ITEM DESCRIPCION METRADO UND DIAS 7-Jul 8-Jul 9-Jul 10-Jul 11-Jul 12-Jul 13-Jul 14-Jul 15-Jul 16-Jul

ADO UND DIAS 7-Jul 8-Jul 9-Jul 10-Jul 11-Jul 12-Jul 13-Jul 14-Jul 15-Jul 16-Jul 17-Jul 18-Jul 19-Jul 20-Jul 21-Jul 22-Jul 23-Jul 24-Jul 25-Jul 26-Jul 27-Jul 28-Jul 29-Jul 30-Jul 31-Jul 1-Ago 2-Ago 3-Ago 4-Ago 5-Ago 6-Ago 7-Ago 8-Ago 9-Ago 10-Ago 11-Ago 12-Ago 13-Ago 14-Ago 15-Ago 16-Ago 17-Ago 18-Ago 19-Ago 20-Ago 21-Ago 22-Ago 23-Ago 24-Ago 25-Ago 26-Ago 27-Ago 28-Ago 29-Ago 30-Ago 31-Ago 1-Set 2-Set 3-Set 4-Set 5-Set 6-Set 7-Set 8-Set 9-Set 10-Set 11-Set 12-Set 13-Set 14-Set 15-Set 16-Set 17-Set 18-Set 19-Set 20-Set 21-Set 22-Set 23-Set 24-Set 25-Set 26-Set 27-Set 28-Set 29-Set 30-Set 1-Oct 2-Oct 3-Oct 4-Oct

1 OBRAS PROVISIONALES

01.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPO 1.00 GLB 6

02 TRABAJOS PRELIMINARES

02.01 TRAZO Y REPLANTEO 146,168.66 M2 77

02.02 BOMBEO DE AGUA DE LAGUNA 21,889.76 M3 6

02.03 EXTRACCION DE LODO Y TRASLADO A LECHO DE SECADO 12,058.00 M3 4

03 RETIRO , TRASLADO Y MANTENIMIENTO DE ARBOLES

03.01 RETIRO DE ARBOLES 662.00 UND 22

03.02 TRASLADO E INSTALACION DE ARBOLES 235.00 UND 30

03.03 MANTENIMIENTO Y MANEJO DE ARBOLES TRASPLANTADOS 1.00 GLB 5

03.04 ELIMINACION DE MALEZA Y RESIDUOS 331.00 M3 33

4 DESBROCE Y LIMPIEZA 10.93 HA 24

05 MOVIMIENTO DE TIERRAS

05.01 CORTE DE MATERIAL SUELTO RENDIMIENTO=810 M3/DIA 338,370.97 M3 56

05.02 PERFILADO Y COMPACTADO EN ZONA DE CORTE PLATAFORMA 146,168.66 M2 15

05.03 PERFILADO Y COMPACTADO EN ZONA DE LAGUNAS 52,076.00 M2 12

05.04 CARGUIO Y TRANSPORTE MATERIAL EXCAVACION PARA ACOPIO INTERNO, Dprom=1.00 KM EQ PROPIO 327,259.72 M3 63

05.05 CARGUIO Y TRANSPORTE PARA ELIMINACION DE MATERIAL EXCEDENTE, D=1.00 KM 83,999.39 M3 23