TheStateofMinnesotaSustainableBuildingGuidelines

DESIGN&CONSTRUCTIONPHASE
COMMISSIONINGPLAN
TEMPLATE

BaseduponB3MinnesotaSustainableBuildingGuidelinesVERSION2.1




















Notestothereaderhavebeenaddedtothisdocument
withinnumeroustextboxessuchasthis.These
textboxescontainreferencestosupporting
documentation,suggestions,and/orinstructions
pertainingtotheCommissioningPlanTemplate.

Pleasedeletethesetextboxeswhentheyareno
longerneeded.

DesignandConstructionCommissioningPlanTemplate
Page1
TheStateofMinnesotaSustainableBuildingGuidelines

TABLEOFCONTENTS

1 INTRODUCTION.............................................................................................................................................3
2 COMMISSIONINGTEAMMEMBERS..............................................................................................................4
3 SYSTEMSTOBECOMMISSIONED................................................................................................................5
3.1 SystemstobeCommissioned:...............................................................................................................5
4 COMMISSIONINGPROCESSNARRATIVES.....................................................................................................7
4.1 GENERALCOMMISSIONINGACTIVITIES.................................................................................................7
4.1.1 CommissioningReports(1.02):...................................................................................................7
4.1.2 SubmitOutcomeDocumentation(1.03):...................................................................................8
4.2 SYSTEMSCOMMISSIONINGACTIVITIES.................................................................................................8
4.2.1 AGENCYPLANNING.....................................................................................................................8
4.2.2 PREDESIGNPROGRAMMING..................................................................................................8
4.2.3 PREDESIGNSITESELECTION....................................................................................................8
4.2.4 SCHEMATICDESIGN....................................................................................................................9
4.2.5 DESIGNDEVELOPMENT............................................................................................................10
4.2.6 CONSTRUCTIONDOCUMENTS..................................................................................................10
4.2.7 CONSTRUCTION........................................................................................................................11
4.2.8 CORRECTIONPERIOD................................................................................................................12
4.2.9 ONGOINGOPERATIONS...........................................................................................................12
4.3 CONSTRUCTIONAIRQUALITYMANAGEMENTPLAN...........................................................................12
4.4 CORRECTIONPERIODAIRQUALITYMANAGEMENTPLAN...................................................................12
4.5 CONSTRUCTIONWASTEMANAGEMENTPLAN....................................................................................12
4.6 ROLESANDRESPONSIBILITIES..............................................................................................................13
4.6.1 GENERALCOMMISSIONINGACTIVITIES....................................................................................14
4.6.2 AGENCYPLANNING...................................................................................................................16
4.6.3 PREDESIGN/PROGRAMMING..................................................................................................16
4.6.4 PREDESIGN/SITESELECTION....................................................................................................17
4.6.5 SCHEMATICDESIGNPHASE.......................................................................................................17
4.6.6 DESIGNDEVELOPMENT............................................................................................................19
4.6.7 CONSTRUCTIONDOCUMENTS..................................................................................................20
4.6.8 CONSTRUCTION........................................................................................................................22
4.6.9 CORRECTIONPERIOD................................................................................................................26
4.6.10 ONGOINGOPERATIONS...........................................................................................................28
4.6.11 CONSTRUCTIONAIRQUALITYMANAGEMENTPLAN................................................................28
4.6.12 CORRECTIONPERIODAIRQUALITYMANAGEMENTPLAN.......................................................28
4.6.13 CONSTRUCTIONWASTEMANAGEMENTPLAN.........................................................................29
5 SUPPORTINGCOMMISSIONINGDOCUMENTATION...................................................................................30
5.1 B3MSBGTrackingTool(www.msbgtracking.com)................................Error!Bookmarknotdefined.
5.2 AppendixP1SuggestedImplementationforAllPerformanceManagementGuidelines...................30
5.3 AppendixP4DesignandConstructionCommissioningSupportingInformation...............................30
5.4 AppendixP5DesignandConstructionCommissioningMatrix...........................................................30

DesignandConstructionCommissioningPlanTemplate
Page2
TheStateofMinnesotaSustainableBuildingGuidelines

1 INTRODUCTION

DesignandConstructionCommissioningreferstotheprocessthatshallbegininschematicdesign
andconcludeafterthecorrectionperiodoraftercompletionofafullyearofoperation,whichever
islater.

TheDesignandConstructionCommissioningProcessisthemeanstoverifyanddocumentthatthe
facilitysystemsoperateinaccordancewiththeirdesignintentandthattheoperationsstafffully
understandsthesystemoperationalproceduresandarepreparedtocontinueoperatingthe
systemperthedesignintent.Thisincludesdocumentingsystemoperationalgoalsanddesign
parameters,specifyingverificationandtestinginthecontractdocuments,confirmingthe
successfulcompletionoftheverificationprocess,documentingthesystemoperationalprocedures
andtrainingtheoperationsstaff.TheDesignandConstructionCommissioningProcessis
coordinatedbytheCommissioningLeaderandexecutedbytheCommissioningTeam.

ThegoalsoftheDesignandConstructionPlanaretodefinethe:
1) SystemstobeCommissioned
2) Commissioningactivitiesanddocumentation
3) Schedulingparameters
4) Acceptancecriteria
5) RolesandresponsibilitiesoftheCommissioningTeammembers

Add:
6)ConstructionAirQualityManagementPlan
7)CorrectionPeriodAirQualityManagementPlan
8)ConstructionWasteManagementPlan
9)CorrectionPeriodUserComfortandSatisfactionAssessmentPlan



TheDesignandConstructionCommissioningPlanisalivingdocumentthatgrowsindetailover
time,assystemsarespecifiedanddesigndetailsarerefined.Thefollowingisadescriptionofhow
theDesignandConstructionCommissioningPlanshallevolveoverthecourseoftheproject.

DesignandConstructionCommissioningPlanTemplate
Page3
TheStateofMinnesotaSustainableBuildingGuidelines

2 COMMISSIONINGTEAMMEMBERS

Role Company Title Name PhoneNumber EmailAddress

Commissioning
(XXX)XXXXXXX
Leader

FacilitiesOperations
(XXX)XXXXXXX
Manager(FOM)

ProjectManager (XXX)XXXXXXX

(XXX)XXXXXXX

Designers (XXX)XXXXXXX

(XXX)XXXXXXX

(XXX)XXXXXXX

Contractors (XXX)XXXXXXX

(XXX)XXXXXXX

GuidelineLeader (XXX)XXXXXXX

Pleaseinserttheprojectteamcontactinformation(e.g.Company,Title,Name,Phone
Number,andEmail).

DesignandConstructionCommissioningPlanTemplate
Page4
TheStateofMinnesotaSustainableBuildingGuidelines

3 SYSTEMSTOBECOMMISSIONED

PleasesubstitutetheXswithalltherelevantsystemstobecommissioned

3.1 SystemstobeCommissioned:
1) MechanicalHVACSystem(includingTesting,Adjusting,andBalancing)
a) X
b) X
c) X
d)
2) Energy
a) X
b) X
c) X
d)
3) RenewableEnergySystems
a) X
b) X
c) X
d)
OtherelementsrelatedtoperformanceofGuidelines:E.1,E.2,E.3,E.4,I.4,andI.5.

4) PowerandElectricalSystems
a) X
b) X
c) X
d)
OtherelementsrelatedtoperformanceofGuidelines:S.5,E.1,E.2,E.3,I.6,andI.9.

5) LightingandDaylightingControls
a) X
b) X
c) X
d)
6) IndoorAirQualityElementsandSystems
a) X
b) X
c) X
d)
OtherelementsrelatedtoperformanceofGuidelines:I.1,I.2,I.3,I.4,andI.5.

7) SeeAppendixP4formoredetailsonrequirementsunderDesignandConstruction
CommissioningPlan

DesignandConstructionCommissioningPlanTemplate
Page5
TheStateofMinnesotaSustainableBuildingGuidelines

ModifytheSystemstobeCommissionedListtobeprojectspecific.Forexample:

1) MechanicalHVACSystem
a) AirHandlingSystem
b) ChilledWaterSystem
c) HeatingHotWaterSystem
d) DomesticHotWaterSystem
e)
2) RenewableEnergySystem
a) PhotovoltaicSystem
b)
3) PowerandElectricalSystem
a) NormalPowerDistributionSystem
b) EmergencyPowerSystem
c)
4) LightingandDaylightingSystem
a) LightingControlSystem
b)
5) IndoorAirQualityElementsandSystem
a)
6)

This list of the systemstobecommissioned should be modified to accommodate
the projectspecific systems. Refer to Appendix P4 for more details on
requirementsunderDesignandConstructionCommissioningPlan.

RECOMMENDEDSYSTEMSTOBECOMMISSIOED:
1) PlumbingSystems:Inadditiontorequiredflowratecommissioningaboveas
neededtosupportoperationalachievementofguidelines:S.7,S.8,S.13
2) Interior materials (specification, installation): As needed to support
operationalachievementofguidelines:I.2,M.1,M.2
3) Envelope integrity: In addition to required water infiltration commissioning
above as needed to support operational achievement of guidelines: I.3, M.1,
M.2
4) IEQ: Vibrations/acoustics/noise: In addition to occupant surveys above,
perform physical measurements as needed to support operational
achievementofguidelines:I.7,I.8
5) PlumbingSystems:FlowRate
6) EnvelopeIntegrity:TestBuildingEnvelopeforWaterInfiltration

DesignandConstructionCommissioningPlanTemplate
Page6
TheStateofMinnesotaSustainableBuildingGuidelines

4 COMMISSIONINGPROCESSNARRATIVES
ThefollowingsectiondefinestheGeneralCommissioningActivities,SystemCommissioning
Activities(inchronologicalorderfromAgencyPlanningtoOnGoingOperations),andtheroles&
responsibilitiesofthevariousteammembers.

4.1 GENERALCOMMISSIONINGACTIVITIES
ThefollowingarecommonorgeneralCommissioningactivitiesthatoccurthroughouttheProject
PhasefromAgencyPlanningtotheCorrectionPeriod.

Thenumberscapturedenclosedwithinparentheses(e.g.1.01)refertothetasknumberfoundin
AppendixP5:DesignandConstructionCommissioningMatrix.

Design&ConstructionPhaseCommissioningPlan(1.01):
TheCommissioningPlanisadocumentthatoutlinestheCommissioningProcessanditsrelated
activities,theroles&responsibilitiesoftheCommissioningTeam,andCommissioningrelated
requirements.Throughouttheprojectphase,theCommissioningPlanisupdatedtoreflect
changesintheDesignIntentDocument.Criteriathatcouldnotbemet,summationofthe
associatedevents,impactstotheDesignIntentDocument,andtheresultingDesignIntent
Documentmodificationsshouldbedocumented.

