PROSEDUR PARTIAL SHUTDOWN UNTUK ISOLASI HP SCRUBBER IN CASE LEAK AT P

BOTTOM DRUM D0103

N0 Aktivitas Komulative
time

1 Estimate maintenance job 2 jam, detail pekerjan terlampir. 2 hour

Koodinasi dengan spp perihan penutupan sales gas. Surat


2
pemberitahuan akan dikoordinasikan oleh pep

Bean down sumur sesuai intruksi pep. Bila tidak


3 10 minute
memungkinkan shut in rbt 1, kdl 1, ktb 2

Separator Gradually full flare Paralel Switching fuel gas GTG


with solar, switch fuel TOX dari gas ke solar keep temp 1200F,
Agru keep Pressure >300 Psig & keep sirkulasi solvent with
4 0.5 hour
minimum rate solvent 28 kbd. DHU keep sirkulasi minimum
rate glycol, burner keep on (monitor ketersediaan lpg), Pilot
flare switch to LPG (Monitoring ketersediaan LPG)

BSRU unit sirkulasi minimum rate dengan P0401&P0402


running 1 pompa. Keep running k0401 dengan flow 1 mmscfd.
5 Stop K0402, MSPP feeding demin, Decanter PE-0403 stop, 0.5 hour
Chiller K-1901 stop. Prosedur shutdown mengacu pada
prosedur shutdown normal (CPPG-GEN-PCD-01.003)

6 Isolasi scrubber via marshalling


sdv 0110
10 minute
sdv 0203
sdv 0103
7 Estimate depress prosess 2 jam dilakukan via
bypass psv 0103
bypass psv 0104
bypass psv 0105
bypass psv 0106

2 hour
bypass psv 0107
bypass psv 0108 2 hour
2 ea valve 2" drain line HP SCRUBBER to close drain
sampai pressure HP scrubber equal pressure flare, tutup semua
valve bypass PSV. Release sisa pressure HP scrubber dengan
connect hose via PI-0102 dan prewash sistem ke atmosfer,
dilute release gas via drum berisi air, dan portable blower di
area release gas.
IN CASE LEAK AT PIPE

Check List Item