St ,and its
develop their current systems or looking increasingly more difficult for a human assumed that all of the same operations
for new production techniques in order to being to make correct decisions regard- are processed equally. However, in real-
keep pace with the rapid changes in the
fashion industry.

In apparel enterprises a raw material is


processed in different departments before
becoming a garment (Figure 1). There
is no doubt that the sewing department
is the most important department in the
whole firm. Because there are lot of dif- Figure 1. Departments of apparel enterprises.

FIBRES & TEXTILES in Eastern Europe April / June 2008, Vol. 16, No. 2 (67) 75
n Simulation model
The simulation model was built using
Arena version 7.0 simulation software.
The construction period of the model is
based on a production diagram which
was provided by an apparel firm. Sew-
ing machines are organised according to
the production diagram, but the number
of machines which are used for each op-
eration are determined by the line bal-
ancing algorithm. During straight line
production each operator uses only one
machine, whereas in a lean production
system, skilled operators can use differ-
ent machines.

This study represents discrete-event


modelling and the apparel firm works for
Figure 2. Production diagram of a t-shirt; (OL: Overlock Machine, OE: Overedge Stitch
Machine, LS: Lockstitch Machine). 540 minutes in a day. At the beginning
of each order, the production line begins
empty. This start-up condition must also
ity, all operations are completed at dif- of optimum production alternatives [2].
be simulated. Statistics during this part
ferent times because of their stochastic Patel et al. discussed the methodology of
of the simulation may negatively bias the
structure, and the stochasticity of opera- modelling and studying the Final Process final results since the line takes time to
tions makes it almost impossible to fol- System of the automobile manufacturing warm up and begin operating consist-
low a fixed time pattern. Therefore, man- process in order to develop an effective ently in a steady state. When an entity
agers are up against unexpected queues and efficient process to ensure the sys- arrives at a sewing machine, it waits in a
and decreasing levels of performance tem throughput [3]. Choi et al. discusses first-in-first-out queue until the resource
during the sewing process. New calcu- initial efforts to implement simulation is available.
lation methodology which reflects real- modelling as a visual management and
ity better is needed in order to estimate analysis tool at an automotive foundry The following assumptions are used to
more realistic production quantities and plant manufacturing engine blocks [4]. define the problem:
performance. Potoradi et al.described how a large n the assembly line is never starved,
number of products are scheduled by a n set-up times are not taken into consid-
Also, managers want to change whole simulation engine to run in parallel on eration. Because in a real system the
production lines to create lean ones in a pool of wire-bond machines to meet setup process is usually accomplished
order to immediately respond to changes weekly demand [5]. Kibira et al. presents at the end of the working time,
in demand. But the main difficulty of this a virtual-reality simulation of a design n 540 minutes working time does not
is to obtain skilled operators who can use of a production line for a mechanically include breaks,
different kinds of sewing machines. Even assembled product [6]. Altiparmak et al. n no maintenance process is performed
if operators are found, it is hard to calcu- used simulation metamodels to improve during the working period,
late the new line balancing problem with the analysis and understanding of the de- n all process times for sewing operations
the current work force and those who are include insignificant breakdowns
cision-making processes of an asynchro-
skilled. like the detachment of sewing thread,
nous assembly system to optimise the
buffer sizes in the system [7]. Wiendahl n transportation of raw materials is per-
The simulation modelling research pro- formed by workers who arent used
et al. used simulation tools in the field of
posed here is based on how to build a for sewing operations.
assembly planning and due to the differ-
reconfigurable simulation model to meet
ent objectives of the different efforts, the
customer requirements as well as im- Table 1. Distribution types for each opera-
tools are divided into the four-hierarchy
prove system performances. tion; unit, second.
classes of an assembly shop, cell, station
and component [8]. Gurkan et al. Investi-
Several researchers have studied assem- Operations Distribution Type
bly line performance by using simula- gated current problems in an order based Shoulders stitch 8 + LOGN(2.53, 1.24)
tion techniques; Scriber, described a weaving mill so as to propose a new sys- Sleeve sides stitch 7 + ERLA(0.893, 2)
case study for selecting the best probable tem for the aforementioned mill [9]. Sleeve ends stitch 7 + ERLA(0.973, 4)
production system from four proposed Collar attaching NORM(12.3, 1.42)

production systems using simulation [1]. Assembly line description Collar stitch 3.6 (Constant)

Azadeh developed an integrated simu- In this study, the problem under consid- Shoulder + collar stitch 9 + GAMM(2.17, 1.77)

lation model which generates a set of eration is about the production of a ba- Label stitch 6 (Constant)

sic t-shirt. The production diagram of a Label attaching 17 + ERLA(1.25, 3)


optimising alternatives for a heavy con-
Sleeve stitch 33 + WEIB(6.96, 1.17)
tinuous rolling mill system in a full-scale t-shirt consists of 10 different operations
Hem stitch 8 + LOGN(2.53, 1.24)
steel-making factory and generates a set (Figure 2).