4.1.1 CommissioningReports(1.02):
CommissioningReportsshallbepreparedattheendofeachphaseofdesignandconstruction
documentingprogressinandcompliancewiththeCommissioningPlanforthatphase.Eachreport
shouldincluderecommendationsforadjustmentsintheCommissioningPlanforthenextphase.
StartingwiththePreDesignPhaseandgoingthroughtheConstructionDocumentsPhase,the
CommissioningReportsshouldincludedesignreviewcommentsdocumentingtheCommissioning
Teamsevaluationoftheabilityofthefacility,asdefinedordescribedatthePhase,tomeetthe
DesignIntentDocumentcriteria.TheendofCorrectionPeriodCommissioningReportshallbethe
finaldeliverableoftheDesignandConstructionCommissioningProcess.TheReportshallstatethat
theDesignandConstructionCommissioningPlanhasbeencompletedandtheDesignIntent
Documentcriteriahavebeenachieved.IftheowneracceptssystemsthatdonotmeettheDesign
IntentDocumentcriteria,theReportshalldocumentwhichdeviationswereapprovedbythe
owner.Thereportshallalsoinclude,butnotbelimitedto,thefollowing:
DesignIntentDocument
OtherSystemRequirementsandParameters
SpecificsofEquipmentandSystemsOperation
TestProcedures
TestingRecord
O&MTrainingRecord
CommissioningTeamParticipants

DesignandConstructionCommissioningPlanTemplate
Page7
TheStateofMinnesotaSustainableBuildingGuidelines

4.1.2 SubmitOutcomeDocumentation(1.03):
SubmitdocumentationasrequiredbytheMSBGattheendofeachphaseofthedesignand
constructionprocessusingtheonlineB3MSBGTrackingTool(www.msbgtracking.com).

4.2 SYSTEMSCOMMISSIONINGACTIVITIES
4.2.1 AGENCYPLANNING
InconjunctionwiththegeneralCommissioningactivities,thefollowingarespecificCommissioning
activitiesaddressedinduringAgencyPlanning:

PlanningBaseline:TheProjectManagerwillworkwiththeDesignerstodevelopbroadbuilding
wideexpectationsandcriteria.Thisbecomestheframeworkforaninitialdesignintentdocument.
PriortodevelopingthePlanningBaseline,theCommissioningLeadercanprovidetheProject
Managerwithinsightastowhattodefineduringtheseearlystagesfromacommissioning
perspective.

4.2.2 PREDESIGNPROGRAMMING
InconjunctionwiththegeneralCommissioningactivities,thefollowingarespecificCommissioning
activitiesaddressedinduringPreDesignProgramming:

EngageActingCommissioningTeam(2.01):TheActingCommissioningTeamisassembledto
facilitateandoverseecommissioningactivitiesduringthePlanningandPreDesignphasesofthe
project.TheActingCommissioningTeamshallincludethefollowingmembers.Theseteam
membersmayormaynotbethesamepeoplewhoserveoftheDesignandConstruction
CommissioningTeam.
CommissioningLeader
FacilitiesOperationsManager(FOM)
ProjectManager
GuidelineLeader
TheCommissioningLeaderfacilitatesandcoordinatestheeffortsoftheCommissioningTeam.For
DesignandConstructionCommissioning,theCommissioningleadershallhaveadistinctrolefrom
thedesignteambutmaybeemployedwithinafirmprovidingdesignservices.

TheFacilityOperationsManagerisaccountableforfacilityperformanceduringongoingoccupancy
andwillmanageorperformongoingoperationsandmaintenancefollowingconstruction.This
personisavailabletoparticipatethroughoutthedesignandconstructionprocessforcontinuity
intofinaloperation.

ProgrammingBaseline:TheProjectManagerwillcontinuetoworkwithDesignerstorefinethe
buildingcriteriaandexpectations.PriortodevelopingtheProgrammingBaseline,the
CommissioningLeadercanprovidetheProjectManagerwithinsightastowhattodefineduring
theseearlystagesfromacommissioningperspective.

4.2.3 PREDESIGNSITESELECTION
InconjunctionwiththegeneralCommissioningactivities,thefollowingarespecificCommissioning
activitiesaddressedinduringPreDesignSiteSelection:

EngageActingCommissioningTeam(2.01):Refertopreviousdescription.

DesignandConstructionCommissioningPlanTemplate
Page8
TheStateofMinnesotaSustainableBuildingGuidelines


ProgrammingBaseline:TheProjectManagerwillcontinuetoworkwithDesignerstorefinethe
buildingcriteriaandexpectations.PriortodevelopingtheProgrammingBaseline,the
CommissioningLeadercanprovidetheProjectManagerwithinsightastowhattodefineduring
theseearlystagesfromacommissioningperspective.

ReviewSiteAlternativesforAbilitytoAchievePerformanceGoals(2.02):ReviewSiteAlternatives
fortheirimpactontheabilityofthesystemsbeingcommissionedtoachievetheirDesignIntent
criteria.

4.2.4 SCHEMATICDESIGN
InconjunctionwiththegeneralCommissioningactivities,thefollowingarespecificCommissioning
activitiesaddressedinduringSchematicDesign:

DesignBaseline:Giventhepreviouslydevelopedbaselines,theDesignerwilldevelopthedrawings
andspecificationswhichownersneedsandrequirements.Theschematicdesignshouldinclude
(butnotlimitedto):specifications,sitedetails,landscaping,buildingexteriorenvelope,structural,
buildinginterior,elevators,plumbing,HVAC,HVACcontrols,electrical,fireprotection,lighting,
electricalpowerdistribution,firealarm,telecommunications,andservicefacilities.

EngageActingCommissioningTeam(2.01):Refertopreviousdescription.

DesignIntentDocument(2.04):TheDesignIntentDocumentshallquantifyfunctionalperformance
expectationsandparametersforeachsystemtobecommissioned.TheDesignIntentDocument
providesthecommonunderstandingthatfocusesdesign,construction,andcommissioning
activitiesonthedesiredoutcome.TheDesignIntentDocumentshallbewritteninobjectiveand
measurableterms.Quantifyparameterssuchasspacetemperatures,humiditylevels,lighting
levels,soundlevels,andventilationrateswhenappliedtotheconditionedbuildingspaces.The
DesignIntentDocumentshallbeupdatedeverytimetheowneracceptsanalternateperformance
criterionduetoownerdesires,schedule,orbudget.Thismightoccurthroughnormaldesign
evolution,valueengineering,changeorders,orothersupplementalinstructionsduring
construction.DuringtheCorrectionPeriodandOnGoingOperations,theDesignIntentDocument
helpstheowner/operatorsunderstandtheoriginaldesignintent.Italsoprovidesthebenchmark
formaintenance,repair,andreplacementdecisions.TheDesignIntentDocumentisdevelopedby
theOwner.

BasisofDesign(2.05):TheBasisofDesignisanarrativedescriptionofhowthesystemswillbe
designedinordertoachievethedesignintentacceptancecriteria.TheBasisofDesignisdeveloped
bytheDesigners.

CommissioningDesignReview(2.06):AtleastonceduringeachoftheSchematicDesign,Design
Development,andConstructionDocumentsPhases,theCommissioningLeaderwillreviewthe
designprogressagainstthegoalsoftheDesignIntentDocument.CommissioningDesignReview
commentsshallbedocumentedinwritingandresponsespreparedbytheDesigners.
1) PerformanceCheck:CommissioningTeamshallreviewdesignasdocumentedtoverify
thatitmeetsthephysicaloutcomesandoperationalperformancedefinedatthatphase.
Performanceareasinclude,butarenotlimitedto:
a) DesignIntentacceptancecriteriaforallrequiredoradditionalpursuedguidelines

DesignandConstructionCommissioningPlanTemplate
Page9
TheStateofMinnesotaSustainableBuildingGuidelines

b) Requirementsforspecificoperationalscenariosofthebuilding
c) Regularmaintenance,cleaning,andservicing(includingISO14000cleaning
materials)
2) Measurability/TestabilityCheck:CommissioningTeamshallreviewdesignas
documentedtoverifythatitmeetscriteriafortestingandverificationofperformance
forDesignandConstructionCommissioningaswellasOperationsCommissioning
monitoringduringOngoingOccupancy.Performanceareasinclude,butarenotlimited
to:
a) MeasurementsandtestingrequiredduringallphasesofDesignandConstruction
Commissioning.
b) Measurement,monitoring,andcontrolofenergy,water,indoorenvironmental
qualityduringOngoingOccupancy.

CoordinatewithOperationsCommissioningRequirements(2.07):CooperatewiththeOperations
CommissioningTeambyincorporatingdesignfeaturesrequiredtoperformOperations
Commissioning.RefertoGuidelineP.5OperationsCommissioningforanunderstandingofwhat
thesefeaturesmightbe.

4.2.5 DESIGNDEVELOPMENT
InconjunctionwiththegeneralCommissioningactivities,thefollowingarespecificCommissioning
activitiesaddressedinduringDesignDevelopment:

CommissioningDesignReview(2.06):Refertopreviousdescription.

CoordinatewithOperationsCommissioningRequirements(2.07):Refertopreviousdescription.

ListofI/ODataPoints(2.08):TheDesignerwillsubmitalistofinputandoutput(I/O)datapointsas
partofoutcomedocumentationbeforetheendofDesignDevelopmenttotheCommissioning
Leader.Theseshallbesubmittedforallcomputerbasedcontrolsystems,e.g.,HVAC,lighting
controls,etc.

Measurement&VerificationBaseline(2.09):TheMeasurementandVerificationBaseline(s)are
usedtocalculatesavingsaspartoftheMeasurementandVerificationProcess.Seedetailsof
MeasurementandVerificationunderGuidelineP.5OperationsCommissioning.

4.2.6 CONSTRUCTIONDOCUMENTS
InconjunctionwiththegeneralCommissioningactivities,thefollowingarespecificCommissioning
activitiesaddressedinduringConstructionDocumentsdevelopment:

CommissioningDesignReview(2.06):Refertopreviousdescription.

CoordinatewithOperationsCommissioningRequirements(2.07):Refertopreviousdescription.

IncorporateCommissioningCriteria&ScopeintoConstructionDocuments(2.10):TheDesignerwill
incorporateacommissioningspecificationsectionintoDivision1oftheprojectmanual.The
commissioningspecificationshalldefineandelaborateonthecontractorsresponsibilitiesas

DesignandConstructionCommissioningPlanTemplate
Page10
TheStateofMinnesotaSustainableBuildingGuidelines

definedintheCommissioningPlan.IncorporatetheCommissioningPlanintothecontract
documentsbyreferenceinordertocommunicatethecontextofthecommissioningspecification
andinformationregardingotherteammemberresponsibilities.Thecommissioningspecification
willbedevelopedbytheCommissioningLeader.

4.2.7 CONSTRUCTION
InconjunctionwiththegeneralCommissioningactivities,thefollowingarespecificCommissioning
activitiesaddressedinduringConstruction:

CoordinatewithOperationsCommissioningRequirements(2.07):Refertopreviousdescription.

ReviewContractorsSubmittals(2.11):TheCommissioningLeaderwillreviewContractors
submittalsforcommissionedequipmentandothercommissioneddesignelements.Thesedesign
reviewsincludeageneralqualityreview,disciplinecoordination,specificationcoordination,and
adherencetothedesignintent.

VerifyInstallation(2.12):TheContractorwillcompletecustomizedsysteminstallationchecklists
priortoacceptancebytheowner.Theinstallationchecklistswillbedevelopedbythe
CommissioningLeaderandwillbeincludedintheDesignandConstructionCommissioningPlan.

VerifyFunctionalPerformance(2.13):TheContractorwillcompleteallofthecustomizedsystem
functionalperformancetestprocedurespriortosystemacceptancebytheowner.The
CommissioningLeaderwillfacilitatetheContractorsimplementationofthesetests.Thefunctional
performancetestprocedureswillbedevelopedbytheCommissioningLeaderandwillbeincluded
theDesignandConstructionCommissioningPlan.

VerifyO&MDocumentation(2.14):TheO&Mdocumentationprovidesinformationneededto
understand,operate,andmaintainequipment.TheO&Mdocumentationisbythefacilitiesstaffas
referencethroughoutthelifeofthefacility.TheO&MdocumentationisprovidedbyContractors
andiscomponenttothesystemsmanuals.TheCommissioningLeaderwillverifythattheO&M
documentationprovidesthenecessaryinformationtooperationandmaintaintheequipmentprior
toconstructioncompletionandthesystemacceptancebytheOwner.

VerifyO&MTraining(2.15):ThefacilitiesstaffisprovidedwithO&Mtrainingtoensuretheyhave
theknowledgeandskillsrequiredtounderstand,operate,andmaintainthesystemsand
equipment.Typically,theDesignersprovidesystemstrainingandtheContractorsprovide
equipmenttraining.TheCommissioningLeaderwillverifythatthetrainingsessionsprovidethe
necessaryinformationtooperationandmaintainthefacilitypriortoconstructioncompletionand
systemacceptancebytheOwner.

CohesiveO&MSystemsManual(2.16):TheO&MSystemsManualprovidesinformationneededto
understand,operate,andmaintainthesystems.TheO&MSystemsManualsareforthefacilities
staffnotinvolvedinthedesignorconstructionprocessandutilizedthroughoutthelifeofthe
facility.TheO&MSystemsManualarecreatedbytheContractorsandarecontinuallyupdated
throughoutthedesignandconstructionphasesoftheproject.TheContractorwillcoordinatethe
contentsoftheCommissioningReportandcombineintothecohesiveO&MSystemsManualtobe
deliveredtotheOwner.

DesignandConstructionCommissioningPlanTemplate
Page11
TheStateofMinnesotaSustainableBuildingGuidelines

4.2.8 CORRECTIONPERIOD
InconjunctionwiththegeneralCommissioningactivities,thefollowingarespecificCommissioning
activitiesaddressedinduringtheCorrectionPeriod:

CoordinatewithOperationsCommissioningRequirements(2.07):Refertopreviousdescription.

DeferredVerification(2.17):Someofthesystemfunctionalperformancetestprocedureswillnot
bepracticalormeaningfultocompletepriortotheCorrectionPeriod.Thismaybedueto
constructionphasingorclimateconstraints.Thosetestproceduresshallbecompletedatan
appropriatetimeduringtheCorrectionPeriodbytheContractor.TheCommissioningLeaderwill
facilitatethesedeferredtestprocedures.

TenMonthO&MReview(2.18):TenmonthsintotheCorrectionPeriod,theCommissioningTeam
willreviewthebuildingoperationwiththeO&Mstaffandcreateaplanforresolutionof
outstandingcommissioningrelatedissues.

4.2.9 ONGOINGOPERATIONS
InconjunctionwiththegeneralCommissioningactivities,thefollowingarespecificCommissioning
activitiesaddressedinduringOnGoingOperations:

AddanyadditionalCommissioning
activitiesspecifictotheOnGoing
OperationsPhase.

4.3 CONSTRUCTIONAIRQUALITYMANAGEMENTPLAN

AdddescriptionsforConstructionAir
QualityManagementPlan(steps3.01
through3.09)

4.4 CORRECTIONPERIODAIRQUALITYMANAGEMENTPLAN

AdddescriptionsforCorrectionPeriod
AirQualityManagementPlan(steps
4.01to4.02)

4.5 CONSTRUCTIONWASTEMANAGEMENTPLAN

DesignandConstructionCommissioningPlanTemplate
Page12
TheStateofMinnesotaSustainableBuildingGuidelines

AdddescriptionsforConstruction
WasteManagementPlan(steps6.01
through6.03)

4.6 ROLESANDRESPONSIBILITIES
Understandingandclearlydefiningtheroleofeachteammemberiscrucialtosuccessfullyimplementing
theCommissioningProcess.Theserolesandresponsibilitiesshouldbecontractuallydefinedbetween
the(1)OwnerandtheContractorand(2)OwnerandtheDesigners.

TherolesandresponsibilitiesfortheCommissioningLeader,FacilitiesOperationsManager(FOM),
Designers,Contractors,andtheGuidelineLeaderaredefinedbelow:


TheSuggestedImplementationispresentedintheformofthe
attachedDesignandConstructionCommissioningmatrix.

RolesandresponsibilitiesforeachCommissioningTeammember
areflexibleandneedtobedefinedaspartoftheprojectspecific
CommissioningPlan.However,someteammembersare
prohibitedfromperformingsomeoftheactivitiesduetoinherent
conflictsofinterest.

DesignandConstructionCommissioningPlanTemplate
Page13
TheStateofMinnesotaSustainableBuildingGuidelines

4.6.1 GENERALCOMMISSIONINGACTIVITIES

GENERAL Facilities
Commissioning
COMMISSIONING Operations ProjectManager Designers Contractors GuidelineLeader
Leader
ACTIVITIES Manager(FOM)
Design&Construction Developand Review Review Review Review Review
PhaseCommissioning Update
Plan
CommissioningReports Provideperiodic Provideacceptable Reviewperiodic Reviewand Reviewperiodic
Commissioning representation Commissioning commentonthe Commissioning
Reports withthemeans Reports Commissioning Reports
andauthorityto Leaders
prepareand Commissioning
coordinate reportsand
implementationof Commissioning
theCommissioning IssuesLog
Processasdetailed
intheContract
Documents

DesignandConstructionCommissioningPlanTemplate
Page14
TheStateofMinnesotaSustainableBuildingGuidelines

GENERAL Facilities
Commissioning
COMMISSIONING Operations ProjectManager Designers Contractors GuidelineLeader
Leader
ACTIVITIES Manager(FOM)
SubmitOutcome Provideoutcome Submitthe
Documentation documentation Outcome
from Documentationas
Commissioning requiredbythe
activities MSBGattheend
ofeachphaseof
thedesignand
construction
process.

Interpretand
provideguidance
relevanttothe
implementation
Minnesota
Sustainable
BuildingGuidelines
(MSBG)
Meetings Conductand Participate Participate ParticipateinPre Participateinthe Participate
document Design,Schematic preconstruction
Commissioning Design,Design and
Coordination Development Commissioning
Meetings Phasecoordination Teammeetings
andreview
Conductand meetings
document
Commissioning Attendtheprebid
KickoffMeetings andpre
duringthepre construction
designandpre meetingsas
construction scheduledbythe
phases Commissioning
Leader

DesignandConstructionCommissioningPlanTemplate
Page15
TheStateofMinnesotaSustainableBuildingGuidelines

4.6.2 AGENCYPLANNING

Facilities
Commissioning
AGENCYPLANNING Operations ProjectManager Designers Contractors GuidelineLeader
Leader
Manager(FOM)
PlanningBaseline AdvisesOwner Assistsin Assistsin Develops
development development

4.6.3 PREDESIGN/PROGRAMMING

Facilities
Commissioning
PREDESIGN/PROGRAMMING Operations ProjectManager Designers Contractors GuidelineLeader
Leader
Manager(FOM)
EngageActingCommissioning Organize,lead, Participates Participates Participates Participates
Team andengage
Commissioning
Team
ProgrammingBaseline AdvisesOwner Assistsin Assistsin Develops
development development

DesignandConstructionCommissioningPlanTemplate
Page16
TheStateofMinnesotaSustainableBuildingGuidelines

4.6.4 PREDESIGN/SITESELECTION

Facilities
Commissioning
PREDESIGN/SITESELECTION Operations ProjectManager Designers Contractors GuidelineLeader
Leader
Manager(FOM)
EngageActingCommissioning Organize,lead, Participates Participates Participates Participates
Team andengage
Commissioning
Team
ProgrammingBaseline AdvisesOwner Assistsin Assistsin Develops
development development
ReviewSiteAlternativesfor Reviewtoensure
AbilitytoAchievePerformance thatthatsystems
Goals being
commissioned
canachievetheir
DesignIntent
criteria

4.6.5 SCHEMATICDESIGNPHASE

Facilities
Commissioning
SCHEMATICDESIGNPHASE Operations ProjectManager Designers Contractors GuidelineLeader
Leader
Manager(FOM)
DesignBaseline AdvisesOwner Assistsin Assistsin Develops
development development
EngageActingCommissioning Organize,lead, Participates Participates Participates Participates
Team andengage
Commissioning
Team

DesignandConstructionCommissioningPlanTemplate
Page17
TheStateofMinnesotaSustainableBuildingGuidelines

Facilities
Commissioning
SCHEMATICDESIGNPHASE Operations ProjectManager Designers Contractors GuidelineLeader
Leader
Manager(FOM)
DesignIntentDocument Facilitateand Approve Approve Participateand
documentDID assistinthe
documentationof
theDID
BasisofDesign Approve Approve Developsbased
ontheDID
CommissioningDesignReview Reviewschematic Respondto
design Commissioning
documentsin Teamdesign
accordancewith reviewcomments
theDID andotherissues
inatimely
Complete manner
Performance
Check

Complete
Measurability&
TestabilityCheck
CoordinatewithOperations AssistDesigners Cooperatewith
CommissioningRequirements theOperations
Commissioning
Teamby
incorporating
designfeatures
requiredto
perform
Operations
Commissioning

DesignandConstructionCommissioningPlanTemplate
Page18
TheStateofMinnesotaSustainableBuildingGuidelines

4.6.6 DESIGNDEVELOPMENT

Facilities
Commissioning
DESIGNDEVELOPMENT Operations ProjectManager Designers Contractors GuidelineLeader
Leader
Manager(FOM)
CommissioningDesignReview Reviewschematic Respondto Verify
design Commissioning performancethat
documentsin Teamdesign isnotcovered
accordancewith reviewcomments under
theDID andotherissues Commissioning
inatimely Section
Complete manner
Performance
Check Reviewand
incorporate(as
Complete appropriate)the
Measurability& Commissioning
TestabilityCheck Leaders
submittalreviews
CoordinatewithOperations AssistDesigners Cooperatewith
CommissioningRequirements theOperations
Commissioning
Teamby
incorporating
designfeatures
requiredto
perform
Operations
Commissioning
ListofI/ODataPoints ReviewI/OData ProvidelistofI/O
Pointsfor datapointstothe
completeness Commissioning
andaccordance Leaderforreview
withtheDID