76 FIBRES & TEXTILES in Eastern Europe April / June 2008, Vol. 16, No. 2 (67)
The model input Table 2. Number of operators for each alternative; A - alternative models.
During the data collection period, be-
Number of operators
tween 45 and 70 items of data are ob- No Operation (machine) Real system A1 A2 A3 A4 A5
tained for each operation using time model
study techniques. As has already been 1 Sleeve sides stitch (OL) 4
9 6 5 5 4
mentioned, in assumptions, insignificant 2 Sleeve ends stitch (OE) 5
breakdowns are also added to the time 3 Collar stitch (OL) 1
3 2 2 2 2
study data. All data are evaluated by the 4 Label stitch (LS) 2
Arena Input Analyser software in order 5 Shoulders stitch (OL) 4
9 7 7 6 6
to determine distribution types for every 6 Collar attaching (OL) 5
operation (Table 1). 7 Shoulder + collar stitch (OE) 3
8 7 7 7 7
8 Label attaching (LS) 5
9 Sleeve stitch (OL) 8 8 8 8 8 8
n Verification/Validation 10 Hem stitch (OE) 3 3 3 3 3 3
Total number of operators 40 40 33 32 31 30
The following verification efforts were
Throughput 6464 6463 6462 6464 6463 6462
made: The model was coded and de-
Piece per operator 161.6 161.5 195.8 202 208.4 215.4
bugged step by step. Trace and animation
techniques were used to verify that each
program path was correct. We made simu-
lation trial runs under a variety of settings
of the input parameters, and checked the
model output results for appropriacy.

By running the simulation model plenty


of times, the interval times of each en-
tity were taken every 5 seconds. It was
proved by repetition that using less time
for the interarrivals does not change the
throughput, It only makes the simulation
work more slowly. 5 seconds, which is
called the critical time, is the most suit-
able duration to observe queues.

Validation is necessary to show that the


proposed model has an acceptable level of
confidence in the performances process-
ing assumed. Validation is also associ-
ated with whether the proposed model
is indeed an accurate representation of Figure 3. Utilisations for each alternative.
the real system. There are several ways
to validate the model. Model validation
was accomplished through hypothesis nF and nA the number of field samples n Results
tests using a throughput with a 95% con- and runs of the model, respectively.
After the validation process was done,
fidence interval as follows [10];
different decision options were evalu-
The hypotheses are: The average throughput of 50 items of
ated for the design or reconfiguration of
H0: Filed = Arena data (n1 = 50) collected from the field
the assembly line. Skilled operators were
H1: Field Arena was mF = 6463.78 unit with variance
added for suitable operations in order to
S F2 = 48.72. and that for the ARENA
decrease the bottleneck in the assembly
The test is if t0 < t/2,n1+n2-2, we would model was mA = 6462.58 with variance
line. The queue length and the utilisa-
accept the null hypothesis H0, where, S A2 = 1.56 after running the model for a
tion of each resource were also observed.
total of 50 times (n2=50). Thus, five different alternative models
F A
t0 =
1 1 (A1, A2, A3, A4, A5) were developed un-
Sp + Hence, Sp = 5.01 which makes t0 = 1.19 til the best result was gained (Table 2).
nF n A
and from the t table (%95 C.I.)
t/2,n1+n2-2 = t0.025,98 = 1.96 As seen in Table 2, what-if analyses led
(n F 1) S F2 + (n A 1) S A2
S p2 = us to use some skilled operators, for in-
nF + n A 2 Since, stance the first and second operations in
mF is the mean throughput from the field t0 < t/2,n1+n2-2 the real system model was done by four
mA is the mean production rate from the it implies that there is no significant dif- operators who could handle OL and five
ARENA model ference between the means, therefore the operators who could handle OE. Howev-
S p2 is the pooled mean variance simulation model is valid. er, in A1 model 9 operators who can han-