DesignandConstructionCommissioningPlanTemplate
Page19
TheStateofMinnesotaSustainableBuildingGuidelines

Facilities
Commissioning
DESIGNDEVELOPMENT Operations ProjectManager Designers Contractors GuidelineLeader
Leader
Manager(FOM)
Measurements&Verification ReviewM&Vplan DevelopM&V
Baseline andbaseline planandbaseline

4.6.7 CONSTRUCTIONDOCUMENTS

Facilities
Commissioning
CONSTRUCTIONDOCUMENTS Operations ProjectManager Designers Contractors GuidelineLeader
Leader
Manager(FOM)
CommissioningDesignReview Reviewdesign Provide
documentsin submittalsto
accordancewith Commissioning
theDID Leaderforreview

Review
contractors
submittalsfor
completeness
andaccordance
withtheDID
CoordinatewithOperations AssistDesigners Cooperatewith
CommissioningRequirements theOperations
Commissioning
Teamby
incorporating
designfeatures
requiredto
perform
Operations
Commissioning

DesignandConstructionCommissioningPlanTemplate
Page20
TheStateofMinnesotaSustainableBuildingGuidelines

Facilities
Commissioning
CONSTRUCTIONDOCUMENTS Operations ProjectManager Designers Contractors GuidelineLeader
Leader
Manager(FOM)
IncorporateCommissioning Verifythatthe Includecostsfor Preparethe Provide
Criteria&Scopeinto Commissioning the Construction Commissioning
ConstructionDocuments Processisclearly Commissioning Documentswith criteriaandscope
definedinall Processinthe theintegrationof inall
scopesofwork contractprice the subcontractors
Commissioning contracts
Assistinthe criteriaandscope
integrationofthe Includecostsfor
Commissioning Specifyandverify the
criteriaandscope theO&M Commissioning
intoconstruction documentation Processinthe
documents hasbeen contractprice
adequately
Assistin detailedinthe Include
integrating construction Commissioning
Commissioning documents criteria,scope,
activitiesintothe andactivitiesin
projectschedule eachpurchase
orderor
subcontract
written

Obtain
cooperationand
participationof
allsubcontractors
and
manufacturers

Include
Commissioning
activitiesintothe
projectschedule

DesignandConstructionCommissioningPlanTemplate
Page21
TheStateofMinnesotaSustainableBuildingGuidelines

Facilities
Commissioning
CONSTRUCTIONDOCUMENTS Operations ProjectManager Designers Contractors GuidelineLeader
Leader
Manager(FOM)
IncorporateCommissioning Assistin
Criteria&Scopeinto integrating
ConstructionDocuments Commissioning
activitiesintothe
CONTINUED projectschedule

4.6.8 CONSTRUCTION

Facilities
Commissioning
CONSTRUCTION Operations ProjectManager Designers Contractors GuidelineLeader
Leader
Manager(FOM)
CoordinatewithOperations AssistDesigners Cooperatewith
CommissioningRequirements theOperations
Commissioning
Teamby
incorporating
designfeatures
requiredto
perform
Operations
Commissioning
ReviewContractorsSubmittals Reviewand Reviewand Reviewand Reviewand Provide
Commentin Comment Comment Comment submittalstothe
accordancewith Owner,
theDID Designers,and
Commissioning
Leader

DesignandConstructionCommissioningPlanTemplate
Page22
TheStateofMinnesotaSustainableBuildingGuidelines

Facilities
Commissioning
CONSTRUCTION Operations ProjectManager Designers Contractors GuidelineLeader
Leader
Manager(FOM)
VerifyInstallation Verify Reviewand Completeand
installationby acceptrecord submitthe
reviewing drawingsas installation
successful requiredby checklists
completionof construction
installation documents Continuously
checklists maintainthe
recorddrawings
Periodically
reviewRecord
Drawingsfor

accuracy

DesignandConstructionCommissioningPlanTemplate
Page23
TheStateofMinnesotaSustainableBuildingGuidelines

Facilities
Commissioning
CONSTRUCTION Operations ProjectManager Designers Contractors GuidelineLeader
Leader
Manager(FOM)
VerifyFunctionalPerformance VerifyFunctional Reviewtest Notifythe
Performanceby procedures Commissioning
facilitating submittedbythe Leaderwhenthe
successful Contractors systemsand
completionof equipmentare
functional Reviewand readyfortesting
performance commentonthe
tests Commissioning Implementthe
Leaders functional
Develop,track, Commissioning performance
andupdate IssuesLog tests
Commissioning
IssuesLog Remedy
deficiencies
Facilitate identifiedbythe
retestingof Commissioning
functional Leaderduringthe
performance completionofthe
testing installation
checklistsand
functional
performance
testing

DesignandConstructionCommissioningPlanTemplate
Page24
TheStateofMinnesotaSustainableBuildingGuidelines

Facilities
Commissioning
CONSTRUCTION Operations ProjectManager Designers Contractors GuidelineLeader
Leader
Manager(FOM)
VerifyO&MDocumentation Verifythatthe AcceptsO&M AcceptsO&M SubmitO&M
contractor Documentation Documentation documentation
createsand
submitsO&M
manualsforthe
ownerpriorto
construction
completionand
system
acceptanceby
theowner
VerifyO&MTraining Facilitate Providestaffto Providestaffto Participateinthe Implementthe
trainingsessions attendO&M attendO&M trainingsessions O&Mtrainingas
training training presentinga detailedinthe
systemsoverview contract
documents

CohesiveO&MSystemsManual VerifyO&M AcceptsO&M AcceptsO&M Assistin CompleteO&M
SystemManuals SystemsManual SystemsManual developmentof SystemsManuals
for Documentation Documentation O&MSystems
completeness Manual
andaccordance
withtheDID

DesignandConstructionCommissioningPlanTemplate
Page25
TheStateofMinnesotaSustainableBuildingGuidelines

4.6.9 CORRECTIONPERIOD

Facilities
Commissioning
CORRECTIONPERIOD Operations ProjectManager Designers Contractors GuidelineLeader
Leader
Manager(FOM)
CoordinatewithOperations AssistDesigners Cooperatewith
CommissioningRequirements theOperations
Commissioning
Teamby
incorporating
designfeatures
requiredto
perform
Operations
Commissioning
DeferredVerification Facilitate Implement
deferred deferred
verificationof functional
functional performance
performance testing
testing

Develop,track,
andupdate
Commissioning
IssuesLog
TenMonthO&MReview Participatein10 Participatein10 Participatein10 Participatein10 Participatein10
MonthO&M MonthO&M MonthO&M MonthO&M MonthO&M
Review Review Review Review Review

DesignandConstructionCommissioningPlanTemplate
Page26
TheStateofMinnesotaSustainableBuildingGuidelines

Facilities
Commissioning
CORRECTIONPERIOD Operations ProjectManager Designers Contractors GuidelineLeader
Leader
Manager(FOM)
FinalCommissioningReport DevelopFinal ReviewtheFinal ReviewtheFinal
Commissioning Commissioning Commissioning
Report Reports(as Reports(as
necessary) necessary)
Updatefinal
Commissioning
Report(as
necessary)

Addtherolesandresponsibilitiesrelevanttothe
1) ConstructionPhaseAirQualityManagement,
2) CorrectionPeriodAirQualityManagement,
3) ConstructionWasteManagement
4) CorrectionPeriodUserComfort&SatisfactionAssessment

DesignandConstructionCommissioningPlanTemplate
Page27
TheStateofMinnesotaSustainableBuildingGuidelines

4.6.10 ONGOINGOPERATIONS

Facilities
Commissioning
ONGOINGOPERATIONS Operations ProjectManager Designers Contractors GuidelineLeader
Leader
Manager(FOM)
AddCommissioningTask
AddCommissioningTask
AddCommissioningTask

4.6.11 CONSTRUCTIONAIRQUALITYMANAGEMENTPLAN

Facilities
CONSTRUCTIONAIRQUALITY Commissioning
Operations ProjectManager Designers Contractors GuidelineLeader
MANAGEMENTPLAN Leader
Manager(FOM)
AddCommissioningTask
AddCommissioningTask
AddCommissioningTask

4.6.12 CORRECTIONPERIODAIRQUALITYMANAGEMENTPLAN

Facilities
CORRECTIONPERIODAIR Commissioning
Operations ProjectManager Designers Contractors GuidelineLeader
QUALITYMANAGEMENTPLAN Leader
Manager(FOM)
AddCommissioningTask
AddCommissioningTask
AddCommissioningTask

DesignandConstructionCommissioningPlanTemplate
Page28
TheStateofMinnesotaSustainableBuildingGuidelines

4.6.13 CONSTRUCTIONWASTEMANAGEMENTPLAN

Facilities
CONSTRUCTIONWASTE Commissioning
Operations ProjectManager Designers Contractors GuidelineLeader
MANAGEMENTPLAN Leader
Manager(FOM)
AddCommissioningTask
AddCommissioningTask
AddCommissioningTask

DesignandConstructionCommissioningPlanTemplate
Page29
TheStateofMinnesotaSustainableBuildingGuidelines

5 SUPPORTINGCOMMISSIONINGDOCUMENTATION
5.1 B3MSBGTrackingTool(www.msbgtracking.com)
5.2 AppendixP1SuggestedImplementationforAllPerformance
ManagementGuidelines
5.3 AppendixP4DesignandConstructionCommissioningSupporting
Information
5.4 AppendixP5DesignandConstructionCommissioningMatrix

DesignandConstructionCommissioningPlanTemplate
Page30
TheStateofMinnesotaSustainableBuildingGuidelines










DESIGN&CONSTRUCTIONPHASE
COMMISSIONINGPLAN
CONSTRUCTIONAIRQUALITYMANAGEMENTPLANTEMPLATE

BaseduponB3MinnesotaSustainableBuildingGuidelinesVERSION2.1




















Notestothereaderhavebeenaddedtothisdocument
withinnumeroustextboxessuchasthis.These
textboxescontainreferencestosupporting
documentation,suggestions,and/orinstructions
pertainingtotheCommissioningProcess
ConstructionAirQualityManagementPlan.Theyare
intendedtobedeletedoncethetemplateis
customizedforaparticularproject.

DesignandConstructionCommissioningPlanConstructionAirQualityManagementPlan
Page1
TheStateofMinnesotaSustainableBuildingGuidelines

TABLEOFCONTENTS

1 Introduction...............................................................................................................................................................................3

2 ProtectStoredAbsorptiveMaterials(3.02).................................................................................................................4

3 ReplaceFiltrationMedia(3.03).........................................................................................................................................5

4 TemporaryConstructionVentilation(3.04)................................................................................................................8

5 ProtectHVACSystem(3.05).............................................................................................................................................10

6 OffsiteProductPreconditioning(3.06)........................................................................................................................11

7 RemoveMoistureDamagedMaterials(3.07)............................................................................................................14

8 ProtectPorousMaterials(3.08)......................................................................................................................................16

9 BuildingFlushoutPeriod(3.09)....................................................................................................................................18

10 Appendix...................................................................................................................................................................................19

10.1 Design&ConstructionCommissioningMatrixActivities&Responsibilities...........................19

DesignandConstructionCommissioningPlanConstructionAirQualityManagementPlan
Page2
TheStateofMinnesotaSustainableBuildingGuidelines

1 Introduction

TheConstructionAirQualityManagementPlanispartoftheDesignand
ConstructionCommissioningPlan.Itsintentistodefinepracticestopreventthe
introductionofairqualityproblemsasaresultoftheconstructionprocess.A
ConstructionAirQualityspecificationandtheConstructionAirQualityManagement
Planshouldoutline:

1) ProtectingStoredAbsorptiveMaterials
2) ReplacingFiltrationMedia
3) TemporaryConstructionVentilation
4) ProtectingHVACSystem
5) OffsiteProductPreconditioning
6) RemovingMoistureDamagedMaterials
7) ProtectingPorousMaterials
8) BuildingFlushoutPeriod

TheConstructionAirQualityManagementPlanshouldbedevelopedduringdesign,
andtheresultingbiddocumentsshouldcomplywiththeConstructionAirQuality
ManagementPlan.

TheconstructionairqualityrequirementsmustmeettheSMACNAIAQGuidelinefor
OccupiedBuildingsunderConstruction.RequirementsincludeelementsforIAQ
protectionduringconstruction(FromCHPSsection01350,1.6).

PleaserefertotheDesign&ConstructionCommissioningMatrixActivities&
Responsibilities(referto10Appendix).ThismatrixoutlineswhentheConstruction
AirQualityManagementtasksshouldoccur.

ThefollowingsectionsshouldbeincludedintheConstructionAirQuality
ManagementPlan.Itisrecommendedthattheseheadingsbeused.Aspartof
implementingtheConstructionAirQualityManagementPlan,therequirements
definedinthePlanneedtobeincorporatedintotheconstructionspecificationsin
ordertocontractuallyobligateallcontractorsandsubcontractorstoparticipatein
thePlan.

Thenumberdesignationsinparentheses(e.g.3.01,3.02,3.03,etc.)arereferencesto
otherMSGBdocuments.ForexampleinAppendix4.1,theConstructionAirQuality
Managementtasksarereferencedbythesenumberdesignations.

Insertprojectcustomizedintroduction.

DesignandConstructionCommissioningPlanConstructionAirQualityManagementPlan
Page3
TheStateofMinnesotaSustainableBuildingGuidelines

2 ProtectStoredAbsorptiveMaterials(3.02)
2.1 ProcessesandProcedures

Protectstoredonsiteorinstalledabsorptivematerialsfrommoisturedamage.

Provideadetailednarrativedescribingtheprojectsmeansofprotectingstored
absorptivematerialsfrommoisturedamage.UseTable1AbsorptiveMaterialsto
provideaninventoryofallabsorptivematerialsplannedforuseintheprojectand
theintendedpreinstallationstorageandpostinstallationprotectionofthose
materials.



InsertyourProcessesandProceduresalongwithassignedRolesandResponsibilitiestoensure
thattheserequirementswillbeachieved.

# DescriptionofAbsorptive PlanforPreventingMoisture
PreInstallationStorage
Materials DamageafterInstallation
1
2
3
4
5
Table1AbsorptiveMaterials

2.2 EndofProjectSummary

Attheendofconstruction,includeabriefsummaryoftheprojectsmeansof
protectingstoredabsorptivematerials,includecaptionedphotostohighlightthe
ConstructionAirQualityManagementPlanpractices,andprovideinformation
regardingspecialconsiderations,notes,oradditionalcomments.



InsertyourEndofProjectSummaryhere.

DesignandConstructionCommissioningPlanConstructionAirQualityManagementPlan
Page4
TheStateofMinnesotaSustainableBuildingGuidelines

3 ReplaceFiltrationMedia(3.03)
3.1 ProcessesandProcedures

Replaceallfiltrationmediaimmediatelypriortooccupancy.

Iftheairhandlingunitsareutilizedduringconstruction,alltheairfiltrationmedia
shouldbereplaced.Iftheairhandlingunitsarenotusedduringconstruction,clean
filtersmeetingthecontractspecificationsshouldbeinstalledpriortostartup,
testing,andbalancing.



InsertyourProcessesandProceduresalongwithassignedRolesandResponsibilitiestoensure
thattheserequirementswillbeachieved.

DesignandConstructionCommissioningPlanConstructionAirQualityManagementPlan
Page5
TheStateofMinnesotaSustainableBuildingGuidelines


Indicationthatthe
FilterIdentification LocationofInstalled DateofFinalFilter
# FilterManufacturer FilterMERVRating FilterReplacedPrior
(ModelNumber) Filter Installation
toOccupancy1(Days)
1
2
3
4
5
1RecordhowmanydayspriortoofficialOwneroccupancy?
Table2FiltrationMediaReplacement

DesignandConstructionCommissioningPlanConstructionAirQualityManagementPlan
Page6
TheStateofMinnesotaSustainableBuildingGuidelines

3.2 EndofProjectSummary

Attheendofconstruction,submitdocumentationoftheprojects
replacementofallfiltermediaintabularformat(refertoTable2
FiltrationMediaReplacement).


InsertyourEndofProjectSummaryhere.

DesignandConstructionCommissioningPlanConstructionAirQualityManagementPlan
Page7
TheStateofMinnesotaSustainableBuildingGuidelines

4 TemporaryConstructionVentilation(3.04)
4.1 ProcessesandProcedures

Provideadetailednarrativedescribingtheprojectstemporaryconstruction
ventilation.

Consideringtemporaryconstructionventilation,refertothefollowingitemsthat
shouldbeincludedinthespecificationsandConstructionAirQualityManagement
Plan:

1) Maintainsufficienttemporaryventilationofareaswherematerialsarebeing
usedthatemitVOCs.
2) Maintainventilationcontinuouslyduringinstallation,anduntilemissions
dissipateafterinstallation.Ifcontinuousventilationisnotpossiblevia
building'sHVACsystem(s)thenventilationshallbesuppliedviaopen
windowsandtemporaryfans,sufficienttoprovidenolessthanthreeair
changesperhour.
3) Periodafterinstallationshallbesufficienttodissipateodorsandelevated
concentrationsofVOCs.Wherenospecificperiodisstatedinthe
Specifications,atimeperiodof72hoursshallbeused.
4) Ventilateareasdirectlytooutside.Ventilationtootherenclosedareasisnot
acceptable.

UsingTable3TemporaryConstructionVentilation,providerequireddetailsforall
VOCemittingmaterialsintendedtobeusedduringconstruction.



InsertyourProcessesandProceduresalongwithassignedRolesandResponsibilitiestoensure
thattheserequirementswillbeachieved.

DesignandConstructionCommissioningPlanConstructionAirQualityManagementPlan
Page8
TheStateofMinnesotaSustainableBuildingGuidelines



CapacityofTemporary
DescriptionofVOC LocationofVOC DurationofTemporary
VentilationSystem
# EmittingMaterials EmittingMaterials Ventilation
(ACH)
1
2
3
4
5
Table3TemporaryConstructionVentilation

4.2 EndofProjectSummary

Attheendofconstruction,includeabriefsummaryoftheprojectstemporary
constructionventilation,includecaptionedphotostohighlighttheConstructionAir
QualityManagementPlanpractices,andprovideinformationregardingspecial
considerations,notes,oradditionalcomments.


InsertyourEndofProjectSummaryhere.

DesignandConstructionCommissioningPlanConstructionAirQualityManagementPlan
Page9
TheStateofMinnesotaSustainableBuildingGuidelines

5 ProtectHVACSystem(3.05)
5.1 ProcessesandProcedures

ProvideadetailednarrativedescribingthemechanismsbywhichHVACsystem
equipmentanddistributionsystems(ductsandpipes)willbeprotectedfrom
accumulatingdirtanddebrisduringconstruction.ThisappliestoallHVACsystems
whichareputintoserviceduringconstruction.

ConsideringhowtoprotecttheHVACsystem,refertothefollowingitemsthatshould
beincludedinthespecificationsandConstructionAirQualityManagementPlan:
1) Duringdustproducingactivities(e.g.,drywallinstallationandfinishing),
turnventilationsystemoffandprotectopeningsinsupplyandreturnHVAC
systemfromdustinfiltration.
2) Providetemporaryventilationasrequired.
3) Sealductsduringtransportation,delivery,andconstructiontoprevent
accumulationofconstructiondustandconstructiondebrisinsideducts.

ProvideadetailednarrativedescribingthemechanismsbywhichHVACsystem
equipmentanddistributionsystems(ductsandpipes)willbeprotectedfrom
accumulatingdirtanddebrisduringconstruction.ThisappliestoallHVACsystems,
notjustHVACsystemwhichisputintoserviceduringconstruction.Inaddition,
documentthetemporaryconstructionventilationwithTable3below.



InsertyourProcessesandProceduresalongwithassignedRolesandResponsibilitiestoensure
thattheserequirementswillbeachieved.

5.2 EndofProjectSummary

Attheendofconstruction,includeabriefsummaryoftheprojectsmeansof
protectingtheHVACsystem,includecaptionedphotostohighlighttheConstruction
AirQualityManagementPlanpractices,andprovideinformationregardingspecial
considerations,notes,oradditionalcomments.


InsertyourEndofProjectSummaryhere.

DesignandConstructionCommissioningPlanConstructionAirQualityManagementPlan
Page10
TheStateofMinnesotaSustainableBuildingGuidelines

6 OffsiteProductPreconditioning(3.06)
6.1 ProcessesandProcedures

Provideadetailednarrativedescribingtheprojectsmeansofoffsiteproduct
preconditioning,includingadescriptionoftheoffsiteventilationsystems(e.g.,type,
airchangesperhour,temperaturecontrol,etc.).

Consideringoffsiteproductpreconditioning,refertothefollowingitemsthatshould
beincludedinthespecificationsandConstructionAirQualityManagementPlan:
1) AllproductswhichhaveodorsandsignificantVOCemissionsshallbe
preconditionedoffsitepriortodeliverytotheProjectsite.Allowproductsto
offgasinadry,wellventilatedspacefor14calendardaystoallowfor
reasonabledissipationofodorsandemissions.
2) Conditionproductswithoutcontainersandpackagingtomaximizeoff
gassingofVOCs
3) Conditionproductsinventilatedwarehouseorotherbuilding.Complywith
substitutionrequirementsforconsiderationofotherlocations.

UsingTable4OffsiteProductPreconditioning,documentthepreconditioning
detailsforallproductswithsignificantVOCemissionandotherodoroffgassing
propertiestobeinstalledduringconstruction.