FIBRES & TEXTILES in Eastern Europe April / June 2008, Vol. 16, No. 2 (67) 77
Table 3. Simulation results of modular pro- order to change the assembly lines References
duction. cumbersome structure,
n All operators are allocated suitable 1. Scriber T. J. An introduction to simulation
Modular production
Operations Number of Utilization jobs according to their utilisations, using GPSS/H New York: Wiley, 1991.
operators 2. Azadeh, M. A., Optimization of a he-
n Entity interarrival times were changed
Sleeve sides stitch avy continuous rolling mill system via
(OL) every 10 seconds after the critical
simulation Proceedings of the Seventh
Sleeve ends stitch 3 0.9997 time is determined in order to rapidly
(OE) International Conference on Industrial En-
simulate the model.
Collar stitch (OL) gineering and Engineering Management,
Label stitch (LS) 2000, Guangzhou, China pp. 378-384.
2 0.9191 As is seen in Table 3, the results of one
Shoulders stitch (OL) 3. Patel, V., J. Ashby, and J. Ma. 2002.
modular production are better than all the
Collar Attaching (OL) 2 0.9989 Discrete event simulation in automotive
Shoulder + collar
alternatives above; especially the produc-
1 0.8802 Final Process System, Proceedings of the
stitch (OE) tion of piece per operator, which has the
2002 Winter Simulation Conference, ed.
Label attaching (LS) 1 0.9997 highest rank.
E. Ycesan, C.-H. Chen, J. L. Snowdon,
Sleeve stitch (OL) 4 0.9265
and J. M. Charnes, pp. 1030-1034, San
Hem stitch (OE) 1 0.9924
Total number of 14
n Discussion & conclusions Diego, California.
operators 4. Choi, S.D., A.R. Kumar, and A. Houshy-
Throughput 3030 n Our proposed simulation approach, ar., A simulation study of an automotive
Piece per operator 216.42 developed for the line balancing of foundry plant manufacturing engine
t-shirt production, provides the plan- blocks Proceedings of the 2002 Winter
ning manager with a simulation based Simulation Conference, ed. E. Ycesan,
dle OL and also OE is used. In the appar- optimisation tool that can achieve the C. H. Chen, J. L. Snowdon, and J. M.
el industry there are two ways of fulfill- following objectives: gaining infor- Charnes, 2002 San Diego, California,
ing this purpose: to employ new workers mation without disturbing the actual pp.1035-1040.
or to train current workers. In any case, system, improved system perform- 5. Potoradi, J., O.S. Boon, S.J. Mason, J.
more efficient production is achieved by ance, testing new systems before im- W. Fowler, and M. E. Pfund, Using si-
using alternative models. When we ana- plementation, and labour requirement mulation-based scheduling to maximize
lyse Figure 3, changes in utilisation can planning. demand fulfillment in a semiconductor
easily be seen. assembly facility Proceedings of the
n The base model was a replicate of the
2002 Winter Simulation Conference, ed.
The development of utilisation is under- existing system without variation. The
E. Ycesan, C.H. Chen, J. L. Snowdon,
taken by observing the utilisation of each reconfigured/redesigned models were
and J. M. Charnes, 2002, San Diego,
operator after every repetition of a mod- developed in order to add skilled oper-
California pp.1857-1861.
el. Operations which have insufficient ators to the current system. However,
6. Kibira, D., McLean C., Virtual reality
utilisation are reorganised by removing the application of simulation technol-
simulation of a mechanical assembly
redundant operators. So after developing ogy today is not very widespread in
production line Proceedings of the 2002
five different alternatives, the best model the apparel industry; these models can
Winter Simulation Conference, ed. E.
be applied in a real system to analyse
is obtained according to the throughput Ycesan, C. H. Chen, J. L. Snowdon,
the system performance more effi-
and utilisation rate. and J. M. Charnes, 2002, San Diego,
ciently and effectively. The modelling
California pp. 1130-1137.
environments can easily be used for
Designing the assembly line for 7. A ltiparmak, F., B. Dengiz, and A. A.
line balancing and assessing the be-
modular production Bulgak., Optimization of buffer sizes in
haviour of a line. Thus, managers can
assembly systems using intelligent tech-
Also, a different scenario analysis was prevent any unexpected situations by
niques. Proceedings of the 2002 Winter
done to modify the assembly line to be- analysing results using the simulation
Simulation Conference, ed. E. Ycesan,
come a modular production line. The model.
C.H. Chen, J. L. Snowdon, and J.M.
main advantage of this production style
n Nowadays, apparel mills, particularly Charnes, 2002, San Diego, California pp.
is as follows;
those based upon small lots and or- 1157-1162.
n increment in production speed, ders, must respond rapidly to changes 8. Wiendahl, H., Garlichs R., Zeugtraeger
n ease of control, in style. It is essential to know the K., Modeling and simulation of assembly
n it gives the opportunity to create a current situation of a system in order systems CIRP Annals 1991, 40(2), pp.
competitive atmosphere between op- to process orders on time. In order to 577-585.
erators, increase productivity, it is essential 9. Gurkan P., Taskin C., Application of simu-
n fewer operators required, to describe the behaviour of a system lation technique in weaving mills Fibers &
n flexibility. and to generate alternative systems. Textiles in Eastern Europe, 2005, Vol.13,
For this purpose, by developing a suit- No.3(51), pp. 8-10.
However, this type of production fre- able simulation program for an enter- 10. Hines W. W., Mongomery D. C., Proba-
quently needs more skilled operators who prise, the situation of the company in bility and statistics in engineering and
can perform two or three different jobs at the short-term future can be predicted management science. New York: Wiley,
the same time. A new scenario was devel- and productivity can be increased. 1989.
oped by using these steps;
n The whole production line is divided
into two different small groups in Received 21.02.2007 Reviewed 09.03.2008

78 FIBRES & TEXTILES in Eastern Europe April / June 2008, Vol. 16, No. 2 (67)

You might also like