InsertyourProcessesandProceduresalongwithassignedRolesandResponsibilitiestoensure
thattheserequirementswillbeachieved.

DesignandConstructionCommissioningPlanConstructionAirQualityManagementPlan
Page11
TheStateofMinnesotaSustainableBuildingGuidelines

Locationto
Descriptionof EstimatedDate
whicheach Provisionsfor Durationof ProvisionsforRe
SignificantVOC ofShipment Space
# Productwillbe Unpackingfor Preconditioning packingforDeliveryto
Emitting&OtherOdor from Requirements1
Shippedfor Preconditioning Period ProjectSite
OffGassingProducts Manufacturer
Preconditioning
1
2
3
4
5
1Forexample,thefloorspace,volume,etc.requiredforpreconditioning
Table4OffsiteProductPreconditioning

DesignandConstructionCommissioningPlanConstructionAirQualityManagementPlan
Page12
TheStateofMinnesotaSustainableBuildingGuidelines

6.2 EndofProjectSummary

Attheendofconstruction,includeabriefsummaryoftheprojectsoffsiteproduct
preconditioning;includedescriptionsofoffsiteproducts,meansofpreconditioning
andlocations,captionedphotostohighlighttheConstructionAirQuality
ManagementPlanpractices,andprovideinformationregardingspecial
considerations,notes,oradditionalcomments.


InsertyourEndofProjectSummaryhere.

DesignandConstructionCommissioningPlanConstructionAirQualityManagementPlan
Page13
TheStateofMinnesotaSustainableBuildingGuidelines

7 RemoveMoistureDamagedMaterials(3.07)
7.1 ProcessesandProcedures

Provideadetailednarrativedescribingtheprojectsprocessforidentifying(regular
inspections),removing,anddisposingofmoisturedamagedmaterialsand
replacementprocedures.Narrativeshouldincludethenameoftheresponsibleparty
forthisactivity.Consideringtheremovalofmoisturedamagedmaterials,referto
thefollowingitemsthatshouldbeincludedinthespecificationsandConstructionAir
QualityManagementPlan:
1) Materialswithevidenceofmoisturedamage,includingstains,arenot
acceptable.Thisincludesbothstoredandinstalledmaterials.Immediately
removeallsuchmaterialsfromthesiteandproperlydispose.
2) Takespecialcaretopreventaccumulationofmoistureoninstalledmaterials
andwithinpackagingduringdelivery,storage,andhandlingtoprevent
developmentofmoldsandmildewonpackagingandonproducts.
3) Immediatelyremovefromsiteandproperlydisposeofmaterialsshowing
signsofmoldand/orsignsofmildew,includingmaterialswithmoisture
stains.
4) Replacemoldymaterialswithnew,undamagedmaterials.

Provideadetailednarrativedescribingtheprojectsprocessforidentifying(regular
inspections),removing,anddisposingofmoisturedamagedmaterialsand
replacementprocedures.Narrativeshouldincludethenameoftheresponsibleparty
forthisactivity.



InsertyourProcessesandProceduresalongwithassignedRolesandResponsibilitiestoensure
thattheserequirementswillbeachieved.

7.2 EndofProjectSummary

Attheendofconstruction,usingTable5 MoistureDamagedMaterials,includea
briefsummaryoftheprojectsmoisturedamagedmaterials,replacement
occurrences,preventiveandcorrectiveprocedures,includecaptionedphotosto
highlighttheConstructionAirQualityManagementPlanpractices,andprovide
informationregardingspecialconsiderations,notes,oradditionalcomments.


InsertyourEndofProjectSummaryhere.

DesignandConstructionCommissioningPlanConstructionAirQualityManagementPlan
Page14
TheStateofMinnesotaSustainableBuildingGuidelines

Actionstakento
DescriptionofMoisture Dateof CauseofMoisture DescriptionofDisposal PreventSimilar
# DateofRemoval
DamagedMaterials1 Identification Damage Method2 MoistureDamageinthe
Future
1
2
3
4
5
1Includephotos
2Forexample,recyclinglandfill,etc.
Table5MoistureDamagedMaterials

DesignandConstructionCommissioningPlanConstructionAirQualityManagementPlan
Page15
TheStateofMinnesotaSustainableBuildingGuidelines

8 ProtectPorousMaterials(3.08)
8.1 ProcessesandProcedures

Provideadetailednarrativedescribingtheprojectsmeanstoprotectporous
materials.

Whereodorousand/orhighVOCemittingproductsareappliedonsite,applyprior
toinstallationofporousandfibrousmaterials.Wherethisisnotpossible,protect
porousmaterialswithpolyethylenevaporretarders.

Provideadetailednarrativedescribingtheprojectsmeanstoprotectporous
materials.UsingTable6PorousMaterialdocumentthefollowinginformation:
1) InventoryofallVOCemittingorodoremittingmaterialsandwheretheyare
tobeused
2) Inventoryofallporousandfibrousmaterialsandwheretheyaretobeused
3) Highlightlocationswherebothcategoriesofmaterialsaretobeusedinthe
samelocation
4) DescribemeansofpreventingtheabsorptionofVOCsand/orodorsbythe
porousandfibrousmaterialsineachoftheselocations.



InsertyourProcessesandProceduresalongwithassignedRolesandResponsibilitiestoensure
thattheserequirementswillbeachieved.

8.2 EndofProjectSummary

Attheendofconstruction,includeabriefsummaryoftheprojectsmeansof
protectingporousmaterials,includecaptionedphotostohighlighttheConstruction
AirQualityManagementPlanpractices,andprovideinformationregardingspecial
considerations,notes,oradditionalcomments.



InsertyourEndofProjectSummaryhere.

DesignandConstructionCommissioningPlanConstructionAirQualityManagementPlan
Page16
TheStateofMinnesotaSustainableBuildingGuidelines



VOCEmittingorOdorEmitting
Location Porous&FibrousMaterials DescriptionofAbsorptionPrevention1
Materials
1) 1)
Room100 2) 2)
3) 3)

1) 1)
Room101 2) 2)
3) 3)

1) 1)
Room102 2) 2)
3) 3)
1DescriptionofmeanstopreventabsorptionofVOCand/orodorsbyporous&fibrousmaterialsineachoftheselocations.
Table6PorousMaterials

DesignandConstructionCommissioningPlanConstructionAirQualityManagementPlan
Page17
TheStateofMinnesotaSustainableBuildingGuidelines

9 BuildingFlushoutPeriod(3.09)
9.1 ProcessesandProcedures

Provideadetailednarrativedescribingtheprojectspreoccupancyflushout
procedures.

ComplywithapreoccupancybuildingflushoutasdescribedinLEEDNCVersion2.2
whichstates,"Afterconstructionends,priortooccupancyandwithallinterior
finishesinstalled,performabuildingflushoutbysupplyingatotalairvolumeof
14,000cu.ft.ofoutdoorairpersquarefeetoffloorareawhilemaintainingan
internaltemperatureofatleast60Fandrelativehumiditynohigherthan60%."

(Source:LEEDNCVersion2.2,October2005,CreditEQ3.2FirstpartofOption1,
page323.)Note:Schedulethecompletionofinteriorfinishmaterialsandoccupancy
accordinglytoaccommodatetheflushoutperiod.

Provideadetailednarrativedescribingtheprojectspreoccupancyflushout
procedures.



InsertyourProcessesandProceduresalongwithassignedRolesandResponsibilitiestoensure
thattheserequirementswillbeachieved.

9.2 EndofProjectSummary

Attheendofconstruction,includeabriefsummaryofthebuildingflushoutperiod,
includedataregardingtemperature,airflow,anddurationofflushoutandprovide
informationregardingspecialconsiderations,notes,oradditionalcomments.



InsertyourEndofProjectSummaryhere.

DesignandConstructionCommissioningPlanConstructionAirQualityManagementPlan
Page18
TheStateofMinnesotaSustainableBuildingGuidelines

10 Appendix
10.1 Design&ConstructionCommissioningMatrixActivities&
Responsibilities

DesignandConstructionCommissioningPlanConstructionAirQualityManagementPlan
Page19
TheStateofMinnesotaSustainableBuildingGuidelines










DESIGN&CONSTRUCTIONPHASE
COMMISSIONINGPLAN
CONSTRUCTIONWASTEMANAGEMENTPLAN
TEMPLATE

BaseduponB3MinnesotaSustainableBuildingGuidelinesVERSION2.1



















Notestothereaderhavebeenaddedtothisdocument
withinnumeroustextboxessuchasthis.These
textboxescontainreferencestosupporting
documentation,suggestions,and/orinstructions
pertainingtotheCommissioningProcess
ConstructionWasteManagementPlan.Theyare
intendedtobedeletedoncethetemplateis
customizedforaparticularproject.

DesignandConstructionCommissioningPlanConstructionWasteManagementPlan
Page1
TheStateofMinnesotaSustainableBuildingGuidelines

TABLEOFCONTENTS

1 Introduction...............................................................................................................................................................................3

2 ConstructionWasteManagementSpecification(5.01)...........................................................................................4

3 DebrisDiversion(5.03).........................................................................................................................................................5

4 RecyclePackaging(5.04)......................................................................................................................................................6

5 APPENDIX...................................................................................................................................................................................7

5.1 Design&ConstructionCommissioningMatrixActivities&Responsibilities.....................................7

5.2 WorksheetM2ConstructionWasteRecyclingEconomics...........................................................................7

5.3 WorksheetM3PackagingWasteRecyclingEconomics.................................................................................7

DesignandConstructionCommissioningPlanConstructionWasteManagementPlan
Page2
TheStateofMinnesotaSustainableBuildingGuidelines

1 Introduction

TheintentoftheConstructionWasteManagementPlanistominimizeuseof
resourcesandnegativeenvironmentalimpactsthroughcarfulreductionand
managementofwastesgeneratedduringtheconstructionprocessandbuilding
occupancy.

TheConstructionWasteManagementPlanoutlines:
1) ConstructionWasteManagementSpecification
2) ConstructionWasteManagementPlan
3) DebrisPackaging
4) RecyclePackaging

PleasenotethatportionsofthistemplateareadaptedfromLEEDVersion2.0.

Thenumberdesignationsinparentheses(e.g.5.01,5.02,5.03,etc.)arereferencesto
otherMSBGdocuments.ForexampleinAppendix5.1,theConstructionWaste
Managementtasksarereferencedbythesenumberdesignations.




Insertprojectcustomizedintroduction.

DesignandConstructionCommissioningPlanConstructionWasteManagementPlan
Page3
TheStateofMinnesotaSustainableBuildingGuidelines

2 ConstructionWasteManagementSpecification(5.01)
2.1 ProcessesandProcedures

Provideadetailedspecificationdescribingtherequiredactivitiesandperformance
metricsforconstructionphasewastemanagementinthebiddocuments.The
specificationshouldincludetherequiredperformancecriteria:
1) ConstructionWaste:Minimizewastegeneratedfromconstruction,
renovationanddemolitionofbuildingsthroughdetailingandspecifications.
2) ConstructionWaste:Divertatleast75%(byweight)construction,
demolition,andlandclearingdebrisfromlandfilldisposal.
3) OperationsWaste:Reduceandrecycleatleast50%ofthewastegenerated
duringbuildingoperation.Providededicatedrecyclingareas,processingand
holdingspace,andreversedistributionspaceinthebuilding.

Ifapplicable,thespecificationshouldincludetherecommendedperformance
criteria:
4) ConstructionWaste:Reuse,recycleand/orsalvageanadditional15%(90%
totalbyweight)oftheconstruction,demolition,andlandclearingwaste.
5) PackagingWaste:Reduceandrecyclepackagingwasteassociatedwiththe
constructionprocess,andencouragemanufacturerstoshiptheirproduct
usingreusable,recyclable,returnable,orrecycledcontentpackaging.Reuse
orreturn50%ofallpackagingmaterial,byweight,tosuppliersor
manufacturers.
6) PackagingWaste:Returnanadditional25%(75%totalbyweight)ofall
packagingmaterialtosuppliersormanufacturers

Foradditionaldetails,pleaserefertoGuidelineM.3WasteReductionand
Management(http://www.msbg.umn.edu/m_3.html)andAppendixM1
SuggestedImplementationofAllMaterialandWasteGuidelines
(http://www.msbg.umn.edu/downloads_v2_0/6Materials_AppM1.pdf).



InsertyourProcessesandProceduresalongwithassignedRolesandResponsibilitiestoensure
thattheserequirementswillbeachieved.

DesignandConstructionCommissioningPlanConstructionWasteManagementPlan
Page4
TheStateofMinnesotaSustainableBuildingGuidelines

3 DebrisDiversion(5.03)
3.1 ProcessesandProcedures

Thegoalofdebrisdiversionistodivertconstruction,demolition,andlandcleaning
debrisawayfromlandfills.

Theconstruction,demolition,andlandclearingdebrisshouldbedocumentedusing
WorksheetM2ConstructionWasteRecyclingEconomics(seeAppendix5.2).
WorksheetM2ConstructionWasteRecyclingEconomicsdocumentsthefollowing:
1) Adescriptionofdiverted/recycledmaterials,
2) Wherethesematerialsweredivertedorrecycled,
3) Thequantityofdiverted/recycledmaterials(intonsorcubicyards),
4) Adescriptionoflandfillmaterial,
5) Thelandfillhaulerorthelandfilllocation,
6) Thequantityofthelandfillwaste.

PleaserefertoGuidelineM.3WasteReductionandManagement.GuidelineM.3
WasteReductionandManagementincludesalinktoWorksheetM2Construction
WasteRecyclingEconomics(Appendix5.2)whichappliestoConstructionWaste.



InsertyourProcessesandProceduresalongwithassignedRolesandResponsibilitiestoensure
thattheserequirementswillbeachieved.

3.2 EndofProjectSummary

TheM2worksheetshouldbestartedduringdemolitionandcontinuouslyupdated
throughouttheconstructionprocess.Attheendofconstruction,theM2worksheet
representsaprojecthistoryoftheconstruction,demolition,andlandclearingdebris.
Thisprojecthistorydemonstratesthattherequiredandrecommendedperformance
criteriaaresatisfiedattheendofconstruction.



InsertyourEndofProjectSummaryhere.

DesignandConstructionCommissioningPlanConstructionWasteManagementPlan
Page5
TheStateofMinnesotaSustainableBuildingGuidelines

4 RecyclePackaging(5.04)
4.1 ProcessesandProcedures

Thegoalistorecyclematerialsandequipmentpackaginggeneratedduring
construction.

TherecycledmaterialsandequipmentshouldbedocumentedusingWorksheetM3
PackagingWasteRecyclingEconomics(Appendix5.3)TheM3worksheetincludes:
1) Adescriptionofthepackagingandoperationswastediverted/recycled
materials,
2) Wherethesematerialsweredivertedorrecycled,
3) Thequantityofpackagingandoperationswastediverted/recycled
materials(intonsorcubicyards)
4) Adescriptionoflandfillmaterial,
5) Thelandfillhaulerorthelandfilllocation,
6) Thequantityofthelandfillwaste.

PleaserefertoGuidelineM.3WasteReductionandManagement.GuidelineM.3
WasteReductionandManagementincludesalinktoWorksheetM3Packaging
WasteRecyclingEconomics(Appendix5.3)whichappliestoPackagingand
OperationsWaste



InsertyourProcessesandProceduresalongwithassignedRolesandResponsibilitiestoensure
thattheserequirementswillbeachieved.

4.2 EndofProjectSummary

TheM3worksheetshouldbestartedduringdemolitionandcontinuouslyupdated
throughouttheconstructionprocess.Attheendofconstruction,theM3worksheet
representsaprojecthistoryofthepackingrecycling.Thisprojecthistory
demonstratesthattherequiredandrecommendedperformancecriteriaaresatisfied
attheendofconstruction.



InsertyourEndofProjectSummaryhere

DesignandConstructionCommissioningPlanConstructionWasteManagementPlan
Page6
TheStateofMinnesotaSustainableBuildingGuidelines

5 APPENDIX
5.1 Design&ConstructionCommissioningMatrixActivities&
Responsibilities
5.2 WorksheetM2ConstructionWasteRecyclingEconomics
5.3 WorksheetM3PackagingWasteRecyclingEconomics

DesignandConstructionCommissioningPlanConstructionWasteManagementPlan
Page7
TheStateofMinnesotaSustainableBuildingGuidelines










DESIGN&CONSTRUCTIONPHASE
COMMISSIONINGPLAN
CORRECTIVEPERIODAIRQUALITYMANAGEMENTPLAN
TEMPLATE

BaseduponB3MinnesotaSustainableBuildingGuidelinesVERSION2.1
















Notestothereaderhavebeenaddedtothisdocument
withinnumeroustextboxessuchasthis.These
textboxescontainreferencestosupporting
documentation,suggestions,and/orinstructions
pertainingtotheCommissioningProcessCorrection
PeriodAirQualityPlan.Theyareintendedtobe
deletedoncethetemplateiscustomizedfora
particularproject.

DesignandConstructionCommissioningPlanCorrectionPeriodAirQualityManagementPlan
Page1
TheStateofMinnesotaSustainableBuildingGuidelines

TABLEOFCONTENTS

1 Introduction...............................................................................................................................................................................3

2 CorrectionPeriodAirQualityManagementSpecification(4.01)........................................................................4

3 ThreeMonthBuildingAirQualityEvaluation&Modifications(4.02)..............................................................5

4 SixMonthBuildingAirQualityEvaluation&Modifications(4.03)....................................................................8

5 TenMonthBuildingAirQualityEvaluation&Modifications(4.04)................................................................11

6 Appendix...................................................................................................................................................................................14

6.1 Design&ConstructionCommissioningMatrixActivities&Responsibilities...................................14

DesignandConstructionCommissioningPlanCorrectionPeriodAirQualityManagementPlan
Page2
TheStateofMinnesotaSustainableBuildingGuidelines

1 Introduction


TheCorrectionPeriodAirQualityManagementPlanispartoftheDesignand
ConstructionCommissioningPlanandshallinvolveperiodicindoorairquality
testing.TheintentoftheConstructionAirQualityManagementPlanistoevaluate
thebuildingairqualitythreemonths,sixmonths,andtenmonthsafteroccupancy
withtestingthatverifiesthattheventilationsystemisbetterthanorwithindesign
guidelines.

PleaserefertotheDesign&ConstructionCommissioningMatrixActivities&
Responsibilities(refertoAppendix6.1).ThismatrixoutlineswhentheCorrection
PeriodAirQualityManagementtasksshouldoccur.

Thenumberdesignationsinparentheses(e.g.4.01,4.02,4.03,etc.)arereferencesto
otherMSBGdocuments.ForexampleinAppendix6.1,theCorrectionPeriodAir
QualityManagementtasksarereferencedbythesenumberdesignations.

Consider(recommended,notrequired),monitoringthreemonths,sixmonths,and
tenmonthsafteroccupancyofotherpollutantsonI.4guidelinelistwhicharenot
pollutantsthatdeterminetheventilationrate.Concentrationsshouldbeinguideline
rangeandbelowactionvalueforeachpollutant.Samplepollutantactionlevelsare
giveninAppendixI1.



Insertprojectcustomizedintroduction.

DesignandConstructionCommissioningPlanCorrectionPeriodAirQualityManagementPlan
Page3
TheStateofMinnesotaSustainableBuildingGuidelines

2 CorrectionPeriodAirQualityManagementSpecification(4.01)
2.1 ProcessesandProcedures

Duringthedesignphase,theteamshoulddeterminewhich,ifany,ofthe
responsibilitiesassociatedwiththeCorrectionPeriodAirQualityManagementPlan
willbeassignedtothebiddingcontractors.Ifthecontractorswillberesponsiblefor
anypartofthecorrectionperiodtestingormodifications,thedesignteamshould
prepareaCorrectionPeriodAirQualityManagementSpecificationforthecontract
documentsinordertoobligatethecontractorstofollowtheprovisionsofthis
CorrectionPeriodAirQualityManagementPlan.



InsertyourProcessesandProceduresalongwithassignedRolesandResponsibilitiestoensure
thattheserequirementswillbeachieved.

DesignandConstructionCommissioningPlanCorrectionPeriodAirQualityManagementPlan
Page4
TheStateofMinnesotaSustainableBuildingGuidelines

3 ThreeMonthBuildingAirQualityEvaluation&Modifications(4.02)
3.1 ProcessesandProcedures

Provideadetailednarrativedescribingtheindoorairqualitytestingplanand
strategiesatanintervalofthreemonthsafteroccupancy.Outlinespecificoccupied
zones,documentzonesquarefootage,locationsofspecificpollutants,CO2
concentrationsateachzone,andconcentrationlimits(refertoTable1aThree
MonthBuildingAirQuality).

ThreemonthsintotheCorrectionPeriod,measurethekeyfactorthatdetermines
ventilationrateforbuilding(majorpollutantand/orCO2)inallbuildingoccupied
zones.Occupiedzonesshallbe,ataminimum,oneperairhandlingsystem.No
singleoccupiedzoneshallbegreaterthan5,000squarefeet.Thetestingplanshall
takeintoaccounthighoccupancyspacesandthelocationsofspecificpollutant
sourcesandshallnotnecessarilydependoncombinedoraveragereturnair
concentrationsateachairhandler.
RecordCO2concentrationsineachzone.
IfCO2levelsareaboveexpectedvalues,additionalventilationmustbe
provideduntilconcentrationsfallbelowtheselevels.
RefertoLEEDNCVersion2.2ReferenceGuideIndoorAirQualityCredit2for
greaterdetail.



InsertyourProcessesandProceduresalongwithassignedRolesandResponsibilitiestoensure
thattheserequirementswillbeachieved.

DesignandConstructionCommissioningPlanCorrectionPeriodAirQualityManagementPlan
Page5
TheStateofMinnesotaSustainableBuildingGuidelines

3Month 6Month 10Month


CO2
Concentration Evaluation Evaluation Evaluation
DescriptionofOccupied ZoneSquare LocationsofSpecific
# Zone Footage(ft2) Pollutants Limits(PPM) CO2Concentration(PPM)
1
2
3
4
5
Table1aThreeMonthBuildingAirQuality

DesignandConstructionCommissioningPlanCorrectionPeriodAirQualityManagementPlan
Page6
TheStateofMinnesotaSustainableBuildingGuidelines

3.2 ThreeMonthSummary

Attheconclusionofthethreemonthevaluation,composeabriefsummaryofthe
testingresults(Table1a)andsystemmodificationsthatwerenecessarytoachieve
satisfactoryconcentrationlevels.



Insertyoursummaryhere.

DesignandConstructionCommissioningPlanCorrectionPeriodAirQualityManagementPlan
Page7
TheStateofMinnesotaSustainableBuildingGuidelines

4 SixMonthBuildingAirQualityEvaluation&Modifications(4.03)
4.1 ProcessesandProcedures

SixmonthsintotheCorrectionPeriod,repeattheIndoorAirQualitytesting
performedatthreemonthsandrecordfindingsinTable1b(i.e.,addmoredatato
Table1a).Makeanynecessarycorrectionsuntilconcentrationsfallbelowaction
levels.



InsertyourProcessesandProceduresalongwithassignedRolesandResponsibilitiestoensure
thattheserequirementswillbeachieved.

DesignandConstructionCommissioningPlanCorrectionPeriodAirQualityManagementPlan
Page8
TheStateofMinnesotaSustainableBuildingGuidelines

CO2 3Month 6Month 10Month


DescriptionofOccupied ZoneSquare LocationsofSpecific Evaluation Evaluation Evaluation
# Concentration
Zone Footage(ft2) Pollutants
Limits(PPM) CO2Concentration(PPM)
1
2
3
4
5
Table1bSixMonthBuildingAirQuality

DesignandConstructionCommissioningPlanCorrectionPeriodAirQualityManagementPlan
Page9
TheStateofMinnesotaSustainableBuildingGuidelines

4.2 SixMonthSummary

Attheconclusionofthesixmonthevaluation,composeabriefsummaryofthe
testingresults(Table1b)andsystemmodificationsthatwerenecessarytoachieve
satisfactoryconcentrationlevels.

Insertyoursummaryhere.

DesignandConstructionCommissioningPlanCorrectionPeriodAirQualityManagementPlan
Page10
TheStateofMinnesotaSustainableBuildingGuidelines

5 TenMonthBuildingAirQualityEvaluation&Modifications(4.04)
5.1 ProcessesandProcedures

TenmonthsintotheCorrectionPeriod,repeattheIndoorAirQualitytesting
performedatthreemonthsandrecordfindingsinTable1c(i.e.,addmoredatato
Table1b).Makeanynecessarycorrectionsuntilconcentrationsfallbelowaction
levels.



InsertyourProcessesandProceduresalongwithassignedRolesandResponsibilitiestoensure
thattheserequirementswillbeachieved.

DesignandConstructionCommissioningPlanCorrectionPeriodAirQualityManagementPlan
Page11
TheStateofMinnesotaSustainableBuildingGuidelines


CO2 3Month 6Month 10Month
DescriptionofOccupied ZoneSquare LocationsofSpecific Evaluation Evaluation Evaluation
# Concentration
Zone Footage(ft2) Pollutants
Limits(PPM) CO2Concentration(PPM)
1
2
3
4
5
Table1cTenMonthBuildingAirQuality

DesignandConstructionCommissioningPlanCorrectionPeriodAirQualityManagementPlan
Page12
TheStateofMinnesotaSustainableBuildingGuidelines

5.2 TenMonthSummary

Attheconclusionofthetenmonthevaluation,composeabriefsummaryofthe
testingresults(Table1c)andsystemmodificationsthatwerenecessarytoachieve
satisfactoryconcentrationlevels.



Insertyoursummaryhere.

DesignandConstructionCommissioningPlanCorrectionPeriodAirQualityManagementPlan
Page13
TheStateofMinnesotaSustainableBuildingGuidelines

6 Appendix
6.1 Design&ConstructionCommissioningMatrixActivities&
Responsibilities

DesignandConstructionCommissioningPlanCorrectionPeriodAirQualityManagementPlan
Page14
TheStateofMinnesotaSustainableBuildingGuidelines










DESIGN&CONSTRUCTIONPHASE
COMMISSIONINGPLAN
CORRECTIVEPERIODUSERCOMFORT&
SATISFACTIONASSESSMENTPLANTEMPLATE

BaseduponB3MinnesotaSustainableBuildingGuidelinesVERSION2.1














Notestothereaderhavebeenaddedtothisdocument
withinnumeroustextboxessuchasthis.These
textboxescontainreferencestosupporting
documentation,suggestions,and/orinstructions
pertainingtotheCommissioningProcessCorrection
PeriodUserComfort&SatisfactionAssessmentPlan.
Theyareintendedtobedeletedoncethetemplate
iscustomizedforaparticularproject.

DesignandConstructionCommissioningPlan
CorrectionPeriodUserComfort&SatisfactionAssessmentPlan
Page1
TheStateofMinnesotaSustainableBuildingGuidelines

TABLEOFCONTENTS

1 Introduction...............................................................................................................................................................................3

2 CorrectionPeriodUserComfort&SatisfactionAssessmentSpecification(6.01)........................................4

3 ThreeMonthOccupantSurvey(6.02)............................................................................................................................5

4 TenMonthOccupantSurvey(6.03)................................................................................................................................6

5 Appendix.....................................................................................................................................................................................7

5.1 Design&ConstructionCommissioningMatrixActivities&Responsibilities.....................................7

DesignandConstructionCommissioningPlan
CorrectionPeriodUserComfort&SatisfactionAssessmentPlan
Page2
TheStateofMinnesotaSustainableBuildingGuidelines

1 Introduction

TheCorrectionPeriodUserComfort&SatisfactionAssessmentPlanispartofthe
DesignandConstructionCommissioningPlanandshallinvolveperiodicoccupant
surveys.Theintentistoassesscomfortandsatisfactionviaoccupantsurveysthree
monthsandtenmonthsafteroccupancy.Asimilarsurveyduringthemovein
processisrecommended.

IssuesforassessmentincludethefollowingareasoutlinedintheMSBGIEQ
Guidelines:
1) AirQuality(I.4)
2) ThermalComfort(I.5)
3) AccesstoDaylight,Qualityoflighting,Viewspaceandwindowaccess(I.8,I.9,
andI.10)
4) Vibrations,AcousticsandNoise(I.11,I.12)
5) PersonalControlofIEQconditionsandimpacts(I.13)
6) Opportunitiesandencouragementforhealthfulphysicalactivity(I.14.)

PleaserefertotheDesign&ConstructionCommissioningMatrixActivities&
Responsibilities(refertoAppendix5.1).ThismatrixoutlineswhentheCorrection
PeriodUserComfort&SatisfactionAssessmenttasksshouldoccur.

Thenumberdesignationsinparentheses(e.g.6.01,6.02,6.03,etc.)arereferencesto
otherMSBGdocuments.ForexampleinAppendix5.1,theCorrectionPeriodUser
Comfort&SatisfactionAssessmenttasksarereferencedbythesenumber
designations.



Insertprojectcustomizedintroduction.

DesignandConstructionCommissioningPlan
CorrectionPeriodUserComfort&SatisfactionAssessmentPlan
Page3
TheStateofMinnesotaSustainableBuildingGuidelines

2 CorrectionPeriodUserComfort&SatisfactionAssessment
Specification(6.01)
2.1 ProcessesandProcedures

Duringthedesignphase,theteamshoulddeterminewhich,ifany,ofthe
responsibilitiesassociatedwiththeCorrectionPeriodUserComfort&Satisfaction
AssessmentPlanwillbeassignedtothebiddingcontractors.Ifthecontractorswillbe
responsibleforanypartofthesurveyorassessment,thedesignteamshouldprepare
aCorrectionPeriodComfort&SatisfactionAssessmentSpecificationforthecontract
documentsinordertoobligatethecontractorstofollowtheprovisionsofthis
CorrectionPeriodComfort&SatisfactionAssessmentPlan.



InsertyourProcessesandProceduresalongwithassignedRolesandResponsibilitiestoensure
thattheserequirementswillbeachieved.

DesignandConstructionCommissioningPlan
CorrectionPeriodUserComfort&SatisfactionAssessmentPlan
Page4
TheStateofMinnesotaSustainableBuildingGuidelines

3 ThreeMonthOccupantSurvey(6.02)
3.1 ProcessesandProcedures

ThreemonthsintotheCorrectionPeriodconductthefirstUserComfort&
SatisfactionSurveyasdefinedintheAssessmentPlan.

Distribute,collect,analyze,composeabriefsummaryofthethreemonthsurvey
results,andcomparethethreemonthresultstothemoveinsurveyresults.



InsertyourProcessesandProceduresalongwithassignedRolesandResponsibilitiestoensure
thattheserequirementswillbeachieved.

InsertCustomizedSurveyQuestionnaireforthisproject.

3.1 ThreeMonthSummary

ProvideasummaryreportofThreeMonthSurveyresultsandcorrectionactions
takenasaresult.

Insertsummaryreporthere.

DesignandConstructionCommissioningPlan
CorrectionPeriodUserComfort&SatisfactionAssessmentPlan
Page5
TheStateofMinnesotaSustainableBuildingGuidelines

4 TenMonthOccupantSurvey(6.03)
4.1 ProcessesandProcedures

TenmonthsintotheCorrectionPeriodconductthesecondUserComfort&
SatisfactionSurveyasdefinedintheAssessmentPlan.UsethesameSurvey
QuestionnaireusedfortheThreeMonthOccupantSurvey.

Distribute,collect,analyze,composeabriefsummaryofthetenmonthsurvey
results,andcomparethetenmonthresultstotheprevioussurveyresults.


Insert your Processes and Procedures along with assigned Roles and Responsibilities to ensure
thattheserequirementswillbeachieved.

4.2 TenMonthSummary

ProvideasummaryreportofTenMonthSurveyresultsandcorrectionactionstaken
asaresult.

Insertsummaryreporthere.

DesignandConstructionCommissioningPlan
CorrectionPeriodUserComfort&SatisfactionAssessmentPlan
Page6
TheStateofMinnesotaSustainableBuildingGuidelines

5 Appendix
5.1 Design&ConstructionCommissioningMatrixActivities&
Responsibilities

DesignandConstructionCommissioningPlan
CorrectionPeriodUserComfort&SatisfactionAssessmentPlan
Page7